APPENDIX B – Fire Protection Phasing Plan
Temporary feed from existing underground to new overhead main during upper half/phase of work (Lower half is still occupied).
This section's two foam systems are out of service for work in upper half of bay.
3 Trench systems to remain in service.
Temporary feed from existing underground to new overhead main during lower half/phase of work (Upper half is still occupied).
This section's two foam systems are out of service for work in lower half of bay.
3 Trench systems to remain in service.