ATT 5-NUWC B-990 HVAC Renovation_Bid Schedule and Summary of Work rev 2.pdf
PDF 83 KB Posted
- Solicitation number
- N4008523B2511
About this file
This document package includes bid documents and specifications for the NUWC B-990 HVAC Renovation federal contract opportunity. The bid documents call for lump sum pricing for the HVAC system renovation at Building 990 of the Naval Undersea Warfare Center, including removal and replacement of the existing HVAC system and related work. The specifications indicate the work includes renovation of the HVAC system and incidental related work, at an unspecified location at Building 990. Offerors are required to submit a salvage plan as part of their preconstruction submittals. The building will be unoccupied for 18 months during performance.
View the file
Other files
Show 40 more
Latest 50 of 58 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NUWC B-990 HVAC System Renovation eProjects#1621549
DOCUMENT 00 22 13.00 20
SUPPLEMENTARY INSTRUCTIONS TO OFFERORS
PART 1 GENERAL
1.1 CONTRACT LINE ITEMS
The terms Offeror and Bidder and versions thereof (offer/bid) have the same definition as used within this contract.
Provide the Contract Line Item (CLIN) lump sum price for the following items:
CLIN 0001 - BASE PRICE. Price includes the following:
CLIN 0001AA. Price for the entire work for NUWC B-990 HVAV System Renovation and related work in accordance with the drawings and specifications.
CLIN DESCRIPTION TOTAL PRICE FOR CLIN
0001AA
0001AA NUWC B-990 HVAV system Renovation
1.2 GENERAL BID NOTES
a. Award will be made on the lump sum of Contract Line Item 0001AA.
PART 2PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
-- End of Document --
DOCUMENT 00 22 13.00 20 Page 1
NUWC B-990 HVAC System Renovation eProjects#1621549
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for all submittals, submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals Salvage Plan
1.2 WORK COVERED BY CONTRACT DOCUMENTS
1.2.1 Project Description
The work includes the renovation of the HVAC system at Bldg. 990, NUWC and incidental related work.
1.2.2 Location
The work is located at B-990, NUWC, approximately as indicated.
1.3 OCCUPANCY OF PREMISES
Building will be unoccupied for 18 months within the overall period of performance of this Contract. Contractor will give the government three months notice when to vacate the building so they may start this 18 month unoccupied period.
Before work is started, arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.
1.4 EXISTING WORK
In addition to FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements:
a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.
1.5 LOCATION OF UNDERGROUND UTILITIES
If necessary, obtain digging permits prior to start of excavation, and comply with Installation requirements for locating and marking underground utilities. Contact local utility locating service a minimum of 15 days prior to excavating, to mark utilities, and within sufficient time required if work occurs on a Monday or after a Holiday. Verify existing utility locations indicated on contract drawings, within area of work.