This document is a Schedule of Indefinite Quantity Work for a Roofing and Exterior Painting IDIQ Contract. It outlines pricing and specifications for a wide range of roofing, waterproofing, painting, and miscellaneous construction tasks to be performed on various projects at the U.S. Marine Corps Air Station in Iwakuni, Japan.

The contract has four ordering periods, with pricing and estimated quantities for each period provided in separate exhibits. The work includes removing and replacing roofing systems, coatings, flashing, gutters, and related items; painting and surface preparation for steel, concrete, and other substrates; and various repair and maintenance activities. Specific tasks are detailed along with estimated quantities and unit prices. The contract also includes requirements for lead-based paint and asbestos abatement, sampling, and disposal. This document serves as a comprehensive pricing schedule for the IDIQ contract.

View the file

Other files

Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

EXIBIT-A

ROOFING AND PAINTING SCHEDULE OF INDEFINITE QUANTITY WORK
SCHEDULE OF INDEFINITE QUANTITY WORK - "A"
EXHIBIT A Price for Ordering Period 1
ITEMDESCRIPTIONESTUTUNITEST AMT
NOQTYPRICETOTAL
ROOFING
A001Remove all existing mineral surfaced built-up roofing.1,000SM¥¥0
A002Remove all existing sheet waterproofing.100SM¥¥0
A003Remove all existing urethane waterproof coating.100SM¥¥0
A004Remove existing mineral surfaced built-up roofing. (100% vertical area , 5% horizontal area)1,500SM¥¥0
A005Remove existing sheet waterproofing. (100% vertical area , 5% horizontal area)100SM¥¥0
A006Remove existing urethane waterproof coating. (100% vertical area , 5% horizontal area)100SM¥¥0
A007Remove existing insulation board.400SM¥¥0
A008Remove existing asbestos contained mineral surfaced built-up roofing.500SM¥¥0
A009Remove existing asbestos contained sheet waterproof.300SM¥¥0
A010Remove existing asbestos contained waterproof coating.100SM¥¥0
A011Clean up existing built-up roofing surface by water blasting.2,000SM¥¥0
A012Clean up existing gutter surface by water blasting.200LM¥¥0
A013Cut and remove existing local deteriorated asphalt roofing system and repair them.200SM¥¥0
A014Repair existing blister of asphalt roofing system.
100SM¥¥0
A015Repair existing concrete covering of the slab.100LM¥¥0
A016Repair existing concrete crack with U-cut.200LM¥¥0
A017Provide polymer modified bitumen roofing system with heat resistant rigid urethane insulation board on existing mineral surfaced built-up roofing (up to 300SM).100SM¥¥0
A018Provide polymer modified bitumen roofing system with heat resistant rigid urethane insulation board on existing mineral surfaced built-up roofing (over 300SM).800SM¥¥0
A019Provide polymer modified bitumen roofing system with heat resistant rigid urethane insulation board on existing urethane membrane waterproof coating (up to 300SM).100SM¥¥0
A020Provide polymer modified bitumen roofing system with heat resistant rigid urethane insulation board on existing urethane membrane waterproof coating (over 300SM).500SM¥¥0
A021Provide polymer modified bitumen roofing system with heat resistant rigid urethane insulation board on existing concrete slab or concrete covering (up to 300SM).
100SM¥¥0
A022Provide polymer modified bitumen roofing system with heat resistant rigid urethane insulation board on existing concrete slab or concrete covering (over 300SM).500SM¥¥0
A023Provide polymer modified bitumen roofing system on existing mineral surfaced built-up roofing (up to 300SM).200SM¥¥0
A024Provide polymer modified bitumen roofing system on existing mineral surfaced built-up roofing (over 300SM).
500SM¥¥0
A025Provide polymer modified bitumen roofing system on existing urethane membrane waterproof coating (up to 300SM).
100SM¥¥0
A026Provide polymer modified bitumen roofing system on existing urethane membrane waterproof coating (over 300SM).
400SM¥¥0
A027Provide polymer modified bitumen roofing system on existing concrete slab or concrete cover (up to 300SM).
100SM¥¥0
A028Provide polymer modified bitumen roofing system on existing concrete slab or concrete cover (over 300SM).
400SM¥¥0
A029Provide polymer modified bitumen roofing system on existing riser surface.
200SM¥¥0
A030Provide urethane membrane waterproof coating system on existing mineral surfaced built-up roofing (up to 300SM).
100SM¥¥0
A031Provide urethane membrane waterproof coating system on existing mineral surfaced built-up roofing (over 300SM).
400SM¥¥0
A032Provide urethane membrane waterproof coating system on existing urethane membrane waterproof coating (up to 300SM).
200SM¥¥0
A033Provide urethane membrane waterproof coating system on existing urethane membrane waterproof coating (over 300SM).400SM¥¥0
A034Provide urethane membrane waterproof coating system on existing concrete slab or concrete cover (up to 300SM).200SM¥¥0
A035Provide urethane membrane waterproof coating system on existing concrete surface (over 300SM).
400SM¥¥0
A036Provide urethane membrane waterproof coating system on existing riser surface.
50SM¥¥0
A037Provide urethane membrane waterproof coating system on existing & concrete structure and foundation surface.50SM¥¥0
A038Provide mineral surfaced built-up roofing for maintenance access.
50SM¥¥0
A039Remove existing asphalt shingle roofing system and provide asphalt shingle roofing system.
100SM¥¥0
A040Remove existing asbestos contained asphalt shingle roofing & asphalt roofing felt and provide asphalt shingle roofing & asphalt roofing felt.100SM¥¥0
A041Apply heat resistant coating on existing mineral surfaced built-up roofing or urethane membrane waterproof coating surface (up to 300SM).
250SM¥¥0
A042Apply heat resistant coating on existing mineral surfaced built-up roofing or urethane membrane waterproof coating surface (over 300SM).
1,000SM¥¥0
A043Provide polymer modified bitumen roofing system on steel surface of vent pipe.
10EA¥¥0
A044Remove existing roof tile & asphalt roofing felt and provide structural plywood, asphalt roofing felt and roof tile on existing sheathing roof board.100SM¥¥0
A045Remove existing fascia & gable wood board and provide wood fascia & gable board.
50LM¥¥0
A046Provide 0.6 thk precoated galvanized metal sheet on the existing fascia & gable board.
50LM¥¥0
A047Remove existing metal roof and provide high profile folded sheet metal roof.
20SM¥¥0
A048Remove existing metal roof and provide low profile folded sheet metal roof.
30SM¥¥0
A049Provide precoated galvanized metal roof on existing metal roof.
30SM¥¥0
