Attach 2_IDIQ PAINTING Solicitation Bid schedule_2.18.22.xlsx

XLSX spreadsheet 61 KB Posted

Attached to
N4008422B0099, IDIQ EXTERIOR/INTERIOR PAINTING AND MISCELLANEOUS REPAIRS OF SINGLE AND MULTIPLE STORY FACILITIES AT VARIOUS U. S. GOVERNMENT INSTALLATIONS, OKINAWA, JAPAN
Solicitation number
N4008422B0099
Issued by

View the file

Other files

File Type Posted
Amend 0005.pdf PDF
Amend 0004.pdf PDF
Amend 0004 cover and spec.pdf PDF
Amend 0003.pdf PDF
Attach 2_IDIQ PAINTING Solicitation Bid schedule_2.3.22.xlsx XLSX spreadsheet
Amend 0002.2.3.22.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Summary

***Noice: This Summary Tab automatically calculates what you fill out all items price in each tabs.
***Do not create your own or change formula.***
PAINTING Indefinite Delivery Indefinite Quantity Work
PROVIDE UNIT PRICES FOR LINE ITEMS BELOW IN ACCORDANCE WITH THE CONTRACT SPECIFICATIONS

AND DRAWINGS.

Offerror/ Company Name:
Printed Name and Signature: Date:

ITEM NO. SUPPLIES/ SERVICES Total Amount (in JPY)

A001AA ~ A001AXOrdering Period 1: All supplies and services for line item A001AA through A001AX¥21,000,000
B001AA ~ B001AXOrdering Period 2: All supplies and services for line item B001AA through B001AX¥21,000,000
C001AA ~ C001AXOrdering Period 3: All supplies and services for line item C001AA through C001AX¥21,000,000
D001AA ~ D001AXOrdering Period 4: All supplies and services for line item D001AA through D001AX¥21,000,000
E001AA~ E001AXOrdering Period 5: All supplies and services for line item E001AA through E001AX¥21,000,000
TOTAL ( Base Period): CLIN 0001¥105,000,000
F001AA ~ F001AXOrdering Period 6: All supplies and services for line item F001AA through F001AX¥21,000,000
G001AA ~ G001AXOrdering Period 7: All supplies and services for line item G001AA through G001AX¥21,000,000
H001AA ~ H001AXOrdering Period 8: All supplies and services for line item H001AAthrough H001AX¥21,000,000
TOTAL ( Option Period 1): CLIN 0002¥63,000,000

TOTAL CONTRACT AMOUNT ¥168,000,000

Abbreviations used:
LM: Linear Meter
TN: One metric ton (1,000 kg)
CM: Cubic Meter
SHT: One drawing sheet (A1 size)
Perf: Performance

CUI //FEDCON [when filled in] Source Selection Information -- See FAR 2.101 and 3.104 [When filled in] Amendment 0004

CUI //FEDCON [when filled in] Source Selection Information -- See FAR 2.101 and 3.104 [When filled in}

BASE - OP1

GOVERNMENT ESTIMATE
Prepared by :FOR OFFICIAL USE ONLY
Signature :
Date :
Base Period - Ordering Period 1REFERNCE NO. OF DOCUMENT:
NAME OF OFFFEROR OR CONTRACTOR
BID SCHEDULE
ITEM NOSECTION AND PARASUPPLIES/SERVICESQUANTITYUNITUNIT PRICE (Including applicable performance bond)TOTAL AMOUNT
A001BASE PERIOD - SCHEDULE OF INDEFINITE QUANTITY WORK: THE LINE ITEMS LISTED BELOW ARE FOR ONE YEAR BASE PERIOD AS ESTABLISHED BY THE CONTRACTING OFFICER. Indefinite Quantity Work: Price to perform indefinite quantity work in accordance with all the terms of this contract. The contract price is the sum of contract lines from A001AA to A001AX.
Units: SM = Square Meters LM = Linear Meter TO = Task Order HRS = Hours EA = Each OC = Occasion NTE=Not to exceed
Line Item Tasks - Material and Labor Hours Provision:

The following representative amount of work is for the evaluation of bids only and not necessarily the quantity for which work will be ordered by the Government. The following Line Item Tasks represent anticipated scope of work, that may be requested in Task Orders in any combination, and shall be based on Unit Costs that include Direct Labor,Material, Setup, Equipment/ Equipment Rental, Cleanup and Waste Disposal costs, plus Contractor Markups, Overhead and Profit.

