Attachment (3) N4008423R3600 WWTP PWS FINAL_rev1.pdf

PDF 10 MB Posted

Attached to
Wastewater Treatment Plant (WWTP) Operation and Maintenance (O&M) Services, White Beach, Okinawa, Japan
Solicitation number
N4008423R3600
Issued by

About this file

This document is a request for proposal for operation and maintenance contract services for a wastewater treatment plant located at White Beach in Okinawa, Japan. The U.S. Navy Naval Facilities Engineering Command is seeking proposals for operation and maintenance of the wastewater treatment plant, to include plant operations, maintenance of equipment, compliance monitoring, record keeping, and reporting. The performance period is one base year with four one-year options. Interested offerors must register in the System for Award Management and submit any requests to attend an optional site visit by December 12, 2022. Proposals are due by the date specified in the full solicitation document.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CUI//FEDCON

eProject NO.: 1707134

ACQR NO.: 5956750

OPERATION AND MAINTENANCE SERVICE FOR WASTEWATER TREATMENT

PLANT AND COLLECTION SYSTEM FOR

COMMANDER FLEET ACTIVITIES OKINAWA (CFAO),

OKINAWA, JAPAN

NAVFAC FAR EAST

PUBLIC WORKS DEPARTMENT, OKINAWA

Facility Support Contracts Branch

PSC 480 BOX 778

FPO AP 96370-0001

1 February 2023

APPROVED BY:

TITLE NAME SIGNATURE DATE

FSC Branch Manager

NAVFAC FE, PWD Okinawa ENS Kensey Dahlquist

Controlled by: NAVFAC FAR EAST Controlled by: PWD CUI Category: DCRIT Distribution/Dissemination Control: FEDCON POC: kensey.m.dahlquist.mil@us.navy.mil mailto:kensey.m.dahlquist.mil@us.navy.mil

Section C – 0100000 General Information

CUI//FEDCON

0100000 – General Information Spec Item Title 1 General Information

1.1 Outline of Services

1.2 Acquisition of Additional Work

1.3 Background Information

1.4 Navy PBSA Approach

1.5 Standard Template

1.6 Related Information

1.7 Verification of Workload and Conditions

1.8 Contractor’s Knowledge

1.9 Technical Proposal Certification

General Information

0100000 – General Information Spec Item Title Description 1 General Information

1.1 Outline of Services Except where otherwise stated, the Contractor shall furnish all labor, supervision, management, tools, materials, equipment, facilities, transportation, incidental engineering, and other items necessary to provide the services outlined below and described in this Performance Work Statement (PWS) for the Wastewater Treatment Plant and Collection System at White Beach Naval Facility, Commander Fleet Activities Okinawa (CFAO), Japan, under a performance-based contract that is comprised of Recurring Work and Non- Recurring Work Items.

The PWS is organized into annexes. Annex 1 is “General Information”. Annex 2 contains the on-site project management and administration requirements.

Annexes 3 through 18 contain the technical requirements. The annex numbers are identified as 1 through 18 in the description column, but the fully expanded annex numbers include seven digits (e.g., Annex 1 expanded number is 0100000 as shown in the header row at the top of this page).

Annex 1 General Information Annex 2 Management and Administration Annex 3 Command and Staff – N/A Annex 4 Public Safety – N/A Annex 5 Air Operations – N/A Annex 6 Port Operations Annex 7 Ordnance – N/A Annex 8 Range Operations – N/A Annex 9 Health Care Support – N/A Annex 10 Supply – N/A Annex 11 Personnel Support – N/A Annex 12 Morale, Welfare and Recreation Support – N/A Annex 13 Galley – N/A Annex 14 Housing – N/A Annex 15 Facilities Support Sub-Annex 1501000 Facility Management Sub-Annex 1502000 Facility Investment Annex 16 Utilities Sub-Annex 1601000 Utility Management Sub-Annex 1604000 Wastewater Annex 17 Base Support Vehicles and Equipment – N/A Annex 18 Environmental – N/A

1.2 Acquisition of

Additional Work

The Government reserves the right to acquire additional services at additional locations, within the scope of the annexes and areas included in Spec Item 1.1 Outline of Services, in addition to the services and locations identified in the requirements of this contract. Additional services will be incorporated into the contract in accordance with the CHANGES clause, SECTION I or ordered under the non-recurring work provisions of the contract. Items of work not covered by this contract but within the general intent are considered in the scope of this contract.

1.3 Background

Information

See the website at https://cnrj.cnic.navy.mil/Installations/CFA-Okinawa/ for locality information.

1.4 Navy PBSA

Approach

The Navy’s approach to performance-based service acquisition (PBSA) includes four component parts, which are 1) performance outcomes, 2) measurable standards, 3) consideration of incentives, and 4) performance assessment plan.

https://cnrj.cnic.navy.mil/Installations/CFA-Okinawa/

Spec Item Title Description

1.5 Standard Template Key to implementing the PBSA approach is using a standard template that ensures Navy-wide consistency yet affords appropriate tailoring to meet local needs.

The standard template contains 18 standard annexes. Annex 1 will always contain General Information that is relevant to the entire scope of the contract.

Annex 2 contains Management and Administration requirements that are relevant to the entire scope of the contract. Annexes 3 through 18 and their associated sub-annexes contain the General Information, Management and Administration requirements, Performance Objectives, Related Information, and Performance Standards that are relevant to that technical annex. Except where otherwise stated, Annexes 3 through 18 and their associated sub-annex requirements are not relevant to one another. Within each technical annex and sub-annex, the organization of information and requirements are also standardized. Specification Item 1 will always contain General Information.

