Attachment G - BLDG 7101-7102 Chillers Specification.pdf
PDF 26 MB Posted
- Solicitation number
- N4008523R2518
About this file
This document is an attachment to a solicitation for an Indefinite Delivery/Indefinite Quantity (IDIQ) Multiple Award Construction Contract (MACC) for Mechanical, Electrical, Plumbing, and Fire Protection Projects at Naval Station Great Lakes and NOSCs. The attachment provides specifications for replacing two chillers at Building 7101-7102, including requirements for demolition, equipment, installation, testing, and commissioning. Offerors are required to visit the procurement website to obtain full solicitation details. The solicitation seeks multiple awardees for an ordering period of five years and includes projects for repair, renovation, minor construction, and utilities work. The Naval Facilities Engineering Command is the contracting agency.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| MACC Site Visit 2nd.pdf | ||
| 23R2518 Amendment 0003.pdf | ||
| B7101-7102 as-builts.pdf | ||
| Amendment 0002.pdf | ||
| Site Visit Attendance Log.pdf | ||
| Attachment D - Past Performance Questionnaire.docx | DOCX document | |
| Attachment A - PPI Log Template.xlsx | XLSX spreadsheet | |
| Attachment B - PIEE Vendor Access Instructions.pdf | ||
| Attachment E - Price Proposal Form.docx | DOCX document | |
| Attachment C - Construction and Design Experience Project Data Sheet.docx | DOCX document | |
| 23R2518 Amendment 0001 - Rev Capacity to 50M.pdf | ||
| Attachment F - Site Visit Map.jpg | JPG image |
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Buildings 7101/7102
Replace Chillers & Cooling Tower
At the
Naval Station Great Lakes, Great Lakes, IL
Bldg 7101 eProject# 1627596 Bldg 7102 eProject# 1627595
Cooling Tower eProject# 1651208
SUBMITTED BY:
NAVFAC MID-ATLANTIC, PWD GREAT LAKES FEAD
310 Seabee Way, Building 1H Great Lakes, IL 60088-2814
PREPARED BY:
Design Manager: Trevor Parmley, PE, NAVFAC Mechanical Engineer: Kirk Brandys, PE, NAVFAC
Lead Engineer: Trevor Parmley, PE, NAVFAC
FINAL SUBMITTAL
Date: FEBRUARY 28, 2022
APPROVED BY:
For Commander, NAVFAC Mid-Atlantic Date: [Month Day, Year]
Bldgs 7101/7102 Replace Chillers & Cooling Tower
B7101 - WON: 1627596
B7102 - WON: 1627595
Tower – WON: 1651208
TABLE OF CONTENTS - Page 1
Table of Contents
Part 2 General Requirements
Part 3 Statement of Work / Project Program
Part 4 Minimum Materials, Engineering and Construction Requirements
Part 5 Prescriptive Specifications
Part 6 Attachments
Preface
This Request for Proposal (RFP) consists of five parts.
Part 2 contains general contract administrative and execution requirements including, but not limited to safety, design criteria & process, quality control, security, schedule, invoicing, temporary facilities, and design and construction oversight processes.
Part 3 lists the project requirements, specific scope items, and expected quality level above and beyond those outlined in Part 4.
Part 4 contains Performance Specifications and minimum quality requirements.
Part 5, prescriptive specifications, contains necessary edited UFGS. Typically the scheduling, ECMS, Sustainability and safety spec are included here.
Part 6 contains background project information, references, and other project-specific requirements.
REVISED: 28 FEB 2022
B7101 - WON: 1627596
PART 2 GENERAL REQUIREMENTS - Page 1
Part 2 General Requirements
PART 2
GENERAL REQUIREMENTS
TABLE OF CONTENTS
1/20
DIVISION 01 – GENERAL REQUIREMENTS
• 00 00 00 GENERAL REQUIREMENTS
• 01 11 00 SUMMARY OF WORK
• 01 14 00.05 20 WORK RESTRICTIONS
• 01 20 00.05 20 PRICE AND PAYMENT PROCEDURES
• 01 30 00.05 20 ADMINISTRATIVE REQUIREMENTS
• 01 31 19.05 20 POST AWARD MEETINGS
• 01 31 23.13 20 ELECTRONIC CONSTRUCTION AND FACILITY SUPPORT CONTRACT
MANAGEMENT SYSTEM
• 01 32 16.00 20 SMALL PROJECT CONSTRUCTION PROGRESS SCHEDULES
• 01 33 00.05 20 CONSTRUCTION SUBMITTAL PROCEDURES
• 01 33 10.05 20 DESIGN SUBMITTAL PROCEDURES
• 01 35 26.05 20 GOVERNMENT SAFETY REQUIREMENTS FOR DESIGN BUILD
• 01 45 00.05 20 DESIGN AND CONSTRUCTION QUALITY CONTROL
• 01 50 00.05 20 TEMPORARY FACILITIES AND CONTROLS
• 01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS
• 01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL
- - End of Part 2 Table of Contents - -
B7101 - WON: 1627596
PART 2 GENERAL REQUIREMENTS - Page 2
00 00 00 GENERAL REQUIREMENTS
1.1 Definitions
As used throughout the contract, the following terms have the meaning set forth below: Contracting Officer (KO): The individual designated to administer the contract. Throughout this contract this individual will be responsible and possess the authority to act on behalf of the Government with respect to the specific contract.
Contracting Officer Representative (COR): The individual designated by the Contracting Officer as the authorized representative of the Contracting Officer. The COR is responsible for monitoring performance and technical management of the effort required and should be contacted regarding questions or problems of a technical nature.
Contract: Contract or task order.