A001AA Water-blasting concrete/masonry surfaces. ( High pressure pump 10-15 Mpa)

60,000SM¥0
A001ABRepair of concrete spall (Interior and Exterior). Assume Average Depth of 30mm. (Including chipping, scrape, Anti-rust Treatment of rebar and Polymer resin mortar backfill finish)5,000SM¥0
A001ACExterior painting on textured concrete & masonry surfaces. (Including Taping/Masking of adjacent surfaces like doors, windows and louvers)55,000SM¥0
A001ADExterior painting on non textured concrete & masonry surfaces. (Including Taping/Masking of adjacent surfaces like doors, windows and louvers)100SM¥0
A001AEScaffolding up to 12 meters. (Including Materials and Labor to assemble/disassemble)30,000SM¥0
A001AFScaffolding up to 22 meters. (Including Materials and Labor to assemble/disassemble)16,000SM¥0
A001AGExterior Painting of metal surfaces. (Including surface preparation/restoration and painting)5,000SM¥0
A001AHGWB Repair, Nail/Screw Pops
(Assume 1 per 1 S.M. of Int. GWB)1,500EA¥0
A001AJGWB Repair, Cut/Patch/Tape 50mm x 100mm Hole
(Assume 1 per 300 S.M. of Int. GWB)10EA¥0
A001AKGWB Replace, Demo Existing/ Install New
(Assume 10% of Int. GWB)150SM¥0
A001ALInterior painting of concrete, masonry, wallboard, plaster, interior and wood surfaces. (Including taping / masking of adjacent surfaces such as doors, windows, louvers, tiles, etc. Including base treatment such as putty).7,000SM¥0
A001AMInterior painting of ceilings (gypsum ceiling board and plaster board). (Including taping / masking of adjacent surfaces such as doors, windows, louvers, tiles, etc. Including base treatment such as putty).9,000SM¥0
A001ANInterior re-staining of wood floors. (Based on 2 Coats of Low VOC Polyurethane Varnish, including sanding and refinishing )500SM¥0
A001APInterior Painting of high wetness areas (all surfaces). ( including Taping/Masking of adjacent surfaces like doors, windows, louvers and tile)150SM¥0
A001AQInterior moving type scaffolding, up to 5.4 meters, walls and ceilings. (Including Materials and Labor to assemble/disassemble) 4 rolling towers, 4 month usage period (H=5.4m).1EA¥0
A001ARInterior scaffolding, up to 1.8 meters, walls and ceilings. (Including Materials Transport and Labor to assemble/disassemble)2,000SM¥0
A001ASSealants around existing doors and windows,
Demo Existing/Install New8,000LM¥0
A001ATOnly the transportation costs of workers and work vehicles required for one task on Ie Island21DAY¥0
A001AUNon-specific work- Any work not identified on the ELINS but required to complete the project.1NTE¥21,000,000¥21,000,000
A001AVACM sampling and testting20EA¥0
A001AWLEAD sampling and testing20EA¥0
A001AXACM and LEAD abatement20SM¥0
TOTAL PRICE FOR CONTRACT LINE ITEMS A001AA THRU A001AX¥21,000,000
BASE PERIOD - Ordering Period 1

Source Selection Information -- See FAR 2.101 and 3.104 [When filled in] Amendment 0004

Source Selection Information -- See FAR 2.101 and 3.104 [When filled in]

BASE - OP2

GOVERNMENT ESTIMATE
Prepared by :FOR OFFICIAL USE ONLY
Signature :
Date :
Base Period - Ordering Period 2REFERNCE NO. OF DOCUMENT:
NAME OF OFFFEROR OR CONTRACTOR
BID SCHEDULE
ITEM NOSECTION AND PARASUPPLIES/SERVICESQUANTITYUNITUNIT PRICE (Including applicable performance bond)TOTAL AMOUNT
B001OPTION YEAR 1 - SCHEDULE OF INDEFINITE QUANTITY WORK: THE LINE ITEMS LISTED BELOW ARE FOR ONE YEAR BASE PERIOD AS ESTABLISHED BY THE CONTRACTING OFFICER. Indefinite Quantity Work: Price to perform indefinite quantity work in accordance with all the terms of this contract. The contract price is the sum of contract lines from B001AA to B001AX.
Units: SM = Square Meters LM = Linear Meter TO = Task Order HRS = Hours EA = Each OC = Occasion NTE=Not to exceed
Line Item Tasks - Material and Labor Hours Provision:

The following representative amount of work is for the evaluation of bids only and not necessarily the quantity for which work will be ordered by the Government. The following Line Item Tasks represent anticipated scope of work, that may be requested in Task Orders in any combination, and shall be based on Unit Costs that include Direct Labor,Material, Setup, Equipment, Cleanup and Waste Disposal costs, plus Contractor Markups, Overhead and Profit.

B001AA Water-blasting concrete/masonry surfaces. ( High pressure pump 10-15 Mpa)

