N40085-22-R-2812_Solicitation.pdf
PDF 943 KB Posted
- Attached to
- Regional Subsurface Utility Marking Services Federal contract opportunity
- Solicitation number
- N4008522R2812
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| N4008522R2812_Amendment 0007.pdf | ||
| Amendment 0006.pdf | ||
| 22r2812 amendment 0005.pdf | ||
| N4008522R2812_Amendment 0004.pdf | ||
| N4008522R2812_Amendment 0003.pdf | ||
| Rev-01-ANNEX 0200000 C Management and Administration.pdf | ||
| N4008522R2812-Amendment 0002.pdf | ||
| Amendment 001.pdf | ||
| 1503040 J Sub-Surface Utility Marking - 22R2812.pdf | ||
| SECTION_ J_ ATTACHMENTS_ EXHIBITS-22R2812.pdf | ||
| Non-Priced ELINs_N40085-22-R-2812.xlsx | XLSX spreadsheet |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CODE
(Hour)
PAGE(S)
until 02:00 PM local time 28 Nov 2022
X
A X B X C
D
EX
X G F 98 - 114
115 - 123 X H 124 - 134 darlene.tucker@navy.mil
RATING PAGE OF PAGES
7. ISSUED BY
(Date)
IMPORTANT - Award will be made on this Form, or on Standard Form 26, or by other authorized official written notice.
Previous Edition is Unusable 33-134 STANDARD FORM 33 (REV. 9-97)
Prescribed by GSA FAR (48 CFR) 53.214(c)
1 134
(If other than Item 7)
15A. NAME 16. NAME AND TITLE OF PERSON AUTHORIZED TO
AND
ADDRESS
SIGN OFFER (Type or print)
OF
OFFEROR
AMENDMENT NO. DATE
15B. TELEPHONE NO (Include area code) 17. SIGNATURE15C. CHECK IF REMITTANCE ADDRESS
IS DIFFERENT FROM ABOVE - ENTER
SUCH ADDRESS IN SCHEDULE.
18. OFFER DATE
1. THIS CONTRACT IS A RATED ORDER
UNDER DPAS (15 CFR 700)
2. CONTRACT NO.
N40085 8. ADDRESS OFFER TO
See Item 7
9. Sealed offers in original and 2 copies for furnishing the supplies or services in the Schedule will be received at the place specified in Item 8, or if handcarried, in the depository located in
CAUTION - LATE Submissions, Modifications, and Withdrawals: See Section L, Provision No. 52.214-7 or 52.215-1. All offers are subject to all terms and
Building Z-140, Room 216 conditions contained in this solicitation.
10. FOR INFORMATION
CALL:
A. NAME (NO COLLECT CALLS)
DARLENE H. TUCKER (757) 341-0093
11. TABLE OF CONTENTS
SOLICITATION/ CONTRACT FORM
SUPPLIES OR SERVICES AND PRICES/ COSTS
1 - 2 3 - 10
X I CONTRACT CLAUSES
DESCRIPTION/ SPECS./ WORK STATEMENT X
PACKAGING AND MARKING
11 - 50 J LIST OF ATTACHMENTS
INSPECTION AND ACCEPTANCE
DELIVERIES OR PERFORMANCE
51 - 53 54 - 64
X K
REPRESENTATIONS, CERTIFICATIONS AND
OTHER STATEMENTS OF OFFERORS
CONTRACT ADMINISTRATION DATA 65 - 68 X
SPECIAL CONTRACT REQUIREMENTS
OFFER (Must be fully completed by offeror) 69 - 71 X M
L INSTRS., CONDS., AND NOTICES TO OFFERORS
EVALUATION FACTORS FOR AWARD
NOTE: Item 12 does not apply if the solicitation includes the provisions at 52.214-16, Minimum Bid Acceptance Period.
is inserted by the offeror) from the date for receipt of offers specified above, to furnish any or all items upon which prices are offered at the price set opposite each item, delivered at the designated point(s), within the time specified in the schedule.
13. DISCOUNT FOR PROMPT PAYMENT
(See Section I, Clause No. 52.232-8)
14. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments
AMENDMENT NO. DATE
to the SOLICITATION for offerors and related documents numbered and dated):
FACILITY
12. In compliance with the above, the undersigned agrees, if this offer is accepted within calendar days (60 calendar days unless a different period
SOLICITATION, OFFER AND AWARD
X
(X) SEC. DESCRIPTION (X) SEC. DESCRIPTION PAGE(S)
PART I - THE SCHEDULE
26. NAME OF CONTRACTING OFFICER (Type or print) 27. UNITED STATES OF AMERICA 28. AWARD DATE
EMAIL:TEL: (Signature of Contracting Officer)
CODE CODE
B. TELEPHONE (Include area code) C. E-MAIL ADDRESS
AWARD (To be completed by Government)
19. ACCEPTED AS TO ITEMS NUMBERED 20. AMOUNT 21. ACCOUNTING AND APPROPRIATION
22. AUTHORITY FOR USING OTHER THAN FULL AND OPEN COMPETITION:
10 U.S.C. 2304(c)( ) 41 U.S.C. 253(c)( ) (4 copies unless otherwise specified)
23. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM
24. ADMINISTERED BY (If other than Item 7) CODE 25. PAYMENT WILL BE MADE BY CODE
PART IV - REPRESENTATIONS AND INSTRUCTIONS
PART III - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS
72 - 96
PART II - CONTRACT CLAUSES
NAVFACSYSCOM MID-ATLANTIC
CONTRACTING CORE
9324 VIRGINIA AVENUE
NORFOLK VA 23511-3095
FAX:
TEL:
FAX:
TEL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".