Specification Item 2 will always contain the Management and Administrative requirements. Specification Item 3 will always contain the Recurring Work requirements. Specification Item 4 will always contain the Non-Recurring Work requirements. Requirements and standards for higher level specification items apply to all subordinate specification items, e.g., Specification Item 3 standards apply to all recurring work specification items. Specification Item

3.1 is applicable to all 3.1 subordinate specification items. Specification Items

3.2 and 3.3 are not considered subordinate to 3.1 nor are they considered subordinate to one another. All costs associated with Annexes 1 and 2 and Specification Items 1 and 2 shall be priced, and their prices shall be allocated to the Exhibit Line Items.

1.6 Related Information There are four types of Related Information that can be found in the Description and Related Information columns of the specification as follows:

Informational Notes as used throughout this PWS provides additional information to offerors to be used in developing a thorough understanding of the work to be performed in this contract. Any block of text marked “Informational Notes” throughout Annexes 1 through 18 and their associated sub-annexes are subject to this disclaimer. Offerors may not rely upon the “Informational Notes” as material representations of the Government.

Information provided in “Informational Notes” does not create a contractually binding requirement on either party.

Clarifying Information describes client expectations in a more detailed manner than the Performance Objective and Performance standard alone.

Constraining Information describes limitations to the work performed to meet the Performance Objective and Performance Standard.

Requirement Information further describes client requirements associated with each Performance Objective.

1.7 Verification of

Workload and Conditions

Throughout the PWS, the workload data is generally referred to as being located in Sections C and J. Section C provides data such as descriptions, specifications, and the statement of work. Section J provides data such as system descriptions, maps, floor plans, and tables to represent the type and location of services to be provided.

Spec Item Title Description

All facilities, systems, and assets identified in this contract shall be accepted by the Contractor in an “AS-IS” condition. The Contractor is fully responsible for all work up to and including the limits of liabilities specified.

As prescribed in FAR 52.237-1, offerors or quoters are urged and expected to inspect the site where services are to be performed and to satisfy themselves regarding all general and local conditions that may affect the cost of contract performance, to the extent that the information is reasonably obtainable. In no event shall failure to inspect the site constitute grounds for a claim after contract award.

1.8 Contractor’s

Knowledge

The Navy expects to receive insightful management from its contractors. This management will include the knowledge, skills, authority and willingness to use contractor resources to find better ways of serving Navy clients’ strategic and operational goals and objectives. The Navy’s use of performance-based objectives evidences this principle. Although performance work statements will typically contain several levels of performance assessment, the Navy wants its contractors to exercise maximum discretion within bounds of prudent risk management to adjust processes and resources needed to reach specified objectives at the highest performance level.

1.9 Technical Proposal

Certification

The Contractor warrants that its proposal incorporated herein by reference will meet or exceed the performance objectives set forth in this contract.

Section C – 0200000 Management and Administration

0200000 – Management and Administration Spec Item Title 2 Management and Administration

2.1 Definitions and Acronyms

2.2 General Information

2.2.1 Government Regular Working Hours

2.2.1.1 Observed Federal Holidays

2.2.1.2 Restriction to Contractor Working Hours

2.2.2 Requirements Hierarchy

2.3 General Administrative Requirements

2.3.1 Required Conferences and Meetings

2.3.2 Training for Maintenance and Operation of New and Replacement Systems and Equipment

2.3.3 Partnering

2.3.3.1 Formal Partnering

2.3.3.2 Contract Partnering Administration

2.3.3.3 Contract Partnering Session Attendees

2.3.4 Permits and Licenses

2.3.5 Insurance

2.3.5.1 Certificate of Insurance

2.3.5.2 Minimum Insurance Amounts

2.3.6 Protection of Government Property

2.3.7 Directives, Instructions, and References

2.3.8 Invoicing Procedures

2.3.9 Forms

2.4 Government-Furnished Items

2.4.1 Government-Furnished Utilities

2.4.2 Government-Furnished Services

2.5 Contractor-Furnished Items

2.6 Management

2.6.1 Safeguarding Information

2.6.2 Dissemination of Information

2.6.3 Work Reception

2.6.4 Work Control

2.6.5 Work Schedule

2.6.6 Mobilization (Phase-In)

2.6.7 Demobilization (Phase-Out)

2.6.8 Deliverables

2.6.9 Service Interruptions

2.6.10 NAVFAC Maximo

2.6.10.1 NAVFAC Maximo Data

2.6.10.2 NAVFAC Maximo Method of Data Entry

2.6.10.3 NAVFAC Maximo Access

2.6.10.4 NAVFAC Maximo Training

2.6.11 Quality Management System (QMS)

2.6.11.1 Quality Management (QM) Plan

2.6.11.2 Quality Inspection and Surveillance

2.6.11.3 Quality Inspection and Surveillance Report

2.6.12 Property Management Plan

2.6.13 System and Equipment Replacement

2.7 Personnel Requirements

2.7.1 Key Personnel

2.7.1.1 Project Manager (PM)

2.7.1.2 Quality Manager

Spec Item Title

2.7.1.3 Site Safety and Health Officer (SSHO)

2.7.1.4 Environmental/Energy Manager

2.7.2 Employee Requirements

2.7.2.1 Employee Certification and Training

2.7.2.2 Employee Appearance

2.7.2.3 Employee Conduct

2.7.2.4 Identification as Contractor Employee

2.7.2.5 Removal of Employees

2.7.2.6 Proof of Legal Residency

2.7.3 Service Contract Reporting (SCR)

2.8 Security Requirements

2.8.1 Employee Listing

2.8.2 Vehicles

2.8.3 Passes and Badges

2.8.4 Access to Installation

2.8.4.1 DBIDS Program

2.8.4.2 DBIDS Credentials

2.8.5 Access to Buildings

2.8.6 Access Arrangements

2.8.6.1 Escort Arrangement for Secured Areas

2.8.7 Access to Controlled Unclassified Information

2.8.7.1 Information Security

2.8.7.2 Information Safeguarding Requirements

2.8.7.3 Disclosure of Information Requirements

2.8.7.4 Operations Security (OPSEC) Requirements

2.8.7.5 Violation of the Information Security Requirement

2.8.8 Access to Government Information Technology (IT), Operation Technology (OT), and Facility

Related Control Systems (FRCS)