60,000SM¥0
B001ABRepair of concrete spall (Interior and Exterior). Assume Average Depth of 30mm. (Including chipping, scrape, Anti-rust Treatment of rebar and Polymer resin mortar backfill finish)5,000SM¥0
B001ACExterior painting on textured concrete & masonry surfaces. (Including Taping/Masking of adjacent surfaces like doors, windows and louvers)55,000SM¥0
B001ADExterior painting on non textured concrete & masonry surfaces. (Including Taping/Masking of adjacent surfaces like doors, windows and louvers)100SM¥0
B001AEScaffolding up to 12 meters. (Including Materials and Labor to assemble/disassemble)30,000SM¥0
B001AFScaffolding up to 22 meters. (Including Materials and Labor to assemble/disassemble)16,000SM¥0
B001AGExterior Painting of metal surfaces. (Including surface preparation/restoration and painting)5,000SM¥0
B001AHGWB Repair, Nail/Screw Pops
(Assume 1 per 1 S.M. of Int. GWB)1,500EA¥0
B001AJGWB Repair, Cut/Patch/Tape 50mm x 100mm Hole
(Assume 1 per 300 S.M. of Int. GWB)10EA¥0
B001AKGWB Replace, Demo Existing/ Install New
(Assume 10% of Int. GWB)150SM¥0
B001ALInterior painting of concrete, masonry, wallboard, plaster, interior and wood surfaces. (Including taping / masking of adjacent surfaces such as doors, windows, louvers, tiles, etc. Including base treatment such as putty).7,000SM¥0
B001AMInterior painting of ceilings (gypsum ceiling board and plaster board). (Including taping / masking of adjacent surfaces such as doors, windows, louvers, tiles, etc. Including base treatment such as putty).9,000SM¥0
B001ANInterior re-staining of wood floors. (Based on 2 Coats of Low VOC Polyurethane Varnish, including sanding and refinishing )500SM¥0
B001APInterior Painting of high wetness areas (all surfaces). ( including Taping/Masking of adjacent surfaces like doors, windows, louvers and tile)150SM¥0
B001AQInterior moving type scaffolding, up to 5.4 meters, walls and ceilings. (Including Materials and Labor to assemble/disassemble) 4 rolling towers, 4 month usage period (H=5.4m).1EA¥0
B001ARInterior scaffolding, up to 1.8 meters, walls and ceilings. (Including Materials Transport and Labor to assemble/disassemble)2,000SM¥0
B001ASSealants around existing doors and windows,
Demo Existing/Install New8,000LM¥0
B001ATOnly the transportation costs of workers and work vehicles required for one task on Ie Island21DAY¥0
B001AUNon-specific work- Any work not identified on the ELINS but required to complete the project.1NTE¥21,000,000¥21,000,000
B001AVACM sampling and testting20EA¥0
B001AWLEAD sampling and testing20EA¥0
B001AXACM and LEAD abatement20SM¥0
TOTAL PRICE FOR CONTRACT LINE ITEMS B001AA THRU B001AX¥21,000,000
BASE PERIOD - Ordering Period 2

Source Selection Information -- See FAR 2.101 and 3.104 [When filled in] Amendment 0004

Source Selection Information -- See FAR 2.101 and 3.104 [When filled in]

BASE - OP3

GOVERNMENT ESTIMATE
Prepared by :FOR OFFICIAL USE ONLY
Signature :
Date :
Base Period - Ordering Period 3REFERNCE NO. OF DOCUMENT:
NAME OF OFFFEROR OR CONTRACTOR
BID SCHEDULE
ITEM NOSECTION AND PARASUPPLIES/SERVICESQUANTITYUNITUNIT PRICE (Including applicable performance bond)TOTAL AMOUNT
C001OPTION YEAR 2 - SCHEDULE OF INDEFINITE QUANTITY WORK: THE LINE ITEMS LISTED BELOW ARE FOR ONE YEAR BASE PERIOD AS ESTABLISHED BY THE CONTRACTING OFFICER. Indefinite Quantity Work: Price to perform indefinite quantity work in accordance with all the terms of this contract. The contract price is the sum of contract lines from C001AA to C001AX.
Units: SM = Square Meters LM = Linear Meter TO = Task Order HRS = Hours EA = Each OC = Occasion NTE=Not to exceed
Line Item Tasks - Material and Labor Hours Provision:

The following representative amount of work is for the evaluation of bids only and not necessarily the quantity for which work will be ordered by the Government. The following Line Item Tasks represent anticipated scope of work, that may be requested in Task Orders in any combination, and shall be based on Unit Costs that include Direct Labor,Material, Setup, Equipment, Cleanup and Waste Disposal costs, plus Contractor Markups, Overhead and Profit.

C001AA Water-blasting concrete/masonry surfaces. ( High pressure pump 10-15 Mpa)