A050Remove existing metal roof fascia & gable and provide precoated galvanized metal fascia & gable.30LM¥¥0
A051Remove existing slate roofing system and provide slate roofing system.50SM¥¥0
A052Remove existing sheet roofing and provide synthetic polymer roofing system.50SM¥¥0
A053Remove existing sheet roofing and provide synthetic polymer roofing system with heat resistant rigid insulation board.
70SM¥¥0
A054Remove existing expansion joint filler & sealant and provide expansion joint filler & sealant .100LM¥¥0
A055Provide SST air ventilator pipe.40EA¥¥0
A056Remove existing cement mortar cover and/or various sheet waterproof for existing vent pipe and provide polymer modified bitumen roofing system around existing vent pipe with SST band.
50EA¥¥0
A057Remove existing aluminum coping and provide aluminum coping.
300LM¥¥0
A058Remove existing PC coping and provide aluminum coping.
100LM¥¥0
A059Remove existing aluminum coping temporarily and reinstall existing aluminum coping.
200LM¥¥0
A060Provide aluminum coping to existing concrete parapet/wall.200LM¥¥0
A061Remove existing aluminum expansion cover (up to W=450) and provide aluminum expansion cover.
70LM¥¥0
A062Remove existing aluminum expansion cover (W=450 ~ 600) and provide aluminum expansion cover.
100LM¥¥0
A063Remove existing metal strap with sealant and provide aluminum strap with sealant.
300LM¥¥0
A064Provide aluminum strap with sealant.
200LM¥¥0
A065Remove existing aluminum strap or flashing with sealant and provide aluminum flashing with sealant.
200LM¥¥0
A066Provide aluminum flashing with sealant.
100LM¥¥0
A067Remove existing metal flashing and provide precoated galvanized flashing of roof edge.
100LM¥¥0
A068Remove existing metal flashing and provide aluminum or stainless steel flashing of roof edge.
100LM¥¥0
A069Remove existing horizontal roof drain strainer with clamping base and provide copper roof drain and aluminum die-cast strainer.
40EA¥¥0
A070Remove existing horizontal roof drain strainer with clamping base temporarily. Clean/repaint existing roof drain, strainer and clamping base and reinstall them.40EA¥¥0
A071Remove existing vertical roof drain strainer with clamping base and provide copper roof drain and aluminum die-cast strainer.50EA¥¥0
A072Remove existing vertical roof drain strainer with clamping base temporarily. and clean/repaint existing roof drain, strainer and clamping base and reinstall them.50EA¥¥0
A073Provide urethane membrane waterproof coating system on existing cement mortar surface of roof gutter (up to W=200).20LM¥¥0
A074Provide urethane membrane waterproof coating system on existing cement mortar surface of roof gutter (W=200~400).50LM¥¥0
A075Provide urethane membrane waterproof coating system on existing cement mortar surface of roof gutter (over W=400).50LM¥¥0
A076Remove existing stainless mesh strainer in the gutter and provide SST mesh strainer.30EA¥¥0
A077Remove existing rain gutter & gutter hanger and provide PVC gutter & stainless gutter hanger.50LM¥¥0
A078Remove existing downspout with leader straps and provide PVC downspout with SST leader straps with concrete splash block.50LM¥¥0
A079Remove existing concrete foundation.20CM¥¥0
A080Remove existing cement mortar and provide waterproof cement mortar for existing concrete foundation.20SM¥¥0
A081Provide raised concrete foundation (300x300~400x400x200H).10EA¥¥0
A082Provide raised concrete foundation (400x400~600x600x300H).10EA¥¥0
A083Provide raised concrete foundation (over 600x600x300H).10EA¥¥0
A084Remove temporarily and reinstall existing mechanical equipment (various capacity A/C outside unit) and concrete block base. Replace existing rubber sheet and anti-vibration rubber with.10EA¥¥0
A085Temporarily lifting of existing conductors for lightning protection, remove existing support materials and provide new.10EA¥¥0
A086Cut and weld existing steel leg (up to 40x40 angle or up to 40x75 channel) of steel pipe support for mechanical pipe lines (including associated works). Remove existing isolation rubber sheet and provide isolation rubber sheet.10EA¥¥0
A087Cut and weld existing steel leg (up to 75x75 angle or up to 65x125 channel) of steel pipe support for mechanical pipe lines (including associated works). Remove existing isolation rubber sheet and provide isolation rubber sheet.30EA¥¥0
A088Cut and weld existing steel leg (over 75x75 angle or up to 65x125 channel) of steel pipe support for mechanical pipe lines (including associated works). Remove existing isolation rubber sheet and provide isolation rubber sheet.30EA¥¥0
A089Cut and weld existing steel leg (up to 40x40 angle or up to 40x75 channel) of steel pipe support for mechanical pipe lines (including associated works). Remove existing concrete base and isolation rubber sheet and provide concrete base and isolation rubber sheet.30EA¥¥0
A090Cut and weld existing steel leg (up to 75x75 angle or up to 65x125 channel) of steel pipe support for mechanical pipe lines (including associated works). Remove existing concrete base and isolation rubber sheet and provide concrete base and isolation rubber sheet.30EA¥¥0
A091Cut and weld existing steel leg (over 75x75 angle or over 65x125 channel) of steel pipe support for mechanical pipe lines (including associated works). Remove existing concrete base and isolation rubber sheet and provide concrete base and isolation rubber sheet.20EA¥¥0
A092Remove existing steel leg with concrete base and provide steel leg support with isolation rubber sheet.20EA¥¥0
A093Paint/Repaint exposed surface of existing steel & wood surfaces.20LM¥¥0
A094Repaint exposed surface of existing lead based paint contained steel surfaces.20LM¥¥0
A095Erect and dismantle scaffolding.2,000SM¥¥0
A096Erect and dismantle safety handrail to the parapet for roof work.500LM¥¥0
A097ACM sampling of existing roofing material.10EA¥¥0
A098ACM sampling of existing roofing material and request sampling analysis.50EA¥¥0
A099LBP sampling of existing painted steel surface at roof.5EA¥¥0
A100LBP sampling of existing painted steel surface at roof and request sampling analysis.20EA¥¥0
A101Temporary enclosure for ACM / LBP control area.400SM¥¥0
A102Air, wipe and / or soil sampling and monitoring for ACM / LBP control area.
40EA¥¥0
A103PCM air sampling and monitoring for ACM / LBP control.40EA¥¥0
A104TEM air sampling and monitoring for ACM / LBP control.40EA¥¥0
A105Change room for ACM / LBP control area.10EA¥¥0
A106Disposal of ACM / LBP.30CM¥¥0
A107Remove existing acrylic skylight and provide acrylic skylight (±600x600).
20EA¥¥0
A108Remove existing acrylic skylight and provide acrylic skylight (±900x900).