Contractor: The term Contractor refers to both the prime Contractor and all subcontractors, whether in contract with the Prime Contractor or other subcontractors at any tier, including the Designer of Record.
Designer of Record (DOR): Licensed architect/engineer working as subcontractor to or partner with prime Contractor who provides design for this contract.
Quality Control (QC): Contractor's system to control the quality of design, material, equipment and construction.
Quality Assurance (QA) Program: Government's program to evaluate the effectiveness of the Contractor's quality control. The Government's QA Program is not a substitute for the Contractor's QC Program.
Federal Holidays: New Year's Day, Martin Luther King Jr. Day, President's Day, Memorial Day, Independence Day; Labor Day, Columbus Day, Veterans Day, Thanksgiving Day, and Christmas Day.
1.2 Accessibility
Provide barrier-free design in accordance with UFC 1-200-01, DoD Building Code.
1.3 Changes
No oral statement by any person other than the Contracting Officer, as provided in the Federal Acquisition Regulation (FAR) clause 52.243-5 entitled, "CHANGES AND CHANGED CONDITIONS," will in any manner or degree modify or otherwise affect the terms of this contract.
1.4 No Waiver by the Government
The failure of the Government in any one or more instances to insist upon strict performance to any of the terms of this contract or to exercise any option herein conferred is not to be construed as a wavier or relinquishment to any extent of the right to assert or rely upon such terms or options on any future occasion.
1.5 Equitable Adjustments
a. Whenever the Contractor submits a claim for equitable adjustment under a clause which provides for equitable adjustment of the contract, such claim must include all types of adjustments in the total amounts to which the clause entitles the Contractor, including, but not limited to, adjustment arising out of delays or disruptions.
b. Except as the parties may otherwise expressly agree, the Contractor must be deemed to have
B7101 - WON: 1627596
PART 2 GENERAL REQUIREMENTS - Page 3 waived: (1) any adjustments to which he otherwise might be entitled under the clause where such claim fails to request such adjustments; and (2) any increase in the amount of equitable adjustments additional to those requested in its claim.
c. If required by the Contracting Officer, the Contractor agrees to execute a release, in form and substance satisfactory to the Contracting Officer, as part of the supplemental agreement setting forth the aforesaid equitable adjustment. The Contractor further agrees that such release will discharge the Government, including its officers, agents, and employees, from any further claims, including, but not limited to, further claims arising out of delays or disruptions caused by the aforesaid change.
1.6 Warranty
Warrant all materials and work for not less than one year after final acceptance of the work, except as otherwise indicated in this RFP. If required to provide remedial repair of previously installed work due to latent defect or unacceptable work performance, warrant the repaired work for one year after the completion and acceptance of the repair. For warranted items, furnish the manufacturer’s original written warranty accompanied by a copy of the supplier's receipt showing place of purchase, telephone number of supplier, address, delivery order number if applicable, and ticket number.
-- End of Section –
B7101 - WON: 1627596
PART 2 GENERAL REQUIREMENTS - Page 4
01 11 00 SUMMARY OF WORK
1.0 Protection of Government Property
Take special care to protect Government property. Return areas damaged as a result of construction under this contract to their original condition. In addition to FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements, perform the following:
a. Remove or alter existing work or facilities in such a manner as to prevent injury or damage to any portion of the existing work or facilities that remain.
b. Repair or replace portions of existing work altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.
c. Preserve the natural resources in accordance with the approved environmental protection plan prepared in accordance with UFGS 01 57 19 Temporary Environmental Controls.
1.1 Government Furnished Material and Equipment
If applicable, the Government will furnish the materials and equipment for installation by the Contractor pursuant to contract clause FAR 52.245-2, Government Property (Fixed Price Contracts). Notify the Contracting Officer in writing at least 15 calendar days before the materials and equipment are required.
Pick up materials and equipment no later than 30 calendar days after such date. When materials and equipment are not picked up by the 30th day, the Contractor will be charged for storage at the prevailing rate. The Contracting Officer will specify the location of materials and equipment and the delivery location.
B7101 - WON: 1627596
PART 2 GENERAL REQUIREMENTS - Page 5
01 14 00.05 20 WORK RESTRICTIONS
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. Code (USC)
10 USC 6011 Navy Regulations
8 USC 1101 Definitions
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation; submittals not having a "G" designation are for Contractor Quality Control approval. Submittals with an "S" are for inclusion in the Sustainability Notebook, in conformance with Section 01 33 29.05 20 SUSTAINABILITY REPORTING FOR DESIGN-BUILD.
Submit the following in accordance with Section 01 33 00.05 20 CONSTRUCTION SUBMITTAL PROCEDURES and 01 33 10.05 20 DESIGN SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
List Of Contact Personnel; G
Contractor Regulations; G
Transportation Of Personnel, Materials, And Equipment; G
Purchase Orders; G
List of Contact Personnel; G
Personnel List; G
Vehicle List; G
Statement of Acknowledgement Form SF 1413; G
1.3 SPECIAL SCHEDULING REQUIREMENTS
a. Have materials, equipment, and personnel required to perform the work at the site prior to the commencement of the work.
b. The building will remain in operation during the entire construction period. Conduct operations so as to cause the least possible interference with normal operations of the activity.
c. Permission to interrupt any Activity roads, railroads, or utility service must be requested in writing a minimum of 15 calendar days prior to the desired date of interruption.
d. The work under this contract requires special attention to the scheduling and conduct of the work in connection with existing operations. Identify on the construction schedule each factor which constitutes a potential interruption to operations.