SOLICITATION
6. REQUISITION/PURCHASE NO.
ACQR5936277
5. DATE ISSUED
28 Oct 2022
4. TYPE OF SOLICITATION
SEALED BID (IFB)
NEGOTIATED (RFP)
[ X ]
3. SOLICITATION NO.
N4008522R2812
Section A - Solicitation/Contract Form
COVER SHEET
COMMANDER
NAVAL FACILITIES ENTINEERING COMMAND
MID-ATLANTIC DIVISION
CONTRACTING CORE
NORFOLK, VIRGINIA 23511-3095
NOTICE: NAVFAC SPECIFICATION
Proposals to be submitted by 2:00 P.M. No. 05-22-2812 November 28, 2022 REF NUMBER N4008522R2812 Darlene H. Tucker By Commercial Carrier to:
darlene.h.tucker.civ@us.navy.mil
REGIONAL SUBSURFACE UTILITY MARKING SERVICES FOR HAMPTON ROADS AOR AT THE
NORFOLK NAVAL STATION, NORFOLK VIRGINIA; NAVAL WEAPONS STATION, YORKTOWN,
VIRGINIA; CHEATHAM ANNEX, WILLIAMSBURG, VIRGINIA; NAVAL AIR STATION OCEANA,
VIRGINIA BEACH, VIRGINIA; DAM NECK ANNEX, VIRGINIA BEACH, VIRGINIA; AND NORFOLK
NAVAL SHIPYARD, PORTSMOUTH, VIRGINIA AS WELL AS SITES LOCATED WITHIN A 50-MILE
RADIUS OF THE LISTED SITES
NOTICE
All inquiries concerning any phase of the specification, prior to the proposal due date shall be submitted
Electronically, Attn: Darlene H. Tucker, darlene.h.tucker.civ@us.navy.mil.
Contracts or purchase order to be awarded as a result of this contract shall be assigned (as Appropriate for specific procurement), DO-S1 rating in accordance with the provisions of DPA Regulation 1 and/or DMS.
Section B - Supplies or Services and Prices
GENERAL INFORMATION
B.1 Contract Title: Regional Subsurface Utility Marking Services at the Norfolk Naval Station, Norfolk Virginia, Naval Weapons Station, Yorktown, Virginia; Cheatham Annex, Williamsburg, Virginia; Naval Air Station Oceana, Virginia Beach, Virginia; Dam Neck Annex, Virginia Beach, Virginia; and the Norfolk Naval Shipyard, Portsmouth, Virginia as well as sites located within a 50-mile radius of the listed sites.
B.2 Type of Contract: This is a Facilities Support, Indefinite Delivery/Indefinite Quantity Contract with
Non-Recurring Services as noted in Section L, Instructions, Conditions, and Notices to Offeror.
B.3 Minimum Guarantee: The only work authorized under this contract is that which is ordered by the government through issuance of a Task Order. The Government makes no representation as to the number of Task Orders or the total actual amount of work to be ordered. However, during the term of the contract, a minimum of $2,500 is guaranteed to be ordered to the awardee under the performance period of the contract. Contractors are not guaranteed work in excess of the minimum guarantee specified herein. The $2,500 minimum guarantee is the only minimum guarantee for the entire contract period, and that value of work or dollar amount may be ordered or paid at any time during the duration of the contract, including the base and any option periods, to satisfy the minimum guarantee. The minimum guarantee is subject to deductive offsets for failure to perform work, failure to complete work, and or defective work.
B.4 Set-Aside: This requirement is being solicited as 100% Small Business Set-Aside Competitive
Procurement. Refer to Section I, FAR Clause 52.219-6, Notice of Total Small Business Set-Aside.
B.5 NAICS Code: The NAICS Code assigned to this procurement is 561990 with a small business size standard of $14,500,000.00. Refer to On-Line Representations and Certifications Application (ORCA) via System for Award Management (SAM) at https://www.sam.gov/portal/public/SAM .
B.6 Wage Determination (Service)/Wage Decision (Construction): Service Contract Act (SCA) are included in this solicitation. Refer to Section J, Attachments.
B.7 Bid Guarantee/Bonding Requirements: NOT REQUIRED for this procurement.
B.8 Contract Term: This contract contains provisions for a Base Period with four (4) Option Periods, not to exceed a total of sixty (60) months. The Government has the option to extend the term of the contract in accordance with Section I, Contract Clauses, 52.217-9, Option to Extend the Term of the Contract-Services (Mar 2000). In the option periods, the Government will adjust the prices, if applicable, based on the new Department of Labor Wage Determination.
B.9 Period of Performance: The period of performance will be determined at the time of award.
B.10 Evaluation of Proposal: Proposers shall submit a lump sum price for Section B, CLINs 0001 through 0005 and unit prices for Exhibit A through Exhibit E, referenced in Section J.
For purposes of evaluating offers for award, the Government will utilize the pricing submitted for the base year and all option periods. Refer to Section M, FAR 52.217-5, Evaluation of Options (JUL 1990).
B.11 Contract Line Items And Contract Exhibit Line Items
a. Proposers shall enter unit prices and amounts for Contract Line Items (CLINs) and Contract Exhibit line items (ELINs) as indicated in the schedules and accompanying exhibits.
b. In the event there is a difference between a unit price and the extended total amount, the unit price will be held to be the intended bid and the total of the CLIN, the ELIN will be recomputed accordingly. The CLIN will also be recomputed to take into account the change in the contract
ELINs. If the offeror provides a total amount for an ELIN, but fails to enter the unit price, the total amount divided by the ELIN quantity will be held to be the intended unit price.
c. The Schedule of Non-Recurring Work (CLIN 0001, 0002, 0003, 0004 and 0005) will be used as the basis for deductions in accordance with FAR Clause 52.246-4, Inspection of Services
– Fixed Price, Section E.
B.12 Unit Price Adjustments In Option Periods
This contract incorporates the Service Contract Act (SCA) and the Wage Rates-Construction. The SCA Wage Determination incorporated in Section J is for the Base Year performance period only.
The latest Wage Determination available at the time for each option exercise will be incorporated into the contract. Unit prices will ONLY be adjusted for the Service Contract Act (SCA) wage increases in accordance with FAR Clauses 52.222-43, Fair Labor Standards Act and Service Contract Act – Price Adjustment. The contractor warrants, by submission of his proposal, that the price does not include any contingency for future wage increases with the exception of Wage Rates-Construction.
