Specifications.pdf
PDF 2 MB Posted
- Solicitation number
- N4008313R0032
About this file
Specifications
View the file
Other files
| File | Type | Posted |
|---|---|---|
| N40083-13-R-0032_Amend_09.pdf | ||
| N40083-13-R-0032_Amend_08.pdf | ||
| N40083-13-R-0032_Amend_07.pdf | ||
| Grand_Forks_RFI_Response.pdf | ||
| N40083-13-R-0032_Amend_06.pdf | ||
| Evaluation_Factors_Rev_3_dtd_9-10.pdf | ||
| Evaluation_Factors_Rev_2_dtd_9-10.pdf | ||
| N40083-13-R-0032_Amend_05.pdf | ||
| Evaluation_Factors_Rev_9-10.pdf | ||
| N40083-13-R-0032_Amend_04.pdf | ||
| Grand_Forks_Cost_Breakdown.xls | XLS spreadsheet | |
| N40083-13-R-0032_Amend_03.pdf | ||
| Evaluation_Factors_FINAL.pdf | ||
| RFI_Responses_Grand_Forks.pdf | ||
| Grand_Forks_SF-30_01.pdf | ||
| N40083-13-R-0032_Amend_1.pdf | ||
| Evaluation_Factors.pdf | ||
| Past_Performance_Questionnaire.doc | DOC document | |
| FORM_-_Contractor_RFI_Form.xls | XLS spreadsheet | |
| N4008313R0032.pdf | ||
| Instructions_to_Offerors.pdf | ||
| Drawings.pdf | ||
| Grand_Forks_Wage_Determination.pdf |
Show all 23
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SMART Magazine Modifications eProject #1156885 Grand Forks, ND
DESIGN BID BUILD REQUEST FOR PROPOSAL
FINAL BID DOCUMENTS
CONSTRUCTION CONTRACT No.
N40083-13-R-0006
DOD Lock Program RDT&E Project SMART Magazine Modifications
Earth Covered Concrete Arch Magazine AW 33-13-01
AT
Grand Forks Air Force Base (AFB)
Grand Forks, North Dakota
PREPARED BY:
NAVFAC MIDWEST CI
NAVFAC EXWC
ABS Consulting
Structural: M. Mainridge, P.E. (ABS Consulting) Design Manager: S. Smaby, R.A. (NAVFAC EXWC) Project Manager: R. Wilmot (NAVFAC MW)
REQUEST FOR PROPOSAL APPROVED BY:
Capital Improvements Business Line Team Leader:
J. Blayne Kirsch, P.E., P.G.
For Commander, NAVFAC MW Date: 7 June 2013
4/18/2013 Final Submittal
SMART Magazine Modifications Grand Forks AFB eProject #1156885
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 SUMMARY OF WORK
01 14 00 WORK RESTRICTIONS
01 20 00.00 20 PRICE AND PAYMENT PROCEDURES
01 30 00 ADMINISTRATIVE REQUIREMENTS
01 32 01.00 10 PROJECT SCHEDULE
01 32 17.00 20 NETWORK ANALYSIS SCHEDULES (NAS)
01 33 00 SUBMITTAL PROCEDURES
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 35 40.00 20 ENVIRONMENTAL MANAGEMENT
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00.00 20 QUALITY CONTROL
01 57 19.00 20 TEMPORARY ENVIRONMENTAL CONTROLS
01 57 20.00 10 ENVIRONMENTAL PROTECTION
01 62 35 RECYCLED / RECOVERED MATERIALS
01 74 19 CONSTRUCTION AND DEMOLITION WASTE MANAGEMENT
01 78 00 CLOSEOUT SUBMITTALS
01 78 23 OPERATION AND MAINTENANCE DATA
DIVISION 02 - EXISTING CONDITIONS
02 41 00 DEMOLITION
DIVISION 03 - CONCRETE
03 11 13.00 10 STRUCTURAL CAST-IN-PLACE CONCRETE FORMING
03 15 00.00 10 CONCRETE ACCESSORIES
03 20 00.00 10 CONCRETE REINFORCING
03 31 00.00 10 CAST-IN-PLACE STRUCTURAL CONCRETE
DIVISION 05 - METALS
05 05 23 WELDING, STRUCTURAL
05 12 00 STRUCTURAL STEEL
05 50 13 MISCELLANEOUS METAL FABRICATIONS
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 41 13 METAL ROOF PANELS
07 92 00 JOINT SEALANTS
DIVISION 08 - OPENINGS
08 39 53 BLAST RESISTANT SLIDING DOORS
DIVISION 09 - FINISHES
09 97 13.00 40 STEEL COATINGS
DIVISION 26 - ELECTRICAL
26 20 00 INTERIOR DISTRIBUTION SYSTEM
26 70 00 HEAT TRACING FOR SNOW AND ICE MELTING
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
PROJECT TABLE OF CONTENTS Page 1
28 05 26.00 40 GROUNDING AND BONDING FOR ELECTRONIC SAFETY AND SECURITY
DIVISION 31 - EARTHWORK
31 23 00.00 20 EXCAVATION AND FILL
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 13 13.06 PORTLAND CEMENT CONCRETE PAVEMENT FOR ROADS AND SITE
FACILITIES
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 2
SECTION 01 11 00