2.8.9 Employee Status

2.9 Contractor Safety Program

2.9.1 Contractor Safety Requirements

2.9.2 Accident Prevention Plan (APP)

2.9.3 Activity Hazard Analysis (AHA)

2.9.4 Safety and Occupational Health (SOH) Risks and Compliance Plans

2.9.4.1 Alcohol and Drug Abuse Prevention Plan

2.9.4.2 Chemical Hazard Communication Program

2.9.4.3 Confined Space Program

2.9.4.4 Critical Lift Plan

2.9.4.5 Fall Prevention and Protection Plan

2.9.4.6 Pathogen Exposure

2.9.4.7 Control of Hazardous Energy (Lockout/Tagout)

2.9.5 Crane Operations

2.9.5.1 Crane Inspections

2.9.5.2 Rigging Gear

2.9.5.3 Crane Operators

2.9.6 Accident and Damage Reporting

2.9.6.1 Accident Reporting and Notification Criteria

2.9.7 Fire Protection

2.9.8 Monthly On-Site Labor Report

2.9.9 OSHA/Japanese Labor Standards Inspection Office (LSIO) Citations and Violations

2.9.10 Safety Inspections and Monitoring

Spec Item Title

2.9.11 Safety Certification

2.9.12 Safety Apparel on Jobsites

2.9.13 Emergency Medical Treatment

2.9.14 Excavations

2.10 Environmental Management and Sustainability

2.10.1 Energy Management Program

2.10.1.1 Water Conservation Plan

2.10.1.2 Energy Efficient Products

2.10.2 Environmental Protection

2.10.2.1 Sampling, Testing and Laboratory Services

2.10.2.2 ODS Requirements for Refrigerant Recycling

2.10.2.3 Solid Waste Management and Recycling

2.10.2.4 Non-Regulated Waste Disposal

2.10.2.5 Regulated Waste Disposal

2.10.2.6 Universal Waste

2.10.2.7 Spill Prevention, Containment, and Clean-up

2.10.2.8 Hazardous Material Management

2.10.2.9 Protection of Endangered and Threatened Species (Flora and Fauna)

2.10.2.10 Noise Control

2.10.2.11 Salvage

2.10.2.12 Asbestos Containing Material (ACM)

2.10.2.13 Air Quality

2.10.3 Sustainable Procurement and Practices

2.10.3.1 Environmentally Preferable Products

2.10.3.2 Use of Recovered Materials

2.10.3.3 Use of Biobased Products

2.11 Disaster Preparedness

2.12 Technical Library

2.13 Warranty Management

2.14 Recurring Work Procedures

2.14.1 Notification to the Government for Work Above the Recurring Work Limitations

2.14.2 Recurring Work Exhibit Line Item Numbers (ELINs)

2.15 Non-Recurring Work

2.15.1 Unit Priced Task (UPT) Work (Non-Negotiated)

2.15.1.1 Acceptance and Performance

2.15.1.2 Invoicing and Receiving Payment

2.15.2 Unit Priced Labor (UPL) Work (Negotiated)

2.15.2.1 Non-Recurring Work Preparation of Proposals

2.15.2.1.1 Labor Requirements

2.15.2.1.2 Direct Material and Construction Equipment Requirements

2.15.2.2 Issuance of Final Task Order

2.15.3 Non-Recurring Work ELINS

Spec Item Title Description 2 Management and

Administration

2.1 Definitions and

Acronyms

Definitions and Acronyms are listed in J-0200000-01.

2.2 General

Information

2.2.1 Government

Regular Working Hours

The Government's regular working hours are from 0730-1630, five days per week, Monday through Friday, except observed Federal holidays. Exceptions to the regular hours of operation are detailed in subsequent sections of this PWS. Work in certain annexes or sub-annexes require Contractor continuous operations, 24 hours a day, every day of the year including holidays. The performance of other work requirements shall be accomplished within the Government’s regular working hours unless the specific work requirement specified herein necessitates otherwise. Any other work outside Government regular working hours must be authorized by the Contracting Officer (KO) prior to commencement of work.

2.2.1.1 Observed Federal

Holidays

The Government observes the following holidays: New Year’s Day, Martin Luther King Jr.’s Birthday, President’s Day, Memorial Day, Juneteenth National Independence Day, Independence Day, Labor Day, Columbus Day, Veterans Day, Thanksgiving Day, and Christmas Day.

2.2.1.2 Restriction to

Contractor Working Hours

Black and Gray Wastewater shall be collected and transferred from ship(s) to the wastewater treatment plant and treated 24 hours a day, seven days a week.

If the Contractor wishes to work outside of the Government's regular working hours for the Contractor’s convenience, the Contractor shall submit a written Request to Work Outside Government’s Regular Working Hours per Section F.