60,000SM¥0
C001ABRepair of concrete spall (Interior and Exterior). Assume Average Depth of 30mm. (Including chipping, scrape, Anti-rust Treatment of rebar and Polymer resin mortar backfill finish)5,000SM¥0
C001ACExterior painting on textured concrete & masonry surfaces. (Including Taping/Masking of adjacent surfaces like doors, windows and louvers)55,000SM¥0
C001ADExterior painting on non textured concrete & masonry surfaces. (Including Taping/Masking of adjacent surfaces like doors, windows and louvers)100SM¥0
C001AEScaffolding up to 12 meters. (Including Materials and Labor to assemble/disassemble)30,000SM¥0
C001AFScaffolding up to 22 meters. (Including Materials and Labor to assemble/disassemble)16,000SM¥0
C001AGExterior Painting of metal surfaces. (Including surface preparation/restoration and painting)5,000SM¥0
C001AHGWB Repair, Nail/Screw Pops
(Assume 1 per 1 S.M. of Int. GWB)1,500EA¥0
C001AJGWB Repair, Cut/Patch/Tape 50mm x 100mm Hole
(Assume 1 per 300 S.M. of Int. GWB)10EA¥0
C001AKGWB Replace, Demo Existing/ Install New
(Assume 10% of Int. GWB)150SM¥0
C001ALInterior painting of concrete, masonry, wallboard, plaster, interior and wood surfaces. (Including taping / masking of adjacent surfaces such as doors, windows, louvers, tiles, etc. Including base treatment such as putty).7,000SM¥0
C001AMInterior painting of ceilings (gypsum ceiling board and plaster board). (Including taping / masking of adjacent surfaces such as doors, windows, louvers, tiles, etc. Including base treatment such as putty).9,000SM¥0
C001ANInterior re-staining of wood floors. (Based on 2 Coats of Low VOC Polyurethane Varnish, including sanding and refinishing )500SM¥0
C001APInterior Painting of high wetness areas (all surfaces). ( including Taping/Masking of adjacent surfaces like doors, windows, louvers and tile)150SM¥0
C001AQInterior moving type scaffolding, up to 5.4 meters, walls and ceilings. (Including Materials and Labor to assemble/disassemble) 4 rolling towers, 4 month usage period (H=5.4m).1EA¥0
C001ARInterior scaffolding, up to 1.8 meters, walls and ceilings. (Including Materials Transport and Labor to assemble/disassemble)2,000SM¥0
C001ASSealants around existing doors and windows,
Demo Existing/Install New8,000LM¥0
C001ATOnly the transportation costs of workers and work vehicles required for one task on Ie Island21DAY¥0
C001AUNon-specific work- Any work not identified on the ELINS but required to complete the project.1NTE¥21,000,000¥21,000,000
C001AVACM sampling and testting20EA¥0
C001AWLEAD sampling and testing20EA¥0
C001AXACM and LEAD abatement20SM¥0
TOTAL PRICE FOR CONTRACT LINE ITEMS C001AA THRU C001AX¥21,000,000
BASE PERIOD - Ordering Period 3

Source Selection Information -- See FAR 2.101 and 3.104 [When filled in] Amendment 0004

Source Selection Information -- See FAR 2.101 and 3.104 [When filled in]

BASE - OP4

GOVERNMENT ESTIMATE
Prepared by :FOR OFFICIAL USE ONLY
Signature :
Date :
Base Period - Ordering Period 4REFERNCE NO. OF DOCUMENT:
NAME OF OFFFEROR OR CONTRACTOR
BID SCHEDULE
ITEM NOSECTION AND PARASUPPLIES/SERVICESQUANTITYUNITUNIT PRICE (Including applicable performance bond)TOTAL AMOUNT
D001OPTION YEAR 3 - SCHEDULE OF INDEFINITE QUANTITY WORK: THE LINE ITEMS LISTED BELOW ARE FOR ONE YEAR BASE PERIOD AS ESTABLISHED BY THE CONTRACTING OFFICER. Indefinite Quantity Work: Price to perform indefinite quantity work in accordance with all the terms of this contract. The contract price is the sum of contract lines from D001AA to D001AX.
Units: SM = Square Meters LM = Linear Meter TO = Task Order HRS = Hours EA = Each OC = Occasion NTE=Not to exceed
Line Item Tasks - Material and Labor Hours Provision:

The following representative amount of work is for the evaluation of bids only and not necessarily the quantity for which work will be ordered by the Government. The following Line Item Tasks represent anticipated scope of work, that may be requested in Task Orders in any combination, and shall be based on Unit Costs that include Direct Labor,Material, Setup, Equipment, Cleanup and Waste Disposal costs, plus Contractor Markups, Overhead and Profit.

D001AA Water-blasting concrete/masonry surfaces. ( High pressure pump 10-15 Mpa)

60,000SM¥0
D001ABRepair of concrete spall (Interior and Exterior). Assume Average Depth of 30mm. (Including chipping, scrape, Anti-rust Treatment of rebar and Polymer resin mortar backfill finish)5,000SM¥0
D001ACExterior painting on textured concrete & masonry surfaces. (Including Taping/Masking of adjacent surfaces like doors, windows and louvers)55,000SM¥0
D001ADExterior painting on non textured concrete & masonry surfaces. (Including Taping/Masking of adjacent surfaces like doors, windows and louvers)100SM¥0
D001AEScaffolding up to 12 meters. (Including Materials and Labor to assemble/disassemble)30,000SM¥0
D001AFScaffolding up to 22 meters. (Including Materials and Labor to assemble/disassemble)16,000SM¥0
D001AGExterior Painting of metal surfaces. (Including surface preparation/restoration and painting)5,000SM¥0
D001AHGWB Repair, Nail/Screw Pops
(Assume 1 per 1 S.M. of Int. GWB)1,500EA¥0
D001AJGWB Repair, Cut/Patch/Tape 50mm x 100mm Hole
(Assume 1 per 300 S.M. of Int. GWB)10EA¥0
D001AKGWB Replace, Demo Existing/ Install New
(Assume 10% of Int. GWB)150SM¥0
D001ALInterior painting of concrete, masonry, wallboard, plaster, interior and wood surfaces. (Including taping / masking of adjacent surfaces such as doors, windows, louvers, tiles, etc. Including base treatment such as putty).7,000SM¥0
D001AMInterior painting of ceilings (gypsum ceiling board and plaster board). (Including taping / masking of adjacent surfaces such as doors, windows, louvers, tiles, etc. Including base treatment such as putty).9,000SM¥0
D001ANInterior re-staining of wood floors. (Based on 2 Coats of Low VOC Polyurethane Varnish, including sanding and refinishing )500SM¥0
D001APInterior Painting of high wetness areas (all surfaces). ( including Taping/Masking of adjacent surfaces like doors, windows, louvers and tile)150SM¥0
D001AQInterior moving type scaffolding, up to 5.4 meters, walls and ceilings. (Including Materials and Labor to assemble/disassemble) 4 rolling towers, 4 month usage period (H=5.4m).1EA¥0
D001ARInterior scaffolding, up to 1.8 meters, walls and ceilings. (Including Materials Transport and Labor to assemble/disassemble)2,000SM¥0
D001ASSealants around existing doors and windows,
Demo Existing/Install New8,000LM¥0
D001ATOnly the transportation costs of workers and work vehicles required for one task on Ie Island21DAY¥0
D001AUNon-specific work- Any work not identified on the ELINS but required to complete the project.1NTE¥21,000,000¥21,000,000
D001AVACM sampling and testting20EA¥0
D001AWLEAD sampling and testing20EA¥0
D001AXACM and LEAD abatement20SM¥0
TOTAL PRICE FOR CONTRACT LINE ITEMS D001AA THRU D001AX¥21,000,000
BASE PERIOD - Ordering Period 4