B.13 Indefinite Quantity Individual Contract Line Item Quantities
Once the estimated quantities for individual line items shown in the Schedule have been ordered, additional quantities may be ordered as long as the overall not-to-exceed (NTE) amount of the contract per year is not exceeded and the Contractor agrees by signing the task order.
B.14 Unit Prices For Labor
a. A portion of the work included in the scope of this contract cannot be identified in advance in sufficient detail to be as a Unit Price Task in this contract. Labor for this work will be ordered and paid for based on unit prices for labor proposed by the Contractor listed in the Schedule of Non-Recurring Quantity Work.
b. Estimated hours in the Schedule are a forecast of future requirements. These estimated hours are for performing "Non-Recurring Quantity Work” accomplished in the time period shown.
c. The Contractor shall enter, in the unit price proposal space, the unit price for performing composite labor. The composite labor price shall include all direct and indirect costs associated with performing an hour of work. The composite labor price should be the Contractor's hourly craft wage adjusted to allow for the offerors work force productivity (i.e., the Contractor's estimate of how its’ work force will perform in relation to the Means Facilities Cost Data and/or the Engineered Performance Standards). The Composite Labor Rate shall include all costs for preparation of the cost proposal, job preparation, travel, pre- expended bin materials and supplies, ordering and stockpiling job material, additional material handling, items of equipment necessary to perform work (I.e. bucket truck, lifting equipment, staging, etc.), profit, tools, equipment, field and home office overhead, clerical support, supervision, inspection, fees, taxes, licenses, bonds, permits, insurance, etc.
B.15 Period Of Performance – Less than One Year
Offer shall be submitted for the performance of work for a period of one year. The contractor is cautioned to recognize that the initial term of the contract may be for a period of less than one year in accordance with the “Term of Contract” clause in Section F. In the event that the period of performance is less than one year, the Government will reduce the individual line item quantities to reflect work remaining in the contract term and no other adjustments to the pro-rated contract price will be made.
B.16 Government Purchase Card
Non-Recurring quantity work may be ordered at the prices offered by two ways: 1) by the issuing activity using a DD Form 1155 “Order for Supplies and Services”; 2) by an authorized Government user via a Government Purchase Card (GPC). When receiving GPC orders against Section B, the contractor shall provide the supplies and services at the offered price without additional markup or handling fee.
B.17 Contractor Support Of Electronic Facilities Support Contracting (e-FSC)
This procurement allows for the use of FEDMALL for issuing orders. Refer to Section H, Special Contract Requirement.
B.18 Incorporation of Technical Proposal
a. The Contractor’s technical proposal, including revisions and amendments made prior to contract award and a copy of which is in the possession of both parties, will be incorporated into this contract upon award by reference with the same force and effect as if set forth in full text.
All contractor personnel shall meet or exceed the qualification standards, experience levels, and trade backgrounds set forth in the technical proposal.
b. In the event of an inconsistency between the provisions of this contract and the technical proposal, the inconsistency shall be resolved by giving precedence in the following order: (i) the contract (excluding the technical proposal), and then (ii) the technical proposal.
B.19 Request For Proposals (RFP) Information/Clarification Questions
Contractors are required to review the entire solicitation package before submitting questions.
All questions must be submitted at least 10 days before proposals are due, by email to darlene.h.tucker.civ@us.navy.mil. This is the most efficient way to ensure all questions are addressed in a timely manner.
B.20 Request for Proposal (RFP) Files:
Solicitations are posted to the Contract Opportunities website (https://www.sam.gov) as mandated by our Agency. By necessity, these files are protected to prevent unauthorized editing.
It is the sole responsibility of the offeror to obtain the RFP files, along with any amendments, from this website.
Unprotected editable file copies of the RFP documents including: Word, Excel and/or .pdf files (Adobe Acrobat Files) will not be provided. Please plan accordingly.
B.21 Solicitation
This solicitation incorporates by reference a Performance Work Statement (PWS) developed by using NAVFAC performance-based specifications. The PWS consists of Annexes 1, 2, and 15.
The contractor will be required to meet the specifications in those Annexes per Section C of this solicitation.
B.22 Notice to Offerors:
Offerors are required to submit Section B, Contract Line Items (CLINs) Schedule, and Section J, Exhibit Line Items (ELINs) with their proposal. The total of the CLIN is equal to the sum of the ELINs as shown below:
CLINS ELINs 0001 A700 through A707 0002 B700 through B707 0003 C700 through C707 0004 D700 through D707 0005 E700 through E707
B.23 Proposal Delivery;
DBIDS INFORMATION
Access to Installation: All Contractor personnel shall obtain access to the installation through enrollment and registration into the Defense Biometric Identification System (DBIDS).
The Contractor shall provide the KO with the name of their designated Service Contractor Administrator (SCA) for enrollment in DBIDS. Once enrolled, the Contractor must provide the DBIDS Registrar with an approved employee list and then direct their employees to register into DBIDS.
DBIDS Program: DBIDS is an enterprise identity management and perimeter installation access control solution in which Contractor personnel who enroll, and are approved, are subsequently granted access to the installation for a period up to three years, or the length of the contract, whichever is less, and are not required to obtain a new pass from the Base Pass and Identification Office for each visit. There are no fees associated with obtaining a DBIDS credential.
The Government performs background screening and credentialing. Throughout the year the Contractor employee must continue to meet background screening standards. Periodic background screenings are conducted to verify continued DBIDS participation and installation access privileges. DBIDS access privileges will be immediately suspended or revoked if at any time a Contractor employee becomes ineligible.
DBIDS Credentials: Contractor employees shall furnish a completed copy of the SECNAV 5512/1 form to obtain the required background check and visit the local Navy Installation Visitor Control Center to obtain a DBIDS credential once approved. The SECNAV 5512/1 form and additional information about DBIDS can be found at: https://www.cnic.navy.mil/om/dbids.html .