SUMMARY OF WORK
08/11
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM E2114 (2008) Standard Terminology for Sustainability Relative to the Performance of Buildings
1.2 DEFINITIONS
Definitions pertaining to sustainable development are as defined in ASTM E2114, Section 01 35 40.00 20 ENVIRONMENTAL MANAGEMENTSection 01 57 20.00 10 ENVIRONMENTAL PROTECTION, and as specified.
a. "Environmentally preferable products" have a lesser or reduced effect on the environment in comparison to conventional products and services. This comparison may consider raw materials acquisition, production, manufacturing, packaging, distribution, reuse, operation, maintenance, or disposal of the product.
b. "Indoor environmental quality" is the physical characteristics of the building interior that impact occupants, including air quality, illumination, acoustics, occupant control, thermal comfort, daylighting, and views.
c. "Operational performance" is the functional behavior of the building as a whole or of the building components.
d. "Sustainability" is the balance of environmental, economic, and societal considerations.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.
The following shall be submitted in accordance with Section 01 33 00
SUBMITTAL PROCEDURES:
SD-07 Certificates
Energy Performance Rating
SECTION 01 11 00 Page 1
1.4 WORK COVERED BY CONTRACT DOCUMENTS
1.4.1 Project Description
The work includes fabrication of single steel security door and its supporting components for an existing munitions magazine. The existing magazine will require retorfitting and renovation to except the new door as specified in the contract documents. The retrofit/renovation will; but not limited to, new concrete foundations, concrete pilasters, concrete door track, steel door header, paving repair, electrical upgrades, and incidental related work.
The Notice to Proceed for the awarded contract shall be instruction to commencement of work under this contract. Work shall begin within the number of days specified on the contract.
All work not specifically addressed in this specification or specifications there after shall be installed in strict accordance to the latest publications of the National Electric Code, Uniform Building Code, Uniform Mechanical Code, Uniform Plumbing Code, NFPA 101 Life Safety Code, and Grand Forks AFB Architectural Compatibility Guide. The GFAFB Architectural Compatibility Guide is not included in specifications package, but will be provided upon request.
International Conference of Building Officials has established the basic building code standards for construction, renovation, repair, and maintenance. These standards, commonly referred to as the International Building Code (IBC), together with the Unified Facilities Criteria UFC 1-200-01 found at http://www.wbdg.org/ccb/DOD/UFC/ufc_1_200_01.pdf shall constitute the minimum acceptable levels of construction, function, and safety for all projects.
All material selections, construction, renovation, repair, and maintenance shall comply with the latest addition of Unified Facilities Criteria UFC 3-600-1 Fire Protection Engineering for Facilities.
All articles, supplies and equipment, parts, and assemblies thereof, of standard manufacturers or for which design requirements are not prescribed by these specifications shall be guaranteed against any failure in the proper use or operation caused by defective material, workmanship, or design for the full warranty time which is standard with the manufacturer and/or supplier.
The contractor shall provide a minimum one year warranty on all work performed. A copy of the warranty shall be submitted to the Contracting Officer before final inspection of the facility.
