Amend 0001.pdf

PDF 997 KB Posted

Attached to
Base Landfill Cell #9 Repair and Install Rain Cap Liner
Solicitation number
N4008521R0253
Issued by

View the file

Other files

File Type Posted
Repair Base Landfill Cell 9 CAD DWGS.zip ZIP file
Install Landfill Rain Cap Liner CAD DWGS.zip ZIP file
N4008520B0086 Dwgs.pdf PDF
N4008520B0086 Specs.pdf PDF
N4008518B0006 Dwgs_Part1.pdf PDF
N4008518B0006 Dwgs_Part2.pdf PDF
N4008518B0006 Specs.pdf PDF
RFP 18006.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

N40085-21-R-0253

Amendment 0001

CONTINUATION SHEET

1. QUESTION: Spec Section(s) 01 57 19, Paragraph(s) 1.7.1 for both projects for RFP

N40085-21-R-0253 indicates for the contractor to prepare a completed Notice of Intent (NOI) form in accordance with the requirements of the State's general permit for storm water discharges from construction sites. Submit NOI, and the appropriate permit fee to the

Contracting Office a minimum of 14 days prior to start of construction. On previous General

MACC RFP Solicitations and Task Orders, all applicable permits have been applied for and paid for by MCB Camp Lejeune. Is this correct?

ANSWER: No ESC required

2. QUESTION: Is the 12" Stone protective cover layer existing, on top of the 12" drainage layer as shown on sheet C-502 detail C.

ANSWER: Yes, detail is as per original landfill construction drawings.

3. QUESTION: Drawings indicate we are to replace &/or repair leachite pumps, risers & piping. How do we determine what to repair/replace?

ANSWER: Demolition Note #2 requires that the leachate lines be inspected after the stone is removed to determine if there is any damage. Any repairs would need to be handled by a

Change Order due to unforeseen site conditions. The same requirement would apply to the risers and the pump. There may not be any needed repairs.

4. QUESTION: Can Specifications be provided by Amendment for the leachite pumps, risers & piping that require replacement on the project

ANSWER: Leachate pipe sizes are shown on detail Sheet C501. The sump detail with pump are shown on detail Sheet C-502 with the horsepower and operating parameters. If there damage is identified upon inspection intent would be to match existing.

5. QUESTION: Can a site visit be scheduled for the project?

ANSWER: There will not be a site visit scheduled. Site is accessible to contractors.

6. QUESTION: Can the CAD files be provided by Amendment?

ANSWER: CAD files have been posted to http://sam.gov

7. All other terms and conditions remain unchanged.