Source Selection Information -- See FAR 2.101 and 3.104 [When filled in] Amendment 0004

Source Selection Information -- See FAR 2.101 and 3.104 [When filled in]

BASE - OP5

GOVERNMENT ESTIMATE
Prepared by :FOR OFFICIAL USE ONLY
Signature :
Date :
Base Period - Ordering Period 5REFERNCE NO. OF DOCUMENT:
NAME OF OFFFEROR OR CONTRACTOR
BID SCHEDULE
ITEM NOSECTION AND PARASUPPLIES/SERVICESQUANTITYUNITUNIT PRICE (Including applicable performance bond)TOTAL AMOUNT
E001OPTION YEAR 4 - SCHEDULE OF INDEFINITE QUANTITY WORK: THE LINE ITEMS LISTED BELOW ARE FOR ONE YEAR BASE PERIOD AS ESTABLISHED BY THE CONTRACTING OFFICER. Indefinite Quantity Work: Price to perform indefinite quantity work in accordance with all the terms of this contract. The contract price is the sum of contract lines from E001AA to E001AX.
Units: SM = Square Meters LM = Linear Meter TO = Task Order HRS = Hours EA = Each OC = Occasion NTE=Not to exceed
Line Item Tasks - Material and Labor Hours Provision:

The following representative amount of work is for the evaluation of bids only and not necessarily the quantity for which work will be ordered by the Government. The following Line Item Tasks represent anticipated scope of work, that may be requested in Task Orders in any combination, and shall be based on Unit Costs that include Direct Labor,Material, Setup, Equipment, Cleanup and Waste Disposal costs, plus Contractor Markups, Overhead and Profit.

E001AA Water-blasting concrete/masonry surfaces. ( High pressure pump 10-15 Mpa)

60,000SM¥0
E001ABRepair of concrete spall (Interior and Exterior). Assume Average Depth of 30mm. (Including chipping, scrape, Anti-rust Treatment of rebar and Polymer resin mortar backfill finish)5,000SM¥0
E001ACExterior painting on textured concrete & masonry surfaces. (Including Taping/Masking of adjacent surfaces like doors, windows and louvers)55,000SM¥0
E001ADExterior painting on non textured concrete & masonry surfaces. (Including Taping/Masking of adjacent surfaces like doors, windows and louvers)100SM¥0
E001AEScaffolding up to 12 meters. (Including Materials and Labor to assemble/disassemble)30,000SM¥0
E001AFScaffolding up to 22 meters. (Including Materials and Labor to assemble/disassemble)16,000SM¥0
E001AGExterior Painting of metal surfaces. (Including surface preparation/restoration and painting)5,000SM¥0
E001AHGWB Repair, Nail/Screw Pops
(Assume 1 per 1 S.M. of Int. GWB)1,500EA¥0
E001AJGWB Repair, Cut/Patch/Tape 50mm x 100mm Hole
(Assume 1 per 300 S.M. of Int. GWB)10EA¥0
E001AKGWB Replace, Demo Existing/ Install New
(Assume 10% of Int. GWB)150SM¥0
E001ALInterior painting of concrete, masonry, wallboard, plaster, interior and wood surfaces. (Including taping / masking of adjacent surfaces such as doors, windows, louvers, tiles, etc. Including base treatment such as putty).7,000SM¥0
E001AMInterior painting of ceilings (gypsum ceiling board and plaster board). (Including taping / masking of adjacent surfaces such as doors, windows, louvers, tiles, etc. Including base treatment such as putty).9,000SM¥0
E001ANInterior re-staining of wood floors. (Based on 2 Coats of Low VOC Polyurethane Varnish, including sanding and refinishing )500SM¥0
E001APInterior Painting of high wetness areas (all surfaces). ( including Taping/Masking of adjacent surfaces like doors, windows, louvers and tile)150SM¥0
E001AQInterior moving type scaffolding, up to 5.4 meters, walls and ceilings. (Including Materials and Labor to assemble/disassemble) 4 rolling towers, 4 month usage period (H=5.4m).1EA¥0
E001ARInterior scaffolding, up to 1.8 meters, walls and ceilings. (Including Materials Transport and Labor to assemble/disassemble)2,000SM¥0
E001ASSealants around existing doors and windows,
Demo Existing/Install New8,000LM¥0
E001ATOnly the transportation costs of workers and work vehicles required for one task on Ie Island21DAY¥0
E001AUNon-specific work- Any work not identified on the ELINS but required to complete the project.1NTE¥21,000,000¥21,000,000
E001AVACM sampling and testting20EA¥0
E001AWLEAD sampling and testing20EA¥0
E001AXACM and LEAD abatement20SM¥0
TOTAL PRICE FOR CONTRACT LINE ITEMS E001AA THRU E001AX¥21,000,000
BASE PERIOD - Ordering Period 5