1.4.2 Location
The work shall be located at the Grand Forks AFB, ND, approximately as indicated. The exact location will be shown by the Contracting Officer.
1.5 OCCUPANCY OF PREMISES
Building(s) will not be occupied during performance of work under this Contract.
SECTION 01 11 00 Page 2
1.6 LOCATION OF UNDERGROUND UTILITIES
Record drawings (as-builts) showing existing facilities and underground utilities are available to the contractor through the Base Civil Engineer Drafting Office, and Operations Customer Service. The government does not guarantee the accuracy or adequacy of existing as-built/record drawings.
The contractor is responsible for field verifying all dimensions and actual conditions when developing individual delivery order proposals. Failure to verify the dimensions and locations will be at the contractor's risk and shall not relieve the contractor from accomplishing the work required by the contract at the price awarded by the government. The contractor shall immediately repair any utility lines shown on a record drawing (or made known to the contractor via ground marking) and damaged during construction work at no cost to the government. Prior to digging, the contractor shall review available drawings and located utilities to determine if all utilities on the drawings have been located. Should the drawings indicate the existence of an underground utility, but there are no markings to indicate the utility has been located, the contractor shall verify all locates are completed prior to below grade excavations.
Scan the construction site with Ground Penetrating Radar and electromagnetic or sonic equipment, and mark the surface of the ground where existing underground utilities are discovered. Verify the elevations of existing piping, utilities,and any type of underground obstruction not indicated to be specified or removed but indicated or discovered during scanning in locations to be traversed by piping, ducts, and other work to be conducted or installed.
1.6.1 CORDINATION AND OUTAGES
The contractor shall perform the work under this contract with a minimum of outage time for all utilities, for any facility or system. The contractor shall make every attempt schedule any work that requires utility outages which will close down or limit normal activities in the building, construction area, or other affected areas (as determined by the contractor with coordination of engineering project management personnel) at a time other than regular work periods of the organization occupying the facility. Whenever outages occur on weekends, holidays or after normal duty hours, the contractor shall perform the work at such times as designated at no additional cost to the Government.
Wherever possible, portions of the work that can be accomplished without an outage shall be done prior to actual outage. All materials, equipment, and labor required to facilitate work during an outage shall be on hand before the utility service is interrupted.
A process and policy has been established by 319 CES for scheduling and notifications regarding all utility outages. Attachment One to this specification contains the process and policy for the scheduling of utility outages at Grand Forks AFB. This coordination shall be the responsibility of contractor. As this policy and other attachments are updated, new revisions will be provided to the contractor by the CO. In addition to the previous requirement, the contractor shall personally coordinate all utility outages with the affected facility users, and the Base Civil Engineering Operations Flight shops that oversees/controls the system(s).
Notifying the Construction Representative (CR) is NOT adequate. The contractor shall submit requests for utility outages a minimum of ten (10)
SECTION 01 11 00 Page 3 working days prior to commencing work. The contractor must receive approval from the CO and/or CR before interrupting utilities. Any disruption of utilities service to the military family housing area shall include coordination with the base housing office. This coordination shall be the responsibility of the contractor. The contractor is responsible for shutting down the utility using his own workforce or by requesting the shutdown from the utility company (or Civil Engineer Shop) responsible for the service. Typically, the civil engineer shop having jurisdiction will shutdown the primary utility. Once work begins on an approved outage, work must continue without interruption until utility services to the affected line(s) and/or facility are restored. Exceptions require pre-approval from the CO/CR.
Control of the base electrical system is the responsibility of the Base Utility Superintendent (Bldg 411). All switching of electrical equipment/circuits must be approved by the base Utility Superintendent or his authorized representative. Work on de-energized high voltage lines or equipment is not permitted until the Base Utility Superintendent or his authorized representative has issued a safe clearance procedure to the Contractor Superintendent in accordance with AFI 32-1064, 25 May 2006 (a copy is available upon request).
The contractor shall not disturb communication wiring to facilities. Where such facilities require removal of existing, reconfiguration of existing, and/or installation of new communication equipment and wiring to accomplish the work involved, the contractor shall coordinate with the Communications Squadron prior to actual work, to determine the scope of effort and gain authority from the Communications Squadron to work on communications systems. The contractor shall allow for the accomplishment of such removals by the telephone company or communications personnel for the systems they service. If construction activities damage communication equipment or wiring, the contractor shall restore services as soon as possible, but no later than 24 hours, and at no cost to the government.
