This document is a Performance Work Statement (PWS) for a Facility Investment contract at the Naval Station Newport Complex Area in Newport, Rhode Island. The PWS outlines the services required, including refuse collection, disposal, and recycling, as well as on-site project management and administration. The contract will be performance-based, with measurable standards and an assessment plan. The PWS is organized into 18 annexes, with Annex 1 providing general information and Annex 2 covering management and administration requirements. The remaining annexes detail the technical requirements for various functional areas. The contract will be awarded by the Department of the Navy Naval Facilities Engineering Command. The PWS includes details on government-furnished items, contractor safety requirements, environmental management, and procedures for recurring and non-recurring work.

View the file

Other files

Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NAVSTA CONSOLIDATED CONTRACT

Section C – 0100000 General Information

0100000 – General Information Spec Item Title 1 General Information

1.1 Outline of Services

1.2 Acquisition of Additional Work

1.3 Background Information

1.4 Navy PBSA Approach

1.5 Standard Template

1.6 Related Information

1.7 Verification of Workload and Conditions

1.8 Contractor's Knowledge

1.9 Technical Proposal Certification

Spec Item Title Description 1 General Information

1.1 Outline of Services Except where otherwise stated, the Contractor shall furnish all labor, supervision, management, tools, materials, equipment, facilities, transportation, incidental engineering, and other items necessary to provide the services outlined below and described in this Performance Work Statement (PWS) at The Contractor shall provide all labor, management, supervision, tools, material, and equipment required to perform refuse collection, disposal and recycling at Naval Station, Naval Undersea Warfare Center, Naval War College, Naval Health Clinic New England, at Newport Rhode Island

The PWS is organized into annexes. Annex 1 is "General Information".

Annex 2 contains the on-site project management and administration requirements. Annexes 3 through 18 contain the technical requirements.

The annex numbers are identified as 1 through 18 in the description column, but the fully expanded annex numbers include seven digits (e.g., Annex 1 expanded number is 0100000 as shown in the header row at the top of this page).

Annex 1 General Information Annex 2 Management and Administration Annex 3 Command and Staff – N/A Annex 4 Public Safety – N/A Annex 5 Air Operations – N/A Annex 6 Port Operations – N/A Annex 7 Ordnance – N/A Annex 8 Range Operations – N/A Annex 9 Health Care Support – N/A Annex 10 Supply – N/A Annex 11 Personnel Support – N/A Annex 12 Morale, Welfare and Recreation Support – N/A Annex 13 Galley – N/A Annex 14 Housing – N/A Annex 15 Facilities Support – N/A Sub Annex 1503030 Integrated Solid Waste Management Annex 16 Utilities – N/A Annex 17 Base Support Vehicles and Equipment – N/A Annex 18 Environmental – N/A

1.2 Acquisition of

Additional Work

The Government reserves the right to acquire additional services at additional locations, within the scope of the annexes and areas included in Spec Item 1.1 Outline of Services, in addition to the services and locations identified in the requirements of this contract. Additional services will be incorporated into the contract in accordance with the CHANGES clause, SECTION I or ordered under the non-recurring work provisions of the contract. Items of work not covered by this contract but within the general intent are considered in the scope of this contract.

1.3 Background Information Naval Station Newport is home to more than 42 naval and defense commands and activities. Newport is the Navy’s premier site for training officers, officer candidates, senior enlisted personnel and midshipman candidates, as well as conducting advanced undersea warfare and development systems. Naval Station Newport’s mission is to fulfill the diverse requirements of its tenant commands by providing the facilities and infrastructure that are essential to their optimum performance. Navy personnel assigned to Newport come from all parts of the United States and many free nations of the world. Newport is the home of the Navy’s most prestigious educational institution, the Naval War college. Each year, over 500 outstanding mid-career level officers of the Navy, all other services, civilian federal agencies, and international naval officers come here to pursue a rigorous 10 month course of post-graduate studies.

Military and civilian personnel get deeply involved in local community affairs. Naval station Newport is the largest employer in Newport County both in terms of personnel and payroll, with approximately 5,800 employees and an additiona15, 000 students attending classes each year at one of the many schools on base. The Naval Undersea Warfare Center Division Newport provides research, development, test and evaluation, engineering, analysis, and assessment, and fleet support capabilities for submarines, autonomous underwater systems, and offensive and defensive undersea weapon systems, and stewards existing and emerging technologies in support of undersea warfare, and executes other responsibilities as assigned by the Commander, Naval Undersea Warfare Center.

1.4 Navy PBSA Approach The Navy’s approach to performance-based service acquisition (PBSA) includes four component parts, which are 1) performance outcomes, 2) measurable standards, 3) consideration of incentives, and 4) performance assessment plan.

1.5 Standard Template Key to implementing the PBSA approach is using a standard template that ensures Navy-wide consistency yet affords appropriate tailoring to meet local needs.

The standard template contains 18 standard annexes. Annex 1 will always contain General Information that is relevant to the entire scope of the contract. Annex 2 contains Management and Administration requirements that are relevant to the entire scope of the contract. Annexes 3 through 18 and their associated sub-annexes contain the General Information, Management and Administration requirements, Performance Objectives, Related Information, and Performance Standards that are relevant to that technical annex. Except where otherwise stated, Annexes 3 through 18 and their associated sub-annex requirements are not relevant to one another. Within each technical annex and sub-annex, the organization of information and requirements are also standardized. Specification Item 1 will always contain General Information. Specification Item 2 will always contain the Management and Administrative requirements. Specification Item 3 will always contain the Recurring Work requirements.