Source Selection Information -- See FAR 2.101 and 3.104 [When filled in] Amendment 0004

Source Selection Information -- See FAR 2.101 and 3.104 [When filled in]

OPTION PERIOD 1 - OP6

GOVERNMENT ESTIMATE
Prepared by :FOR OFFICIAL USE ONLY
Signature :
Date :
Option Period 1 - Ordering Period 6REFERNCE NO. OF DOCUMENT:
NAME OF OFFFEROR OR CONTRACTOR
BID SCHEDULE
ITEM NOSECTION AND PARASUPPLIES/SERVICESQUANTITYUNITUNIT PRICE (Including applicable performance bond)TOTAL AMOUNT
F001OPTION YEAR 5 - SCHEDULE OF INDEFINITE QUANTITY WORK: THE LINE ITEMS LISTED BELOW ARE FOR ONE YEAR BASE PERIOD AS ESTABLISHED BY THE CONTRACTING OFFICER. Indefinite Quantity Work: Price to perform indefinite quantity work in accordance with all the terms of this contract. The contract price is the sum of contract lines from F001AA to F001AX.
Units: SM = Square Meters LM = Linear Meter TO = Task Order HRS = Hours EA = Each OC = Occasion NTE=Not to exceed
Line Item Tasks - Material and Labor Hours Provision:

The following representative amount of work is for the evaluation of bids only and not necessarily the quantity for which work will be ordered by the Government. The following Line Item Tasks represent anticipated scope of work, that may be requested in Task Orders in any combination, and shall be based on Unit Costs that include Direct Labor,Material, Setup, Equipment, Cleanup and Waste Disposal costs, plus Contractor Markups, Overhead and Profit.

F001AA Water-blasting concrete/masonry surfaces. ( High pressure pump 10-15 Mpa)

60,000SM¥0
F001ABRepair of concrete spall (Interior and Exterior). Assume Average Depth of 30mm. (Including chipping, scrape, Anti-rust Treatment of rebar and Polymer resin mortar backfill finish)5,000SM¥0
F001ACExterior painting on textured concrete & masonry surfaces. (Including Taping/Masking of adjacent surfaces like doors, windows and louvers)55,000SM¥0
F001ADExterior painting on non textured concrete & masonry surfaces. (Including Taping/Masking of adjacent surfaces like doors, windows and louvers)100SM¥0
F001AEScaffolding up to 12 meters. (Including Materials and Labor to assemble/disassemble)30,000SM¥0
F001AFScaffolding up to 22 meters. (Including Materials and Labor to assemble/disassemble)16,000SM¥0
F001AGExterior Painting of metal surfaces. (Including surface preparation/restoration and painting)5,000SM¥0
F01AHGWB Repair, Nail/Screw Pops
(Assume 1 per 1 S.M. of Int. GWB)1,500EA¥0
F001AJGWB Repair, Cut/Patch/Tape 50mm x 100mm Hole
(Assume 1 per 300 S.M. of Int. GWB)10EA¥0
F001AKGWB Replace, Demo Existing/ Install New
(Assume 10% of Int. GWB)150SM¥0
F001ALInterior painting of concrete, masonry, wallboard, plaster, interior and wood surfaces. (Including taping / masking of adjacent surfaces such as doors, windows, louvers, tiles, etc. Including base treatment such as putty).7,000SM¥0
F001AMInterior painting of ceilings (gypsum ceiling board and plaster board). (Including taping / masking of adjacent surfaces such as doors, windows, louvers, tiles, etc. Including base treatment such as putty).9,000SM¥0
F001ANInterior re-staining of wood floors. (Based on 2 Coats of Low VOC Polyurethane Varnish, including sanding and refinishing )500SM¥0
F001APInterior Painting of high wetness areas (all surfaces). ( including Taping/Masking of adjacent surfaces like doors, windows, louvers and tile)150SM¥0
F001AQInterior moving type scaffolding, up to 5.4 meters, walls and ceilings. (Including Materials and Labor to assemble/disassemble) 4 rolling towers, 4 month usage period (H=5.4m).1EA¥0
F001ARInterior scaffolding, up to 1.8 meters, walls and ceilings. (Including Materials Transport and Labor to assemble/disassemble)2,000SM¥0
F001ASSealants around existing doors and windows,
Demo Existing/Install New8,000LM¥0
F001ATOnly the transportation costs of workers and work vehicles required for one task on Ie Island21DAY¥0
F001AUNon-specific work- Any work not identified on the ELINS but required to complete the project.1NTE¥21,000,000¥21,000,000
F001AVACM sampling and testting20EA¥0
F001AWLEAD sampling and testing20EA¥0
F001AXACM and LEAD abatement20SM¥0
TOTAL PRICE FOR CONTRACT LINE ITEMS F001AA THRU F001AX¥21,000,000
OPTION PERIOD 1 - Ordering Period 6