The Contractor may initiate the adjudication process when a background screen failure results in disqualification from participation in DBIDS and the Contractor employees do not agree with the reason for disqualification. The Contractor may also apply for a waiver when a background screening failure results in disqualification from participation in DBIDS. The Commanding Officer will be the final waiver determination authority.
The Contractor shall immediately collect employee DBIDS credentials and notify the KO in writing:
(1) That an employee has departed the company without having properly returned or surrendered their DBIDS credentials.
(2) That there is a reasonable basis to conclude that an employee, or former employee, might pose a risk, compromise, or threat to the safety or security of the installation or anyone therein.
DBIDS Paper Passes: In the event that a visitor, vendor, or Contractor employee elects not to participate in DBIDS, the individual will be issued DBIDS paper pass from the Base Pass and Identification Office in order to access to the installation. The time standard for the validity of a pass to access an installation will be not more than thirty (30) days and may be further restricted based on local policy or by Federal, DOD, Navy, and CNIC guidance.
The Government will not be responsible for any cost or lost time associated with obtaining paper passes or added vetting or inspections incurred by non-participants in the DBIDS credentialing process.
Submitting Your Proposal
Proposals should be sent via a commercial carrier, such as Federal Express, and shall be addressed to:
NAVFAC MIDLANT
Attn: Darlene H. Tucker 9324 Virginia Avenue Building Z-140, Room 216 Norfolk, Virginia 23511
Proposals that are hand carried will NOT be accepted.
ITEM NO SUPPLIES/SERVICES MAX
QUANTITY
UNIT UNIT PRICE MAX AMOUNT
0001 UNDEFINED Each
BASE YEAR- NON-RECURRING WORK
FFP
Provide all labor, management, supervision, tools, material and equipment and other items necessary to perform Regional Subsurface Utility Marking Services.
FOB: Destination
FOB: Destination
PURCHASE REQUEST NUMBER: ACQR5936277
PSC CD: S119
MAX
NET AMT
UNIT UNIT PRICE MAX AMOUNT
0002 UNDEFINED Each
OPTION OPTION YEAR 1 - NON-RECURRING WORK
FFP
Provide all labor, management, supervision, tools, material and equipment and other items necessary to perform Regional Subsurface Utility Marking Services.
FOB: Destination
*****Put in contract title here FOB: Destination
PSC CD: S119
UNIT UNIT PRICE MAX AMOUNT
0003 UNDEFINED Each
OPTION OPTION YEAR 2 - NON-RECURRING WORK
FFP
Provide all labor, management, supervision, tools, material and equipment and other items necessary to perform Regional Subsurface Utility Marking Services.
FOB: Destination
*****Put in contract title here FOB: Destination
UNIT UNIT PRICE MAX AMOUNT
0004 UNDEFINED Each
OPTION OPTION YEAR 3 - NON-RECURRING WORK
FFP
Provide all labor, management, supervision, tools, material and equipment and other items necessary to perform Regional Subsurface Utility Marking Services.
FOB: Destination
*****Put in contract title here
UNIT UNIT PRICE MAX AMOUNT
0005 UNDEFINED Each
OPTION OPTION YEAR 4 - NON-RECURRING WORK
FFP
Provide all labor, management, supervision, tools, material and equipment and other items necessary to perform Regional Subsurface Utility Marking Services.
FOB: Destination
*****Put in contract title here
Section C - Descriptions and Specifications
ANNEX 0100000
0100000 – General Information Spec Item Title 1 General Information
1.1 Outline of Services
1.2 Acquisition of Additional Work
1.3 Background Information
1.4 Navy PBSA Approach
1.5 Standard Template
1.6 Related Information
1.7 Verification of Workload and Conditions
1.8 Contractor's Knowledge
1.9 Technical Proposal Certification
0100000 – General Information Spec Item Title Description 1 General Information
1.1 Outline of Services Except where otherwise stated, the Contractor shall furnish all labor, supervision, management, tools, materials, equipment, facilities, transportation, incidental engineering, and other items necessary to provide Surface Utility Marking services at various Naval Facilities located throughout the entire Hampton Roads region. This is a performance-based contract that is comprised of Non-Recurring Work Items.
The PWS is organized into annexes. Annex 1 is "General Information".
Annex 2 contains the on-site project management and administration requirements. Annexes 3 through 18 contain the technical requirements.
The annex numbers are identified as 1 through 18 in the description column, but the fully expanded annex numbers include seven digits (e.g., Annex 1 expanded number is 0100000 as shown in the header row at the top of this page).
Annex 1 General Information Annex 2 Management and Administration Annex 3 Command and Staff - N/A Annex 4 Public Safety – N/A Annex 5 Air Operations – N/A Annex 6 Port Operations – N/A Annex 7 Ordnance – N/A Annex 8 Range Operations – N/A Annex 9 Health Care Support – N/A Annex 10 Supply – N/A Annex 11 Personnel Support Annex 12 Morale, Welfare and Recreation Support – N/A Annex 13 Galley – N/A Annex 14 Housing – N/A Annex 15 Facilities Support Sub-Annex 1503040 – Subsurface Utilities Marking Annex 16 Utilities – N/A Annex 17 Base Support Vehicles and Equipment – N/A Annex 18 Environmental – N/A
1.2 Acquisition of
Additional Work
The Government reserves the right to acquire additional sub-surface utility marking services at additional locations in addition to the services and locations identified in the non-recurring work requirements of this contract. Additional services will be incorporated into the contract in accordance with the CHANGES clause, SECTION I or ordered under the non-recurring provisions of the contract. Items of work not covered by this contract but within the general intent are considered in the scope of this contract.
1.3 Background Information As an integral part of the Naval Facilities Engineering Command (NAVFACSYSCOM) enterprise, we at NAVFACSYSCOM Mid-Atlantic are the Navy's installation facility experts, managing the planning, design, and construction of shore facilities for the U.S. Navy from Maine to North Carolina. Headquartered in Norfolk, Va., we fully support the mission of Commander, Navy Region Mid-Atlantic (CNRMA) and Commander, Navy Installations Command (CNIC) to enable and enhance Navy combat power by providing the most effective, efficient and cost-wise shore services and support. We operate with an annual Navy Working Capital Fund business volume of approximately $560 million and execute over
$1.5 billion a year in construction, professional engineering and facilities services for the Navy and Marine Corps.
