Amendment_0005.pdf
PDF 474 KB Posted
- Solicitation number
- N4008519R9023
About this file
Amendment_0005.pdf
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment_0004.pdf | ||
| Attachment_E_-_REV2_PRICE_PROPOSAL_FORM.docx | DOCX document | |
| Amendment_0003.pdf | ||
| 1700.1701.Elec._COMB.pdf | ||
| 1701.4393824-4393856.pdf | ||
| Attachment_E_-_REVISED_PRICE_PROPOSAL_FORM.docx | DOCX document | |
| Amendment_0002.pdf | ||
| Amendment_0001.pdf | ||
| P199_Demo_Site_Visit_Sign_In_Sheet.pdf | ||
| Attachment_B_-_SECNAV_5512.pdf | ||
| Attachment_A_-_Pre-Proposal_Inquiry_Form.xlsx | XLSX spreadsheet | |
| Attachment_C_-_Construction_Experience_Project_Data_Sheet.docx | DOCX document | |
| Solicitation_N4008519R9023.pdf |
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The purpose of this amendment is to respond Pre-Proposal Inquiries.
Proposal Due Date Remains Tuesday, 12 March 2019 by 2:00PM EST
1. CONTRACT ID CODE PAGE OF PAGES
J 1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 08-Mar-2019
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X N4008519R9023
X 9B. DATED (SEE ITEM 11)
06-Feb-2019
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
08-Mar-2019
CODE
NAVFAC MID ATLANTIC
ACQUISITION CORE
9324 VIRGINIA AVENUE
NORFOLK VA 23511-3095
N40085 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
N4008519R9023
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
The following have been added by full text:
AMENDMENT 0005
Pre-Proposal Inquiry Submission Form N40085-19-R-9023, P199 BUILDING DEMOLITION
MCAS CHERRY POINT
Date Submitted
LEAVE
BLANK Reference Question Response Response
Provided in Amendment
# Page Section Paragraph
57 03/07/19 Paragraph 3(2)(b) requires the offeror to use a 12-point font for the Technical Factors; however, Paragraph 3(2)(b)(1) indicates that the Construction Experience Project Data Sheet (Attachment C) is MANDATORY and SHALL be used to submit project information.
However, the font used in Attachment C is set at 11-point Arial and doesn't comply with the 12-point requirement. Additionally, Amendment 0003, Question #14 allowed the offeror to use 10-point type for tables/graphics...is Attachment C considered a table;
therefore, allowing us to use 10 point type? Can you please clarify?
11 point font is acceptable for Attachment C
58 03/07/19 3 SF1442 Based on the change in Amendment 0003 requiring us to price several additional items in the Price Proposal Form, would you please consider a one-week extension to the proposal due date, particularly because Amendment 0003 was just released on 01 March, just 10 days prior to when we will need to produce and deliver our proposal to NAVFAC?
Proposal Due Date remains: Tuesday, 12 March 2019 by
2PM EST
(End of Summary of Changes)