Specification Item 4 will always contain the Non-Recurring Work requirements. Requirements and standards for higher level specification items apply to all subordinate specification items, e.g., Specification Item 3 standards apply to all recurring work specification items. Specification Item 3.1 is applicable to all 3.1 subordinate specification items.

Specification Items 3.2 and 3.3 are not considered subordinate to 3.1 nor are they considered subordinate to one another. All costs associated with Annexes 1 and 2 and Specification Items 1 and 2 shall be priced, and their price shall be allocated to the Exhibit Line Items.

1.6 Related Information There are four types of Related Information that can be found in the Description and Related Information columns of the specification as follows:

Informational Notes as used throughout this PWS provides additional information to offerors’ to be used in developing a thorough understanding of the work to be performed in this contract. Any block of text marked “Informational Notes” throughout Annexes 1 through 18 and their associated sub-annexes are subject to this disclaimer. Offerors’ may not rely upon the "Informational Notes" as material representations of the Government. Information provided in "Informational Notes" does not create a contractually binding requirement on either party.

Clarifying Information describes client expectations in a more detailed manner than the Performance Objective and Performance standard alone.

Constraining Information describes limitations to the work performed to meet the Performance Objective and Performance Standard.

Requirement Information further describes client requirements associated with each Performance Objective.

1.7 Verification of

Workload and Conditions

Throughout the PWS, the workload data is generally referred to as being located in Sections C and J. Section C provides data such as descriptions, specifications, and the statement of work. Section J provides data such as system descriptions, maps, floor plans, and tables to represent the type and location of services to be provided.

All facilities, systems, and assets identified in this contract shall be accepted by the Contractor in "AS-IS" condition. The Contractor is fully responsible for all work up to and including the limits of liabilities specified.

As prescribed in FAR 52.237-1, offerors’ or quoters are urged and expected to inspect the site where services are to be performed and to satisfy themselves regarding all general and local conditions that may affect the cost of contract performance, to the extent that the information is reasonably obtainable. In no event shall failure to inspect the site constitute grounds for a claim after contract award.

1.8 Contractor's Knowledge The Navy expects to receive insightful management from its contractors.

This management will include the knowledge, skills, authority and willingness to use contractor resources to find better ways of serving Navy clients’ strategic and operational goals and objectives. The Navy's use of performance-based objectives evidences this principle. Although performance work statements will typically contain several levels of performance assessment, the Navy wants its contractors to exercise maximum discretion within bounds of prudent risk management to adjust processes and resources needed to reach specified objectives at the highest performance level.

1.9 Technical Proposal

Certification

The Contractor warrants that its proposal incorporated herein by reference will meet or exceed the performance objectives set forth in this contract.

Section C – 0200000

Management and Administration

0200000 – Management and Administration Spec Item Title 2 Management and Administration

2.1 Definitions and Acronyms

2.2 General Information

2.2.1 Government Regular Working Hours

2.2.1.1 Observed Federal Holidays

2.2.1.2 Restriction to Contractor Working Hours

2.2.2 Wage Determinations

2.2.3 Requirements Hierarchy

2.3 General Administrative Requirements

2.3.1 Required Conferences and Meetings

2.3.2 Training for Maintenance and Operation of New and Replacement Systems and Equipment

2.3.3 Partnering

2.3.3.1 Formal Partnering and Informal Partnering

2.3.3.2 Contract Partnering Administration

2.3.3.3 Contract Partnering Session Attendees

2.3.4 Permits and Licenses

2.3.5 Insurance

2.3.5.1 Certificate of Insurance

2.3.5.2 Minimum Insurance Amounts

2.3.6 Protection of Government Property

2.3.7 Directives, Instructions, and References

2.3.8 Invoicing Procedures

2.3.9 Forms

2.4 Government-Furnished Items

2.4.1 Government-Furnished Property (GFP)

2.4.2 Government-Furnished Facilities

2.4.3 Government-Furnished Vehicles and Equipment

2.4.4 Government-Furnished Utilities

2.5 Contractor-Furnished Items

2.6 Management

2.6.1 Safeguarding Information

2.6.2 Dissemination of Information

2.6.3 Work Reception

2.6.4 Work Control

2.6.5 Work Schedule

2.6.6 Deliverables

2.6.7 Service Interruptions

2.6.8 NAVFAC Maximo

2.6.8.1 NAVFAC Maximo Data

2.6.8.2 NAVFAC Maximo Method of Data Entry

2.6.8.3 NAVFAC Maximo Access

2.6.8.4 NAVFAC Maximo Training

2.6.9 Quality Management System (QMS)

2.6.9.1 Quality Management (QM) Plan

2.6.9.2 Quality Inspection and Surveillance

2.6.9.3 Quality Inspection and Surveillance Report

2.6.9.4 Daily Work Report

2.6.10 Property Management Plan

2.6.11 System and Equipment Replacement

2.7 Personnel Requirements

2.7.1 Key Personnel

Management and Administration

0200000 – Management and Administration Spec Item Title

2.7.1.1 Project Manager (PM)

2.7.1.2 Quality Manager

2.7.1.2.1 Quality Control Personnel

2.7.1.3 Site Safety and Health Officer (SSHO)

2.7.1.4 Environmental/Energy Manager

2.7.2 Employee Requirements

2.7.2.1 Employee Certification and Training

2.7.2.2 Employee Appearance

2.7.2.3 Employee Conduct

2.7.2.4 Identification as Contractor Employee

2.7.2.5 Removal of Employees

2.7.2.6 Proof of Legal Residency

2.7.3 Service Contract Reporting (SCR)

2.8 Security Requirements

2.8.1 Employee Listing

2.8.2 Vehicles

2.8.3 Passes and Badges

2.8.4 Access to Installation

2.8.4.1 DBIDS Program

2.8.4.2 DBIDS Credentials

2.8.5 Access to Buildings

2.8.6 Access Arrangements

2.8.6.1 Escort Arrangement for Secured Areas

2.8.7 Security Clearances

2.8.8 Access to Controlled Unclassified Information

2.8.9 Access to Government Information Technology (IT), Operating Technology (OT), and Facility

Related Control Systems (FRCS)