2.2.2 Requirements

Hierarchy

Requirements or definitions specified in each spec item of this contract apply to subordinate paragraphs. For example, requirements shown in spec item 3.1 would apply to spec items 3.1.1, 3.1.2, 3.1.2.1 and so on.

Likewise, Performance Standards specified at a lower digit level (i.e. spec item 3.1.1, 3.1.2, 3.1.2.1) apply when performance is assessed at a higher tier (i.e., spec item 3.1) based on the composite work requirements.

2.3 General

Administrative Requirements

2.3.1 Required

Conferences and Meetings

The Contractor shall attend administrative, coordination, and work status meetings. The Contractor shall provide sign-in sheets and prepare minutes of all meetings and submit per Section F for review and comments. Comments received within two working days shall be incorporated into the minutes and a copy of the final revision shall be submitted per Section F for concurrence.

The Government estimates the number of meetings to range from two to six meetings per month. Required meetings may be held remotely as directed by the KO.

2.3.2 Training for

Maintenance and Operation of New and Replacement Systems and Equipment

When construction, renovation, or repair work is performed by means other than this contract, the Contractor shall attend Government provided training, as applicable, for maintenance and operation of new and replacement systems and equipment at no additional cost to the Government.

Spec Item Title Description

2.3.3 Partnering The Government requires cohesive partnerships with its Contractors and subcontractors. Key stakeholders, including the supported commands who may receive services, principal individuals from Naval Facilities Engineering Systems Command (NAVFAC), the performance assessment team, and representative(s) of the installation(s) will be invited to participate in the partnering process. Key members of the prime and sub-contractor teams, including senior management personnel must participate. The partnership will draw on the strength of each organization in an effort to achieve quality contract services done right the first time, within the contract price, as scheduled, and without any safety mishaps.

The goal of Partnering is to develop a cohesive team with common purpose, commitment and established communication processes.

2.3.3.1 Formal Partnering The initial session should be scheduled concurrent with the Pre-Performance Conference and held no later than 30 days after award. The initial Partnering Meeting will be at least one day in duration and held at a neutral location off the installation that is acceptable to the Contractor and to the Government.

Follow-on sessions should be scheduled every three to six months and typically last a half day or less. The frequency, duration, and locations of follow-on sessions should be agreed to by both parties during the initial Partnering Meeting. The Contractor shall pay all costs associated with the partnering effort including facilitator, meeting room, and other incidental items. Before the partnering session, the Contractor shall coordinate with the facilitator the requirements for incidental items (audio-visual equipment, computer(s), two easels, flipchart paper, colored markers, note paper, pens/pencils, colored flash cards, etc.) and have these items available at the partnering session. The Contractor will provide copies of any documents used for the Partnering Meeting for distribution to all attendees. The facilitator must be acceptable to both the Contractor and the Government.

The participants shall pay their own costs for meals, lodging, and transportation associated with partnering.

2.3.3.2 Contract Partnering

Administration

Upon award, the Administrative Contracting Officer (ACO) will contact the Contractor, supported command(s), Region, and Installation(s) stakeholders, and the performance assessment team to discuss implementation of partnering. Commence discussions with the Contractor to select a facilitator and location that are acceptable to both partners. A partnership agreement, The Charter, should be in place as early as possible so issues arising, even before work begins, can be resolved using the issues resolution process.

Replacement of Core Management Team members (stakeholders who attended the initial session and manage the contract work day-to-day) is discouraged since it will disrupt the synergy that has been developed. If replacement of a team member proves to be unavoidable, a follow-on partnering session must be held to officially turn the responsibilities of the position over to the new member.

The Core Management Team consisting of the attendees below must be present during the initial and all follow-on partnering sessions. These are the core mandatory attendees. Other stakeholders may attend if they desire or as recommended by the partners.

2.3.3.3 Contract Partnering

Session Attendees

The Contractor shall bring the necessary personnel to successfully partner on this contract. Asterisk indicates mandatory personnel.

* President/Vice President

* Project Manager

Spec Item Title Description

* Quality Manager

* Site Safety and Health Officer Sub-contractor Reps

2.3.4 Permits and

Licenses

The Contractor shall obtain all required permits, licenses, and authorizations to perform work under this contract and comply with all the applicable U.S.

Federal, Government of Japan, local, and installation laws and regulations.

The Contractor shall submit copies of Permits and Licenses per Section F.

The Prime Contractor under this contract shall be registered under the “Ministry of Land, Infrastructure and Transport, Government of Japan” in accordance with “Prescription of Business Registration for Operation and Maintenance Services of Sewage Treatment Plant, Notice No. 1348”.

The Prime Contractor or subcontractor shall have a License for Collection and Transportation of Industrial Waste (産業廃棄物収集運搬許可証) and a

License for Disposal of Industrial Waste (産業廃棄物処分業許可証) for transportation and disposal of industrial waste at the off base disposal facility and to perform work under this contract. The Contractor shall comply with Japanese laws and regulations and legal enforcement.

2.3.5 Insurance The Contractor shall submit a Certificate of Insurance per Section F as evidence of the existence of the following insurance coverage in amounts not less than the amounts specified below in accordance with the FAR Clause

52.228-5, INSURANCE – WORK ON A GOVERNMENT

INSTALLATION. This insurance must be maintained during the performance period.

2.3.5.1 Certificate of

Insurance

The Certificate of Insurance shall provide for at least 30 calendar days written notice to the KO by the insurance company prior to cancellation or material change in policy coverage. Other requirements and information are contained in the aforementioned insurance clause.