20EA¥¥0
A109Remove existing acrylic skylight and provide acrylic skylight (±1300x1300).
15EA¥¥0
A110Provide 50dia stainless steel overflow drain pipe with mesh.40EA¥¥0
A111Provide cast-iron vent cap over exist vent pipe.20EA¥¥0
A112Temporary remove, clean and reinstall existing aluminum roof skylight canopy (up to 30 SM).5EA¥¥0
A113Temporary remove, clean and reinstall existing skylight/ventilator.20EA¥¥0
PAINTING
A114Prepare Lead-free surfaces with water cleaning.31,000SM¥¥0
A115Remove debris and clean existing gutter.600LM¥¥0
A116Remove debris and clean existing downspout.200EA¥¥0
A117Prepare Lead-free surfaces with SSPCW Type 3 (RC-Type).5,000SM¥¥0
A118Prepare Lead-free surfaces with SSPCW Type 2 (RB-Type).2,000SM¥¥0
A119Prepare Lead-free surfaces with SSPCW Type 1 (RA-Type).1,000SM¥¥0
A120Remove existing paint for no-paint concrete surfaces and trowel finish repair.300SM¥¥0
A121Repaint existing steel and galvanized steel siding/ roof/ wall surfaces with polyurethane type paint. 300SM >2,500SM¥¥0
A122Repaint existing steel and galvanized steel siding/ roof/ wall surfaces with polyurethane type paint. 300SM <200SM¥¥0
A123Repaint existing wooden siding and board surfaces.500SM¥¥0
A124Repaint existing calcium silicate board surfaces after surface preparation.1,000SM¥¥0
A125Repaint existing wooden beams and columns after surface preparation.500SM¥¥0
A126Repaint existing steel doors / Roll up doors and door frames.100SM¥¥0
A127Repaint existing steel doors / Roll up doors and door frames w/ water-based paint and water-based primer.100SM¥¥0
A128Repaint existing steel window and window frames.50SM¥¥0
A129Repaint existing steel square pipe surfaces, up to 400mm outside perimeter with polyurethane type coating.3,000LM¥¥0
A130Repaint existing steel square pipe surfaces, up to 800mm outside perimeter with polyurethane type coating.3,000LM¥¥0
A131Repaint existing steel square pipe surfaces, up to 1200mm outside perimeter with polyurethane type coating.1,000LM¥¥0
A132Repaint existing steel H-section surfaces, up to 150mm height with polyurethane type coating.1,000LM¥¥0
A133Repaint existing steel H-section surfaces, up to 250mm height with polyurethane type coating.2,000LM¥¥0
A134Repaint existing steel H-section surfaces, up to 350mm height with polyurethane type coating.2,000LM¥¥0
A135Repaint existing steel H-section surfaces, up to 450mm height with polyurethane type coating.1,000LM¥¥0
A136Repaint existing steel channel surfaces, up to 50mm height with polyurethane type coating.3,000LM¥¥0
A137Repaint existing steel channel surfaces, up to 100mm height with polyurethane type coating.2,000LM¥¥0
A138Repaint existing steel channel surfaces, up to 150mm height with polyurethane type coating.2,000LM¥¥0
A139Repaint existing steel and galvanized steel box surfaces.50SM¥¥0
A140Repaint existing steel doors and door frames with polyurethane type coating.150SM¥¥0
A141Repaint existing steel windows and window frames with polyurethane type coating.30SM¥¥0
A142Repaint existing steel and galvanized steel box surfaces with polyurethane type coating.20SM¥¥0
A143Repaint existing wood doors and door frames.
200SM¥¥0
A144Repaint existing glazed wood windows and frames.
100SM¥¥0
A145Repaint existing aluminum panel surfaces.500SM¥¥0
A146Repaint existing steel and galvanized steel pipe surfaces, up to 50mm outside diameter.
250LM¥¥0
A147Repaint existing steel and galvanized steel pipe surfaces, up to 50mm outside diameter with polyurethane type coating.150LM¥¥0
A148Repaint existing steel and galvanized steel pipe surfaces, up to 150mm outside diameter.
200LM¥¥0
A149Repaint existing steel and galvanized steel pipe surfaces, up to 150mm outside diameter with polyurethane type coating.150LM¥¥0
A150Repaint existing steel and galvanized steel pipe surfaces, up to 300mm outside diameter.
200LM¥¥0
A151Repaint existing steel and galvanized steel pipe surfaces, up to 300mm outside diameter with polyurethane type coating.150LM¥¥0
A152Repaint existing steel and galvanized steel pipe surfaces, up to 600mm outside diameter.
100LM¥¥0
A153Repaint existing steel and galvanized steel pipe surfaces, over 600mm outside diameter with polyurethane type coating.50LM¥¥0
A154Paint existing galvanized steel pipe surfaces, up to 50mm outside diameter.
250LM¥¥0
A155Paint existing galvanized steel pipe surfaces, up to 50mm outside diameter with polyurethane type coating.150LM¥¥0
A156Paint existing galvanized steel pipe surfaces, up to 150mm outside diameter.
200LM¥¥0
A157Paint existing galvanized steel pipe surfaces, up to 150mm outside diameter with polyurethane type coating.150LM¥¥0
A158Repaint existing PVC gutter surfaces after surface preparation.
1,000LM¥¥0
A159Repaint existing PVC downspout surfaces after surface preparation up to 100mm outside diameter.
1,000LM¥¥0
A160Repaint existing PVC downspout surfaces after surface preparation up to 200mm outside diameter.
100LM¥¥0
A161Repaint existing concrete, concrete masonary unit(CMU), and cement mortar surfaces. 300SM >
2,000SM¥¥0
A162Repaint existing concrete, concrete masonary unit(CMU), and cement mortar surfaces. 300SM <
250SM¥¥0
A163Repaint existing multi-layer coating surfaces with rubber type top coating. 300SM >
2,000SM¥¥0
A164Repaint existing multi-layer coating surfaces with rubber type top coating. 300SM <
250SM¥¥0
A165Repaint existing multi-layer coating surfaces with top coating. 300SM >
6,000SM¥¥0
A166Repaint existing multi-layer coating surfaces with top coating. 300SM <
250SM¥¥0
A167Repaint existing building numbers and unit number text.25EA¥¥0
A168Repaint letters, unit: continuous letters (one word)/ EA.100EA¥¥0
A169Repaint existing ACB/Cement board surfaces.50SM¥¥0
A170Repaint fire alarm bell.20EA¥¥0
A171Repaint plaster (Shikkui) surfaces.800SM¥¥0
A172Repaint existing non-slip floor coating.400SM¥¥0
A173Provide urethane roof coating over existing roof coating.2,000SM¥¥0
A174Provide roof coating over existing roof (for single).500SM¥¥0
A175Provide rubber type multi-layer coating system.300SM¥¥0
A176Provide acrylic type multi-layer coating system.500SM¥¥0
A177Provide slight-elastic type multi-layer coating system.500SM¥¥0
A178Provide waterproof urethane type floor coating on concrete and cement mortar surfaces.
50SM¥¥0
A179Provide waterproof epoxy resin non-skid type floor coating on concrete and cement mortar surfaces. 300SM>
300SM¥¥0
A180Provide waterproof epoxy resin non-skid type floor coating on concrete and cement mortar surfaces. 300SM<
100SM¥¥0