1.4 Navy PBSA Approach The Navy’s approach to performance-based service acquisition (PBSA) includes four component parts, which are 1) performance outcomes, 2) measurable standards, 3) consideration of incentives, and 4) performance assessment plan.
1.5 Standard Template Key to implementing the PBSA approach is using a standard template that ensures Navy-wide consistency yet affords appropriate tailoring to meet local needs.
The standard template contains 18 standard annexes. Annex 1 will always contain General Information that is relevant to the entire scope of the contract. Annex 2 contains Management and Administration requirements that are relevant to the entire scope of the contract. Annexes 3 through 18 and their associated sub-annexes contain the General Information, Management and Administration requirements, Performance Objectives, Related Information, and Performance Standards that are relevant to that technical annex. Except where otherwise stated, Annexes 3 through 18 and their associated sub-annex requirements are not relevant to one another. Within each technical annex and sub-annex, the organization of information and requirements are also standardized. Specification Item 1 will always contain General Information. Specification Item 2 will always contain the Management and Administrative requirements. Specification Item 3 will always contain the Recurring Work requirements.
Specification Item 4 will always contain the Non-Recurring Work requirements. Requirements and standards for higher level specification items apply to all subordinate specification items, e.g., Specification Item 3 standards apply to all recurring work specification items. Specification Item 3.1 is applicable to all 3.1 subordinate specification items.
Specification Items 3.2 and 3.3 are not considered subordinate to 3.1 nor are they considered subordinate to one another. All costs associated with Annexes 1 and 2 and Specification Items 1 and 2 shall be priced, and their price shall be allocated to the Exhibit Line Items.
1.6 Related Information There are four types of Related Information that can be found in the Description and Related Information columns of the specification as follows:
Informational Notes as used throughout this PWS provides additional information to offerors’ to be used in developing a thorough understanding of the work to be performed in this contract. Any block of text marked “Informational Notes” throughout Annexes 1 through 18 and their associated sub-annexes are subject to this disclaimer. Offerors’ may not rely upon the "Informational Notes" as material representations of the Government. Information provided in "Informational Notes" does not create a contractually binding requirement on either party.
Clarifying Information describes client expectations in a more detailed manner than the Performance Objective and Performance standard alone.
Constraining Information describes limitations to the work performed to meet the Performance Objective and Performance Standard.
Requirement Information further describes client requirements associated with each Performance Objective.
1.7 Verification of
Workload and Conditions
Throughout the PWS, the workload data is generally referred to as being located in Sections C and J. Section C provides data such as descriptions, specifications, and the statement of work. Section J provides data such as system descriptions, maps, floor plans, and tables to represent the type and location of services to be provided.
All facilities, systems, and assets identified in this contract shall be accepted by the Contractor in "AS-IS" condition. The Contractor is fully responsible for all work up to and including the limits of liabilities specified.
As prescribed in FAR 52.237-1, offerors’ or quoters are urged and expected to inspect the site where services are to be performed and to satisfy themselves regarding all general and local conditions that may affect the cost of contract performance, to the extent that the information is reasonably obtainable. In no event shall failure to inspect the site constitute grounds for a claim after contract award.
1.8 Contractor's Knowledge The Navy expects to receive insightful management from its contractors.
This management will include the knowledge, skills, authority and willingness to use contractor resources to find better ways of serving Navy clients’ strategic and operational goals and objectives. The Navy's use of performance-based objectives evidences this principle. Although performance work statements will typically contain several levels of performance assessment, the Navy wants its contractors to exercise maximum discretion within bounds of prudent risk management to adjust processes and resources needed to reach specified objectives at the highest performance level.
1.9 Technical Proposal
Certification
The Contractor warrants that its proposal incorporated herein by reference will meet or exceed the performance objectives set forth in this contract.
ANNEX 0200000
0200000 – Management and Administration Spec Item Title 2 Management and Administration
2.1 Definitions and Acronyms
2.2 General Information
2.2.1 Government Regular Working Hours
2.2.1.1 Observed Federal Holidays
2.2.1.2 Restriction to Contractor Working Hours
2.2.2 Wage Determinations
2.2.3 Requirements Hierarchy
2.3 General Administrative Requirements
2.3.1 Required Conferences and Meetings
2.3.2 Training for Maintenance and Operation of New and Replacement Systems and Equipment
2.3.3 Partnering
2.3.3.1 <<Note to Spec Writer: Insert correct title, e.g., Formal Partnering -OR- Informal Partnering>>
2.3.3.2 Contract Partnering Administration
2.3.3.3 Contract Partnering Session Attendees
2.3.4 Permits and Licenses
2.3.5 Insurance
2.3.5.1 Certificate of Insurance
2.3.5.2 Minimum Insurance Amounts
2.3.6 Protection of Government Property