REVISED: 28 FEB 2022
file://NAEAMECHFS101V.NADSUSEA.NADS.NAVY.MIL/NAVFAC2$/GRLK/NAVFAC%20MIDWEST/OPERATIONS/PWD%20Glakes/FEAD/Project%20Folder/01_PMEB_DESIGN/02_Project_Templates/Word/01%2033%2029.05%2020.doc file://NAEAMECHFS101V.NADSUSEA.NADS.NAVY.MIL/NAVFAC2$/GRLK/NAVFAC%20MIDWEST/OPERATIONS/PWD%20Glakes/FEAD/Project%20Folder/01_PMEB_DESIGN/02_Project_Templates/Word/01%2033%2000.05%2020.doc file://NAEAMECHFS101V.NADSUSEA.NADS.NAVY.MIL/NAVFAC2$/GRLK/NAVFAC%20MIDWEST/OPERATIONS/PWD%20Glakes/FEAD/Project%20Folder/01_PMEB_DESIGN/02_Project_Templates/Word/01%2033%2010.05%2020.doc
B7101 - WON: 1627596
PART 2 GENERAL REQUIREMENTS - Page 6
The following conditions apply:
(1) Drill Weekends
f. NMCI Contractor Access: The NMCI Contractor must be allowed access to the facility towards the end of construction (finishes 90 percent complete, rough-in 100 percent complete, Inside Plant (ISP)/Outside Plant (OSP) infrastructure in place) to provide equipment in the telecommunications rooms and make final connections. The Contractor will be required to coordinate their efforts with the NMCI contractor to facilitate joint use of building spaces during the final phases of construction and work the coordination effort into the construction schedule. Requirements for NMCI are specified in Part 4, D50 ELECTRICAL and G40 SITE ELECTRICAL UTILITIES.
1.4 CONTRACTOR ACCESS AND USE OF PREMISES
1.4.1 Activity Regulations
Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. To minimize traffic congestion, delivery of materials shall be outside of peak traffic hours (6:30 to 8:00 a.m. and 3:30 to 5:00 p.m.) unless otherwise approved by the Contracting Officer. Wear hard hats in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry.
Mark Contractor equipment for identification.
1.4.1.1 Subcontractors and Personnel Contacts
Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.
1.4.1.2 Identification Badges and Installation Access
Application for and use of badges will be as directed. Obtain access to the installation by participating in the mandatory Defense Biometric Identification System (DBIDS).
The Defense Biometric Identification System (DBIDS) increases installation security and communications by receiving frequent database updates on changes to personnel/credential status, law enforcement warrants, lost/stolen cards, and force protection conditions. The system provides a continuous vetting anytime the DBIDS card is scanned at an installation entry point.
To obtain a DBIDS credential, complete and submit to the base sponsor a minimum of 15 days in advance a SECNAV FORM 5512/1 for each individual requiring access to the base. There is no cost to obtain a DBIDS credential.
Upon completion of the background check, the Visitor Control Center representative will complete the DBIDS enrollment process, which includes your photo, finger prints, base restrictions, and other assessments prior to issuing the DBIDS credential.
Under DBIDS, no commercial vehicle inspection is required, other than for Random Anti-Terrorism Measures (RAM) or in the case of an elevation of Force Protection Conditions (FPCON).
Immediately report instances of lost or stolen DBIDS credentials to the Contracting Officer.
See DBIDS Standard Operating Procedures Attachment for further information and requirements.
B7101 - WON: 1627596
PART 2 GENERAL REQUIREMENTS - Page 7
1.4.1.7 No Smoking Policy
Smoking is prohibited within and outside of all buildings on installation, except in designated smoking areas.
This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines.
The Contracting Officer will identify designated smoking areas.
1.4.5 Working Hours
Regular working hours must consist of an 8 1/2 hour period, between 7 a.m. and 4 p.m., Monday through Friday, excluding Government holidays.
1.4.6 Work Outside Regular Hours
Work outside regular working hours requires Contracting Officer approval. Make application 15 calendar days prior to such work to allow arrangements to be made by the Government, giving the specific dates, hours, location, type of work to be performed, contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During periods of darkness, the different parts of the work must be lighted in a manner approved by the Contracting Officer. Make utility cutovers after normal working hours or on Saturdays, Sundays, and Government holidays unless directed otherwise.
1.4.8 Occupied and Existing Buildings
The Contractor will be working in an existing building and around existing buildings which are occupied.
The existing buildings and their contents must be kept secure at all times. Provide temporary closures as required to maintain security as directed by the Contracting Officer.
Provide dust covers or protective enclosures to protect existing work that remains and Government material located throughout the building during the construction period.
Relocate movable furniture as required to perform the work, protect the furniture, and replace the furniture in their original locations upon completion of the work. Leave attached equipment in place, and protect them against damage, or temporarily disconnect, relocate, protect, and reinstall them at the completion of the work.
1.4.9 Utility Cutovers and Interruptions
a. Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and Government holidays. Conform to procedures required in the paragraph WORK OUTSIDE REGULAR
HOURS.
b. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.
c. Interruption to water, sanitary sewer, storm sewer, telephone service, electric service, air conditioning, heating, fire alarm, compressed air, are considered utility cutovers pursuant to the paragraph WORK
OUTSIDE REGULAR HOURS.
d. Operation of Station Utilities: The Contractor must not operate nor disturb the setting of control devices in the station utilities system, including water, sewer, electrical, and steam services. The Government will operate the control devices as required for normal conduct of the work. The Contractor must notify the Contracting Officer giving reasonable advance notice when such operation is required.
1.4.9.1 Location of Underground Utilities
B7101 - WON: 1627596
PART 2 GENERAL REQUIREMENTS - Page 8
Obtain digging permits prior to start of excavation by contacting the Contracting Officer 15 calendar days in advance. Scan the construction site with electromagnetic or sonic equipment, and mark the surface of the ground or paved surface where existing underground utilities or utilities encased in pier structures are discovered. Verify the elevations of existing piping, utilities, and any type of underground or encased obstruction not indicated to be specified or removed but indicated or discovered during scanning in locations to be traversed by piping, ducts, and other work to be conducted or installed.