2.8.10 Access to Navy Marine Corps Intranet (NMCI)

2.8.11 Employee Status

2.9 Contractor Safety Program

2.9.1 Contractor Safety Requirements

2.9.1.1 Experience Modification Rate (EMR)

2.9.1.2 OSHA Days Away From Work, Restricted Duty, or Job Transfer (DART) Rate

2.9.2 Accident Prevention Plan (APP)

2.9.3 Activity Hazard Analysis (AHA)

2.9.4 Safety and Occupational Health (SOH) Risks and Compliance Plans

2.9.4.1 Alcohol and Drug Abuse Prevention Plan

2.9.4.2 Chemical Hazard Communication Program

2.9.4.3 Confined Space Program

2.9.4.4 Critical Lift Plan

2.9.4.5 Fall Prevention and Protection Plan

2.9.4.6 Pathogen Exposure

2.9.4.7 Control of Hazardous Energy (lockout/tag out)

2.9.5 Crane Operations

2.9.5.1 Crane Inspections

2.9.5.2 Rigging Gear

2.9.5.3 Crane Operators

2.9.6 Accident and Damage Reporting

2.9.6.1 Accident Reporting and Notification Criteria

2.9.7 Fire Protection

2.9.8 Monthly On-Site Labor Report

2.9.9 OSHA Citations and Violations

Management and Administration

0200000 – Management and Administration Spec Item Title

2.9.10 Safety Inspections and Monitoring

2.9.11 Safety Certification

2.9.12 Safety Apparel on Jobsites

2.9.13 Emergency Medical Treatment

2.9.14 Excavations

2.10 Environmental Management and Sustainability

2.10.1 Energy Management Program

2.10.1.1 Water Conservation Plan

2.10.1.2 Energy Efficient Products

2.10.2 Environmental Protection

2.10.2.1 Sampling, Testing and Laboratory Services

2.10.2.2 ODS Requirements for Refrigerant Recycling

2.10.2.3 Solid Waste Management and Recycling

2.10.2.4 Non-Regulated Waste Disposal

2.10.2.5 Regulated Waste Disposal

2.10.2.6 Universal Waste

2.10.2.7 Spill Prevention, Containment, and Clean-up

2.10.2.8 Hazardous Material Management

2.10.2.9 Protection of Endangered and Threatened Species (Flora and Fauna)

2.10.2.10 Noise Control

2.10.2.11 Salvage

2.10.2.12 Asbestos Containing Material (ACM)

2.10.2.13 Clean Air Act (CAA)

2.10.3 Sustainable Procurement and Practices

2.10.3.1 Environmentally Preferable Products

2.10.3.2 Use of Recovered Materials

2.10.3.3 Use of Bio-based Products

2.11 Disaster Preparedness

2.12 Technical Library

2.13 Warranty Management

2.14 Recurring Work Procedures

2.14.1 Recurring Work Preparation of Proposals

2.14.2 Notification to the Government for Work Above the Recurring Work Limitations

2.14.3 Recurring Work Exhibit Line Item Numbers (ELINs)

2.15 Non-Recurring Work

2.15.1 Unit Priced Task (UPT) Work (Non-Negotiated)

2.15.1.1 Acceptance and Performance

2.15.1.2 Invoicing and Receiving Payment

2.15.2 Unit Priced Labor (UPL)Work (Negotiated)

2.15.2.1 Non-recurring Work Preparation of Proposals

2.15.2.1.1 Labor Requirements

2.15.2.1.2 Direct Material and Construction Equipment Requirements

2.15.2.2 Issuance of Final Task Order

2.15.3 Non-Recurring Work ELINS

Management and Administration

0200000 - Management and Administration Spec Item Title Description 2 Management and

Administration

2.1 Definitions and

Acronyms

Definitions and Acronyms are listed in J-0200000-01.

2.2 General

Information

2.2.1 Government

Regular Working Hours

The Government's regular working hours are from 0700-1600, five days per week, Monday through Friday, except observed Federal holidays. Exceptions to the regular hours of operation are detailed in subsequent sections of this PWS. Work in certain annexes or sub-annexes require Contractor continuous operations, 24 hours a day, every day of the year including holidays. The performance of other work requirements shall be accomplished within the Government’s regular working hours unless the specific work requirement specified herein necessitates otherwise. Any other work outside Government regular working hours must be authorized by the KO prior to commencement of work.

2.2.1.1 Observed Federal

Holidays

The Government observes the following holidays: New Year’s Day, Martin Luther King Jr.’s Birthday, President’s Day, Memorial Day, Juneteenth, Independence Day, Labor Day, Columbus Day, Veterans’ Day, Thanksgiving Day, and Christmas Day.

