The document outlines the various deliverables the contractor will be required to provide, including request to work outside regular hours, meeting minutes, permits and licenses, insurance documentation, cybersecurity incident reports, work scheduling and status updates, quality management plans, personnel qualification documents, safety plans and inspections, environmental management plans, and recurring and non-recurring work proposals. The deliverables have specific due dates, distribution requirements, and submission frequencies. The contract is being issued by the Department of the Navy Naval Facilities Engineering Command.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Section F – 0200000

Management and Administration

Section F 0200000

Deliveries or Performance

DELIVERABLES

Spec Item

Form

Attachment

Number Deliverable Title

Date (s) of

Submission

Distribution

Frequency Original

Copies

(including original)

2.2.1.2 N/A Request to Work

Outside

Government’s

Regular Working

Hours

At least seven calendar days prior to requested day.

KO and

COR

1 As required

2.3.1 N/A Sign-in Sheets and

Minutes Final

Revision

Within two working days

KO, COR

and all attendees

1 As

Required

2.3.4 N/A Permits and

Licenses

Before work commences and as requested by the KO.

KO and

COR

1 As specified

2.3.5 N/A Certificate of

Insurance

Within 15 calendar days prior to contract start.

KO and

COR

1 As specified

2.3.5 N/A Written Notice of

cancellation or material change in policy coverage

At least 30 calendar days prior to cancellation or material change in policy coverage

KO and

COR

1 As required

2.6.1 N/A Cybersecurity

Incident

Immediately upon discovery during regular working hours and by

0800 the following work day for discoveries after regular working hours

KO, COR,

and

Command

Security

Manager

1 As required

2.6.4 N/A Scheduling and

Work Status

Updates

Weekly, within

30 minutes of the inquiry during regular working hours, and by

08:00 the following work day for inquiries after regular working hours

KO and

COR

1 As

Specified

Form

Attachment

Number Deliverable Title

Date (s) of

Submission

Distribution

Frequency Original

Copies

(including original)

2.6.4 N/A Work Schedules Within 15

calendar days prior to contract start, 10 days prior to the beginning of the month in which services are scheduled to be performance, and within two calendar days of changes.

COR 1 Monthly

2.6.5 N/A Notification of any

Difficulty in

Scheduling Work

By the end of each workday

KO and

COR

1 As required

2.6.6 N/A Status of

Deliverables

Within 30 minutes of the inquiry during regular working hours, and by

0800 the following work day for inquiries after regular working hours

KO and

COR

1 As required

2.6.7 N/A Service

Interruptions

At least five working days in advance

KO and

COR

1 As required

2.6.8.2 N/A Pipe Delimited

Flat-File

By the end of each workday

KO or a representat ive designated by the KO

1 Daily

2.6.8.2 N/A Sample Pipe

Delimited Flat-File

Within 30 calendar days prior to contract start.

KO or a representat ive designated by the KO

1 As required to demonstrat e the ability to properly format the flat-file

2.6.8.2 N/A Asset and

Specification Data

When an asset is repaired, replaced, installed, or otherwise affected

KO or a representat ive designated by the KO

1 As required

Form

Attachment

Number Deliverable Title

Date (s) of

Submission

Distribution

Frequency Original

Copies

(including original)

2.6.8.3 N/A List of personnel

requiring access to

Government’s

Maximo

Within 30 calendar days prior to contract start.

KO and

COR

1 As specified

2.6.9.1 N/A Quality

Management Plan

Within 15 calendar days prior to contract start.

KO and

COR

1 As specified

2.6.9.2 N/A QC Inspection File Within five

calendar days of completion/ termination of the contract.

KO and

COR

1 As specified

2.6.9.3 N/A Contractor Quality

Inspection and

Surveillance

Report

First work day of each month.

KO and

COR

1 Monthly

2.6.10 N/A Property

Management Plan

Within 45 calendar days after award.