2.3.5.2 Minimum

Insurance Amounts

The Contractor shall procure and maintain, during the entire period of performance under this contract, the following minimum insurance coverage:

Comprehensive General Liability: ¥50,000,000 per occurrence

Automobile Liability: ¥20,000,000 per person, ¥50,000,000 per occurrence for bodily injury, ¥2,000,000 per occurrence for property damage

Workmen's Compensation: As required by Japanese worker's compensation and occupational disease statutes

Employer's Liability coverage: ¥10,000,000, except in where worker's compensation may not be written by private carriers

Other as required by Japanese law

2.3.6 Protection of

Government Property

During execution of the work, the Contractor shall protect Government property. The Contractor shall return areas damaged as a result of Contractor negligence under this contract to their original condition at no cost to the Government.

Berchan.Torrejon Highlight

Spec Item Title Description

2.3.7 Directives, Instructions, and References

Department of Defense (DoD), Secretary of the Navy (SECNAV), Chief of Naval Operations (OPNAV), and other applicable Directives, Instructions, and References are listed in the J attachments of the annexes and sub-annexes of this PWS. The Contractor shall comply with the most current version of directives, instructions, and references including versions published during the term of the contract.

2.3.8 Invoicing

Procedures

Refer to Section G for invoicing instructions.

Invoices shall be submitted in a format compatible with the most recent Government installed Microsoft Office Version. Invoice data shall be capable of being sorted by CLIN, annex/sub-annex, spec item, spec item title, and Exhibit Line Item Numbers (ELIN)/Sub-ELIN.

2.3.9 Forms Forms referenced in this Annex, e.g. accident reporting, and damage reporting are included among the Forms in J-0200000-03.

2.4 Government-

Furnished Items

Except for items identified below as Government-Furnished, the Contractor shall furnish all labor, supervision, management, tools, materials, equipment, facilities, transportation, incidental engineering, and other items necessary to provide the services described in this PWS.

2.4.1 Government-

Furnished Utilities

The Government will make available water and electricity at existing outlets required for the work to be performed under the contract. The Contractor shall provide and maintain, at its expense, the necessary service lines from the existing Government outlets to the work site. Provide and maintain backflow prevention devices on connections to domestic water lines and electrical transformer provisions on connections to electric lines. Meet all U.S. Federal, Government of Japan, local, and installation codes and regulations for backflow prevention devices and electrical transformer provisions. Services required by the Contractor, for which there are no available Government outlets, shall be provided by the Contractor at no cost to the Government.

2.4.2 Government-

Furnished Services

The Government will provide only municipal solid waste disposal, i.e., everyday trash from administrative operations. The Contractor shall be responsible for industrial and special controlled industrial waste disposal.

Janitorial services for the facilities shall be provided by the Contractor. The Contractor shall be responsible and accountable for the facilities operated and maintained under this contract and shall take adequate precautions to prevent fire hazards, odors, and vermin.

2.5 Contractor-

Furnished Items

Except for items identified as Government Furnished, the Contractor shall provide all equipment, materials, parts, supplies, components, and facilities to perform the requirements of this contract. The KO may inspect Contractor-furnished items for adequacy and compliance with contract requirements.

Inadequate or unsafe items shall be removed and replaced by the Contractor at no cost to the Government. Materials containing asbestos, lead, and polychlorinated biphenyls (PCBs) shall not be brought onsite. Energy efficient tools and equipment shall be used when available. The KO may at any time require Samples, Safety Data Sheets (SDS) or Manufacturer’s Data Cut Sheets of Materials used in this contract.

Contractor-Furnished Items shall include items such as laboratory equipment and supplies and office equipment, furniture, and supplies. At contract award, the Wastewater Treatment Plant and all associated buildings will have minimal furnishings and supplies.

2.6 Management The Contractor shall manage the total work effort associated with the services required herein to meet the performance objectives and standards. Such management includes but is not limited to planning, scheduling, cost

Spec Item Title Description accounting, report preparation, establishing and maintaining records, and quality assurance. The Contractor shall provide a staff with the necessary management expertise to ensure performance objectives and standards are met.

2.6.1 Safeguarding

Information

The Contractor shall safeguard controlled unclassified information and information associated with Government property in accordance with the latest revision of CNSSI 1253, DoDI 5200.48, DoDI 8582.01, NIST SP 800- 53, NIST SP 800-171, SECNAV Defense Industrial Base (DIB) Memo, and applicable contract clauses. At a minimum, this information shall be protected at the moderate confidentiality level as defined in NIST SP 800- 171.

Contractor information and data systems that contain information associated with Government property shall comply with DoD Risk Management Framework (RMF).

If a cybersecurity incident is encountered or suspected related to any (Contractor or Government) Information Technology (IT) or Operating Technology (OT) systems, including Monitoring and Control Systems, the Contractor shall notify the Government per Section F.

2.6.2 Dissemination of

Information

DoD policy limits the dissemination of certain information. Instructions, Directives, and References not releasable to the public, e.g., Floor Plans, Maps, Post Orders, and Standard Operating Procedures, will be made available after contract award to the successful offeror with appropriate credentials and a need to know.

2.6.3 Work Reception The Contractor shall provide the capability to receive, prioritize, correspond, and respond to trouble/service calls and task orders during Government regular working hours and provide a point of contact at a local or toll free number who can perform the above function during other than Government regular working hours.

2.6.4 Work Control The Contractor shall implement all necessary work control procedures to ensure timely accomplishment of work requirements, as well as to permit tracking and reporting of work in progress. The Contractor shall plan and schedule work to assure material, labor, and equipment are available to complete work requirements within the specified time limits and in conformance with the quality standards established herein. Verbal scheduling and work status updates shall be provided when requested by the Government. A status update of any item of work must be provided within two hours of the inquiry during regular working hours, and by 0800 the following work day for inquiries after regular working hours.