Notification Prior to Excavation: Notify the Contracting Officer at least 15 days prior to starting excavation work.
Contact Miss Utility 48 hours prior to excavating. Contractor is responsible for marking all utilities not marked by Miss Utility.
1.5 SECURITY REQUIREMENTS
Contract Clause "FAR 52.204-2, Security Requirements and Alternate II," "FAC 5252.236-9301, Special Working Conditions and Entry to Work Area."
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
B7101 - WON: 1627596
PART 2 GENERAL REQUIREMENTS - Page 9
01 20 00.05 20 PRICE AND PAYMENT PROCEDURES
1.1 Schedule of Prices
Submit a schedule of prices for approval on forms furnished by the Government. The initial schedule of prices may be preliminary for construction activities until the design is developed. Include a detailed breakdown of the contract price with quantities and unit prices for each work activity or definable feature of work. Include general conditions, profit, and overhead costs within the unit prices. Break down into design and construction is required. The Contractor may invoice for bonds once the Government has approved the bonds, however, no other requests for payment will be processed without an approved schedule of prices and baseline schedule.
1.2 Contractor Invoices
Contractor requests for payment must conform and will be processed in accordance with the requirements of FAR 52.232-5 and FAR 52.232-27.
a. Content of Invoice: Requests for payment in accordance with the terms of the contract must consist of the following: (If NFAS Clause 5252.232-9301 is present in the contract, documents must be provided as attachments in Wide Area Workflow (WAWF). The maximum size limit per attachment is less than 2 megabytes, but there are no limits on the number of attachments. If a document cannot be attached to WAWF due to system or size restrictions it must be provided as instructed by the contracting officer). If NFAS Clause 5252.232.9301 is not present in the contract, follow the invoicing instructions provided in the contract.
1. Contractor's Invoice on NAVFAC Form 7300/30, must show, in summary form, the basis for arriving at the amount of the invoice.
2. Contractor's Estimate for Voucher/ Contract Performance Statement on NAVFAC Form
7300/31 furnished by the Government, showing in detail: the estimated cost, percentage of completion, and value of completed performance for each of the construction categories stated in this contract. Use NAVFAC LANT Form 4-330/110 (New 7/84) on NAVFAC Atlantic contracts when a Monthly Estimate for Voucher is required.
3. Affidavit to accompany invoice (LANTDIV NORVA Form 4-4235/4 (Rev. 5/81)).
4. Updated copy of submittal register.
5. Updated copy of progress schedule. Furnish as specified in "FAR 52.236-15, Schedules for Construction Contracts."
6. Contractor Safety Self Evaluation Checklist (original)
7. Final release (for final payment only). Final invoice must be accompanied by the certification required by DFARS 252.247.7023 TRANSPORTATION OF SUPPLIES BY SEA, and the Contractor's Final Release.
i. Payment:
1. Payment will be made on Contractor's submission of itemized requests and will be subject to reduction for overpayments or increased for underpayments from previous payments.
The Government may withhold payment or reduce payments for the following:
a. Defects in material or workmanship.
b. Claims the Government may have against the Contractor under or in connection with this contract.
c. Contractor's failure to submit an updated schedule.
d. Payroll violations.
e. Unless otherwise adjusted, repayment to the Government upon demand for overpayments made to the Contractor.
2. Payments may be made for materials, stored off construction sites, under the following conditions:
a. Materials to be considered for progress payment prior to installation must be located and
B7101 - WON: 1627596
PART 2 GENERAL REQUIREMENTS - Page 10 stored within 20 miles by streets and roads of the construction site.
b. Materials adequately insured and protected from theft and exposure. Payment requests for offsite materials must include the consent of surety.
c. Materials not susceptible to deterioration or physical damage in storage or in transit to the job site are acceptable for progress payments. Items such as steel, machinery, pipe and fittings and electrical cable are acceptable, but items such as gypsum board; glass, insulation and wall covering are not.
d. Materials in transit to the job or storage site are not acceptable for payment.
e. Conditions specified in FAR 52.232-5(b) Payments under Fixed Price Construction
Contracts.
1.3 Budget Management
The Contractor must be responsible for budget management throughout the entire project. It is the intent of the Government to partner with the Contractor to maximize project value while strictly controlling contract modifications and maintaining overall fiscal control. When required, develop a Budget Management System for each phase of the design.
This project requires a Budget Management System be developed and maintained. The Budget Management System must represent major portions of the work such as HVAC, site work, and exterior skin.
The purpose of budget management is to balance scope and value during critical project design decisions.
Update the budget management status at regular intervals during design, at a minimum with design submittals, for review by and discussion with the COR.
B7101 - WON: 1627596
PART 2 GENERAL REQUIREMENTS - Page 11
01 30 00.05 20 ADMINISTRATIVE REQUIREMENTS
1.1 Supervision
The Contractor must have a superintendent fluent in English [and host nation language] on the job site during working hours.
The Superintendent must have a minimum of 5 years of experience as a Superintendent on previous projects of similar size and complexity. The Superintendent may [not] serve as the Site Safety and Health Officer. Provide a Superintendent Resume for the proposed on-site Project Superintendent describing experience with references and qualifications to the Contracting Officer for approval. The Contracting Officer reserves the right to interview the proposed on-site Project Superintendent at any time in order to verify the submitted qualifications.