A181Provide corrosion-proof non-skid waterproof epoxy resin type floor coating on concrete and cement mortar surfaces (Dog Kennel Floor) . 100SM>250SM¥¥0
A182Provide corrosion-proof non-skid waterproof epoxy resin type floor coating on concrete and cement mortar surfaces (Dog Kennel Floor) . 100SM<100SM¥¥0
A183Provide corrosion-proof waterproof epoxy resin type wall coating on concrete and cement mortar surfaces (Dog Kennel wall) . 100SM>250SM¥¥0
A184Provide corrosion-proof waterproof epoxy resin type wall coating on concrete and cement mortar surfaces (Dog Kennel wall) . 100SM<100SM¥¥0
A185Provide waterproof silicon hydride type coating on concrete and cement mortar foundation surfaces.100SM¥¥0
A186Provide silicon type for foundation use paint on concrete and cement mortar foundation surfaces.100SM¥¥0
A187Remove existing cement mortar, and provide waterproof cement mortar.
50SM¥¥0
A188Remove existing floor coating on concrete and prepare surfaces with resin mortar.
50SM¥¥0
A189Repair concrete spalling.50SM¥¥0
A190Repair concrete crack with Seal method.1,000LM¥¥0
A191Repair concrete crack with U-cut seal material filling method.1,000LM¥¥0
A192Repair concrete crack with epoxy resin injection method.200LM¥¥0
A193Remove existing cement board and provide cement board.250SM¥¥0
A194Remove existing metal flashing and provide metal flashing.500LM¥¥0
A195Remove existing ALUM expansion joint and provide ALUM expansion joint (Exterior wall + Exterior wall 100mm type).20LM¥¥0
A196Remove existing ALUM expansion joint and provide ALUM expansion joint (Exterior wall + Exterior wall corner 100mm type).20LM¥¥0
A197Remove existing SST expansion joint and provide stainless steel expansion joint (Floor + Floor 100mm type).20LM¥¥0
A198Remove existing SST expansion joint and provide stainless steel expansion joint (Floor + Floor corner 100mm type).20LM¥¥0
A199Remove existing aluminum expansion joint and provide aluminum expansion joint (Exterior wall + Exterior wall corner 200mm type).20LM¥¥0
A200Remove existing galvanized steel sheet and provide galvanized steel sheet.
400SM¥¥0
A201Remove existing reinforced FRP and provide reinforced FRP.
100SM¥¥0
A202Remove existing vent cover and provide aluminum air vent cover (up to 200mm diameter).200EA¥¥0
A203Remove existing vent cover and provide SST deep type air vent cover (up to 200mm diameter).50EA¥¥0
A204Remove existing vent cover and provide SST deep type air vent cover (200mm and over diameter).20EA¥¥0
A205Provide building number sign.20EA¥¥0
A206Provide ALUM building identification signs (H=610mm).50EA¥¥0
A207Provide ALUM building identification signs (H=457mm).50EA¥¥0
A208Provide ALUM building identification signs (H=305mm).50EA¥¥0
A209Provide SST building identification signs (H=610mm).10EA¥¥0
A210Provide SST building identification signs (H=457mm).10EA¥¥0
A211Provide SST building identification signs (H=305mm).10EA¥¥0
A212Provide SST illuminated signs with Electrical work.30EA¥¥0
A213Remove existing building signs.50EA¥¥0
A214Remove existing sealants for windows/ doors and provide sealants for windows/ doors.
1,500LM¥¥0
A215Remove existing joint sealants and provide joint sealants.1,000LM¥¥0
A216Remove existing wood window w/ glazing and provide wood window w/ tinted glazing including ALUM bottom and upper guide rails. Paint wood window and frames.
10SM¥¥0
A217Remove damaged decorative wood post and filler and provide decorative wood post and filler (up to 150mm x 150mm).
1LM¥¥0
A218Remove damaged wood beam and provide wood beam (up to 400mm x 200mm).
1LM¥¥0
A219Remove half-round PVC gutter and provide half-round PVC gutter (up to W=200mm).100LM¥¥0
A220Remove square PVC gutter and provide square PVC gutter (up to radius 200mm).100LM¥¥0
A221Remove PVC downspout and provide PVC downspout (up to 125mm outside diameter).50LM¥¥0
A222Remove PVC downspout and provide PVC downspout (up to 200mm outside diameter).200LM¥¥0
A223Remove existing downspout bracket and band and provide SST bracket and band.200EA¥¥0
A224Remove damaged polycarbonate roofing and provide polycarbonate (THK=5mm).10SM¥¥0
A225Remove damaged clear glass panes on aluminum framed door or window and provide clear glass panes.
5SM¥¥0
A226Remove damaged frosted glass panes on aluminum framed door or window and provide frosted glass panes.
5SM¥¥0
A227Remove damaged tempered glass panes on aluminum framed door or window and provide tempered glass panes.
5SM¥¥0
A228Remove damaged wired glass panes on aluminum framed door or window and provide wired glass panes.
5SM¥¥0
A229Remove existing acrylic lighting fixture covers and provide acrylic lighting fixture covers.
20EA¥¥0
A230Patch repair hole on steel and galvanized steel with galvanized steel sheet, Unit: up to 0.05SM hole/EA.
100EA¥¥0
A231Remove existing ACB and provide cement board.50SM¥¥0
A232Patch repair hole of ACB with galvanized steel sheet/FRP, Unit: Up to 0.50SM hole/EA.
20EA¥¥0
A233LBP surface preparation with SSPCW Type 3.200SM¥¥0
A234LBP surface preparation with solvent cleaning.200SM¥¥0
A235ACM surface preparation with solvent cleaning.
200SM¥¥0
A236Provide temporary enclosure for LBP / ACM control area.800SM¥¥0
A237Air, wipe and/or soil sampling and monitoring for LBP control area.
25EA¥¥0
A238PCM air sampling and monitoring for ACM control.25EA¥¥0
A239TEM air sampling and monitoring for ACM control.25EA¥¥0
A240Provide temporary Change Room for LBP / ACM control area.10EA¥¥0
A241Disposal of LBP / ACM.5CM¥¥0
A242ACM sampling of existing material.10EA¥¥0
A243Laboratory reports of ACM sampling of existing material.10EA¥¥0
A244LBP sampling of existing steel surfaces of material.10EA¥¥0
A245Laboratory reports of LBP sampling of existing steel surfaces of material.10EA¥¥0
A246Provide bucket truck lift.10DAY¥¥0
A247Provide scaffolding.6,000SM¥¥0
A248Provide safety barricade and safety sign.2,000LM¥¥0
A249Remove and provide pigeon net, Unit: Up to 16SM of opening size/EA.
50EA¥¥0
A250Remove and provide bird spike, Unit: Up to 10LM of length size/EA.
50EA¥¥0
A251Temporarily remove and reinstall existing steel window security grills, Unit: Up to 2SM of guard size/EA.
50EA¥¥0
A252Temporarily remove and reinstall existing steel window security grills, Unit: Up to 3SM of guard size/EA.
20EA¥¥0
A253Temporarily remove and reinstall existing steel window security grills, Unit: Up to 4SM of guard size/EA.
20EA¥¥0
A254Clean existing SST handrails.150SM¥¥0
A255Clean existing SST guardrails.200LM¥¥0
A256Clean existing SST surfaces.200SM¥¥0
A257Clean existing ALUM / glass windows and frames.200LM¥¥0
A258Other related miscellaneous work (must be negotiated at time of order). (Estimated)