2.2.1.2 Restriction to

Contractor Working Hours

If the Contractor wishes to work outside of the Government's regular working hours for the Contractor’s convenience, the Contractor shall submit a written Request to Work Outside Government’s Regular Working Hours per Section F. Excludes work to be performed during specified hours.

2.2.2 Wage

Determinations

Service Contract Act and Davis-Bacon Act wage determinations in Section J.

Wage Determinations are included in J-0200000-02.

2.2.3 Requirements

Hierarchy

Requirement or definitions specified in each spec item of this contract apply to subordinate paragraphs. For example, requirements shown in spec item 3.1 would apply to spec items 3.1.1, 3.1.2, 3.1.2.1 and so on.

Likewise, Performance Standards specified at a lower digit level (i.e. spec item 3.1.1, 3.1.2, 3.1.2.1) apply when performance is assessed at a higher tier (i.e., spec item 3.1) based on the composite work requirements.

2.3 General

Administrative Requirements

2.3.1 Required

Conferences and Meetings

The Contractor shall attend administrative and coordination meetings. The Contractor shall provide sign-in sheets and prepare minutes of all meetings and submit per Section F for review and comments. Comments received within two working days shall be incorporated into the minutes and a copy of the final revision shall be submitted per Section F for concurrence.

Historically, there have been approximately four meetings per week.

2.3.2 Training for

Maintenance and Operation of New and Replacement Systems and Equipment

When construction, renovation, or repair work is performed by means other than this contract, the Contractor shall attend Government provided training, as applicable, for maintenance and operation of new and replacement systems and equipment at no additional cost to the Government.

2.3.3 Partnering The Government requires cohesive partnerships with its Contractors and subcontractors. Key stakeholders, including the supported commands who may receive services, principal individuals from NAVFAC, the performance assessment team, and representative(s) of the installation(s) will be invited to participate in the partnering process. Key members of the prime and sub-

Management and Administration

0200000 - Management and Administration Spec Item Title Description contractor teams, including senior management personnel must participate.

The partnership will draw on the strength of each organization in an effort to achieve quality contract services done right the first time, within the contract price, as scheduled, and without any safety mishaps.

The goal of Partnering is to develop a cohesive team with common purpose, commitment and established communication processes.

A project’s characteristics determine whether the formal or informal partnering process level is to be used. Per BMS B-14.16, insert appropriate Partnering requirements by selecting one of the following two specification items and deleting the other.

2.3.3.1 Formal Partnering

Formal Partnering is recommended if annual contract dollar value is $10M or more, first time BOS contract, high visibility, many supported commands, large geographic area, services provided concurrently at multiple activities or for multiple functions, and complex management and coordination issues.

The initial session should be scheduled concurrent with the Pre-Performance Conference and held no later than 30 days after award. The initial Partnering Meeting will be at least one day in duration and held at a Government provided facility as designated by the KO. Follow-on sessions should be scheduled every three to six months and typically last a half day or less. The frequency, duration, and locations of follow-on sessions should be agreed to by both parties during the initial Partnering Meeting. The Contractor shall pay all costs associated with the partnering effort including facilitator, meeting room, and other incidental items. Before the partnering session, the Contractor shall coordinate with the facilitator the requirements for incidental items (audio-visual equipment, computer(s), two easels, flipchart paper, colored markers, note paper, pens/pencils, colored flash cards, etc.) and have these items available at the partnering session. The Contractor will provide copies of any documents used for the Partnering Meeting for distribution to all attendees. The facilitator must be acceptable to both the Contractor and the Government. The participants shall pay their own costs for meals, lodging, and transportation associated with partnering.

2.3.3.3 Contract Partnering

Session Attendees

The Contractor shall bring the necessary personnel to successfully partner on this contract. Asterisk indicates mandatory personnel.

* President/Vice President

* Project Manager

* Quality Manager

* Site Safety and Health Officer Sub-contractor Reps

2.3.4 Permits and

Licenses

The Contractor shall obtain all required permits, licenses, and authorizations to perform work under this contract and comply with all the applicable Federal, state and local laws and regulations. The Contractor shall submit copies of Permits and Licenses per Section F.

2.3.5 Insurance The Contractor shall submit a Certificate of Insurance per Section F as evidence of the existence of the following insurance coverage in amounts not less than the amounts specified below in accordance with the FAR Clause

52.228-5, INSURANCE – WORK ON A GOVERNMENT

INSTALLATION. This insurance must be maintained during the performance period.

2.3.5.1 Certificate of

Insurance

The Certificate of Insurance shall provide for at least 30 calendar days written notice to the KO by the insurance company prior to cancellation or material change in policy coverage. Other requirements and information are contained in the aforementioned insurance clause.

Management and Administration

0200000 - Management and Administration Spec Item Title Description

2.3.5.2 Minimum

Insurance Amounts The Contractor shall procure and maintain, during the entire period of performance under this contract, the following minimum insurance coverage:

Ensure insurance amounts are current.

Comprehensive General Liability: $500,000 per occurrence

Automobile Liability: $200,000 per person, $500,000 per occurrence, $20,000 per occurrence for property damage

Workmen's Compensation: As required by Federal and state worker's compensation and occupational disease statutes

Employer's Liability coverage: $100,000, except in states where worker's compensation may not be written by private carriers

Other as required by state law

2.3.6 Protection of

Government Property

During execution of the work, the Contractor shall protect Government property. The Contractor shall return areas damaged as a result of Contractor negligence under this contract to their original condition at no cost to the Government.