1.2 Required Insurance
Within 15 calendar days after award, furnish the Contracting Officer a Certificate of Insurance as evidence of the following insurance coverage amounts not less than the amount specified below in accordance with FAR Clause 52.228-5, Insurance Work On A Government Installation:
a. Comprehensive General Liability: $500,000 per occurrence.
b. Automobile Liability: $200,000 per person, $500,000 per occurrence for bodily injury; $20,000 per occurrence for property damage.
c. Worker's Compensation: As required by Federal and State Worker's compensation and occupational disease and other laws.
d. Employer's Liability Coverage: $100,000, except in states where worker's compensation may not be written by private carriers.
e. Others as required by state law.
f. Above insurance coverages are to extend to Contractor personnel operating Government owned equipment and vehicles.
g. The Certificate of Insurance must provide for 30 calendar days written notice to the Contracting Officer by the insurance company prior to cancellation or material change in policy coverage.
For projects which require removal of asbestos containing materials the Asbestos Contractor or Subcontractor, as the case may be is required to provide occurrence-based liability insurance with asbestos coverages in an amount not less than $1,000,000 and must name the Government and Private Qualified Person (PQP) as additional insureds.
B7101 - WON: 1627596
PART 2 GENERAL REQUIREMENTS - Page 12
01 31 19.05 20 POST AWARD MEETINGS
1.1 Post Award Kick-off Meeting (PAK)
Prior to commencement of design, and within 21 calendar days of award, meet with representatives of the Contracting Officer, installation and client to present the concept design for discussion and acceptance.
The project team will develop a mutual understanding relative to the approved proposal, safety program, environmental permits and requirements, quality control procedures, and design and construction schedule.
During the meeting, Contractor must propose and gain acceptance for any critical path work activities requiring advance submittal and approval. If the contract includes work on any fire protection system, including fire alarm and mass notification systems, the Contractor and the appropriate DOR must meet with the NAVFAC Fire Protection Engineer (FPE) to establish clear expectations of fire protection requirements of the project.
The Contractor's key personnel must attend including the Project Manager, Superintendent, Site Safety and Health officer, Construction Quality (CQ) Manager, Design Quality Control (DQC) Manager, Designer of Record (DOR), and major subcontractors.
1.2 Partnering
The Contracting Officer will organize initial and follow-up informal partnering sessions with key personnel of the project team, including Contractor's personnel and Government personnel. The initial session may be a part of the PAK Meeting. The initial partnering session will be conducted and facilitated using electronic media provided by the Contracting Officer. Follow-on partnering sessions will be conducted every 6 months or less frequent as determined by the Contracting Officer.
1.3 Pre-Construction Conference
Prior to construction or demolition, meet with representatives of the Contracting Officer to discuss and develop mutual understanding relative to administration of the safety programs, environmental issues, safety of building occupants and surrounding area, hazardous materials, waste disposal, construction QC procedures, construction schedule, labor provisions and other construction phase contract procedures.
1.4 NAVFAC Red Zone Meeting (NRZ)
Participate in NAVFAC Red Zone (NRZ) meetings with the Contracting Officer to identify strategies to ensure the project is carried to expeditious closure and turnover to the client. The Contracting Officer will provide a template to the Contractor to use to develop a NRZ Checklist. Revise the template to include critical work activities and their planned completion dates based on the project scope of work and schedule.
Discuss any progress changes with items listed on the NRZ Checklist during regularly scheduled NRZ Meetings beginning approximately at 75% stage of construction prior to project completion.
B7101 - WON: 1627596
PART 2 GENERAL REQUIREMENTS - Page 13
01 31 23.13 20 ELECTRONIC CONSTRUCTION AND FACILITY SUPPORT
CONTRACT MANAGEMENT SYSTEM
See UFGS Section 01 31 23.13 20 Electronic Construction and Facility Support Contract Management System in Part 5 of this RFP for requirements for the use of eCMS.
B7101 - WON: 1627596
PART 2 GENERAL REQUIREMENTS - Page 14
01 32 16.00 20 SMALL PROJECT CONSTRUCTION PROGRESS SCHEDULES
Develop and implement a design and construction schedule in accordance with UFGS 01 32 16.00 20 in Part 5 of this RFP.
B7101 - WON: 1627596
PART 2 GENERAL REQUIREMENTS - Page 15
01 33 00.05 20 CONSTRUCTION SUBMITTAL PROCEDURES
1.1 Construction submittals are to be Contractor-approved, except those listed below:
a. DOR Approval required for:
1. Fire Protection related submittals
2. Earthwork and Geotechnical submittals
3. All components of the roof and exterior wall.
4. HVAC Testing, Adjusting, and Balancing.
5. SID submittals and Furnishings, fixtures, and equipment packages for review and approval by NAVFAC Interior Designer
b. Government Approval required for:
1. Government approved submittals as required by UFGS specification sections edited by the DOR.
2. Substations
3. Transformers
4. Medium Voltaqe Switchgear
5. Medium Voltage Cable
6. 400-Hz Converters
7. Emergency Generators
8. Automatic Transfer Switches
9. Uninterruptible Power Supplies
10. Electronic Security Systems
11. Section 23 09 13 and 23 09 23.02
12. Section 23 05 93
1.2 Submit the following construction submittals, approved by the DOR, to the Government for surveillance:
a. Submit fire protection related submittals pertaining to spray-applied fire proofing and fire stopping, exterior fire alarm reporting systems, interior fire alarm & detection systems, and fire suppression systems including fire pumps and standpipe systems.
b. Submit geotechnical related submittals pertaining to the soils investigations (reports and soils analysis), foundations (shallow and deep), pavements structure design, test pile and production pile testing and installation.
c. Submit roofing submittals pertaining to materials and systems used to make up the roof system.
d. Submit HVAC Testing, Adjusting, and Balancing required submittals.
e. Submit telecommunications shop drawings for coordination with the NMCI Contractor. Note: For the purpose of this document, the term "NMCI" is used to reference the network provided for use by the Navy and Marine Corps; the terms Continuation of Service Contract (COSC) and Next Generation Enterprise Network (NGEN) will be used to reference the contract between the government and the Contractor providing the NMCI network service.
f. Submit Performance Verification and Acceptance Testing required by IBC or this RFP.
g. Submit all Interim Special Inspection Reports on a bi-weekly basis until work requiring special inspections is complete. Submit all Structural Observation Reports and the Final Report of IBC Special Inspections.