Source Selection Information -- See FAR 2.101 and 3.104 [When filled in] Amendment 0004

Source Selection Information -- See FAR 2.101 and 3.104 [When filled in]

OPTION PERIOD 1 - OP7

GOVERNMENT ESTIMATE
Prepared by :FOR OFFICIAL USE ONLY
Signature :
Date :
Option Period 1 - Ordering Period 7REFERNCE NO. OF DOCUMENT:
NAME OF OFFFEROR OR CONTRACTOR
BID SCHEDULE
ITEM NOSECTION AND PARASUPPLIES/SERVICESQUANTITYUNITUNIT PRICE (Including applicable performance bond)TOTAL AMOUNT
G001OPTION YEAR 6 - SCHEDULE OF INDEFINITE QUANTITY WORK: THE LINE ITEMS LISTED BELOW ARE FOR ONE YEAR BASE PERIOD AS ESTABLISHED BY THE CONTRACTING OFFICER. Indefinite Quantity Work: Price to perform indefinite quantity work in accordance with all the terms of this contract. The contract price is the sum of contract lines from G001AA to G001AX.
Units: SM = Square Meters LM = Linear Meter TO = Task Order HRS = Hours EA = Each OC = Occasion NTE=Not to exceed
Line Item Tasks - Material and Labor Hours Provision:

The following representative amount of work is for the evaluation of bids only and not necessarily the quantity for which work will be ordered by the Government. The following Line Item Tasks represent anticipated scope of work, that may be requested in Task Orders in any combination, and shall be based on Unit Costs that include Direct Labor,Material, Setup, Equipment, Cleanup and Waste Disposal costs, plus Contractor Markups, Overhead and Profit.

G001AA Water-blasting concrete/masonry surfaces. ( High pressure pump 10-15 Mpa)

60,000SM¥0
G001ABRepair of concrete spall (Interior and Exterior). Assume Average Depth of 30mm. (Including chipping, scrape, Anti-rust Treatment of rebar and Polymer resin mortar backfill finish)5,000SM¥0
G001ACExterior painting on textured concrete & masonry surfaces. (Including Taping/Masking of adjacent surfaces like doors, windows and louvers)55,000SM¥0
G001ADExterior painting on non textured concrete & masonry surfaces. (Including Taping/Masking of adjacent surfaces like doors, windows and louvers)100SM¥0
G001AEScaffolding up to 12 meters. (Including Materials and Labor to assemble/disassemble)30,000SM¥0
G001AFScaffolding up to 22 meters. (Including Materials and Labor to assemble/disassemble)16,000SM¥0
G001AGExterior Painting of metal surfaces. (Including surface preparation/restoration and painting)5,000SM¥0
G001AHGWB Repair, Nail/Screw Pops
(Assume 1 per 1 S.M. of Int. GWB)1,500EA¥0
G001AJGWB Repair, Cut/Patch/Tape 50mm x 100mm Hole
(Assume 1 per 300 S.M. of Int. GWB)10EA¥0
G001AKGWB Replace, Demo Existing/ Install New
(Assume 10% of Int. GWB)150SM¥0
G001ALInterior painting of concrete, masonry, wallboard, plaster, interior and wood surfaces. (Including taping / masking of adjacent surfaces such as doors, windows, louvers, tiles, etc. Including base treatment such as putty).7,000SM¥0
G001AMInterior painting of ceilings (gypsum ceiling board and plaster board). (Including taping / masking of adjacent surfaces such as doors, windows, louvers, tiles, etc. Including base treatment such as putty).9,000SM¥0
G001ANInterior re-staining of wood floors. (Based on 2 Coats of Low VOC Polyurethane Varnish, including sanding and refinishing )500SM¥0
G001APInterior Painting of high wetness areas (all surfaces). ( including Taping/Masking of adjacent surfaces like doors, windows, louvers and tile)150SM¥0
G001AQInterior moving type scaffolding, up to 5.4 meters, walls and ceilings. (Including Materials and Labor to assemble/disassemble) 4 rolling towers, 4 month usage period (H=5.4m).1EA¥0
G001ARInterior scaffolding, up to 1.8 meters, walls and ceilings. (Including Materials Transport and Labor to assemble/disassemble)2,000SM¥0
G001ASSealants around existing doors and windows,
Demo Existing/Install New8,000LM¥0
G001ATOnly the transportation costs of workers and work vehicles required for one task on Ie Island21DAY¥0
G001AUNon-specific work- Any work not identified on the ELINS but required to complete the project.1NTE¥21,000,000¥21,000,000
G001AVACM sampling and testting20EA¥0
G001AWLEAD sampling and testing20EA¥0
G001AXACM and LEAD abatement20SM¥0
TOTAL PRICE FOR CONTRACT LINE ITEMS G001AA THRU G001AX¥21,000,000
OPTION PERIOD 1 - Ordering Period 7