1 LS ¥ ¥ 60,000,000

TOTAL (A001 through A258) Not-To-Exceed ¥ 0

Abbreviations:
ALUM=Aluminum, EST AMT = Estimated Amount, EST QTY = Estimated Quantity, SM = Square Meter, LM = Linear Meter, CM Cubic Meter, EA = Each, LS = Lump Sum, ACB = Asbestos Cement Board, PCM = Phase Contrast Microscopy, TEM = Transmission Electron Microscopy, LBP = Lead Based Paint, ACM = Asbestos Contain Material, H = Height, W = Width, SSPCW = Standard Specifications for Public Construction Work, SST = Stainless Steel

&8&K000000Roofing and Painting IDIQ Contract for Various Projects &9 &"-,Bold"&10CUI//FEDCON [when filled in] Source Selection Information-See FAR 2 101 and 3.104 [when filled in]

&"-,Bold"&8&K000000CUI//FEDCON [when filled in] Source Selection Information-See FAR 2 101 and 3.104 [when filled in]&"-,Regular"&10 &"-,Bold"ROOFING AND PAINTING SCHDULE OF INDEFINITE QUANTITY WORK - "A"&"-,Regular"

PAGE &P

EXIBIT-B

ROOFING AND PAINTING SCHEDULE OF INDEFINITE QUANTITY WORK
SCHEDULE OF INDEFINITE QUANTITY WORK - "B"
EXHIBIT B Price for Ordering Period 2
ITEMDESCRIPTIONESTUTUNITEST AMT
NOQTYPRICETOTAL
ROOFING
B001Remove all existing mineral surfaced built-up roofing.1,000SM¥¥0
B002Remove all existing sheet waterproofing.100SM¥¥0
B003Remove all existing urethane waterproof coating.100SM¥¥0
B004Remove existing mineral surfaced built-up roofing. (100% vertical area , 5% horizontal area)1,500SM¥¥0
B005Remove existing sheet waterproofing. (100% vertical area , 5% horizontal area)100SM¥¥0
B006Remove existing urethane waterproof coating. (100% vertical area , 5% horizontal area)100SM¥¥0
B007Remove existing insulation board.400SM¥¥0
B008Remove existing asbestos contained mineral surfaced built-up roofing.500SM¥¥0
B009Remove existing asbestos contained sheet waterproof.300SM¥¥0
B010Remove existing asbestos contained waterproof coating.100SM¥¥0
B011Clean up existing built-up roofing surface by water blasting.2,000SM¥¥0
B012Clean up existing gutter surface by water blasting.200LM¥¥0
B013Cut and remove existing local deteriorated asphalt roofing system and repair them.200SM¥¥0
B014Repair existing blister of asphalt roofing system.
100SM¥¥0
B015Repair existing concrete covering of the slab.100LM¥¥0
B016Repair existing concrete crack with U-cut.200LM¥¥0
B017Provide polymer modified bitumen roofing system with heat resistant rigid urethane insulation board on existing mineral surfaced built-up roofing (up to 300SM).100SM¥¥0
B018Provide polymer modified bitumen roofing system with heat resistant rigid urethane insulation board on existing mineral surfaced built-up roofing (over 300SM).800SM¥¥0
B019Provide polymer modified bitumen roofing system with heat resistant rigid urethane insulation board on existing urethane membrane waterproof coating (up to 300SM).100SM¥¥0
B020Provide polymer modified bitumen roofing system with heat resistant rigid urethane insulation board on existing urethane membrane waterproof coating (over 300SM).500SM¥¥0
B021Provide polymer modified bitumen roofing system with heat resistant rigid urethane insulation board on existing concrete slab or concrete covering (up to 300SM).
100SM¥¥0
B022Provide polymer modified bitumen roofing system with heat resistant rigid urethane insulation board on existing concrete slab or concrete covering (over 300SM).500SM¥¥0
B023Provide polymer modified bitumen roofing system on existing mineral surfaced built-up roofing (up to 300SM).200SM¥¥0
B024Provide polymer modified bitumen roofing system on existing mineral surfaced built-up roofing (over 300SM).
500SM¥¥0
B025Provide polymer modified bitumen roofing system on existing urethane membrane waterproof coating (up to 300SM).
100SM¥¥0
B026Provide polymer modified bitumen roofing system on existing urethane membrane waterproof coating (over 300SM).
400SM¥¥0
B027Provide polymer modified bitumen roofing system on existing concrete slab or concrete cover (up to 300SM).
100SM¥¥0
B028Provide polymer modified bitumen roofing system on existing concrete slab or concrete cover (over 300SM).
400SM¥¥0
B029Provide polymer modified bitumen roofing system on existing riser surface.
200SM¥¥0
B030Provide urethane membrane waterproof coating system on existing mineral surfaced built-up roofing (up to 300SM).
100SM¥¥0
B031Provide urethane membrane waterproof coating system on existing mineral surfaced built-up roofing (over 300SM).
400SM¥¥0
B032Provide urethane membrane waterproof coating system on existing urethane membrane waterproof coating (up to 300SM).
200SM¥¥0
B033Provide urethane membrane waterproof coating system on existing urethane membrane waterproof coating (over 300SM).400SM¥¥0
B034Provide urethane membrane waterproof coating system on existing concrete slab or concrete cover (up to 300SM).200SM¥¥0
B035Provide urethane membrane waterproof coating system on existing concrete surface (over 300SM).
400SM¥¥0
B036Provide urethane membrane waterproof coating system on existing riser surface.
50SM¥¥0
B037Provide urethane membrane waterproof coating system on existing & concrete structure and foundation surface.50SM¥¥0
B038Provide mineral surfaced built-up roofing for maintenance access.
50SM¥¥0
B039Remove existing asphalt shingle roofing system and provide asphalt shingle roofing system.
100SM¥¥0
