P4042_PPI_LOG_Attachment_5.3.pdf
PDF 89 KB Posted
- Attached to
- P4042 MEDICAL/DENTAL REPLACEMENT CLINIC, MARINE CORPS BASE(MCB) CAMP LEJEUNE, NORTH CAROLINA
- Solicitation number
- N4008518R0613
About this file
P4042_PPI_LOG_Attachment_5.3.pdf
View the file
Other files
| File | Type | Posted |
|---|---|---|
| P4042_AMENDMENT_0010.pdf | ||
| UPDATED_WAGE_DETERMINATION_FOR_P4042.pdf | ||
| AMENDMENT_0009_FOR_P4042.pdf | ||
| Pricing_Schedule_0008.pdf | ||
| AMENDMENT_0008.pdf | ||
| P4042_Bid_sheet.pdf | ||
| Amendment_7.pdf | ||
| Amend_0006.pdf | ||
| SK01_PPi_35.pdf | ||
| SECNAV_5512_1_FORM.PDF | ||
| PPi_30_.pdf | ||
| Amendment_0005.pdf | ||
| AMENDMENT_0004.doc.pdf | ||
| P4042_AMENDMENT_0003.pdf | ||
| P4042_SITE_VISIT_SIGN-IN_LOG.pdf | ||
| P4042_AMENDMENT_0002.pdf | ||
| N40085-18-R-0613_P4042_AMENDMENT_0001.pdf |
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PRE‐PROPOSAL INQUIRY ATTACHMENT (5.3)
Solicitation Number: N40085‐18‐R‐0613
Contractor Name:
Contractor POC (Name and email):
Instructions: DO NOT submit in PDF format. DO submit as a word document
Contractor
PPI#
Section of RFP or Page Number
Paragraph Reference
Drawing Number
Questions Answers
Solicitation Will an amendment be pushed out which lists a date and time of a site walk as referenced by the solicitation?
Site Visit has been schedule for June 28, 2018 at 10:00 a.m.
EASTERN. Please see Continuation Page on Amendment for more details.
Solicitation Please consider pushing the bid date to a minimum of July 9th. Many subcontractors will be out of the office the days after the 4th.
Proposal due date has been change to July 12, 2018.
Solicitation What is the RFI cut‐off date? Please note we are currently 16 workdays away from the bid date and no site walk has been published thus impacting potential RFI’s.
PPI cut-off date is July 6, 2018.
Mentioned on Room Finish Schedule AF601‐603 is ‘WG‐ 2’ and on Finish Plans IN111‐1 thru IN112‐3 is ‘Wall Guard’. There is no item labeled or named “Wall Guard” on the Finish Legend AF611. Which item is this Wall Guard?
1. WG-2 is a Wall Finish. Refer to the
WALL FINISH
IDENTIFICATION
Schedule on AF610
FINISH
IDENTIFICATION for the WG-2 Wall Guard Basis of Design Information.
- The Abbreviation List on AF601 - AF603 indicates that WG is the abbreviation for Wall Guard.
- Remarks Note 13 on the FINISH SCHEDULE indicates the installation height.
- Wall Protection items on AF611 are items (CG, BG, HR) that do not schedule on the Wall Finish Schedule so they are called out on the
MISCELLANEOUS
FINISH
IDENTIFICATION
Schedule.
Wall Finish Plans referenced above show symbols for wall protections i.e. BG/BG, BG/WG. It does not distinguish between BG‐1 or BG‐2. Please clarify.
BG-2 is intended to be the general use bumper guard mounted as indicated on QH200.
- BG-1 is intended to be used when wall protection line code BG/BG is indicated on the IN111-series plans.
- BG-1 would be installed above BG-2, the height for BG-2 is wrong on QH200.
The top of BG-2 should be 34" to match the handrail HR-1 height.
Drawing QH200 shows mounting heights but does not specify scenarios as they are noted on Wall Finish Plans.
Agree, QH200 BG mounting heights do not show the BG/BG condition and should indicate the BG-1 and BG-2mounting height intent. See answer in question 2 for mounting heights.
08 33 13.00 50 Coiling Counter Doors
2.2 Various paragraphs
including paragraph 2.2 give reference to non‐rated counter doors but all counter doors on the drawings appear to be rated. Are there any coiling counter doors not rated on the project and, if so, where are they shown?
All coiling counter doors in the project are fire rated.
08 33 23 Overhead Coiling Doors
1.3.2 Paragraph 1.3.2 calls for
fire‐rated doors but all overhead coiling doors on drawings appear to be non‐ rated. Are there any rated overhead coiling doors on
There are no rated exterior overhead coiling doors on the project.
the project and, if so, where are they shown?
08 33 23
Coiling Doors
2.2.1 Various paragraphs
including paragraph 2.2.1 call for guides to be galvanized and finished to match curtain slats.
Unfortunately, a finish will not adhere to the type of galvanizing used on these components. Please address how we should deal with this conflict in the spec.
Provide finishes in accordance with 2.6.1, apply baked enamel or powder coated finish over galvanized surfaces as indicated.
010 08 33 23
Coiling Doors
2.3 Paragraph 2.3 calls for
integral frame fire‐rated rolling counter door but none are shown in drawings. Are integral frames required on this project?
Provide the optional powder coat finish available in 180 colors, the drawings call for Bone White.
011 08 33 23 Overhead Coiling Doors
2.6.1 Paragraph 2.6.1 Calls for a
baked enamel or powder coat finish. Do they want the manufacturer’s standard baked enamel available in gray or tan, or the optional powder coat finish available in 180 color choices?
Provide the optional powder coat finish available in 180 colors, the drawings call for Bone White.