KO and

COR

1 As specified

2.7.1 N/A List of Key

Personnel and

Qualifications

Within 15 calendar days prior to contract start

KO and

COR

1 As specified

2.7.2.6 N/A Proof of United

States of America

Citizenship

Prior to be admitted to site of work.

KO and

COR

1 As specified

2.7.3 N/A Service Contract

Reporting (SCR)

No later than 31

October

KO and

COR

1 Annually for labor executed during the period of performanc e during each

Governmen t fiscal year

(FY)

2.8.1 N/A Employee List Within 15

calendar days prior to contract start and within seven calendar days of changes.

KO and

COR

required

Form

Attachment

Number Deliverable Title

Date (s) of

Submission

Distribution

Frequency Original

Copies

(including original)

2.8.8 N/A OF-306

Declaration for

Federal

Employment and

Digital

Fingerprints

Prior to commencement of work

KO, COR,

and

Security

Manager

1 As required

2.8.9 N/A List of personnel

requiring access to and the justification for their access to

Government IT, OT, and FRCS

Within 15 calendar days prior to contract start and within seven calendar days of changes.

KO, COR,

and

Security

Manager

1 As required

2.9.2 N/A Accident

Prevention Plan

Within 15 calendar days prior to contract start and within seven calendar days of changes.

KO and

COR

1 As specified

2.9.3 N/A Activity Hazard

Analysis

Together with the

Accident

Prevention Plan and within seven calendar days of and changes.

KO and

COR

1 As specified

2.9.4 N/A Compliance Plans, Programs, and

Procedures

Together with the

Accident

Prevention Plan and within seven calendar days of and changes.

KO and

COR

1 As specified

2.9.4.7 N/A Control of

Hazardous Energy

(lockout/tagout)

Within 30 calendar days after annual inspection.

KO and

COR

1 Annually

2.9.6 J-0200000-05 NAVFAC

Contractor Incident

Reporting System

(CIRS)

Within five calendar days of accident.

KO and

COR

1 As required

2.9.8 N/A Monthly On-Site

Labor Report

First work day of each month.

KO and

COR

1 Monthly

2.9.9 N/A OSHA Citations

and Violations

Corrective Action

Report

Within 48 hours after receiving a citation.

KO and

COR

Form

Attachment

Number Deliverable Title

Date (s) of

Submission

Distribution

Frequency Original

Copies

(including original)

2.9.10 N/A Safety Inspection

and Monitoring

Report

Upon request. KO and

COR

1 As required

2.9.11 N/A Safety

Certifications

Within 15 calendar days prior to contract start and as old certifications, expire.

KO and

COR

1 As specified

2.10 N/A EMS Goals and

Policy

Measurement

Information

Upon request. KO and

COR

1 As required

2.10.1.1 N/A Water

Conservation Plan

Within 15 calendar days after award and for changes.

KO and

COR

1 As specified

2.10.2 N/A Environmental

Protection Plan

Within 15 calendar days prior to contract start and within seven calendar days of changes.

KO and

COR

1 As specified

2.10.2.1 N/A Sampling Plan Prior to Sampling KO and

COR

1 As required

2.10.2.1 N/A Laboratory

Analysis

Upon Request KO and

COR

1 As specified

2.10.2.2 N/A Class I and II ODS

Report

Within 24 hours following delivery of refrigerant to

DLA

KO and

COR

1 As required

2.10.2.3 J-0200000-05 Solid Waste

Management and

Recycling Reports

First work day of each month.

KO and

COR

1 Monthly

2.10.2.5 N/A Waste Stream

Determination

Within 30 calendar days prior to start of contract performance and within 14 days of identification of any new waste stream.

KO and

COR

Form

Attachment

Number Deliverable Title

Date (s) of

Submission

Distribution

Frequency Original

Copies

(including original)

2.10.2.7 N/A Fuel and hazardous

substance spill notification

As soon as possible but not more 24 hours of discovery

KO and

COR

1 As required

2.10.2.8 N/A Emergency

Planning and

Community Right-

To-Know Act

(EPCRA) Report

Within 15 calendar days prior to contract start and not less than 10 working days prior to planned use of hazardous material.

