AMD 2_Attachment (1) Government Response to RFI.pdf
PDF 135 KB Posted
- Attached to
- Wastewater Treatment Plant (WWTP) Operation and Maintenance (O&M) Services, White Beach, Okinawa, Japan
- Solicitation number
- N4008423R3600
About this file
This document contains questions and answers regarding a request for proposal for wastewater treatment plant operation and maintenance services at White Beach, Okinawa, Japan. The U.S. Navy Naval Facilities Engineering Command is seeking proposals for a five-year contract to operate and maintain the wastewater treatment plant, including treatment of sewage from ships and the base. The contractor will be responsible for plant operations, equipment maintenance, and sludge and wastewater effluent disposal. The proposal due date was extended to February 7, 2023. Pricing should cover all recurring operation and maintenance costs, including chemical and membrane replacement, as well as minor repairs up to specified amounts.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| AMD 3_23R3600.pdf | ||
| Attachment (1) Government Response to RFI 2.pdf | ||
| Attachment (3) N4008423R3600 WWTP PWS FINAL_rev1.pdf | ||
| Attachment (2) Photo and As-built.zip | ZIP file | |
| AMD 2_Attachment (2) Copy of General Waste Treatment Facility Installation Permit.pdf | ||
| AMD 2_23R3600.pdf | ||
| AMD 1_23R3600.pdf | ||
| Attachment (4)_PPQ.docx | DOCX document | |
| RFP_N4008423R3600_WWTP O and M.pdf | ||
| Attachment (7) BEFORE STARTING BUSINESS WITH NAVFAC APR 2022.pdf | ||
| Attachment (3)_Offeror Experience ProjectDataSheet.docx | DOCX document | |
| Attachment (2) 23R3600 J-0200000-14 ELINS FINAL.xlsx | XLSX spreadsheet | |
| Attachment (6) Site Visit Request Form.xlsx | XLSX spreadsheet | |
| Attachment (5) Inquiry Form.xls | XLS spreadsheet |
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PRE PROPOSAL INQUIRY FORM
DATE:
Question No.
Reference (Sect/Para/Page)
QUESTION GOVERNMENT RESPONSE
1 Page.1
SOLICITATION/CONTR
ACT/ORDER FOR
COMMERCIAL ITEMS
10.This acquisition is
Could you kindly explain us what "Size Standard $31,000,000" means? With respect to the NAICS code, size standards represent the largest size that a business (including subsidiaries and affiliates) may be to remain classified as a small business for SBA and federal contracting programs.
(source: https://www.sba.gov/document/support-table-size-standards).
This does not apply to foreign (non-US) businesses.
2 Page.49 Attachment C was not included in the downloadable documents on the SAM site. Could you please upload attachment C?
Please disregard references to "Attachment C". The correct Experience Form is Attachment (3)_Offeror Experience Project Data Sheet.
3 0200000, 2.3.4 Permits and Licenses
The presolicitation only required subcontractor licenses for waste disposal and transportation. Now, the SPEC requires the prime contractor to have those. We would like to request the deadline for solicitation to be postponed as JV dealing taking time.
Noted. The RFP due date was extended through 7 Feb 2023, 10:00 A.M.
4 0200000, 2.10, Environmental Management and Sustainability
The operation shall follow the Japanese laws and standards for effluent water. Are there any other applicable laws or standards?
JEGS 2022, and OPNAV 5090
5 0200000, 2.10.2.4, Non-Regulated Waste Disposal & 2.10.2.5, Regulated Waste Disposal
Contractor disposes of regulated waste. Hazardous waste is to be handed over to the Gov. How about waste does not fit either of above?
For other form of waste caught at the auto coarse screen (grit chamber), it can be treated as normal trash.
6 0200000, 2.3.4 Permits and Licenses
The SPEC requires a license for waste disposal. Should the treatment plant be licensed for sludge disposal?
The plant has already permit from Okinawa Prefectural Government;
pls. see attached PDF.
7 0200000, 2.3.4, Permits and Licenses
We assume that the number of authorized/licensed disposal companies of industrial waste (dewatered sludge) in Okinawa Prefecture is small (not many) and if only specific JV holds/adds the disposal company of indsutrial waste (dewatered sludge) to the JV as member, it results in unfair and uncompetitive situation for this bidding. Therefore, would you please accept that disposal companies can join this bidding as not member of JV, but as subcontracor, so that any bidder can have a chance to use disposal company of industrial waste (dewatered sludge).
The Japan Environmental Governing Standards prohibits contracting with a licensed transporter that subcontracts with a licensed disposal company. It is our intention to contract only with a single contractor who is both licensed for transportation and disposal.
8 0600000, 3.1, CHT
Hook-up and Disconnects
Should the contractor keep a watch around the clock when CHT is hooked up to a ship?