The Contractor shall provide work schedules for both Recurring and Non- Recurring Work per Section F. At a minimum, work schedules shall include:

• Description of service(s) to be accomplished

• Location

• Date service(s) are scheduled to be accomplished

2.6.5 Work Schedule The Contractor's work shall not interfere with normal Government business.

In those cases where some interference is unavoidable, the Contractor shall minimize the impact and effects of the interference. The Contractor shall provide advance access of all of its work schedules to the Government. The Contractor shall provide written notification of any difficulty in scheduling work due to Government controls, per Section F. At a minimum, the notification shall include the following:

Spec Item Title Description

• The date and time the work was initially coordinated.

• The name and phone number of the Government person with whom the work was initially coordinated.

• The name and phone number of the Government person who prevented the work from being performed as previously coordinated.

• The alternative date and time, the Government person requested the work be accomplished.

2.6.6 Mobilization

(Phase-In) The Contractor shall submit a Mobilization/Phase-In Plan per Section F for Government review and acceptance. The plan shall include at a minimum, a time line on how the Contractor will mobilize/phase-in, approximately 60-90 calendar days prior to full contract performance. The Contractor shall mobilize/phase-in in accordance with the Government-accepted Mobilization Plan and in partnership with the outgoing Contractor so as to minimize disruption to the Government.

The new Contractor will be allowed access to Government facilities to familiarize key personnel and top functional managers with property, existing operations, and procedures. However, to preclude interference with the work efforts of the incumbent Contractor, arrangements for access to Government facilities shall be made with the KO.

During the mobilization period, the Contractor shall attend Government-provided training (On-the-Job Training [OJT]), as applicable, for maintenance and operation of the new Waste Water Treatment Plant and Collection System.

Full performance during the mobilization period shall be required only for the sub-annex(es) indicated on the Exhibit Line Item Numbers (ELINs).

2.6.7 Demobilization

(Phase-Out)

The Contractor shall submit a Demobilization/Phase-Out Plan per Section F for Government review and acceptance. The Contractor shall phase out in accordance with the Government-accepted Demobilization Plan and in partnership with the incoming Contractor so as to minimize disruption to the Government. The plan shall include a time line on how the Contractor will demobilize/phase-out, 60 calendar days prior to contract end, how the incumbent will familiarize the incoming Contractor’s key personnel and top functional managers with existing operations, property, and procedures, completing a Reconciliation Survey, and the Contractor’s strategy for transferring work-in-progress to the new Contractor. The plan shall also provide for Contractor contingency services during the Demobilization/ Phase-Out period in the event of:

1) a work disruption or stoppage or

2) the incumbent’s inability to fill a vacated position during the

Demobilization/Phase-Out period.

During the Demobilization/Phase-Out period, the Contractor shall be responsible for full performance of all sub-annexes through the last day of the contract.

The Government reserves the right to conduct site visits in all Contractor-operated facilities in conjunction with the solicitation of offers for the follow-on contract. In the event the follow-on contract is awarded to other than the incumbent, the incumbent Contractor shall cooperate to permit an orderly changeover to the successor Contractor. A recruitment notice may be placed

Spec Item Title Description by the successor Contractor in each facility during the Mobilization/Phase-In period of the follow-on contract.

2.6.8 Deliverables Except where otherwise stated, deliverable requirements are specified in Sections C, F, H, I, J, and within the Directives, Instructions, and References.

The Contractor shall submit accurate and complete documents within the specified timeframes. The Contractor shall revise/modify deliverables, as directed by the KO, at no additional cost to the Government. All Contractor deliverables shall be in English or may be submitted in Japanese with English translations.

Except where otherwise specified, all deliverables shall be submitted electronically in a Microsoft Office format compatible with the latest version of the Government’s Microsoft Office Suite. Deliverables shall include the company name, contract number, contract title, date, and shall be unprotected and capable of being sorted by CLIN, work order number, asset number, section, annex/sub-annex, spec item and ELIN/Sub-ELIN or clause. All formulas shall be traceable. Refer to DoDI 5200.48 for marking requirements (as applicable).

Government acceptance of deliverables shall not relieve the Contractor of the responsibility for any error or omission which may exist in the deliverable, as the Contractor is responsible for all requirements of this contract.

2.6.9 Service

Interruptions

If any utilities or other services must be discontinued (even temporarily) due to scheduled contract work, the Contractor shall notify the KO, COR, affected tenants, and customers in accordance with local procedures. If the discontinued service is due to an emergency breakdown, the Contractor shall notify the KO, COR, affected tenants and customers immediately and provide the status of repairs, as directed by the KO, until normal operation is restored.

Scheduled utility outages and interruptions to equipment, system(s) operation, or other services shall be scheduled after hours of operation.

The Contractor shall shut down, restart, and perform operational checks on all equipment affected by both scheduled and unscheduled utility outages and service interruptions, at no additional cost to the Government.

2.6.10 NAVFAC Maximo NAVFAC Maximo is the Computerized Maintenance Management System (CMMS) used by the Government for work order history, asset management, and condition assessment. The Contractor shall provide all required data for NAVFAC MAXIMO as identified below:

Informational Note:

Not all assets are included in NAVFAC Maximo. Not all of the modules available within the Maximo application are utilized by NAVFAC, and the modules utilized may not be fully implemented. NAVFAC Maximo does not include a detailed inventory of all assets, components, and equipment that the Contractor is required to service under this contract and may include inaccuracies, omissions, and redundancies.

