RM09-1862_Hangar_200_AMENDMENT_0004.pdf

PDF 34 KB Posted

Attached to
RM09-1862 DESIGN BID BUILD, HANGAR 200 FIRE PROTECTION & STRUCTURAL REPAIRNAS OCEANA, VIRGINIA BEACH, VIRGINIA
Solicitation number
N4008513R7758
Issued by

About this file

Amendment 0004

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1. CONTRACT ID CODE PAGE OF PAGES

J 1 3

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ.

PROJECT NO. (If applicable)

0004 30-Jul-2013

6. ISSUED BY Code OPHA 7. ADMINISTERED BY (If other than item 6.) Code

NAVFAC MID ATLANTIC

HAMPTON ROADS IPT

9742 MARYLAND AVENUE

NORFOLK, VA 23511

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code) 9A. AMENDMENT OF SOLICITATION NO.

N40085-13-R-7758

9B. DATED (SEE ITEM 11)

08-Jul-2013

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended is not extended. Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing items 8 and 15, and returning _1 _ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (if required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14. ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATION CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103 (b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER: (specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

DESIGN-BUILD/DESIGN-BID-BUILD GENERAL MULTIPLE AWARD CONSTRUCTION CONTRACT FOR NEW CONSTRUCTION, RENOVATIONS, ALTERATION, AND REPAIR PROJECTS FOR FACILITIES IN HAMPTON ROADS

AREA, VIRGINIA

N40085-13-R-7758, RM09-1862 DESIGN BID BUILD, HANGAR 200 FIRE PROTECTION & STRUCTURAL REPAIR, NAS OCEANA, VIRGINIA BEACH, VIRGINIA

SEE SF 30 BLOCK 14 CONTINUATION PAGE

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR (Same as Item 8)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED

BY

(Signature of person authorized to sign) (Signature of Contracting Officer)

NSN 7540-01-152-8070 30-105 STANDARD FORM 30 (REV.1-83) 0224-3(10-90)

PREVIOUS EDITION UNUSABLE Prescribed by GSA

N40085-13-R-7758

SF 30 BLOCK 14 CONTINUATION PAGE

The following information shall modify the contract documents, and the work shall be accomplished in accordance with such stated modifications.

SPECIFICATIONS

Project Table of Contents

Insert APPENDIX B - Fire Protection Phasing Plan

Section 00 22 13 Supplementary Instructions to Bidders

1. Paragraph 0001C

Add Item No. 2 to table as indicated below:

ITEM

No. ITEM UNIT

UNIT

PRICE

NO.

UNITS EXTENSION

2 Hangar Door Steel Sheeting

Repair

SF $_________ 2750 $__________

Section 01 35 13 Special Project Procedures

Paragraph 3.2.2 insert paragraph e. to read as follows:

e. See Appendix B – Fire Protection Phasing Plan for a partial prescriptive plan for fire protection phasing in the hangar bay areas.

Section 02 82 16.00 22 Engineering Control of Asbestos Containing Material

Replace section in its entirety with the Amendment 04 Section attached.

Section 21 13 13.00 20 Wet Pipe Sprinkler System, Fire Protection

1. Paragraph 2.1.1 Steel Pipe

Revise the second sentence to read “Steel piping shall be Schedule 40 for sizes less than 2 inches and Schedule 10 or greater for sizes 2 inches or larger.”

2. Paragraph 2.1.6 Backflow Prevention Assembly

Revise the first sentence to read “Provide listed reduced pressure principle valve assembly backflow preventers”

3. Paragraph 3.2.5 Drains in its entirety and replace with the following:

“3.2.5 Drains

Terminate all new and existing backflow preventer drainage piping or test piping from the associated appurtenances to the exterior of the building so it will not cause damage. Discharge to the exterior must not interfere with exiting from the building. Water discharge must not cross an exit or exit discharge. Drainage piping of less than ¾ -inch (20 mm) may discharge to a floor drain.”

N40085-13-R-7758

Appendix A- Asbestos and Lead Based Paint Survey

Insert the attached Additional Asbestos Sampling, 7 pages, at the end of the Appendix section.

Appendix B – Fire Protection Phasing Plan

Insert the attached Appendix B – Fire Protection Phasing Plan, 3 pages

DRAWINGS

General

1. Replace the following sheets with the attached revised sheets that contain AMENDMENT 4 dated 07/23/13 in the Revision Block:

AD201

A109 A201 A410 A530 A610 A630

IN600

IN601

2. Replace the following sheets with the attached revised sheets that contain AMENDMENT 4 dated 07/24/13 in the Revision Block:

F002

FD401

F401

ATTACHMENTS

02 82 16.00 22 Appendix A Hanger 200 Additional Sampling Report Appendix B - Fire Protection Phasing Plan Drawings Binder Amend 4 RM09-1862 Hangar 200 Price Proposal Form 7-30-13 RM09-1862 Hangar 200 Site Visit Sign In Sheet

Please note that if your specific question is not addressed, the Solicitation RFP, Specifications or Drawings have adequately addressed your inquiry. Please propose in accordance with the RFP

-End of Amendment