1.6.2 Notification Prior to Excavation
Notify the Contracting Officer at least 15 days prior to starting excavation work. Prior to the start of work, the contractor shall identify and locate all valve or utility shut-off locations for use in the event of accidental damage. To preclude accidental damage, the contractor shall locate all known utilities (i.e., communication, natural gas, fuel supply, water, power, etc.) by hand digging or hydro-excavating prior to any excavation with other power equipment. The contractor shall note any utilities discovered during excavations that are missing or incorrectly represented on the AF Form 103 and it's attachments, the contract drawings (including any erroneous dimensions on government record drawings), or those utilities staked by the user; and clearly identify those discoveries on project as-built drawings.
1.7 GOVERNMENT-INSTALLED WORK
NAVFAC ESC will provide and install internal locking system for security door. Contractor coordination with NAVFAC ESC during construction is critical for proper lock installation.
1.8 SALVAGE MATERIAL AND EQUIPMENT
Items designated by the Contracting Officer to be salvaged shall remain the property of the Government.
SECTION 01 11 00 Page 4
The salvaged property shall be segregated, itemized, delivered, and off-loaded at the Government designated storage area.
Contractor shall maintain property control records for material or equipment designated as salvage. Contractor's system of property control may be used if approved by the Contracting Officer. Contractor shall be responsible for storage and protection of salvaged materials and equipment until disposition by the Contracting Officer.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
-- End of Section --
SECTION 01 11 00 Page 5
SECTION 01 14 00
WORK RESTRICTIONS
11/11
PART 1 GENERAL
1.1 DEFINITIONS
1.1.1 State
"State" when used in reference to states of the United States shall also include the Territory of Guam.
1.2 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for Contractor Quality Control approval. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.
The following shall be submitted in accordance with Section 01 33 00
SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Completed Special Access Determination (NAVSEA 5510/15); G
Contractor regulations G
Transportation of personnel, materials, and equipment G
Purchase orders G
List of Contact Personnel G
Personnel List G
Vehicle List G
Statement of Acknowledgement Form SF 1413 G
1.3 NOTIFICATION TO THE CONSTRUCTION MANAGEMENT OFFICE (CMO) AND PROJECT
COORDINATION
The contractor shall notify CMO (Designated Construction Representative) at least seven days in advance of starting all work. This shall include, but is not limited to, notification when the initial work shall begin; when work shall resume after stoppage exceeding five work days; and when work shall begin following all specified exclusion periods. The official Notice to Proceed does not constitute sufficient notification to CMO that work shall begin.
The contractor shall coordinate all work schedules with the contracting officer (CO) and with the designated Base Civil Engineer Construction Representative (CR) prior to the start of work. The contractor shall participate in progress meetings as directed by the CO and/or the CR.
Attendance at these meetings may include the contractor's corporate management representative(s) at the CO's discretion.
SECTION 01 14 00 Page 1
1.3.1 Interruption of Activities to Base Personnel
If it becomes necessary to interrupt base activities in buildings and/or areas for construction purposes (except as otherwise described in the contract), the contractor shall request permission, in writing, from the CO five (5) working days in advance. The contractor shall submit written requests for approved street/parking lot closings ten (10) working days prior to closing of the street/parking lot.
1.4 CONTRACTOR ACCESS AND USE OF PREMISES
1.4.1 Activity Regulations
Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Ingress and egress of Contractor vehicles at the Activity is limited to the Eielsom Street gate as shown on the contract documents sheet C-001 SITE PLAN. To minimize traffic congestion, delivery of materials shall be outside of peak traffic hours (6:30 to 8:00 a.m. and 3:30 to 5:00 p.m.) unless otherwise approved by the Contracting Officer.
Wear hard hats in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. The Contractor's equipment shall be conspicuously marked for identification.
1.4.1.1 Government Furnished Services and Utility Availability
The government will provide utilities (water, gas, and electricity) for project work areas when available. The government will NOT modify points of distribution to accommodate contractor project activities. The government will not provide utilities (gas/electric) solely for construction heating purposes. At remote project work areas where no utilities are available, the contractor shall furnish his/her own utility services.