2.6.10.1 NAVFAC Maximo

Data

Required data fields for work orders are indicated in the Service Provider Information provided in J-0200000-04. Asset inventory data requirements are indicated in the Asset Information provided in J-0200000-05, including additional data for Utilities assets listed in Specification Information in J- 0200000-06. Required data for documenting condition assessments is

Spec Item Title Description indicated in the Characteristic Meter Reading Information provided in J- 0200000-07.

Specified data shall be provided for all work performed in 1501000 Facility Management, 1502000 Facility Investment, 1601000 Utilities Management, and 1604000 Wastewater. Further instructional information detailing the process for submitting the specified information for NAVFAC Maximo Data Reporting is provided in J-0200000-08.

The Service Provider, Asset, Specification, and Characteristic Meter Reading Interfaces are used in multiple processes for loading data into Maximo by the Government, and the format may be updated periodically.

As part of the update, the Contractor may be asked to modify the file to add/move columns in their submission. The Contractor shall provide up to 10 extra data elements or columns with as many as 150 characters per element for the Government to define during contract performance at no additional cost to the Government. The Government will provide the Contractor 60 calendar days’ notice of modifications to the Service Provider, Asset, Specification, or Characteristic Meter Reading Interfaces file format.

2.6.10.2 NAVFAC Maximo

Method of Data Entry

The Contractor shall provide data for NAVFAC Maximo using the methods detailed below:

DIRECT ENTRY: The Contractor shall manually enter required work order and condition assessment data directly into NAVFAC Maximo. The Contractor shall ensure all information is updated by the end of each workday for all work performed.

If the Contractor does not have access to NAVFAC Maximo at contract start, work order and condition assessment data shall be submitted in a pipe delimited text-file following the NAVFAC Maximo Data Reporting process described in J-0200000-08 per Section F. Any failures in processing of the flat file shall be corrected and resubmitted by the Contractor. In order to demonstrate the ability to properly format the flat file, the Contractor shall provide a Sample Pipe Delimited Text-file prior to contract performance per Section F. Flat file submission of work order and condition assessment data will be allowed for a period not to exceed six months unless an extension is authorized in writing by the KO.

FLAT FILE: The Contractor shall electronically record and report compiled service performance data for exportation of asset and specification data to NAVFAC Maximo. The Contractor shall submit asset and specification data in a spreadsheet flat file following the NAVFAC Maximo Data Reporting process described in J-0200000-08 per Section F.

2.6.10.3 NAVFAC Maximo

Access

The process for obtaining access and establishing NAVFAC Maximo accounts are detailed in the NAVFAC Maximo System Access Procedures provided in J-0200000-09.

Once accounts have been established, NAVFAC Maximo can be accessed at https://maximo.navfac.navy.mil.

https://maximo.navfac.navy.mil/

Spec Item Title Description

The Contractor shall provide all necessary computer equipment and Internet Service Provider (ISP) accounts to access NAVFAC Maximo for Direct Entry of required data.

A maximum of five NAVFAC Maximo accounts will be approved for the Contractor. Changes of personnel requiring NAVFAC Maximo accounts more than once per year may result in required compensation to the Government for the administrative costs in processing account requests.

The Contractor shall submit a list of personnel requiring NAVFAC Maximo accounts per Section F.

2.6.10.4 NAVFAC Maximo

Training

The Government will provide or make available initial training on NAVFAC Maximo to Contractor personnel responsible for direct entry of work order, asset, specification, and condition assessment data. Additional training will be provided by the Government when there are significant changes to the NAVFAC Maximo software or data entry requirements. Training due to changeover of personnel will be the responsibility for the Contractor. The Contractor will be provided a general user guide, local instructions, and other materials by the Government as reference material for the use of NAVFAC Maximo.

2.6.11 Quality

Management System (QMS)

The Contractor shall establish and maintain a complete QMS program in accordance with the provisions specified herein. The Contractor’s QMS program shall provide an effective and efficient means of identifying and correcting problems throughout the entire scope of operations. The Contractor's QMS program shall address:

• Accurate documentation of work processes, procedures, and output measures.

• A systematic procedure for assessing compliance with performance objectives and standards.

• Accurate documentation of quality inspections and surveillance conducted throughout the execution of work.

• Assessment-driven corrective actions and process adjustments as appropriate in a timely manner.

The Contractor QMS Pre-Performance Review Checklist for compliance with this requirement is provided in J-0200000-10.

2.6.11.1 Quality

Management (QM) Plan

The Contractor shall develop and submit a QM Plan per Section F. The QM Plan shall describe the QMS methodology and approaches used under this contract. If any changes are made during the period of performance, the Contractor shall submit the revised QM Plan for acceptance, per Section F.

The Contractor’s QM Plan shall include, at a minimum, the following:

• Policy and objectives of Quality Management System (QMS)

• Quality organization o List of personnel o Organization Chart o Responsibilities & lines of authority o Training and qualifications o Quality Manager resume

• Approach to assuring quality of services provided and conformance with performance objectives and standards

Spec Item Title Description

• Methods and procedures for effective planning, operation and control of processes and performance of work

• Procedures for inspection and surveillance of services to include all contractual requirements o Scheduling and performance of inspection and surveillance o Measurement, data collection and analysis o Corrective action, preventive action, and continuous improvement o Oversight of subcontracted work

• Documentation and records management

• Communication with government (customers)

2.6.11.2 Quality Inspection

and Surveillance

The Contractor shall establish and maintain an inspection and surveillance system in accordance with the FAR Clause 52.246-4, INSPECTION OF SERVICES – FIXED PRICE, to ensure that the work performed conforms to the contract requirements. The Contractor shall document and maintain a file of all scheduled and performed inspections and surveillances, inspection and surveillance results, and dates and details of corrective and preventive actions. The quality inspection and surveillance file shall be the property of the Government and made available during the Government’s regular working hours. The file shall be submitted to the COR after completion/termination of the contract per Section F.