Contractor shall monitor initial connections and operations to ensure no problems but it is not anticipated that an "around the clock" watch will be necessary.
9 0600000, 3.1, CHT
Hook-up and Disconnects
We would like to know the type of connecters used for CHT hoses. If possible, we would like to obtain photos.
Type of connectors are 100mm SUS CamLock models 100C and 100E.
Photo of connectors and hoses are attached..
10 0600000, 3.1, CHT
Hook-up and Disconnects
How many CHT hoses are required to hook up a ship? Depends on the size of the ship, tides and location to the pier connections. Estimated maximum number of hoses is 3.
11 0600000, 3.1, CHT
Hook-up and Disconnects
Are eight CHT hoses sufficient when most number of ships are berthed?
Yes. There are 8 complete hose assemblies and 2 spare hoses without connectors.
12 0600000, 3.1, CHT
Hook-up and Disconnects
Can the contractor use a crane at berth and other utility services? There should be no need for a crane or other utility services at berth.
EMAIL:
SOLICITATION NO.:
ADDRESS:
PHONE NUMBER:
OFFEROR NAME:
SOURCE SELECTION INFORMATION - SEE FAR 2.101 AND 3.104
Question No.
Reference (Sect/Para/Page)
QUESTION GOVERNMENT RESPONSE
EMAIL:
SOLICITATION NO.:
ADDRESS:
PHONE NUMBER:
OFFEROR NAME:
13 0600000, 3.1, CHT
Hook-up and Disconnects
Can we charge for CHT services if more ships than shown in the historical data come to the berths?
No, proposals should be priced accordingly.
14 0600000, 3.2, CHT
Hose Equipment Maintenance
Is the contractor responsible for renewing the CHT hoses? In that case, we would like to know the conditions of the current hoses.
Yes. As of 6 January 2023 there are 2 new spare hoses (no couplings attached), 4 new complete hose assemblies and 4 minimally used hose assemblies. The hoses had not been used prior to 9 December 2022.
15 0600000, 3.2, CHT
Hose Equipment Maintenance
Is there a place where we can store hoses? Hoses may be stored on the pier in the locations they are currently stored. It is anticipated that in the future they will be stored in the vehicle bay of the fire department located near the Army Pier.
16 0600000, 3.2, CHT
Hose Equipment Maintenance
The amount of minor repair is set at 500,000 yen. Does this apply for each occurrence or cumulative?
Please refer to 0600000, 3.2; specifies individual occurrence
17 1502000, 3, Recurring Work
Is the contractor responsible for assessing the conditions of building structures?
Yes.
18 1502000, 3.1, Integrated Maintenance Program (IMP)
The amount of minor repair is set at 2,000,000 yen. Does this apply for each occurrence or cumulative?
Please refer to 1502000, 3.1; specifies individual occurrence
19 1502000, 3.1.7, Uninterruptible Power Systems (UPS)
Is this UPS the one in the control room in the WWTP building?
Yes, this UPS is the power back-up for the central monitoring system in the control room.
20 1502000, 3.1.9, Weight Handling Equipment (WHE)
Inventory of the equipment not available in SPEC Please refer to 1501000, 3.1; the contractor shall input into MAXIMO all asset inventory identified on-site. One small manual crane exists on-site.
21 1604000, 3.2.1, Wastewater Treatment Plant
Should the onsite sewage treatment system shown in Installation Utility Maps (Attachment J-1601000-04) be serviced under this contract?
Onsite sewage treatment system will be removed and not serviced under this contract.
22 1601000, 3, Recurring Work
We would like to obtain the current analysis date for CHT wastewater and base wastewater.
Current ODB contractor is not conducting analysis for CHT wastewater (NIC) and for base wastewater.
23 1604000 3.2.2.1 Sewage Pipelines
Can the contractor use tap water for high pressure washing? Yes.
24 1604000, 3.1, Operation
The quote will be prepared based on certain assumptions. Is there a way for the contractor to charge excessive costs?
No, proposals should be priced accordingly.
25 1604000, 3.1, Operation
Should the contractor place personnel around the clock? Or is it sufficient as long as emergency operation is available.
If emergency operation is available, a normal 8-hr work shift (0730 hrs ~ 1630 hrs) and for trouble calls during unmanned hours is acceptable. The auto-call system was built-in but is not yet activated, pending clearance from NCTS. Once activated, assign DSN number(s) to the auto-calling feature of the central monitoring system.
Question No.
Reference (Sect/Para/Page)
QUESTION GOVERNMENT RESPONSE
EMAIL:
SOLICITATION NO.:
ADDRESS:
PHONE NUMBER:
OFFEROR NAME:
26 1604000, 3, Operation
We understand that this sewage treatment plant is not a typical septic tank, but an MBR(Membrane Bio Reactor) that operates, adjusts, and injects chemicals using a circulating two-stage nitrification-denitrification method to achieve the required performance (water quality below the standard value for discharge into the sea) for sewage discharged from ships of various sizes calling port irregularly and whose water volume and quality are not constant but vary greatly.
