ACQR5144957
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
Solicitation No. N40085-19-R-9053 Design-Bid-Build (DBB), Construction of P1479 Outdoor Infantry Immersion Trainer, Marine Corps Base, Camp Lejeune, NC
The purpose of this amendment is to provide responses to Pre-Proposal Inquiries (PPIs). The proposal due date of 11 December 2018 remains unchanged.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 03-Dec-2018
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X N4008519R9053
X 9B. DATED (SEE ITEM 11)
06-Nov-2018
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
03-Dec-2018
CODE
NAVFAC MID ATLANTIC
ACQUISITION CORE
9324 VIRGINIA AVENUE
NORFOLK VA 23511-3095
N40085 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N4008519R9053
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
The following have been added by full text:
AMENDMENT 0005
Question No.
REFERENCE QUESTION GOVERNMENT RESPONSE
Page Section Para.
62 01 14 00 1.2 e What is the desired gate access for this project? If access to the site is to be solely on the outside of base and off from Hwy 172; is the contractor required to monitor (man) this gate during all work hours or is Camp Lejeune to provide a MP checking identification? This is a challenge because anyone can gain access to other areas of the base from outside this gate without adding temporary barricades or fencing thus restricting access via other roads adjacent to TLZ Lark and through the MOUT facility and thus in return will restrict neighboring ranges. More thought and specific requirements to gauge the level needed to secure this entrance is required.
Use of the Hwy 172, F-3 Range Road Range gate is not authorized.
Commercial Vehicles must enter the Base through the Piney Green Commercial Vehicle Access Gate, and may depart through any manned entry control point gate.
Contractor Personnel not in commercial vehicles who are cleared through DBIDS, can access the Installation through any manned entry control point gate so long as the Contractor requests access through all gates in his Contractor Personnel access letter submitted to the local ROICC Construction Manager.
Manned entry control point gates to the Installation include the Piney Green Rd, Holcomb Blvd, Wilson Blvd, Sneads Ferry Rd, and Triangle Outpost Gates.
The closest gate to the site is the Triangle Outpost Gate on Hwy 172 northeast side of the Installation off Hwy 24 in Hubert, NC.
There are no anticipated impacts to the contractor due to training in other parts of the MOUT Complex, as no scheduling coordination is required to access F-3 range road from Lyman Rd. to the Site
N4008519R9053
(End of Summary of Changes)