This document contains a pre-proposal inquiry attachment and responses to questions regarding Solicitation Number N40085-21-B-0055 for maintenance dredging at Naval Weapons Station Earle. The project involves dredging approximately 2,261,170 cubic yards of material from nine dredging areas to depths of -45 to -47 feet MLLW in two phases during Summer 2022 and Summer 2023. Phase 1 will dredge four areas totaling 1,176,375 cubic yards. Phase 2 will dredge the remaining five areas totaling 1,043,395 cubic yards. Dredged material will be placed in split-hull or bottom dumping scows and barged to the Historic Area Remediation Site for disposal. The daily production rate must be at least 7,500 cubic yards. Clarifications were provided regarding bid submission format and requirements, dredging area details, schedules, and survey data.
View the file
Other files
Show all 25
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PRE-PROPOSAL INQUIRY ATTACHMENT (7)
Solicitation Number: N40085-21-B-0055 Contractor Name:
Contractor POC (Name and email):
Instructions: DO NOT submit in PDF format. DO submit as a word document Contractor
PPI#
Section of RFP or Page Number
Paragraph Reference
Drawing Number
Question RESPONSE
01 Section 00 21 13 - Instructions to Bidders
10. Delivery of Bid Bid Submission
(p. 11)
Please clarify delivery of bid language. Bid submission states " The offeror shall submit one (1) CD-ROM electronic copy, one (1) hard copy marked “Original" and one (1) hard copy marked “Copy,” in a three ring binder.
In the event of a discrepancy between the electronic copy and the hard copies, the “original” hard copy shall govern." It continues that "For electronic copy shall be labeled
“BID SUBMISSION FOR IFB
N4008521B0055, and email shall be sent to georgia.a.scott.civ@us.navy.mil and philip.j.cole.civ@us.navy.mil".
Seeing as a CD cannot be e-mailed, we request that the language be modified so as to accept a PDF as the electronic form allowed for bid submission via email.
Bid Submission sent by (mail courier) shall include one (1) CD-ROM, one (1) hard copy of bid marked “Original" and one
(1) hard copy of bid marked “Copy,” in a three ring binder.
A copy of your bid shall also be emailed to:
georgia.a.scott.civ@us.navy.mil and philip.j.cole.civ@us.navy.mil
02 Section 00 10 00 – Solicitation Attachment 8: Bid Schedule Document
(p. 3-6) There are inconsistencies in the description of what should be included in the price in Section 00 10 00 - Solicitation and the Attachment 8, Schedule. Please update the descriptions to the correct applicable language, so that they reflect the same description.
Please review and use the attached updated bid schedule under Amendment 0001.
03 Section 00 21 13 -
Instructions to Bidders
Bonding Requirements
(p. 12)
The IFB states that a copy of Representation and Certifications must be submitted, however, Section
When submitting requirements for Representation and Certifications please refer to section 00 70 00 and provide all
00 45 00 - Representations and Certifications does not contain any to submit. The Reps & Certs are provided in the following Section 00 70 00 - Conditions of the Contract.
Please clarify which Reps & Certs are required with bid submittal.
information outlined in that section.
04 35 20 23 3.2.6 – 6.1 p7 Is there a particular sub-section within the HARS and SBOBA disposal sites where the dredged material should be placed? Please provide. Or the Contractor is allowed to place the material anywhere within the limits of those disposal areas?
The EPA will designate the disposal sub-area within HARS.
GOV will provide coordinates to the contractor once received from the EPA.
05 01 11 00 Price Proposal Form
1.4 p1-2
CLIN 0001
Note.
CLIN 0002
Note
Please clarify the differing completion dates for the Phases 1 & 2 Works: 01 11 00 – required completion November 2022 & November 2023, while Price Proposal Form Notes indicate December 2022 & December 2023
Phase 1 work shall be completed by December 31, 2022. Phase 2 work shall be completed by December 31, 2023.
06 01 11 00 1.2.1 p1 Please clarify if hopper dredges are allowed to perform the project or portion thereof under this contract.
Hopper dredges are NOT allowed. This project is only permitted for bucket dredging, 07 1.8 p5 “Dredging of side slopes shall follow, as closely as practicable, the lines indicated or specified”. Offeror respectfully requests NAVFAC to consider adding language to the specification common to other dredging contracts procured by the Federal Government that allow box cutting, and payment for the dredged material, as follows:
“Side slopes may be formed by box cutting, step cutting, or dredging along the side slope.
Material actually removed, within the limits approved the CO, to provide for final side
No language change(s) will be incorporated. Payable volume shall be determined pursuant to applicable specifications sections.
slopes not flatter than shown on the contract, but not in excess of the amount originally lying above this limiting side slope, will be measure and paid for in accordance with the provisions contained…Such amount will be estimated and paid for whether dredged in original position or by box cut dredging whereby space is dredged below the allowable side slope plane on the bottom of the slope for upslope material capable of falling into the cut.”
008 V-0002 V-101 – V-121
Please provide the bathymetric survey of the dredging areas:
Phase 1 and Phase 2 works, in electronic or xyz formal.
.XYZ of the government’s most recent bathymetric survey will be furnished.
009 Price Proposal
Form
CLIN 0004
Description
Option 3 Disposal Area C2, D, D1, E, F, G, & H
Please clarify if Area C2 is correct to be included in the Phase 2 Work (placement into the SBOBA), which will happen in 2023. However, this area is already part of the Base – Phase 1 work that will happen in 2022 that will go to HARS.
Presently there is uncertainty regarding the time-line associated with obtaining approval from regulatory agencies for use of SBOBA. It is most likely that material from Area C2 will go to the HARS.
However, should the government obtain the required SBOBA approvals prior to the completion of the AREA C2 dredging then it is possible that the government could exercise Bid Option #4 in time for the material to be placed in SBOBA in lieu of the HARS.