B040Remove existing asbestos contained asphalt shingle roofing & asphalt roofing felt and provide asphalt shingle roofing & asphalt roofing felt.100SM¥¥0
B041Apply heat resistant coating on existing mineral surfaced built-up roofing or urethane membrane waterproof coating surface (up to 300SM).
250SM¥¥0
B042Apply heat resistant coating on existing mineral surfaced built-up roofing or urethane membrane waterproof coating surface (over 300SM).
1,000SM¥¥0
B043Provide polymer modified bitumen roofing system on steel surface of vent pipe.
10EA¥¥0
B044Remove existing roof tile & asphalt roofing felt and provide structural plywood, asphalt roofing felt and roof tile on existing sheathing roof board.100SM¥¥0
B045Remove existing fascia & gable wood board and provide wood fascia & gable board.
50LM¥¥0
B046Provide 0.6 thk precoated galvanized metal sheet on the existing fascia & gable board.
50LM¥¥0
B047Remove existing metal roof and provide high profile folded sheet metal roof.
20SM¥¥0
B048Remove existing metal roof and provide low profile folded sheet metal roof.
30SM¥¥0
B049Provide precoated galvanized metal roof on existing metal roof.
30SM¥¥0
B050Remove existing metal roof fascia & gable and provide precoated galvanized metal fascia & gable.30LM¥¥0
B051Remove existing slate roofing system and provide slate roofing system.50SM¥¥0
B052Remove existing sheet roofing and provide synthetic polymer roofing system.50SM¥¥0
B053Remove existing sheet roofing and provide synthetic polymer roofing system with heat resistant rigid insulation board.
70SM¥¥0
B054Remove existing expansion joint filler & sealant and provide expansion joint filler & sealant .100LM¥¥0
B055Provide SST air ventilator pipe.40EA¥¥0
B056Remove existing cement mortar cover and/or various sheet waterproof for existing vent pipe and provide polymer modified bitumen roofing system around existing vent pipe with SST band.
50EA¥¥0
B057Remove existing aluminum coping and provide aluminum coping.
300LM¥¥0
B058Remove existing PC coping and provide aluminum coping.
100LM¥¥0
B059Remove existing aluminum coping temporarily and reinstall existing aluminum coping.
200LM¥¥0
B060Provide aluminum coping to existing concrete parapet/wall.200LM¥¥0
B061Remove existing aluminum expansion cover (up to W=450) and provide aluminum expansion cover.
70LM¥¥0
B062Remove existing aluminum expansion cover (W=450 ~ 600) and provide aluminum expansion cover.
100LM¥¥0
B063Remove existing metal strap with sealant and provide aluminum strap with sealant.
300LM¥¥0
B064Provide aluminum strap with sealant.
200LM¥¥0
B065Remove existing aluminum strap or flashing with sealant and provide aluminum flashing with sealant.
200LM¥¥0
B066Provide aluminum flashing with sealant.
100LM¥¥0
B067Remove existing metal flashing and provide precoated galvanized flashing of roof edge.
100LM¥¥0
B068Remove existing metal flashing and provide aluminum or stainless steel flashing of roof edge.
100LM¥¥0
B069Remove existing horizontal roof drain strainer with clamping base and provide copper roof drain and aluminum die-cast strainer.
40EA¥¥0
B070Remove existing horizontal roof drain strainer with clamping base temporarily. Clean/repaint existing roof drain, strainer and clamping base and reinstall them.40EA¥¥0
B071Remove existing vertical roof drain strainer with clamping base and provide copper roof drain and aluminum die-cast strainer.50EA¥¥0
B072Remove existing vertical roof drain strainer with clamping base temporarily. and clean/repaint existing roof drain, strainer and clamping base and reinstall them.50EA¥¥0
B073Provide urethane membrane waterproof coating system on existing cement mortar surface of roof gutter (up to W=200).20LM¥¥0
B074Provide urethane membrane waterproof coating system on existing cement mortar surface of roof gutter (W=200~400).50LM¥¥0
B075Provide urethane membrane waterproof coating system on existing cement mortar surface of roof gutter (over W=400).50LM¥¥0
B076Remove existing stainless mesh strainer in the gutter and provide SST mesh strainer.30EA¥¥0
B077Remove existing rain gutter & gutter hanger and provide PVC gutter & stainless gutter hanger.50LM¥¥0
B078Remove existing downspout with leader straps and provide PVC downspout with SST leader straps with concrete splash block.50LM¥¥0
B079Remove existing concrete foundation.20CM¥¥0
B080Remove existing cement mortar and provide waterproof cement mortar for existing concrete foundation.20SM¥¥0
B081Provide raised concrete foundation (300x300~400x400x200H).10EA¥¥0
B082Provide raised concrete foundation (400x400~600x600x300H).10EA¥¥0
B083Provide raised concrete foundation (over 600x600x300H).10EA¥¥0
B084Remove temporarily and reinstall existing mechanical equipment (various capacity A/C outside unit) and concrete block base. Replace existing rubber sheet and anti-vibration rubber with.10EA¥¥0
B085Temporarily lifting of existing conductors for lightning protection, remove existing support materials and provide new.10EA¥¥0
B086Cut and weld existing steel leg (up to 40x40 angle or up to 40x75 channel) of steel pipe support for mechanical pipe lines (including associated works). Remove existing isolation rubber sheet and provide isolation rubber sheet.10EA¥¥0