Am I correct in understanding that even if unexpected fluctuations in water quantity or quality occur during the five-year maintenance period, we must take action to achieve the required performance by operating and adjusting the facilities and injecting chemicals?
That is correct.
27 1604000, 3, Operation
Our company has designed the expected consumption amount of chemicals as shown in the table below for the expected maximum sewage inflow and water quality. Should successful bidder purchase chemicals from chemical manufacturer based on the following table for operation of WWT? Also, is the purchase cost of the chemical inclueded in the contruct amount?
WRT amount of chemicals needed, ODB contractor cannot dictate how much will be needed, as it will depend on the maintenance contractor.
But besides the chemicals listed on the table, there is also need for “Hychlon” (Calcium Hypochlorite, Effective Chorine of above 70%).
Also, high polymer coagulant shall be 40% concentration.
Lastly, inorganic coagulant shall be 11% concentration.
28 1604000, 3.1.1 , Wastewater Effluent Quality
If analysis for water quality is required, would you please inform us of the following two poinst ?
1.Water quality items/factors to be analyzed 2.Where to analyze water from
* Assuming performing water quality testing in the 1F lab, the samples hall be taken from:
1. Inflow sewage: There is a sampling valve on the discharge side of each flow rate control tank sewage transfer pump.
2. Aerobic tank: There is a sampling valve on the discharge side of each aerobic tank circulation pump.
3. Treated water: Sampling valves are located on the discharge side of each membrane treatment tank treated water pump.
4. Discharged water: Sampling is taken from the manhole of the disinfection tank.
Please refer to the Table 9.5: Effluent Discharge Limits for Conventional and Other Pollutants and Table 9.20 on the JEGS 2022. Daily requirement on the "DAILY AVERAGE" column, and monthly requirements on the "MAXIMUM column. As for annual requirements, please refer to the Japanese National Effluent Standards on the link "https://www.env.go.jp/en/water/wq/nes.html"
29 1604000, 3.1.2, Sludge Disposal
Our dewatered cake removal system is designed with the following details.
The maximum amount of generated dewatered cake is 0.9 ton/day at the maximum inflow of sewage and water quality. The storage capacity of the dewatered cake hopper is 9.0 m3, so dewatered cake is needed to be taken out once every 10 days.
Should successful bidder arrange the disposal the dewaterd cake to disposal company of industrial waste? Also, is the disposal cost of dewatered cake inclueded in the contruct amount?
It would be depend on how the awarded contractor will be operating the plant.
But WRT disposal of dewatered cake and its disposal cost, it is believed that it should be included in the bidding amount.
30 1604000, 3.1.2, Sludge Disposal
We would like to obtain analysis data for the sludge to be disposed of, as they are required for a quote from a disposal company.
Pls. refer to Q22.
31 1604000, 3.1.2, Sludge Disposal
Can we get sample sludge? No sludge is available from the new plant.
Question No.
Reference (Sect/Para/Page)
QUESTION GOVERNMENT RESPONSE
EMAIL:
SOLICITATION NO.:
ADDRESS:
PHONE NUMBER:
OFFEROR NAME:
32 1604000, 3.2, Integrated Maintenance Program (IMP)
The amount of minor repair is set at 20,000 dollars. Does this apply for each occurrence or cumulative?
Please refer to 1502000, 3.1; specifies individual occurrence
33 1604000, 3.2.1, Wastewater Treatment Plant
Can the contractor include tank coating services within FFP? Tank coating will not be needed on a re-occurring basis.
34 1604000, 3.2.1, Wastewater Treatment Plant
How often shall the membrane be cleaned and replaced? Once a year is required, including inspection of the pseudoelectrode.
Replacement frequency will vary depending on inflow water quality and quantity over 7 years.
35 1604000, 3.2.2.2, Cleaning of Sewer Pipeline Wet Wells
Can the contractor put back into the sewer line the wastewater vacuumed out while cleaning the pipelines?
Wastewater generated during treatment facility pipe cleaning can be fed into the flow control tank.
36 1604000, 3.2.4 Wet Wells
Are there mixers or aeration at wet wells? Mixer: installed in denitrification tank
Aeration: Installed in flow control tanks, aerobic tanks, and membrane separation tanks.
37 0200000, 2.4, Government- Furnished Items
We would like to request all photos (of the facility) as follows:
1. Control Panel and Control System
2. Main inlet, wastewater & saltwater system
3. Sludge hopper
4. Membrane unit tanks
5. Sludge cake conveyor hopper
6. 3 lines filtering system
7. Deodorizer
8. Chemical injection equipment power control panel
9. Sludge store tank level meter
10. Dewatering cake hopper control panel
11. Other available photos
Please see attachments.