B7101 - WON: 1627596
PART 2 GENERAL REQUIREMENTS - Page 16
h. For any pre-engineered buildings, submit shop drawings showing engineering data and complete building drawings, signed and sealed by a registered professional engineer.
i. Comply with sustainability submittals per UFGS section 01 33 29.05 20 Sustainability Reporting for
Design-Build included in Part 5 of this RFP.
j. Submit FF&E submittals to NAVFAC Interior Designer for review and approval.
k. Submit Structural Shop Drawings and structural product data.
1.3 Construction Submittal Process
Provide to the Government submittals as listed. See Section 01 33 10.05 20 "Design Procedures" for specific design and construction submittal format and approval and surveillance requirements. Design drawings may be prepared more like shop drawings to minimize construction submittals after final designs are approved. Therefore, the Contractor is encouraged to prepare and submit with the design drawings, appropriate connection, fabrication, layout, and product specific drawings.
a. QC Plan, prior to Design/Construction (may be phased).
b. Construction submittals, prior to construction, approved in accordance with QC Plan, the DOR or QC Specialist is the approving authority for submittals unless otherwise indicated.
c. Sustainability Action Plan (and Sustainability Notebook when required) in accordance with 01 33
29.05 20 Sustainability Reporting for Design-Build.
d. DOR-approved construction submittals identifiedfor Government surveillance (typically Fire Protection system and Life Safety submittals). Stamp the submittals "FOR SURVEILLANCE ONLY." Submit Surveillance submittals to the Governmentprior to starting work for that item.
Submittals required for surveillance will be returned only if corrective actions are required.
e. Safety Data Sheets (SDS) as applicable.
f. Baseline Schedule: due prior to PAK.
g. Environmental Protection Plan, prior to start of the work.
h. Contractor Safety Self-Evaluation Checklist.
i. Accident Reports - submit if incidence occurs.
j. Accident Prevention Plan and Activity Hazard Analysis: Submit prior to construction.
k. Schedule of Prices, initial due 21 calendar days after award and a detailed due prior to construction.
l. Record Drawings, due at Beneficial Occupancy
m. Operation and Maintenance Information: Due prior to testing as applicable, no later than 30 calendar days before Beneficial Occupancy.
n. Licenses and Permits: Per this section and Part 4.
o. Completed High Performance and Sustainable Building (HPSB) compliance checklists in accordance with UFC 1-200-02, High Performance and Sustainable Building Requirements and
B7101 - WON: 1627596
PART 2 GENERAL REQUIREMENTS - Page 17
UFGS Section 01 33 29.05 20 Sustainability Reporting for Design-Build. Attach completed HPSB Checklist to Interim DD 1354.
p. DD Form 1354:
Prepare a Draft and Interim DD Form 1354, TRANSFER AND ACCEPTANCE OF MILITARY REAL PROPERTY, in accordance with UFC 1-300-08. Coordinate the identification of appropriate asset construction categories with the Contracting Officer and the Real Property Accounting Officer.
1) Draft DD Form 1354. DOR must determine applicable real property assets broken out by construction categories and submit a "Draft DD Form 1354" for Government approval as a part of the Design Analysis included with the Prefinal Design submittal. "Draft DD Form 1354" must include all quantities and units of measure, but does not require cost breakdown. The Real Property Accountable Officer (RPAO)will provide the first draft of the DD1354 to the contractor with RPUIDs and CCNS on it.
2) Interim DD Form 1354. Contractor must coordinate with the DOR and update the Draft DD Form 1354 submission to include any additional assets, improvements, or alterations that occurred during construction. Use the Draft DD Form 1354 [and the UFGS Section 01 20 00.05 20, Price and Payment Procedures] to identify costs. The costs and quantities must align with the RPUID and unit of measures listed on the RPAO's draft 1354. Submit the final draft Interim DD Form 1354 to the Government for approval 30 days prior to the Beneficial Occupancy Date (BOD). If modifications to the Interim DD Form 1354 are required by the Government, the corrected version must be submitted prior to the BOD.
3) When documenting demolition work, the DD Form 1354 must list the quantitative data associated with this work as a negative value to show the cost should be deleted from the Navy asset data store. Coordinate with the Installation Real Property POC to assist in determining the negative value for demolition work. There are two ways to account for the demolition portion of the project and to document the reduction of real property: (1) attach an Authorization for Demolition form 18 (Service-specific) to the DD Form 1354 to document category codes and quantities of demolished real property. These should be listed separately from constructed/transferred item numbers; or, (2) indicate, as additional DD Form 1354 item numbers, all demolished real property facility numbers and category codes using negative numbers (shown in parenthesis) for units of measure, and in block 18 indicate N/A for costs. Disposal cost within the footprint of the project is added into total construction cost of new facility prompting the demolition.
q. Construction Submittals:
1) In addition to the design submittals noted in Section 01 33 10.05 20, construction submittals will be required. The list of required submittals will be generated from the Contractor-prepared specifications and indicated in the submittal register.