B087Cut and weld existing steel leg (up to 75x75 angle or up to 65x125 channel) of steel pipe support for mechanical pipe lines (including associated works). Remove existing isolation rubber sheet and provide isolation rubber sheet.30EA¥¥0
B088Cut and weld existing steel leg (over 75x75 angle or up to 65x125 channel) of steel pipe support for mechanical pipe lines (including associated works). Remove existing isolation rubber sheet and provide isolation rubber sheet.30EA¥¥0
B089Cut and weld existing steel leg (up to 40x40 angle or up to 40x75 channel) of steel pipe support for mechanical pipe lines (including associated works). Remove existing concrete base and isolation rubber sheet and provide concrete base and isolation rubber sheet.30EA¥¥0
B090Cut and weld existing steel leg (up to 75x75 angle or up to 65x125 channel) of steel pipe support for mechanical pipe lines (including associated works). Remove existing concrete base and isolation rubber sheet and provide concrete base and isolation rubber sheet.30EA¥¥0
B091Cut and weld existing steel leg (over 75x75 angle or over 65x125 channel) of steel pipe support for mechanical pipe lines (including associated works). Remove existing concrete base and isolation rubber sheet and provide concrete base and isolation rubber sheet.20EA¥¥0
B092Remove existing steel leg with concrete base and provide steel leg support with isolation rubber sheet.20EA¥¥0
B093Paint/Repaint exposed surface of existing steel & wood surfaces.20LM¥¥0
B094Repaint exposed surface of existing lead based paint contained steel surfaces.20LM¥¥0
B095Erect and dismantle scaffolding.2,000SM¥¥0
B096Erect and dismantle safety handrail to the parapet for roof work.500LM¥¥0
B097ACM sampling of existing roofing material.10EA¥¥0
B098ACM sampling of existing roofing material and request sampling analysis.50EA¥¥0
B099LBP sampling of existing painted steel surface at roof.5EA¥¥0
B100LBP sampling of existing painted steel surface at roof and request sampling analysis.20EA¥¥0
B101Temporary enclosure for ACM / LBP control area.400SM¥¥0
B102Air, wipe and / or soil sampling and monitoring for ACM / LBP control area.
40EA¥¥0
B103PCM air sampling and monitoring for ACM / LBP control.40EA¥¥0
B104TEM air sampling and monitoring for ACM / LBP control.40EA¥¥0
B105Change room for ACM / LBP control area.10EA¥¥0
B106Disposal of ACM / LBP.30CM¥¥0
B107Remove existing acrylic skylight and provide acrylic skylight (±600x600).
20EA¥¥0
B108Remove existing acrylic skylight and provide acrylic skylight (±900x900).
20EA¥¥0
B109Remove existing acrylic skylight and provide acrylic skylight (±1300x1300).
15EA¥¥0
B110Provide 50dia stainless steel overflow drain pipe with mesh.40EA¥¥0
B111Provide cast-iron vent cap over exist vent pipe.20EA¥¥0
B112Temporary remove, clean and reinstall existing aluminum roof skylight canopy (up to 30 SM).5EA¥¥0
B113Temporary remove, clean and reinstall existing skylight/ventilator.20EA¥¥0
PAINTING
B114Prepare Lead-free surfaces with water cleaning.31,000SM¥¥0
B115Remove debris and clean existing gutter.600LM¥¥0
B116Remove debris and clean existing downspout.200EA¥¥0
B117Prepare Lead-free surfaces with SSPCW Type 3 (RC-Type).5,000SM¥¥0
B118Prepare Lead-free surfaces with SSPCW Type 2 (RB-Type).2,000SM¥¥0
B119Prepare Lead-free surfaces with SSPCW Type 1 (RA-Type).1,000SM¥¥0
B120Remove existing paint for no-paint concrete surfaces and trowel finish repair.300SM¥¥0
B121Repaint existing steel and galvanized steel siding/ roof/ wall surfaces with polyurethane type paint. 300SM >2,500SM¥¥0
B122Repaint existing steel and galvanized steel siding/ roof/ wall surfaces with polyurethane type paint. 300SM <200SM¥¥0
B123Repaint existing wooden siding and board surfaces.500SM¥¥0
B124Repaint existing calcium silicate board surfaces after surface preparation.1,000SM¥¥0
B125Repaint existing wooden beams and columns after surface preparation.500SM¥¥0
B126Repaint existing steel doors / Roll up doors and door frames.100SM¥¥0
B127Repaint existing steel doors / Roll up doors and door frames w/ water-based paint and water-based primer.100SM¥¥0
B128Repaint existing steel window and window frames.50SM¥¥0
B129Repaint existing steel square pipe surfaces, up to 400mm outside perimeter with polyurethane type coating.3,000LM¥¥0
B130Repaint existing steel square pipe surfaces, up to 800mm outside perimeter with polyurethane type coating.3,000LM¥¥0
B131Repaint existing steel square pipe surfaces, up to 1200mm outside perimeter with polyurethane type coating.1,000LM¥¥0
B132Repaint existing steel H-section surfaces, up to 150mm height with polyurethane type coating.1,000LM¥¥0
B133Repaint existing steel H-section surfaces, up to 250mm height with polyurethane type coating.2,000LM¥¥0
B134Repaint existing steel H-section surfaces, up to 350mm height with polyurethane type coating.2,000LM¥¥0
B135Repaint existing steel H-section surfaces, up to 450mm height with polyurethane type coating.1,000LM¥¥0
B136Repaint existing steel channel surfaces, up to 50mm height with polyurethane type coating.3,000LM¥¥0
B137Repaint existing steel channel surfaces, up to 100mm height with polyurethane type coating.2,000LM¥¥0
B138Repaint existing steel channel surfaces, up to 150mm height with polyurethane type coating.2,000LM¥¥0