When required, the government will furnish water from a fire hydrant or an adjacent facilities point of distribution selected by the Base Civil Engineer with coordination through the Base Fire Dept and the Contracting Officer (CO). The contractor shall provide and install the proper backflow prevention device, valve and hydrant wrench. The contractor shall be liable for any damage caused to government property resulting from improper operation of the fire hydrant. A centrally located water filling station for contractors is located at Facility 537. Government provided water is only available at this location. For more information regarding the filling station, contact the designated construction representative.
Contractor personnel may use existing toilet facilities if available on the premises and approved by the facility occupants (except in base housing) unless otherwise instructed by the CO or his/her designated representative. At construction sites where toilet facilities are not readily available, the contractor shall provide his/her own chemical sanitary toilets. The contractor shall service the chemical toilets regularly subject to government inspection by the base medical officer.
The contractor shall correct all identified sanitary deficiencies within 24 hours of inspection.
SECTION 01 14 00 Page 2
1.4.1.2 Security, Police, Fire Protection, and Emergency Services
To prevent outside intrusion, at the end of each day the contractor shall close up each and every exterior wall and roof opening resulting from work in buildings. Closure(s) shall remain in place when the contractor is not actively working on the site(s), including each and every day, night, weekends, and holidays to reduce wind and weather intrusion. Closure(s) shall be constructed of ¾" minimum thickness plywood anchored in place to stud framing if necessary, or similar construction as approved by the base civil engineer through the CO.
The government will provide security police and fire protection to the extent necessary to ensure a secure and safe construction site. In return for these services, the contractor shall adhere to the security and fire directives, instructions, and policies of Grand Forks AFB.
In the event of a severe emergency, the 319th Medical Facility, during hours of operation, will respond and transport, if necessary, a contractor employee to one of the local hospitals. The contractor shall reimburse the government for these services.
The CO, base fire chief, and other base authorized emergency response personnel, or their representative(s), have the authority to order the contractor to terminate work and clear the area of personnel and equipment. The contractor shall comply to such an order with all possible speed. When the previously mentioned authority figures or their representative(s) interrupt the contractor's operations, the contractor shall immediately notify the contracting officer of the delay.
1.4.1.3 Storage Area
All contractor storage shall be located in an area located inside the boundary of project site and will be properly screened and secured. Indoor storage areas are not guaranteed by the government, and there are no alternate storage areas on base. The contractor may be approved to use the existing magazine as temporary indoor storage apon request. The contractor may store materials and trailers off base at his/her own expense.
A visually acceptable site at Grand Forks Air Force Base is an important construction standard. The storage sites made available on the work site shall be properly screened from the public view, kept clean, and secured by the contractor at his/her expense. A safe and visually acceptable (neat, clean, free of rubbish) construction or work site at Grand Forks AFB and Cavalier AFS is an important construction standard and will enforced. The contractor shall maintain trailers and portable storage containers in good condition or must remove them. The exterior appearance of such items shall be in accordance with base color standards (Light Brown SW6093, Linen White SW6119, Medium Brown SW 6067, and Dark Bronze SW 6006). The contractor is solely responsible for the security of his/her property and general housekeeping of the project area(s). This includes, but not limited to, vegetation (weed control) and height maintenance to base standards, daily trash and refuse debris collection and containerization, and construction materials stacked, neatly palletized or in enclosed trailers.
1.4.1.4 Explosive Operated Hand Tools
The contractor shall comply with the OSHA Standard 1910.215© when utilizing explosive operated hand tools. On the installation, the contractor shall
SECTION 01 14 00 Page 3 store explosive cartridges in metal containers and limit the quantity to one day's supply. The contractor shall provide adequate controls to prevent loss/theft of cartridges used and stored on the installation.
1.4.1.5 Severe Weather
The contractor shall develop and be prepared to implement procedures to evacuate and/or protect people and facilities under his/her control in the event of severe weather. These procedures will include provisions for securing or repositioning of equipment. The contractor shall notify the CO of any evacuation procedures. Upon receipt of a severe weather warning, the following sequence of actions will occur.