2.3.7 Directives, Instructions, and References

Department of Defense (DoD), Secretary of the Navy (SECNAV), Chief of Naval Operations (OPNAV), and other applicable Directives, Instructions, and References are listed in J-0200000-03. The Contractor shall comply with the most current version of directives, instructions, and references including versions published during the term of the contract.

2.3.8 Invoicing

Procedures

Refer to Section G for invoicing instructions. Refer to Invoice Form in J- 0200000-04 for sample.

Invoices shall be submitted in a format compatible with the most recent Government installed Microsoft Office Version (currently 2010). Invoice data shall be capable of being sorted by CLIN, annex/sub-annex, spec item, spec item title, and ELIN/Sub-ELIN.

2.3.9 Forms Forms referenced in this Annex, e.g. accident reporting, and damage reporting are included among the Forms in J-0200000-05.

2.4 Government-

Furnished Items

N/A

2.4.1 Government-

Furnished Property

(GFP)

2.4.2 Government-

Furnished Facilities

Government owned Facilities are considered incidental to performance and are not considered GFP. If Government owned facilities will be made available to the Contractor, insert local requirements, e.g., The Government will make available to the Contractor certain facilities for use in connection with this contract. The use of these facilities for any other purposes is prohibited.

The Contractor shall be responsible and accountable for the facilities accepted for use and shall take adequate precautions to prevent fire hazards, odors, and vermin. Janitorial and refuse collection services for the facilities shall be provided by the Contractor. The Contractor shall obtain written approval from the KO prior to making any modifications or alterations to the facilities.

Management and Administration

0200000 - Management and Administration Spec Item Title Description

A list of the facilities that will be made available to the Contractor is provided in J-0200000-06.

2.4.3 Government-

Furnished Vehicles and Equipment

N/A

2.4.4 Government-

Furnished Utilities

2.5 Contractor-

Furnished Items

Except for items identified as Government Furnished, the Contractor shall provide all equipment, materials, parts, supplies, components, and facilities to perform the requirements of this contract. The KO may inspect Contractor-furnished items for adequacy and compliance with contract requirements.

Inadequate or unsafe items shall be removed and replaced by the Contractor at no cost to the Government. Materials containing asbestos, lead, and polychlorinated biphenyls (PCBs) shall not be brought onsite. Energy efficient tools and equipment shall be used when available. The KO may at any time require Samples, Safety Data Sheets (SDS) or Manufacturer’s Data Cut Sheets of Materials used in this contract.

2.6 Management The Contractor shall manage the total work effort associated with the services required herein to meet the performance objectives and standards. Such management includes but is not limited to planning, scheduling, cost accounting, report preparation, establishing and maintaining records, and quality assurance. The Contractor shall provide a staff with the necessary management expertise to ensure performance objectives and standards are met.

2.6.1 Safeguarding

Information

The Contractor shall safeguard controlled unclassified information and information associated with Government property in accordance with the latest revision of CNSSI 1253, DoDI 8582.01, NIST SP 800-53, NIST SP 800-171, SECNAV Defense Industrial Base (DIB) Memo, and applicable contract clauses. At a minimum, this information shall be protected at the moderate confidentiality level as defined in NIST SP 800-171.

Contractor information and data systems that contain information associated with Government property shall comply with DoD Risk Management Framework (RMF).

The Contractor shall develop Plans of Action and Milestones (POA&Ms) per NIST SP 800-171, track accomplishment, and submit to the Government per Section F.

If a cybersecurity incident is encountered or suspected related to any (Contractor or Government) Information Technology (IT) or Operating Technology (OT) systems, including Monitoring and Control Systems, the Contractor shall notify the Government per Section F.

2.6.2 Dissemination of

Information

If certain information cannot be provided to the public, state what information cannot be provided, when it will be provided, and to whom, e.g., DoD policy limits the dissemination of certain information. Instructions, Directives, and References not releasable to the public, e.g., Floor Plans, Maps, Post Orders, and Standard Operating Procedures, will be made available after contract award to the successful offeror with appropriate credentials and a need to know.

2.6.3 Work Reception The Contractor shall provide the capability to receive, prioritize, correspond, and respond to trouble/service calls and task orders during Government regular working hours and provide a point of contact at a local or toll free

Management and Administration

0200000 - Management and Administration Spec Item Title Description number who can perform the above function during other than Government regular working hours.

2.6.4 Work Control The Contractor shall implement all necessary work control procedures to ensure timely accomplishment of work requirements, as well as to permit tracking and reporting of work in progress. The Contractor shall plan and schedule work to assure material, labor, and equipment are available to complete work requirements within the specified time limits and in conformance with the quality standards established herein. Verbal scheduling and work status updates shall be provided when requested by the Government. A status update of any item of work must be provided within

The Contractor shall provide work schedules for both Recurring and Non- Recurring Work per Section F. At a minimum, work schedules shall include:

• Description of service(s) to be accomplished

• Location

• Date service(s) are scheduled to be accomplished

2.6.5 Work Schedule The Contractor's work shall not interfere with normal Government business.

In those cases where some interference is unavoidable, the Contractor shall minimize the impact and effects of the interference. The Contractor shall provide advance access of all of its work schedules to the Government. The Contractor shall provide written notification of any difficulty in scheduling work due to Government controls, per Section F. At a minimum, the notification shall include the following:

• The date and time the work was initially coordinated.

• The name and phone number of the Government person with whom the work was initially coordinated.