2.3.7 Directives, Instructions, and References
2.3.8 Invoicing Procedures
2.3.9 Forms
2.4 Government-Furnished Items
2.4.1 Government-Furnished Property (GFP)
2.4.2 Government-Furnished Facilities
2.4.3 Government-Furnished Vehicles and Equipment
2.4.4 Government-Furnished Utilities
2.5 Contractor-Furnished Items
2.6 Management
2.6.1 Safeguarding Information
2.6.2 Dissemination of Information
2.6.3 Work Reception
2.6.4 Work Control
2.6.5 Work Schedule
2.6.6 Deliverables
2.6.7 Service Interruptions
2.6.8 NAVFAC Maximo
2.6.8.1 NAVFAC Maximo Data
2.6.8.2 NAVFAC Maximo Method of Data Entry
2.6.8.3 NAVFAC Maximo Access
2.6.8.4 NAVFAC Maximo Training
2.6.9 Quality Management System (QMS)
2.6.9.1 Quality Management (QM) Plan
2.6.9.2 Quality Inspection and Surveillance
2.6.9.3 Quality Inspection and Surveillance Report
2.6.10 Property Management Plan
2.6.11 System and Equipment Replacement
Spec Item Title
2.7 Personnel Requirements
2.7.1 Key Personnel
2.7.1.1 Project Manager (PM)
2.7.1.2 Quality Manager
2.7.1.2.1 Quality Control Personnel
2.7.1.3 Site Safety and Health Officer (SSHO)
2.7.1.4 Environmental/Energy Manager
2.7.2 Employee Requirements
2.7.2.1 Employee Certification and Training
2.7.2.2 Employee Appearance
2.7.2.3 Employee Conduct
2.7.2.4 Identification as Contractor Employee
2.7.2.5 Removal of Employees
2.7.2.6 Proof of Legal Residency
2.7.3 Service Contract Reporting (SCR)
2.8 Security Requirements
2.8.1 Employee Listing
2.8.2 Vehicles
2.8.3 Passes and Badges
2.8.4 Access to Installation
2.8.4.1 DBIDS Program
2.8.4.2 DBIDS Credentials
2.8.5 Access to Buildings
2.8.6 Access Arrangements
2.8.6.1 Escort Arrangement for Secured Areas
2.8.7 Security Clearances
2.8.8 Access to Controlled Unclassified Information
2.8.9 Access to Government Information Technology (IT), Operating Technology (OT), and Facility
Related Control Systems (FRCS)
2.8.10 Access to Navy Marine Corps Intranet (NMCI)
2.8.11 Employee Status
2.9 Contractor Safety Program
2.9.1 Contractor Safety Requirements
2.9.1.1 Experience Modification Rate (EMR)
2.9.1.2 OSHA Days Away From Work, Restricted Duty, or Job Transfer (DART) Rate
2.9.2 Accident Prevention Plan (APP)
2.9.3 Activity Hazard Analysis (AHA)
2.9.4 Safety and Occupational Health (SOH) Risks and Compliance Plans
2.9.4.1 Alcohol and Drug Abuse Prevention Plan
2.9.4.2 Chemical Hazard Communication Program
2.9.4.3 Confined Space Program
2.9.4.4 Critical Lift Plan
2.9.4.5 Fall Prevention and Protection Plan
2.9.4.6 Pathogen Exposure
2.9.4.7 Control of Hazardous Energy (lockout/tagout)
2.9.5 Crane Operations
2.9.5.1 Crane Inspections
2.9.5.2 Rigging Gear
2.9.5.3 Crane Operators
2.9.6 Accident and Damage Reporting
2.9.6.1 Accident Reporting and Notification Criteria
Spec Item Title
2.9.7 Fire Protection
2.9.8 Monthly On-Site Labor Report
2.9.9 OSHA Citations and Violations
2.9.10 Safety Inspections and Monitoring
2.9.11 Safety Certification
2.9.12 Safety Apparel on Jobsites
2.9.13 Emergency Medical Treatment
2.9.14 Excavations
2.10 Environmental Management and Sustainability
2.10.1 Energy Management Program
2.10.1.1 Water Conservation Plan
2.10.1.2 Energy Efficient Products
2.10.2 Environmental Protection
2.10.2.1 Sampling, Testing and Laboratory Services
2.10.2.2 ODS Requirements for Refrigerant Recycling
2.10.2.3 Solid Waste Management and Recycling
2.10.2.4 Non-Regulated Waste Disposal
2.10.2.5 Regulated Waste Disposal
2.10.2.6 Universal Waste
2.10.2.7 Spill Prevention, Containment, and Clean-up
2.10.2.8 Hazardous Material Management
2.10.2.9 Protection of Endangered and Threatened Species (Flora and Fauna)
2.10.2.10 Noise Control
2.10.2.11 Salvage
2.10.2.12 Asbestos Containing Material (ACM)
2.10.2.13 Clean Air Act (CAA)
2.10.3 Sustainable Procurement and Practices
2.10.3.1 Environmentally Preferable Products
2.10.3.2 Use of Recovered Materials
2.10.3.3 Use of Biobased Products
2.11 Disaster Preparedness
2.12 Technical Library
2.13 Warranty Management
2.14 Recurring Work Procedures
2.14.1 Recurring Work Preparation of Proposals
2.14.2 Notification to the Government for Work Above the Recurring Work Limitations
2.14.3 Recurring Work Exhibit Line Item Numbers (ELINs)
2.15 Non-Recurring Work
2.15.1 Unit Priced Task (UPT) Work (Non-Negotiated)
2.15.1.1 Acceptance and Performance
2.15.1.2 Invoicing and Receiving Payment
2.15.2 Unit Priced Labor (UPL)Work (Negotiated)
2.15.2.1 Non-recurring Work Preparation of Proposals
2.15.2.1.1 Labor Requirements
2.15.2.1.2 Direct Material and Construction Equipment Requirements
2.15.2.2 Issuance of Final Task Order
2.15.3 Non-Recurring Work ELINS
0200000 - Management and Administration
2 Management and
Administration
2.1 Definitions and
Acronyms
Definitions and Acronyms are listed in J-0200000-01.
2.2 General
Information
2.2.1 Government
Regular Working Hours
The Government's regular working hours are from 0700-1600, five days per week, Monday through Friday, except observed Federal holidays. Exceptions to the regular hours of operation are detailed in subsequent sections of this PWS. Work in certain annexes or sub-annexes require Contractor continuous operations, 24 hours a day, every day of the year including holidays. The performance of other work requirements shall be accomplished within the Government’s regular working hours unless the specific work requirement specified herein necessitates otherwise. Any other work outside Government regular working hours must be authorized by the KO prior to commencement of work.
2.2.1.1 Observed Federal
Holidays
The Government observes the following holidays: New Year’s Day, Martin Luther King Jr.’s Birthday, President’s Day, Memorial Day, Independence Day, Labor Day, Columbus Day, Veterans’ Day, Thanksgiving Day, and Christmas Day.
2.2.1.2 Restriction to
Contractor Working Hours
In housing areas, high security areas, and during special functions the Contactor will schedule work to meet each client requirement.
