01 33 10.5 20 DESIGN SUBMITTAL PROCEDURES

APPENDIX A

PHASE %

CAL. DAYS

PER

PHASE

CAL. DAYS

(CUMULATIVE)

FC 1‐300‐09N DESIGN PROCEDURES AND NOTES DRAWINGS SPECS

CDW MEETING*

STARTS 42 DAYS FROM AWARD

5% 3 45

REFER TO CHAPTER 13. YES OUTLINE SPECS

CDW REPORT DEVELOPMENT 7 52

YES OUTLINE SPECS

GOVERNMENT REVIEW OF CDW REPORT 3 55

SCHEMATIC DESIGN (SD) DEVELOPMENT 20% 14 69

REFER TO CHAPTER 14. YES YES + RED

LINED SPECS

GOVERNMENT REVIEW OF SD 7 76

SCHEMATIC DESIGN MEETING* 1 77

DESIGN DEVELOPMENT (DD) DEVELOPMENT 65% 21 98

REFER TO CHAPTER 15. YES YES + RED

LINED SPECS

GOVERNMENT REVIEW OF DD 7 105

YES YES + RED

LINED SPECS

DESIGN DEVELOPMENT/OVER THE SHOULDER

MEETING*

1 106

PRE‐FINAL DEVELOPMENT (CONSTRUCTION

DOCUMENTS & SITE DESIGN)

100% 21 127

REFER TO CHAPTER 17. YES YES + RED

LINED SPECS

GOVERNMENT REVIEW OF PRE‐FINAL 14 141

FINAL DESIGN DEVELOPMENT 100% 14 155

REFER TO CHAPTER 17. YES YES + RED

LINED SPECS

GOVERNMENT REVIEW OF FINAL 7 162

CONSTRUCTION DOCUMENTS (FOR

CONSTRUCTION) DEVELOPMENT

100% 14 176

REFER TO CHAPTER 17. FINAL, SEALED FINAL, SEALED

DESIGN SUBMITTAL / MEETINGS SCHEDULE