• The name and phone number of the Government person who prevented the work from being performed as previously coordinated.

• The alternative date and time, the Government person requested the work be accomplished.

2.6.6 Deliverables Except where otherwise stated, deliverable requirements are specified in

Sections C, F, H, I, J, and within the Directives, Instructions, and References.

The Contractor shall submit accurate and complete documents within the specified timeframes. The Contractor shall revise/modify deliverables, as directed by the KO, at no additional cost to the Government.

Except where otherwise specified, all deliverables shall be submitted electronically in a Microsoft Office Version 2010 compatible format.

Deliverables shall include the company name, contract number, contract title, date, and shall be unprotected and capable of being sorted by CLIN, work order number, asset number, section, annex/sub-annex, spec item and ELIN/Sub-ELIN or clause. All formulas shall be traceable.

Government acceptance of deliverables shall not relieve the Contractor of the responsibility for any error or omission which may exist in the deliverable, as the Contractor is responsible for all requirements of this contract.

The Contractor shall establish and maintain a secure website for posting an electronic copy of all deliverables listed in Section F. The Contractor shall allow only authorized Government and Contractor personnel to access the website. Government personnel access shall be limited to viewing and downloading of deliverables, but restricted from posting to the website. The Contractor shall notify the Government by email whenever there are new or

Management and Administration

0200000 - Management and Administration Spec Item Title Description updated deliverables posted to the website. Each deliverable posting on the website and each email notification shall include the title of the deliverable, the spec item requiring the deliverable, and the date and time the deliverable was posted. All deliverables shall be available to authorized Government personnel 24 hours/day and 365 days/year for the duration of the contract.

2.6.7 Service

Interruptions

If any utilities or other services must be discontinued (even temporarily) due to scheduled contract work, the Contractor shall notify the KO, COR, affected tenants, and customers in accordance with local procedures. If the discontinued service is due to an emergency breakdown the Contractor shall notify the KO, COR, affected tenants, and customers as soon as practicable and provide the status of repairs, as directed by the KO, until normal operation is restored.

Scheduled utility outages and interruptions to equipment, system(s) operation, or other services shall be scheduled after hours of operation.

The Contractor shall shutdown, restart, and perform operational checks on all equipment affected by both scheduled and unscheduled utility outages and service interruptions, at no additional cost to the Government.

2.6.8 NAVFAC Maximo Contractor is required to provide work order, asset, specification, and condition assessment data for NAVFAC’s Maximo. The data is required for the Government’s use in long term asset management and planning.

Work order, asset, specification, and condition assessment data created by the Contractor is recorded in NAVFAC Maximo for all work performed in 1501000 Facility Management, 1502000 Facility Investment, Annex 16 Utilities sub-annexes and Annex 1700000 BSVE. This spec item should be included in all FSC/BOS contracts above the SAP threshold at Navy PWDs per BMS B-24.8 Facility Support Contractor Data in NAVFAC MAXIMO.

Consult with your local PWD FMD, UEM Director and BSVE Director or FEC FM&S PLC, UEM PLC, and BSVE PLC for further guidance.

The information and format for data submission provided in Section J supports long-term asset management and facilitates transfer to NAVFAC Maximo. These requirements and data format are managed by the FM&S Product Line at the NAVFAC HQ level.

NAVFAC Maximo is the Computerized Maintenance Management System (CMMS) used by the Government for work order history, asset management, and condition assessment. The Contractor shall provide all required data for NAVFAC MAXIMO as identified below:

Informational Note:

Not all supported commands’ assets are included in NAVFAC Maximo. Not all of the modules available within the Maximo application are utilized by NAVFAC and the modules utilized may not be fully implemented.

NAVFAC Maximo does not include a detailed inventory of all assets, components, and equipment that the Contractor is required to service under this contract and may include inaccuracies, omissions, and redundancies.

2.6.8.1 NAVFAC Maximo

Data

Required data fields for work orders are indicated in the Service Provider Information provided in J-0200000-07. Asset inventory data requirements are indicated in the Asset Information provided in J-0200000-08, including additional data for Utilities assets listed in Specification Information in J- 0200000-09. Required data for documenting condition assessments is

Management and Administration

0200000 - Management and Administration Spec Item Title Description indicated in the Characteristic Meter Reading Information provided in J- 0200000-10.

Specified data shall be provided for all work performed is Provided for NAVFAC Maximo, e.g., 1501000 Facility Management, 1502000 Facility Investment. Further instructional information detailing the process for submitting the specified information for NAVFAC Maximo Data Reporting is provided in J-0200000-11.

The Service Provider, Asset, Specification, and Characteristic Meter Reading Interfaces are used in multiple processes for loading data into Maximo by the Government and the format may be updated periodically.

As part of the update the Contractor may be asked to modify the file to add/move columns in their submission. The Contractor shall provide up to 10 extra data elements or columns with as many as 150 characters per element for the Government to define during contract performance at no additional cost to the Government. The Government will provide the Contractor 60 calendar days’ notice of modifications to the Service Provider, Asset, Specification, or Characteristic Meter Reading Interfaces file format.

2.6.8.2 NAVFAC Maximo

Method of Data Entry

The Contractor shall provide data for NAVFAC Maximo using the methods detailed below:

Two primary options for specifying methods for NAVFAC Maximo data are listed below. Either may be selected or tailored further as required for local requirements.

DIRECT ENTRY: The Contractor shall manually enter required work order and condition assessment data directly into NAVFAC Maximo. The Contractor shall ensure all information is updated by the end of each workday for all work performed.