KO and

COR

1 As specified

2.10.2.8 J-0200000-05 Contractor

Hazardous

Material Inventory

Log

Within 15 calendar days after the end of each calendar year and at termination of the contract.

KO and

COR

1 Annually

2.10.2.12 N/A Asbestos

Containing

Material (ACM)

Verbally notify the KO and COR within one hour and follow-up with written

Notification within 24 hours

KO and

COR

1 As specified

2.10.2.13 N/A Hazardous Air

Pollutants Monthly

Data

First workday of each month.

KO, COR,

Installation

Environme ntal

Division

1 Monthly

2.10.3 N/A Sustainable

Delivery of

Services Report

Within five calendar days after each contract period.

KO and

COR

1 Annually

2.10.3.2 N/A Recovered

Material

Certification

As specified KO and

COR

1 When a product containing recovered materials is equal to or better than the original and could be used.

Form

Attachment

Number Deliverable Title

Date (s) of

Submission

Distribution

Frequency Original

Copies

(including original)

2.11 N/A Mission Essential

Contractor

Services Plan

Within 15 calendar days prior to contract start and within seven calendar days of changes.

KO and

COR

1 As

Required

2.12 N/A Technical Library

Table of Contents

Within 15 calendar days after contract start and within seven calendar days of changes

KO and

COR

1 As specified

2.14.1 Recurring Work

Proposals

Within five calendar days following receipt of request

KO and

COR

1 As required

2.14.2 N/A Notification to the

Government for

Work Above the

Recurring Work

Limitations and

Rough Order of

Magnitude

Within two hours of identification

KO and

COR

1 As required

2.15.1.1 N/A Non-Recurring

Work Quantities

Ordered via

FedMall

By the fifth day of the following month

KO and

COR

1 Monthly

2.15.2.1 N/A Non-Recurring

Work Proposals

Within two working days following receipt of request

KO 1 As required

NAVSTA CONSOLIDATED CONTRACT

1502000 – Facility Investment

SECTION F: DELIVERIES OR PERFORMANCE

Annex/

Form

Attachment

Number Deliverable Title

Date (s) of

Submission

Distribution

Frequency

Original/

Copies

Number of

Copies

(including original)

1502000/

2.2.1

N/A

Certification and

Licenses

Within 15 days after award or as requested by the

KO

KO 1 Once for initial submittal, then as requested

1502000/

3.1

J-1502000-04 Service Order

Summary Report

First work day of each month

KO 2 Monthly

1502000/

3.2

N/A Monthly PM Work

Schedule

Five work days prior to the beginning of each month

KO 1 Monthly

1502000/

3.9

N/A

Other Recurring

Services Program

Summary Report

First work day of each month

KO 2 Monthly

Non-recurring

A-701 through

A746

N/A All Hazmat Services must contain a written Plan and

Specifications on removal services

As required per occurrence

KO/PAR 1 AS Needed

NAVSTA CONSOLIDATED CONTRACT

Deliverables Form Preparation Instructions

Deliverable Title: All Mandated Government Report

Form Attachment No.: J-1502000-04

Government Approval Required: X Yes ___ No

Media: Hard Copy X Electronic ___ Direct System Input

Instructions:

The report shall be prepared using Microsoft Office Word software.

The Service Order Summary Report shall be a compilation of the previous months service order reports with the following information:

a. Detailed description of work actually completed, problems encountered and recommended follow-up actions required.

b. Brief description of material and parts used, including quantities and cost.

c. Date and time work began.

d. Date and time work was completed.

e. Total hours of labor (by craft) expended, including travel time.

f. Name of person accepting the work and any comments written on the service order ticket.

g. Last name and first initial of the Contractor employee(s) performing the work.

Submit a copy of the summary report via email to KO for Government review and comment.