If the Contractor wishes to work outside of the Government's regular working hours for the Contractor’s convenience, the Contractor shall submit a written Request to Work Outside Government’s Regular Working Hours per Section F. Excludes work to be performed during specified hours.
2.2.2 Wage
Determinations
Wage Determinations are included in J-0200000-02.
2.2.3 Requirements
Hierarchy
Requirements or definitions specified in each spec item of this contract apply to subordinate paragraphs. For example, requirements shown in spec item 3.1 would apply to spec items 3.1.1, 3.1.2, 3.1.2.1 and so on.
Likewise, Performance Standards specified at a lower digit level (i.e. spec item 3.1.1, 3.1.2, 3.1.2.1) apply when performance is assessed at a higher tier (i.e., spec item 3.1) based on the composite work requirements.
2.3 General
Administrative Requirements
2.3.1 Required
Conferences and Meetings
The Contractor shall attend administrative and coordination meetings, pre-performance conferences, performance assessment board meetings, partnering sessions, etc., as scheduled by the KO.
2.3.2 Training for
Maintenance and Operation of New and Replacement Systems and Equipment
When construction, renovation, or repair work is performed by means other than this contract, the Contractor shall attend Government provided training, as applicable, for maintenance and operation of new and replacement systems and equipment at no additional cost to the Government.
2.3.3 Partnering The Government requires cohesive partnerships with its Contractors and subcontractors. Key stakeholders, including the supported commands who may receive services, principal individuals from NAVFAC, the performance assessment team, and representative(s) of the installation(s) will be invited to participate in the partnering process. Key members of the prime and sub-contractor teams, including senior management personnel must participate.
The partnership will draw on the strength of each organization in an effort to achieve quality contract services done right the first time, within the contract price, as scheduled, and without any safety mishaps.
The goal of Partnering is to develop a cohesive team with common purpose, commitment and established communication processes.
2.3.3.1 Informal Partnering The Contracting Officer shall organize the initial Partnering Meeting with key personnel of the project team, including Contractor's personnel and Government personnel. The initial session will be scheduled concurrent with the Pre-Performance Conference and held no later than 30 days after award and will be held at a Government provided facility as designated by the KO.
The Initial Informal Partnering Session will be conducted and facilitated using electronic media (a video and accompanying forms) provided by Contracting Officer. The senior Government stakeholder present will lead the meeting, however, the Contractor’s PM or senior representative is encouraged to participate as co-lead.
The Partners will determine the frequency of the follow-on sessions.
2.3.3.2 Contract Partnering
Administration
Upon award, the ACO will contact the Contractor, supported command(s), Region, and Installation(s) stakeholders, and the performance assessment team to discuss implementation of partnering.
The Core Management Team consisting of the attendees below must be present during the initial and all follow-on partnering sessions. These are the core mandatory attendees. Other stakeholders may attend if they desire or as recommended by the partners.
2.3.3.3 Contract Partnering
Session Attendees
The Contractor shall bring the necessary personnel to successfully partner on this contract. Asterisk indicates mandatory personnel.
President/Vice President
* Project Manager
* Quality Manager Site Safety and Health Officer
2.3.4 Permits and
Licenses
The Contractor shall obtain all required permits, licenses, and authorizations to perform work under this contract and comply with all the applicable Federal, state and local laws and regulations. The Contractor shall submit copies of Permits and Licenses per Section F.
2.3.5 Insurance The Contractor shall submit a Certificate of Insurance per Section F as evidence of the existence of the following insurance coverage in amounts not less than the amounts specified below in accordance with the FAR Clause
52.228-5, INSURANCE – WORK ON A GOVERNMENT
INSTALLATION. This insurance must be maintained during the performance period.
2.3.5.1 Certificate of
Insurance
The Certificate of Insurance shall provide for at least 30 calendar days written notice to the KO by the insurance company prior to cancellation or material change in policy coverage. Other requirements and information are contained in the aforementioned insurance clause.
2.3.5.2 Minimum
Insurance Amounts The Contractor shall procure and maintain, during the entire period of performance under this contract, the following minimum insurance coverage:
Comprehensive General Liability: $500,000 per occurrence
Automobile Liability: $200,000 per person, $500,000 per occurrence, $20,000 per occurrence for property damage
Workmen's Compensation: As required by Federal and state worker's compensation and occupational disease statutes
Employer's Liability coverage: $100,000, except in states where worker's compensation may not be written by private carriers
Other as required by state law
2.3.6 Protection of
Government Property
During execution of the work, the Contractor shall protect Government property. The Contractor shall return areas damaged as a result of Contractor negligence under this contract to their original condition at no cost to the Government.
2.3.7 Directives, Instructions, and References
Department of Defense (DoD), Secretary of the Navy (SECNAV), Chief of Naval Operations (OPNAV), and other applicable Directives, Instructions, and References are listed in J-0200000-03. The Contractor shall comply with the most current version of directives, instructions, and references including versions published during the term of the contract.
2.3.8 Invoicing
Procedures
Refer to Section G for invoicing instructions.
2.3.9 Forms Refer to Section F for Deliverables Forms.
2.4 Government-
Furnished Items The Government (Norfolk Utilities Department) will make available all drawings, including all revisions and upgrades, indicating the location of known underground utilities in the area to be scoped. These shall be used only as a baseline as to what might be in the area and it should be assumed that the drawings are complete.
2.4.1 Government-
Furnished Property
(GFP)
N/A
2.4.2 Government-
Furnished Facilities
N/A
2.4.3 Government-
Furnished Vehicles and Equipment
N/A
2.4.4 Government-
Furnished Utilities
2.5 Contractor-
Furnished Items
Except for items identified as Government Furnished, the Contractor shall provide all equipment, materials, parts, supplies, components, and facilities to perform the requirements of this contract. The KO may inspect Contractor-furnished items for adequacy and compliance with contract requirements.