If the Contractor does not have access to NAVFAC Maximo at contract start, work order and condition assessment data shall be submitted in a pipe delimited flat-file following the NAVFAC Maximo Data Reporting process described in J-0200000-11 per Section F. Any failures in processing of the flat-file shall be corrected and resubmitted by the Contractor. In order to demonstrate the ability to properly format the flat-file, the Contractor shall provide a Sample Pipe Delimited Flat-file prior to contract performance per Section F. Flat file submission of work order and condition assessment data will be allowed for a period not to exceed, one months unless an extension is authorized in writing by the KO.

FLAT FILE: The Contractor shall electronically record and report compiled service performance data for exportation of asset and specification data to NAVFAC Maximo. The Contractor shall submit asset and specification data in a spreadsheet flat-file following the NAVFAC Maximo Data Reporting process described in J-0200000-11 per Section F.

OR

FLAT FILE: The Contractor shall electronically record and report compiled service performance data for exportation of work order, asset, specification, and condition assessment data to NAVFAC Maximo.

Management and Administration

0200000 - Management and Administration

The Contractor shall submit work order and condition assessment data in a pipe delimited flat-file following the NAVFAC Maximo Data Reporting process described in J-0200000-11 per Section F. Any failures in processing of the pipe delimited flat-file shall be corrected and resubmitted by the Contractor. In order to demonstrate the ability to properly format the pipe delimited flat-file, the Contractor shall provide a Sample Pipe Delimited Flat-file prior to contract performance per Section F.

The Contractor shall submit asset and specification data in a spreadsheet flat-file following the NAVFAC Maximo Data Reporting process described in J- 0200000-11 per Section F.

2.6.8.3 NAVFAC Maximo

Access

Contractor is required to provide Maximo data via Direct Entry.

The process for obtaining access and establishing NAVFAC Maximo accounts are detailed in the NAVFAC Maximo System Access Procedures provided in J-0200000-11.

Once accounts have been established, NAVFAC Maximo can be accessed at https://maximo.navfac.navy.mil.

Two primary options for the Contractor’s access to NAVFAC Maximo are listed below. Either may be selected or tailored further as required for local requirements. If a NMCI workstation is provided to the Contractor, all equipment needs to be included within the list of Government Furnished Property.

The Contractor shall provide all necessary computer equipment and Internet Service Provider (ISP) accounts to access NAVFAC Maximo for Direct Entry of required data.

OR

The Government will provide access to NMCI workstations located in \ for the dedicated use of the Contractor to access NAVFAC Maximo for Direct Entry of required data

A maximum of five NAVFAC Maximo accounts will be approved for the Contractor. Changes of personnel requiring NAVFAC Maximo accounts more than once per year may result in required compensation to the Government for the administrative costs in processing account requests.

The Contractor shall submit a list of personnel requiring NAVFAC Maximo accounts per Section F.

2.6.8.4 NAVFAC Maximo

Training

Contractor is required to provide NAVFAC Maximo data via Direct Entry, e.g., The Government will provide or make available initial training on NAVFAC Maximo to Contractor personnel responsible for direct entry of work order, asset, specification, and condition assessment data. Additional training will be provided by the Government when there are significant changes to the NAVFAC Maximo software or data entry requirements.

Training due to changeover of personnel will be the responsibility for the Contractor. The Contractor will be provided a general user guide, local instructions, and other materials by the Government as reference material for the use of NAVFAC Maximo.

https://maximo.navfac.navy.mil/

Management and Administration

0200000 - Management and Administration Spec Item Title Description

2.6.9 Quality

Management System (QMS)

The Contractor shall establish and maintain a complete QMS program in accordance with the provisions specified herein. The Contractor’s QMS program shall provide an effective and efficient means of identifying and correcting problems throughout the entire scope of operations. The Contractor's QMS program shall address:

• Accurate documentation of work processes, procedures, and output measures.

• A systematic procedure for assessing compliance with performance objectives and standards.

• Accurate documentation of quality inspections and surveillance conducted throughout the execution of work.

• Assessment-driven corrective actions and process adjustments as appropriate in a timely manner.

2.6.9.1 Quality

Management (QM) Plan

The Contractor shall develop and submit a QM Plan per Section F. The QM Plan shall describe the QMS methodology and approaches used under this contract. If any changes are made during the period of performance, the Contractor shall submit the revised QM Plan for acceptance, per Section F.

The Contractor’s QM Plan shall include, at a minimum, the following:

• Policy and objectives of Quality Management System (QMS)

• Quality organization o List of personnel o Responsibilities & lines of authority o Training and qualifications

• Approach to assuring quality of services provided and conformance with performance objectives and standards

• Methods and procedures for effective planning, operation and control of processes and performance of work

• Procedures for inspection and surveillance of services to include all contractual requirements.

o Scheduling and performance of inspection and surveillance o Measurement, data collection and analysis o Corrective action, preventive action, and continuous improvement o Oversight of subcontracted work

• Documentation and records management

• Communication with government (customers)

2.6.9.2 Quality Inspection

and Surveillance

The Contractor shall establish and maintain an inspection and surveillance system in accordance with the FAR Clause 52.246-4, INSPECTION OF SERVICES – FIXED PRICE, to ensure that the work performed conforms to the contract requirements. The Contractor shall document and maintain a file of all scheduled and performed inspections and surveillances, inspection and surveillance results, and dates and details of corrective and preventive actions. The quality inspection and surveillance file shall be the property of the Government and made available during the Government’s regular working hours. The file shall be submitted to the COR after completion/termination of the contract per Section F.