B139Repaint existing steel and galvanized steel box surfaces.50SM¥¥0
B140Repaint existing steel doors and door frames with polyurethane type coating.150SM¥¥0
B141Repaint existing steel windows and window frames with polyurethane type coating.30SM¥¥0
B142Repaint existing steel and galvanized steel box surfaces with polyurethane type coating.20SM¥¥0
B143Repaint existing wood doors and door frames.
200SM¥¥0
B144Repaint existing glazed wood windows and frames.
100SM¥¥0
B145Repaint existing aluminum panel surfaces.500SM¥¥0
B146Repaint existing steel and galvanized steel pipe surfaces, up to 50mm outside diameter.
250LM¥¥0
B147Repaint existing steel and galvanized steel pipe surfaces, up to 50mm outside diameter with polyurethane type coating.150LM¥¥0
B148Repaint existing steel and galvanized steel pipe surfaces, up to 150mm outside diameter.
200LM¥¥0
B149Repaint existing steel and galvanized steel pipe surfaces, up to 150mm outside diameter with polyurethane type coating.150LM¥¥0
B150Repaint existing steel and galvanized steel pipe surfaces, up to 300mm outside diameter.
200LM¥¥0
B151Repaint existing steel and galvanized steel pipe surfaces, up to 300mm outside diameter with polyurethane type coating.150LM¥¥0
B152Repaint existing steel and galvanized steel pipe surfaces, up to 600mm outside diameter.
100LM¥¥0
B153Repaint existing steel and galvanized steel pipe surfaces, over 600mm outside diameter with polyurethane type coating.50LM¥¥0
B154Paint existing galvanized steel pipe surfaces, up to 50mm outside diameter.
250LM¥¥0
B155Paint existing galvanized steel pipe surfaces, up to 50mm outside diameter with polyurethane type coating.150LM¥¥0
B156Paint existing galvanized steel pipe surfaces, up to 150mm outside diameter.
200LM¥¥0
B157Paint existing galvanized steel pipe surfaces, up to 150mm outside diameter with polyurethane type coating.150LM¥¥0
B158Repaint existing PVC gutter surfaces after surface preparation.
1,000LM¥¥0
B159Repaint existing PVC downspout surfaces after surface preparation up to 100mm outside diameter.
1,000LM¥¥0
B160Repaint existing PVC downspout surfaces after surface preparation up to 200mm outside diameter.
100LM¥¥0
B161Repaint existing concrete, concrete masonary unit(CMU), and cement mortar surfaces. 300SM >
2,000SM¥¥0
B162Repaint existing concrete, concrete masonary unit(CMU), and cement mortar surfaces. 300SM <
250SM¥¥0
B163Repaint existing multi-layer coating surfaces with rubber type top coating. 300SM >
2,000SM¥¥0
B164Repaint existing multi-layer coating surfaces with rubber type top coating. 300SM <
250SM¥¥0
B165Repaint existing multi-layer coating surfaces with top coating. 300SM >
6,000SM¥¥0
B166Repaint existing multi-layer coating surfaces with top coating. 300SM <
250SM¥¥0
B167Repaint existing building numbers and unit number text.25EA¥¥0
B168Repaint letters, unit: continuous letters (one word)/ EA.100EA¥¥0
B169Repaint existing ACB/Cement board surfaces.50SM¥¥0
B170Repaint fire alarm bell.20EA¥¥0
B171Repaint plaster (Shikkui) surfaces.800SM¥¥0
B172Repaint existing non-slip floor coating.400SM¥¥0
B173Provide urethane roof coating over existing roof coating.2,000SM¥¥0
B174Provide roof coating over existing roof (for single).500SM¥¥0
B175Provide rubber type multi-layer coating system.300SM¥¥0
B176Provide acrylic type multi-layer coating system.500SM¥¥0
B177Provide slight-elastic type multi-layer coating system.500SM¥¥0
B178Provide waterproof urethane type floor coating on concrete and cement mortar surfaces.
50SM¥¥0
B179Provide waterproof epoxy resin non-skid type floor coating on concrete and cement mortar surfaces. 300SM>
300SM¥¥0
B180Provide waterproof epoxy resin non-skid type floor coating on concrete and cement mortar surfaces. 300SM<
100SM¥¥0
B181Provide corrosion-proof non-skid waterproof epoxy resin type floor coating on concrete and cement mortar surfaces (Dog Kennel Floor) . 100SM>250SM¥¥0
B182Provide corrosion-proof non-skid waterproof epoxy resin type floor coating on concrete and cement mortar surfaces (Dog Kennel Floor) . 100SM<100SM¥¥0
B183Provide corrosion-proof waterproof epoxy resin type wall coating on concrete and cement mortar surfaces (Dog Kennel wall) . 100SM>250SM¥¥0
B184Provide corrosion-proof waterproof epoxy resin type wall coating on concrete and cement mortar surfaces (Dog Kennel wall) . 100SM<100SM¥¥0
B185Provide waterproof silicon hydride type coating on concrete and cement mortar foundation surfaces.100SM¥¥0
B186Provide silicon type for foundation use paint on concrete and cement mortar foundation surfaces.100SM¥¥0
B187Remove existing cement mortar, and provide waterproof cement mortar.
50SM¥¥0
B188Remove existing floor coating on concrete and prepare surfaces with resin mortar.
50SM¥¥0
B189Repair concrete spalling.50SM¥¥0
B190Repair concrete crack with Seal method.1,000LM¥¥0
B191Repair concrete crack with U-cut seal material filling method.1,000LM¥¥0
B192Repair concrete crack with epoxy resin injection method.200LM¥¥0
B193Remove existing cement board and provide cement board.250SM¥¥0
B194Remove existing metal flashing and provide metal flashing.500LM¥¥0
B195Remove existing ALUM expansion joint and provide ALUM expansion joint (Exterior wall + Exterior wall 100mm type).20LM¥¥0

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .