24R2504 Amendment 0003.pdf
PDF 154 KB Posted
- Attached to
- DESIGN-BUILD (DB), G/ATOR SUPPORT FACILITIES, NAS OCEANA, DAM NECK ANNEX, VIRGINIA BEACH, VA
- Solicitation number
- N4008524R2504
About this file
This document is an amendment to a solicitation for a design-bid-build project to construct a steel framed building with a concrete foundation to serve as G/ATOR support facilities at NAS Oceana Dam Neck Annex in Virginia Beach, Virginia.
The amendment provides responses to eleven pre-proposal inquiries, revises the general requirements to change the project delivery method from design-build to design-bid-build, and incorporates specification sections and drawing revisions. The project is located within the MARFORRES area at Dam Neck and standard base access procedures apply. Proposals are due by December 18, 2023 at 2:00 pm EST. The Naval Facilities Engineering Command Mid-Atlantic is the contracting office for this opportunity to construct the support facilities.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
PAGE OF PAGES
1 2
2. AMENDMENT/MODIFICATION NO.
3. EFFECTIVE DATE
08-Dec-2023
4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY CODE 7. ADMINISTERED BY (If other than item 6) CODE
NAVFACSYSCOM MID-ATLANTIC
CONTRACTING CORE
9324 VIRGINIA AVENUE
NORFOLK VA 23511-3095
See Item 6
8. NAME AND ADDRESS OF CONT RACTOR (No., Street, County, State and Zip Code) X 9A. AMENDMENT OF SOLICITATION NO.
N40085-24-R-2504
X 9B. DATED (SEE ITEM 11)
03-Nov-2023
10A. MOD. OF CONT RACT /ORDER NO.
10B. DAT ED (SEE ITEM 13)
CODE FACILITY CODE
11. THIS ITEM ONLY APPLIES TO AMENDMENT S OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT
TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNT ING AND APPROPRIAT ION DAT A (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICAT IONS OF CONT RACTS/ORDERS.
IT MODIFIES THE CONT RACT /ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONT RACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONT RACT /ORDER IS MODIFIED TO REFLECT THE ADMINIST RAT IVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORT ANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
N40085-24-R-2504, DBB P101 G/ATOR Support Facilities
Contract POC: Angie Clifton, angela.j.clifton2.civ@us.navy.mil
SEE SF 30 BLOCK 14 CONTINUATION PAGE
PPI cutoff date is 8 December 2023.
Proposal due date is 18 December 2023 @ 2:00 pm EST.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONT RACTING OFFICER (Type or print)
TEL: EMAIL:
15B. CONT RACT OR/OFFEROR
(Signature of person authorized to sign)
15C. DATE SIGNED 16B. UNIT ED STATES OF AMERICA
BY
(Signature of Contracting Officer)
16C. DATE SIGNED
22-Nov-2023
EXCEPTION TO SF 30
STANDARD FORM 30 (Rev. 11/16) APPROVED BY OIRM 11-84 Prescribed by GSA
FAR (48 CFR) 53.243
N40085-24-R-2504
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
The following have been added by full text:
AMENDMENT 0003
This amendment is issued to incorporate the following:
1. Provide responses to Pre-Proposal Inquiries
2. Revise General Requirements in response to PPI #9
3. Incorporate Section 09 22 00 Supports for Plaster Gypsum Board (attached separately)
4. Incorporate two Drawing revisions referenced in Amendment 0002
a. NAVFAC Dwg No. 12847604 (attached separately)
b. NAVFAC Dwg No. 12847596 (attached separately)
1. Pre-Proposal Inquiries
PPI # Page Section Paragra ph
Question Response Posted on
Amend
No.
7 2 Amendment
PPI #1
and PPI
#4
Responses to Amendment
0002, questions 1 and 4 indicates that revised drawings will be provided to include missing details.
Please confirm and or provide revised drawings.
Attached with
Amendment 0003.
8 N/A N/A N/A The project site is located in the DEVGRU secured area of
Dam Neck. Will awarded contractor and subcontractors be required to obtain access through DEVGRU pass office and will escorts be required throughout the duration of this project?
Complex is
MARFORRES and not
DEVGRU. Standard base access procedures apply but access will be through the gate at the end of Birdneck Road and escorts will not be required.
9 1 11 00 1.2.1 General requirements list this project as a pre-engineered metal building, however spec sections indicated a custom structural steel building.
Could the building structure be modified to a pre-engineered steel building?
No, building should be steel framed as shown on the design drawings
10 N/A N/A N/A General requirements list this as a Design/Build project, however after reviewing the
This project no longer contains design/build elements and should be
N40085-24-R-2504 plans and specs we cannot determine which aspect of this will be design/build. We are requesting clarification on this.
bid as a design / bid / build.
11 PDF
05 40 00 1.4 Paragraph states to refer to specification section 09 22 00
Supports for Plaster and
Gypsum Board. This section does not exist in the specification manual. Please provide.
Specifications section will be provided.
2. Revise General Requirements
Location: Cover Page
From:
PROPOSED TASK ORDER: N40085-24-R-2504
DESIGN-BUILD (DB), G/ATOR SUPPORT FACILITIES, NAS OCEANA, DAM NECK
ANNEX, VIRGINIA BEACH, VA
To:
PROPOSED TASK ORDER: N40085-24-R-2504
DESIGN-BID-BUILD (DBB), G/ATOR SUPPORT FACILITIES, NAS OCEANA, DAM
NECK ANNEX, VIRGINIA BEACH, VA
Location: Page 2, Description of the Work
From:
This project constructs a steel framed Pre-Engineered Insulated Metal Building (PEMB) with a concrete foundation…
To:
This project constructs a steel framed building with a concrete foundation…