2.6.9.3 Quality Inspection

and Surveillance Report

The Contractor shall submit a copy of the Contractor Quality Inspection and Surveillance Report per Section F. The Contractor Quality Inspection and Surveillance Report shall include a narrative of events, a tabulated summary and results of the quality inspection and surveillance events performed, inspection-driven corrective actions taken and the results attained, and management process adjustments during the previous month. The

Management and Administration

0200000 - Management and Administration Spec Item Title Description

Government may adjust the frequency of the submittal based on the Contractor’s quality of performance.

2.6.9.4 Daily Work Report The Contractor shall develop and maintain a daily work report, this report will include all work completed, i.e. PMs, Service Calls, Task Orders, etc.

The report will list all buildings, work completed, and status of all received service calls. Complete Description of work completed and status of started but not completed.

2.6.10 Property

Management Plan

The Contractor shall establish and maintain a plan that meets the contract clause requirements of Specification Item 2.4, Government-Furnished Items, of this Annex. This plan shall identify the Contractor’s policies, procedures, and practices in receiving and performing physical inventories, key control, repairing and maintaining, preserving and protecting, and reporting the disposition of accepted government property in its possession. The Property Management Plan shall be submitted per Section F.

2.6.11 System and

Equipment Replacement

The Contractor shall maintain the integrity and performance of existing energy saving, water conservation or other sustainability design features of systems and equipment in the performance of repair and replacement work.

Except where otherwise specified, replacement components shall be of the same model/style or equivalent as the component being replaced. Substitutes for replacement components must be accepted by the KO prior to use. The KO will furnish available information for the existing systems and equipment.

2.7 Personnel

Requirements

The Contractor shall comply with the personnel requirements stated below:

2.7.1 Key Personnel The Contractor shall submit a List of Key Personnel and Qualifications per Section F. The Contractor shall provide any additional information requested by the KO or COR necessary to validate their qualifications.

The Contractor shall submit an Organizational Chart per Section F showing lines of authority of the key personnel and on-site supervisor(s) for this contract. The chart shall include names of personnel and their position title in this contract. As a minimum, include the PM, Quality Manager, SSHO, and on-site supervisor(s) and who they will report directly to for this contract.

The key personnel shall be revised as applicable for the contract. >>

The Contractor shall provide complete resumes for proposed substitutes and any additional information requested by the KO. Proposed substitutes shall have comparable qualifications to those of the persons being replaced. The KO will notify the Contractor within 15 calendar days after receipt of all required information of the consent on substitutions. No change in fixed unit prices may occur as a result of key personnel substitutions.

2.7.1.1 Project Manager

(PM)

The Contractor shall provide a PM and designated alternate, as applicable, who shall have full authority to act for the Contractor on all contract matters relating to this contract. The PM or alternate shall be on-site during the Government's regular working hours and shall be available on-site within one hour after the Government's regular working hours.

The PM shall have at least five years of experience in managing a workforce providing services on contracts of similar size, scope and complexity.

2.7.1.2 Quality Manager The Quality Manager or designated alternate shall report directly to a senior corporate official and shall not report directly to the Project Manager.

Management and Administration

0200000 - Management and Administration Spec Item Title Description

The Quality Manager or designated alternate shall have fulfilled the following pre-requisite training and experiences before being hired as the Quality Manager under this contract:

For contracts greater than $5M/year or for multi-function or regional contracts with significant performance risk. The Quality Manager or designated alternate shall have a current CMQ/OE certification and at least five years of experience in preparing and enforcing QMS programs on contracts of similar size, scope and complexity. The Quality Manager or designated alternate shall not be the same person as the SSHO.

2.7.1.2.1 Quality Control

Personnel

The Contractor shall provide Quality Control personnel whose primary duty and responsibility is to enforce the Contractor’s Quality Management System on this contract. The Quality Control personnel shall be on-site at all times when the Contractor is performing work during the Government's regular working hours. The Quality Control personnel shall report directly to the Quality Manager and shall not report directly to the Project Manager.

Quality Control personnel shall have fulfilled the following pre-requisite training and experiences before being hired as Quality Control under this contract:

Quality Control personnel shall meet or exceed the qualifications, technical knowledge and experience requirements specified for the personnel performing the work, which they will be inspecting, and have at least three years of experience in enforcing QMS programs on contracts of similar size, scope and complexity.

2.7.1.3 Site Safety and

Health Officer

(SSHO)

The SSHO must meet the requirements of EM 385-1-1 Section 1 and ensure that the requirements of 29 CFR 1926.16 are met for the project. Provide a Safety oversight team that includes a minimum of one Competent Person at each project site to function as the Site Safety and Health Officer (SSHO).

The SSHO or an equally-qualified Designated Representative/alternate shall be on-site at all times when work is being performed to implement and administer the Contractor's safety program and government-accepted Accident Prevention Plan. The SSHO's training, experience, and qualifications shall be as required by EM 385-1-1 paragraph 01.A.17, entitled SITE SAFETY AND HEALTH OFFICER (SSHO), and all associated sub-paragraphs.

A Competent Person shall be provided for all of the hazards identified in the Contractor's Safety and Health Program in accordance with the accepted Accident Prevention Plan, and shall be on-site at all times when the work that presents the hazards associated with their professional expertise is being performed.