2) Shop drawing submissions will be governed by UFGS 01 33 00.05 20 Construction Submittal Procedures, available on the Whole Building Design website (www.wbdg.org ).
Contractor must assume a 15 day review period, and provide 3 hard copies of all submittals (in addition to electronic submittals) to be submitted to FEAD.
1.4 Operations and Maintenace Information (OMSI)
Deliverable FEAD/ ROICC IPT PWO USER
1 Quality Control Plan 2 Material Safety Data Sheets http://www.wbdg.org/
B7101 - WON: 1627596
PART 2 GENERAL REQUIREMENTS - Page 18
3 Design/Construction Schedule 4 Waste Management Plan 5 Safety and Health Plan 6 Schedule of Prices 7 Budget Management Summary 8 Record Drawings 9 Operation and Maintenance Information 10 Licenses and Permits 11 Badge Requests 12 Statement of Acknowledgement SF 1413 13 Demolition and Work Plan 14 Design Development Docs 15 Final Design Docs 16 Submittal Register 17 Waste Management Opportunity Assessment Form 18 Performance/Payment Bonds 19 Environmental Protection Plan 20 Certificates of Insurance 21 DD Form 1354 22 Sustainability Action Plan 23 Sustainability Notebook
24 NAVFAC High Performance and Sustainable Building (HPSB) Checklist
1.5 Licenses and Permits
Obtain all appointments, licenses, and permits required to perform work under this contract at no additional expense to the Government. See "Permits Record of Decision" (PROD) form for list of permits. Comply with all applicable federal, state, and local laws, and base regulations and procedures. Provide evidence of such permits and licenses to the Contracting Officer before work commences and at other times as requested by the Contracting Officer (see FAR 52.236-7, Permits and Responsibilities). Coordinate permit applications with Navy or local environmental office.
The contractor must submit a complete PROD form with the first design submittal package. A blank PROD form can be obtained from the NAVFAC Design-Build website at the following link http://www.wbdg.org/FFC/NAVFAC/NDBM/ST/PROD_Form.doc . Contractor must determine correct permit fees and pay said fees. Copies of all permits, permit applications, and the completed PROD form must be forwarded to the Government's Civil Reviewer and Environmental Reviewer.
Contractor is exclusively responsible for his full compliance with patent laws and must affirm that the company is licensed to use equipment and processes the company employs in this project.
1.6 Record Drawings
http://www.wbdg.org/FFC/NAVFAC/NDBM/ST/PROD_Form.doc
B7101 - WON: 1627596
PART 2 GENERAL REQUIREMENTS - Page 19
The as-built modifications must be accomplished by electronic drafting methods on the Contractor-originated DWG design drawings to create a complete set of record drawings. For each record drawing, provide CAD drawing identical to signed Contractor-originated PDF drawing that incorporate modifications to the as-built conditions. After all as-built conditions are recorded on the DWG files, produce a PDF file of each individual record drawing in conformance with FC 1-300-09N. Electronic signatures are not required on record drawings.
B7101 - WON: 1627596
PART 2 GENERAL REQUIREMENTS - Page 20
01 33 10.05 20 DESIGN SUBMITTAL PROCEDURES
1.1 Summary
This section includes requirements for contractor-originated design documents and design submittals.
1.2 Reference Standards
This RFP references published standards, the titles of which can be found in the Unified Master Reference List (UMRL) on the Whole Building Design Guide at the Unified Facilities Guide Specification (UFGS) Website. The publications referenced form a part of this specification to the extent referenced.
The advisory provisions of all codes, requirements, and standards are mandatory; substitute words such as "must" or "required" for words such as "shall", "should", "may", or "recommended," wherever they appear.
The results of these wording substitutions incorporate these code and standard statements as requirements. Reference to the "authority having jurisdiction" is interpreted to mean Contracting Officer or Contracting Officer Representative. Comply with the required and advisory portions of the current edition of the standard at the time of contract solicitation.
Provide work in compliance with the following design standards and codes, as a minimum. Government standards listed in this RFP take precedence over industry standards. The following list of codes and standards is not comprehensive and is augmented by other codes and standards referenced and cross-referenced in the RFP. Refer to Parts 3 and 4 for specific requirements within other UFC's.
a. U.S. Department of Defense (DoD) Unified Facilities Criteria (UFC)
UFC 1-200-01
DoD Building Code (General Building Requirements)
UFC 1-200-02
High Performance and Sustainable Building Requirements
UFC 1-300-08
Criteria for Transfer and Acceptance of DoD Real Property
FC 1-300-09N
Navy and Marine Corps Design Procedures
UFC 3-560-01
Electrical Safety, O&M
UFC 3-600-01
Fire Protection Engineering
UFC 3-810-01N
Navy and Marine Corps Environmental Engineering for Facility Construction
b. UFC 1-200-01
UFC 1-200-01 DoD Building Code is a hub document that provides general building requirements and references other critical UFCs. A reference to UFC 1-200-01 in the RFP document requires compliance with the Tri-Service Core UFCs. Refer to the UFC 1-200-01 for a complete list of all applicable Tri-Service Core UFCs at website location
B7101 - WON: 1627596
PART 2 GENERAL REQUIREMENTS - Page 21 http://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc . Contractor-originated design documents must provide a project design that complies with the Request For Proposal (RFP), FC 1-300-09N, UFC 1-200-01, UFC 3-810-01N, the Core UFCs, and other UFC's listed above.