Source Selection Information -- See FAR 2.101 and 3.104 [When filled in] Amendment 0004

Source Selection Information -- See FAR 2.101 and 3.104 [When filled in]

OPTION PERIOD 1 - OP8

GOVERNMENT ESTIMATE
Prepared by :FOR OFFICIAL USE ONLY
Signature :
Date :
Option Period 1 - Ordering Period 8REFERNCE NO. OF DOCUMENT:
NAME OF OFFFEROR OR CONTRACTOR
BID SCHEDULE
ITEM NOSECTION AND PARASUPPLIES/SERVICESQUANTITYUNITUNIT PRICE (Including applicable performance bond)TOTAL AMOUNT
H001OPTION YEAR 7 - SCHEDULE OF INDEFINITE QUANTITY WORK: THE LINE ITEMS LISTED BELOW ARE FOR ONE YEAR BASE PERIOD AS ESTABLISHED BY THE CONTRACTING OFFICER. Indefinite Quantity Work: Price to perform indefinite quantity work in accordance with all the terms of this contract. The contract price is the sum of contract lines from H001AA to H001AX.
Units: SM = Square Meters LM = Linear Meter TO = Task Order HRS = Hours EA = Each OC = Occasion NTE=Not to exceed
Line Item Tasks - Material and Labor Hours Provision:

The following representative amount of work is for the evaluation of bids only and not necessarily the quantity for which work will be ordered by the Government. The following Line Item Tasks represent anticipated scope of work, that may be requested in Task Orders in any combination, and shall be based on Unit Costs that include Direct Labor,Material, Setup, Equipment, Cleanup and Waste Disposal costs, plus Contractor Markups, Overhead and Profit.

H001AA Water-blasting concrete/masonry surfaces. ( High pressure pump 10-15 Mpa)

60,000SM¥0
H001ABRepair of concrete spall (Interior and Exterior). Assume Average Depth of 30mm. (Including chipping, scrape, Anti-rust Treatment of rebar and Polymer resin mortar backfill finish)5,000SM¥0
H001ACExterior painting on textured concrete & masonry surfaces. (Including Taping/Masking of adjacent surfaces like doors, windows and louvers)55,000SM¥0
H001ADExterior painting on non textured concrete & masonry surfaces. (Including Taping/Masking of adjacent surfaces like doors, windows and louvers)100SM¥0
H001AEScaffolding up to 12 meters. (Including Materials and Labor to assemble/disassemble)30,000SM¥0
H001AFScaffolding up to 22 meters. (Including Materials and Labor to assemble/disassemble)16,000SM¥0
H001AGExterior Painting of metal surfaces. (Including surface preparation/restoration and painting)5,000SM¥0
H001AHGWB Repair, Nail/Screw Pops
(Assume 1 per 1 S.M. of Int. GWB)1,500EA¥0
H001AJGWB Repair, Cut/Patch/Tape 50mm x 100mm Hole
(Assume 1 per 300 S.M. of Int. GWB)10EA¥0
H001AKGWB Replace, Demo Existing/ Install New
(Assume 10% of Int. GWB)150SM¥0
H001ALInterior painting of concrete, masonry, wallboard, plaster, interior and wood surfaces. (Including taping / masking of adjacent surfaces such as doors, windows, louvers, tiles, etc. Including base treatment such as putty).7,000SM¥0
H001AMInterior painting of ceilings (gypsum ceiling board and plaster board). (Including taping / masking of adjacent surfaces such as doors, windows, louvers, tiles, etc. Including base treatment such as putty).9,000SM¥0
H001ANInterior re-staining of wood floors. (Based on 2 Coats of Low VOC Polyurethane Varnish, including sanding and refinishing )500SM¥0
H001APInterior Painting of high wetness areas (all surfaces). ( including Taping/Masking of adjacent surfaces like doors, windows, louvers and tile)150SM¥0
H001AQInterior moving type scaffolding, up to 5.4 meters, walls and ceilings. (Including Materials and Labor to assemble/disassemble) 4 rolling towers, 4 month usage period (H=5.4m).1EA¥0
H001ARInterior scaffolding, up to 1.8 meters, walls and ceilings. (Including Materials Transport and Labor to assemble/disassemble)2,000SM¥0
H001ASSealants around existing doors and windows,
Demo Existing/Install New8,000LM¥0
H001ATOnly the transportation costs of workers and work vehicles required for one task on Ie Island21DAY¥0
H001AUNon-specific work- Any work not identified on the ELINS but required to complete the project.1NTE¥21,000,000¥21,000,000
H001AVACM sampling and testting20EA¥0
H001AWLEAD sampling and testing20EA¥0
H001AXACM and LEAD abatement20SM¥0
TOTAL PRICE FOR CONTRACT LINE ITEMS H001AA THRU H001AX¥21,000,000
OPTION PERIOD 1 - Ordering Period 8

Source Selection Information -- See FAR 2.101 and 3.104 [When filled in] Amendment 0004

Source Selection Information -- See FAR 2.101 and 3.104 [When filled in]

File details come from the government source that posted it. Updated .