The CO or his/her representative will instruct the contractor of the severe weather warning.
The contractor shall take immediate action to tie down, remove, protect, or secure his/her materials and equipment to the satisfaction of the Air Force construction representative providing reasonable assurance that the severe weather will not damage government property. If the contractor fails to secure materials and equipment and it become a hazard, Air Force personnel may accomplish the work and potential charges to the contractor may result thereof.
1.4.1.6 Access Roads
In accordance with Dirt and Dust Control contained herein, and as required (minimum at the end of each day), the contractor shall inspect for and clear all mud, dirt, debris, foreign objects, or spills of any kind from the contractor's operations (including subcontractors and suppliers) on streets and parking lots used as access to the work or staging areas. The contractor shall ensure all taxiways, runways, parking aprons and hard surfaces in or around the airfield, used to access the work or staging areas, remain clean at all times.
1.4.1.7 Contractor Generated Refuse
Prior to completion of the work each day, the contractor shall handle, transport, store, and dispose of all waste materials and rubbish generated by any work under this contract. If the contractor temporarily stores waste material or rubbish in a dumpster controlled by the contractor, the contractor shall secure the dumpster in such a manner that prevents unauthorized use. Unsecured and unattended dumpsters collect stray refuse from other than contract operations. To avoid this, the contractor shall secure the dumpster during non-working times, and post signs (if necessary) on the dumpster(s) noting it as NOT FOR PUBLIC USE. On a regular (minimum weekly basis), the contractor shall remove and dispose of any waste or excess material, resulting from any contract requirement, off base at no expense to the government. The contractor shall dispose of such materials in accordance with applicable federal, state, or local laws, ordinance or regulations. Trucks for hauling refuse and waste materials shall have tight fitting covers to prevent spillage on roadways. The contractor shall use designated haul routes as agreed upon in pre-delivery order discussions for each project.Prior to completion of the work each day, the contractor shall handle, transport, store, and dispose of all waste materials and rubbish generated by any work under this contract. If the contractor temporarily stores waste material or rubbish in a dumpster controlled by the contractor, the contractor shall secure the dumpster in such a manner that prevents unauthorized use. Unsecured and unattended dumpsters collect
SECTION 01 14 00 Page 4 stray refuse from other than contract operations. To avoid this, the contractor shall secure the dumpster during non-working times, and post signs (if necessary) on the dumpster(s) noting it as NOT FOR PUBLIC USE.
On a regular (minimum weekly basis), the contractor shall remove and dispose of any waste or excess material, resulting from any contract requirement, off base at no expense to the government. The contractor shall dispose of such materials in accordance with applicable federal, state, or local laws, ordinance or regulations. Trucks for hauling refuse and waste materials shall have tight fitting covers to prevent spillage on roadways. The contractor shall use designated haul routes as agreed upon in pre-delivery order discussions for each project.
1.4.1.8 Excavations
The government will not allow piles of soil to reside in the work area for unreasonable amounts of time. The contractor shall backfill all excavations, for whatever purpose, within one week or gain approval to have excavations remain open longer by the CM through the CO. The contractor shall temporarily repair road cuts with cold patch asphalt to assure a smooth transition until accomplishing final patching. Loose gravel or fugitive materials that can be carried by traffic shall not be used. For all disturbances to grounds, the contractor shall complete final grading within one week of the disturbance/backfilling. The contractor shall complete final landscaping or seeding within acceptable recognized planting seasons of the GFAFB local area, and/or the nursery of origin written recommendations for subject plantings.
Work requested of the contractor may include removal and/or dumping of contaminated soils. Contaminated soils are defined as "soils that contain non-hazardous materials such as aircraft fuel, heating fuel oil, solvents, and other materials as identified by the base environmental coordinator."
The contractor shall report any material suspected of containing contaminants to the CO or his/her designated representative. If contaminated soils are discovered the contractor shall NOT use the contaminated soil/debris for backfill or removed from the base without written approval from the CO, or his/her designated representative. The contractor shall store this soil on an impervious liner, compatible with the contaminant, and covered with the same impervious material. These contaminants shall be tested by the con-tractor and coordinated with the applicable base environmental program manager (319 CEAN) as necessary.