1.3 Design Requirements
a. Provide design documents that include basis of design, design drawings and design specifications, reports and submittal register in accordance with FC 1-300-09N Navy and Marine Corps Design Procedures.
b. Design is the work necessary to ensure functionality, quality, and safety for critical facets of the project. Special coordination requirements such as for phone, LAN and cable, are included herein.
c. Part 3 contains the project description, functional and performance requirements, scope items, and expected quality levels that exceed Part 4. Part 4 identifies design criteria, verification requirements, and performance and quality requirements of products.
d. Provide professional registration and design signing and stamping requirements per requirements of FC 1-300-09N, Design Procedures. Interior Designers must be NCIDQ certified per UFC 3- 120-10 Interior Design. The design effort must be overseen by a Design Quality Control (DQC) Manager who will ensure that the design meets the requirements of this RFP. The DQC Manager will prepare a DQC Plan describing how the design process will ensure conformance to the RFP.
e. Provide a Contractor-originated design specification that in conjunction with the drawings, demonstrates compliance with requirements of the RFP. The specified products, materials, systems, and equipment that are approved by the DOR; submitted to the Government by the Contractor; and reviewed by the Contracting Officer must be used to construct the project.
Prescriptive specification sections contained in RFP Part 5 must become a part of the Contractor-originated specification without modification. The Contractor must prepare design specifications that include a UFGS specification for each product, material, or system on the project. Organize the specifications using Construction Specification Institute (CSI) MasterformatTM . Provide project specifications to include the following:
1. Provide the specification cover sheet with the professional seal and signature of the lead licensed architect or engineer of the project design team. Indicate the Contractor's company name and address on the specification coversheet.
2. Table of contents for entire specification.
3. Individual UFGS specification sections for each product, material, and system required by the RFP. Edit UFGS sections in accordance with RFP Part 3 and 4.
4. If proprietary information is provided or required, include a coversheets for the product, material, or system information that is being proprietarily specified. This information must comply with the related UFGS specification.
5. If proprietary information is provided or required, include highlighted and annotated Catalog Cuts, Manufacturer's Product Data, Tests, Certificates, Manufactures information and letters for each product, material, or system that is being proprietary specified.
6. Coordinated submittal register for all products, materials and systems with each design submittal. Provide a cumulative register that identifies the design and construction submittals required by each design package along with previous design submittals. The DOR must assist in developing the submittal register by determining which submittal items are required to be approved by the DOR. Complete all fields in the final submittal register in order to obtain Government approval of the final design.
l. Identification of Manufacturer's Product Data Used as Specifications: Provide complete and legible catalog cut sheets, product data, installation instructions, operation and maintenance instructions, warranty, and certifications for products and equipment for which final material and http://www.wbdg.org/ffc/dod/unified-facilities-criteria-ufc
B7101 - WON: 1627596
PART 2 GENERAL REQUIREMENTS - Page 22 equipment choices have been made. Indicate, by prominent notation, each product that is being submitted including optional manufacturer's features, and indicate where the product data shows compliance with the RFP. Attach this product data to the end of the applicable UFGS specification section that specifies the material.
m. Specification Software: Submit the final specification source files in either MS Word or
SpecsIntact with a Submittal Register generated in Excel or SpecsIntact.
n. Meet sustainability requirements per UFC 1-200-02 High Performance and Sustainable Building requirements and UFGS Section 01 33 29.05 20 Sustainability Reporting for Design-Build. UFGS Section 01 33 29.05 20 Sustainability Reporting for Design-Build must be included in Part 5 of all project RFPs.
o. Submit design drawings or sketches, calculations and manufacturer's data to demonstrate compliance with contract requirements. The Contractor is encouraged to prepare design drawings more like shop drawings to minimize construction submittals.
p. Provide[hard and electronic copies of design submittal package to the following reviewers 21 calendar days to the in-progress review meeting. [All hard copy submittals must be on minimum 30% postconsumer fiber paper, and, when 11x17 or smaller, double-sided.
Deliverable FEAD/ROICC IPT PWO USER Design Development Basis of Design 2 Half-size Drawings or Sketches 2 Outline Specifications 2 Finish Documentation Color Board _____ _____ _____ _____ Calculations 2 Final Design Basis of Design 2 Half-size Drawings or Sketches 2 Specifications and Manufacturer's Cut Sheets 2 Finish Documentation Color Board _____ _____ _____ _____ Quality Control Review - Drawings and Specifications 2 Completed Project Information Form (PIF) including Bid Schedule Structural Interior Design (SID) Preliminary FF&E Calculations 2 Draft DD Form 1354 Facility Recognition Plaque - Design and Specification
q. The final design submittal must be professionally signed and sealed by the DOR and forwarded to the Contracting Officer prior to the start of construction. Separated final design packages will only be considered for Government review and approval during the Post Award Kick-off Meeting.
r. Submit Draft DD Form 1354. See section 01 33 00.05 20 for detailed requirements.
B7101 - WON: 1627596
PART 2 GENERAL REQUIREMENTS - Page 23
1.4 Order of Precedence
The contract consists of the solicitation, the approved proposal, and the final design. In the event of conflict or inconsistency between any of the below described portions of the conformed contract, precedence must be given in the following order:
a. Any portions of the proposal or final design that exceed the requirements of the solicitation.
1. Any portion of the proposal that exceeds the final design.
2. Any portion of the final design that exceeds the proposal.
3. Where portions within either the proposal or the final design conflict, the portion that most exceeds the requirements of the solicitation has precedence.
e. The requirements of the solicitation, in descending order of precedence:
1. Standard Form 1442, Price Schedule, and Davis Bacon Wage Rates.
2. Part 1 - Contract Clauses.
3. Part 2 - General Requirements.
4. Part 3 - Project Program Requirements.
5. Part 6 - Attachments (excluding Concept Drawings).
6. Part 5 - Prescriptive Specifications exclusive of performance specifications.
7. Part 4 - Performance Specifications exclusive of prescriptive specifications.
8. Part 6 - Attachments (Concept Drawings).