2.6.11.3 Quality Inspection

and Surveillance Report

The Contractor shall submit a copy of the Contractor Quality Inspection and Surveillance Report per Section F. The Contractor Quality Inspection and Surveillance Report shall include a narrative of events, a tabulated summary and results of the quality inspection and surveillance events performed, inspection-driven corrective actions taken and the results attained, and management process adjustments during the previous month. The Government may adjust the frequency of the submittal based on the Contractor’s quality of performance.

2.6.12 Property

Management Plan

The Contractor shall establish and maintain a plan identifying the Contractor’s policies, procedures, and practices in receiving and performing physical inventories, key control, repairing and maintaining, preserving and protecting, and reporting the disposition of accepted government property in its possession. The Contractor shall obtain written approval from the KO prior to making any modifications or alterations to the facilities. The Property Management Plan shall be submitted per Section F.

2.6.13 System and

Equipment Replacement

The Contractor shall maintain the integrity and performance of existing energy saving, water conservation or other sustainability design features of systems and equipment in the performance of repair and replacement work.

Except where otherwise specified, replacement components shall be of the same model/style or equivalent as the component being replaced. Substitutes for replacement components must be accepted by the KO prior to use. The KO will furnish available information for the existing systems and equipment.

2.7 Personnel

Requirements

The Contractor shall comply with the personnel requirements stated below:

2.7.1 Key Personnel The Contractor shall submit a List of Key Personnel and Qualifications per Section F. The Contractor shall provide any additional information requested by the KO or COR necessary to validate their qualifications.

The Contractor shall submit an Organizational Chart per Section F showing lines of authority of the key personnel and on-site supervisor(s) for this contract. The chart shall include names of personnel and their position title in this contract. As a minimum, include the PM, Quality Manager, SSHO, and

Spec Item Title Description on-site supervisor(s) and who they will report directly to for this contract.

The key personnel shall be revised as applicable for the contract.

The Contractor shall provide complete resumes for proposed substitutes and any additional information requested by the KO. Proposed substitutes shall have comparable qualifications to those of the persons being replaced. The KO will notify the Contractor within 15 calendar days after receipt of all required information of the consent on substitutions. No change in fixed unit prices may occur as a result of key personnel substitutions.

Key personnel shall be able to speak, read, and comprehend English to the extent that they can perform the contract requirements and comply with installation emergency procedures, or an interpreter shall be available at no additional cost to the Government.

2.7.1.1 Project Manager

(PM)

The Contractor shall provide a PM and designated alternate, as applicable, who shall have full authority to act for the Contractor on all contract matters relating to this contract. The PM or alternate shall be on-site during the Government's regular working hours and shall be available on-site within one hour after the Government's regular working hours.

The PM shall have at least five years of experience in managing a workforce providing services on contracts of similar size, scope and complexity.

2.7.1.2 Quality Manager The Contractor shall provide a Quality Manager or designated alternate who shall be on-site at all times when the Contractor is performing work during the Government's regular working hours and shall be available on-site within two hours after the Government’s regular working hours. The Quality Manager or designated alternate shall report directly to a senior corporate official and shall not report directly to the Project Manager.

The Quality Manager or designated alternate shall have fulfilled the following pre-requisite training and experiences before being hired as the Quality Manager under this contract:

The Quality Manager or designated alternate shall have a current Certified Manager of Quality/Organizational Excellence (CMQ/OE) certification and at least five years of experience in preparing and enforcing QMS programs on contracts of similar size, scope and complexity. The Quality Manager shall not be the same person as the Project Manager or the SSHO.

2.7.1.3 Site Safety and

Health Officer

(SSHO)

The SSHO must meet the requirements of EM 385-1-1 Section 1 and ensure that the requirements of 29 Code of Federal Regulations (CFR) 1926.16 are met for the project. Provide a Safety oversight team that includes a minimum of one Competent Person at each project site to function as the Site Safety and Health Officer (SSHO). The SSHO or an equally-qualified Designated Representative/alternate shall be on-site at all times when work is being performed to implement and administer the Contractor's safety program and government-accepted Accident Prevention Plan. The SSHO's training, experience, and qualifications shall be as required by EM 385-1-1 paragraph 01.A.17, entitled SITE SAFETY AND HEALTH OFFICER (SSHO), and all associated sub-paragraphs.

A Competent Person shall be provided for all of the hazards identified in the Contractor's Safety and Health Program in accordance with the accepted Accident Prevention Plan, and shall be on-site at all times when the work that

Spec Item Title Description presents the hazards associated with their professional expertise is being performed. Provide the credentials of the Competent Persons(s) to the KO for acceptance in consultation with the Safety Office.

The Contractor shall provide a SSHO whose primary duty and responsibility is to prepare and enforce the Contractor’s safety program on this contract.

The SSHO shall have fulfilled the following pre-requisite training and experiences before being hired as the SSHO under this contract:

The SSHO shall have completed five years of satisfactory experience in preparing and enforcing safety programs on contracts of similar size and complexity in the past or three years’ experience if he…

This is the start of the file's text. The full file is on GovTribe.