Inadequate or unsafe items shall be removed and replaced by the Contractor at no cost to the Government. Materials containing asbestos, lead, and polychlorinated biphenyls (PCBs) shall not be brought onsite. Energy efficient tools and equipment shall be used when available. The KO may at any time require Samples, Safety Data Sheets (SDS) or Manufacturer’s Data Cut Sheets of Materials used in this contract.
a. Materials. The Contractor shall provide all supplies to perform work as required by this contract.
b. Equipment. All items of equipment necessary to perform work as required or ordered under this contract shall be furnished, maintained and operated by the Contractor including all locating devises and marking devises. All safety items such as but not limited to, warning signs, warning tape and/or barricades, when required by the Contracting Officer, shall also be furnished by the contractor.
c. Communication Equipment. The Contractor shall obtain, at his own expense, standard local and/or toll free telephone service, a facsimile (fax) machine, cellular telephone service and e-mail address, necessary for the performance of the contract. The Contractor shall provide the Contracting Officer with a telephone number by which the Contractor shall receive after-hour service calls. The standard and cellular telephone service provided by the Contractor shall be available to the Government 24 hours a day, seven days a week. The Contracting Officer must approve any frequency used with portable two-way radios.
The frequency shall be submitted in writing within 15 days after award of the contract. Within 15 days after award of this Contract, the Contractor’s Supervisor must provide the Contracting Officer with the work reception desk’s local telephone number (toll free), e-mail address, fax number and a local Emergency telephone number (toll free) for after normal business hour use, and the Supervisor’s personal pager number.
The Government shall not call a series of phone numbers to locate the Contractor or the designated Representative.
d. Work Reception Desk. The Contractor shall maintain a work reception desk.
2.6 Management The Contractor shall manage the total work effort associated with the services required herein to meet the performance objectives and standards. Such management includes but is not limited to planning, scheduling, cost accounting, report preparation, establishing and maintaining records, and quality assurance. The Contractor shall provide a staff with the necessary management expertise to ensure performance objectives and standards are met.
2.6.1 Safeguarding
Information
The Contractor shall safeguard controlled unclassified information and information associated with Government property in accordance with the latest revision of CNSSI 1253, DoDI 8582.01, NIST SP 800-53, NIST SP 800-171, SECNAV Defense Industrial Base (DIB) Memo, and applicable contract clauses. At a minimum, this information shall be protected at the moderate confidentiality level as defined in NIST SP 800-171.
Contractor information and data systems that contain information associated with Government property shall comply with DoD Risk Management Framework (RMF).
The Contractor shall develop Plans of Action and Milestones (POA&Ms) per NIST SP 800-171, track accomplishment, and submit to the Government per Section F.
If a cybersecurity incident is encountered or suspected related to any (Contractor or Government) Information Technology (IT) or Operating Technology (OT) systems, including Monitoring and Control Systems, the Contractor shall notify the Government per Section F.
2.6.2 Dissemination of
Information
If certain information cannot be provided to the public, state what information cannot be provided, when it will be provided, and to whom, e.g., DoD policy limits the dissemination of certain information. Instructions, Directives, and References not releasable to the public, e.g., Floor Plans, Maps, Post Orders, and Standard Operating Procedures, will be made available after contract award to the successful offeror with appropriate credentials and a need to know.
2.6.3 Work Reception The Contractor shall provide the capability to receive, prioritize, correspond, and respond to trouble/service calls and task orders during Government regular working hours and provide a point of contact at a local or toll free number who can perform the above function during other than Government regular working hours.
2.6.4 Work Control The Contractor shall implement all necessary work control procedures to ensure timely accomplishment of work requirements, as well as to permit tracking and reporting of work in progress. The Contractor shall plan and schedule work to assure material, labor, and equipment are available to complete work requirements within the specified time limits and in conformance with the quality standards established herein. Verbal scheduling and work status updates shall be provided when requested by the Government. A status update of any item of work must be provided within two hours of the inquiry during regular working hours, and by 0800 the following work day for inquiries after regular working hours.
The Contractor shall provide work schedules per Section F. At a minimum, work schedules shall include:
• Description of service(s) to be accomplished
• Location
• Date service(s) are scheduled to be accomplished
2.6.5 Work Schedule The Contractor's work shall not interfere with normal Government business.
In those cases where some interference is unavoidable, the Contractor shall minimize the impact and effects of the interference. The Contractor shall provide advance access of all of its work schedules to the Government. The Contractor shall provide written notification of any difficulty in scheduling work due to Government controls, per Section F. At a minimum, the notification shall include the following:
• The date and time the work was initially coordinated.
• The name and phone number of the Government person with whom the work was initially coordinated.
• The name and phone number of the Government person who prevented the work from being performed as previously coordinated.
• The alternative date and time, the Government person requested the work be accomplished.
2.6.6 Deliverables Except where otherwise stated, deliverable requirements are specified in
Sections C, F, H, I, J, and within the Directives, Instructions, and References.
The Contractor shall submit accurate and complete documents within the specified timeframes. The Contractor shall revise/modify deliverables, as directed by the KO, at no additional cost to the Government.
Except where otherwise specified, all deliverables shall be submitted electronically in a Microsoft Office Version 2010 compatible format.
Deliverables shall include the company name, contract number, contract title, date, and shall be unprotected and capable of being sorted by CLIN, work order number, asset number, section, annex/sub-annex, spec item and ELIN/Sub-ELIN or clause. All formulas shall be traceable.
Government acceptance of deliverables shall not relieve the Contractor of the responsibility for any error or omission which may exist in the deliverable, as the Contractor is responsible for all requirements of this contract.
2.6.7 Service
Interruptions
If any utilities or other services must be discontinued (even temporarily) due to scheduled contract work, the Contractor shall notify the KO, COR, affected tenants, and customers in accordance with local procedures. If the discontinued service is due to an emergency breakdown the Contractor shall notify the KO, COR, affected tenants, and customers as soon as practicable and provide the status of repairs, as directed by the KO, until normal operation is restored.
Scheduled utility outages and interruptions to equipment, system(s) operation, or other services shall be scheduled after hours of operation.
The…