After determining the soil status, the contractor may move the soil as directed by the 319 CEAN through the CO or the appropriate agency (ND State Health Dept, EPA).
Excavation in areas designated as "wet lands" is strictly prohibited. 319 CES/CEAN has the most recent inventory and location of wet lands. Prior to planning work the contractor shall coordinate excavation activities with 319 CES/CEAN to avoid wet land conflicts. Should this type of excavation be required, the requirement will be identified in the RPF and the contractor shall be required to coordinated to ensure the proper wet land excavation permits (Army Corp of Engineers Section 404) through 319 CES/CEAN are obtained prior to work. NOTE Section 404 process may take monthd to gain the proper permissions to proceed with wet land associated work. Any contractor disturbance of a wet prior to coordination and gaining permission shall be subject to penalties under the laws of the EPA, and State of ND. The contractor shall be liable for a penalties and restoration actions imposed by the EPA, State of ND, or Grand Forks AFB through CO determination.
SECTION 01 14 00 Page 5
1.4.1.9 Hazardous Materials and Environmental
The contractor shall control the disposal of fuels, oils, bitumens, calcium chloride, acids, or harmful materials, both on and off government premises and shall comply with applicable federal, state, county, and municipal laws concerning pollution of rivers and streams while per-forming work under this contract. The contractor shall NOT dispose of any waste or residual material on the ground or in any storm sewer or drainage system.
Coordinate with the civil engineer environmental flight for their approval through the CO the discharge of any materiel or diluted material into sanitary or storm water sewer systems. The contractor shall take special measures to prevent chemicals, fuels, oils, greases, bituminous materials, herbicides, and insecticides from entering public waters. Do not allow water used in on-site material processing, concrete curing, foundation and concrete clean-up, and other waste waters to reenter a stream if an increase in the turbidity of the stream could result.
The contractor shall limit emissions of organic solvents into the atmosphere. This rule applies to use, clean-up, and disposal of organic, photo chemically reactive, and non-photochemically reactive solvents and materials containing these solvents.
The contractor shall limit the quantity of volatile organic compounds in architectural coatings. This applies to any coatings applied to stationary structures and their appurtenances, mobile homes, pavements, and curbs.
The contractor shall NOT use paints or coatings containing lead in excess of 0.06 percent by weight of total non-volatile content in accordance with Title 16 of the Code of Federal Regulations, Part 1303. Paints or coatings within reach of children in housing, recreation, and public areas shall have zero lead content. The contractor shall ensure that lead based paint debris is transported, treated, stored, and disposed of as a hazardous waste under the Resource Conservation and Recovery Act (RCRA) (40 CFR 240-280), Department of Transportation (DOT), and Environmental Protection Agency (EPA) regulations.
The contractor shall deliver all items indicated on the drawings or in the specifications containing PCBs and all oil-cooled transformers removed from service for disposal to a storage area on base as directed by the environmental coordinator through the CO. If equipment labels or catalog data does not specify composition, the contractor shall have all electrical equipment cooling liquid tested by a certified laboratory to determine if PCB is present. Drain and properly contain oil from transformers, and flush the system to the required level. Clean, seal, and label all drums.
Include an original of the certified report to the environmental coordinator. New electric equipment shall not contain PCBs, shall be certified to this effect, and shall be stamped or labeled "NO PCB."
The contractor shall comply with all applicable state and local laws, ordinances, and regulations relative to noise control.
The contractor shall instruct all employees and subcontractors to carefully preserve all items having any apparent historical or archaeological interest discovered in the course of any construction activities. The contractor shall leave the archaeological find undisturbed and shall immediately report the find to the CO for reporting to the proper authorities.
When the contractor detects an insect or rodent problem, he/she shall
SECTION 01 14 00 Page 6 notify the appropriate facility manager or construction representative for entomology services.
1.4.1.10 Vehicle Control
The contractor shall NOT park or run vehicles on grass areas for shortcuts, and or convenience. Only equipment required in direct performance of work will be permitted to enter grass areas. The contractor shall repair or replace any damage done to lawns or shrubs caused by construction equipment or related project activities. Contractor personnel shall load all loose debris on trucks leaving the site in a manner that will prevent dropping materials on streets, and conform to local ordinances. Fasten suitable cover such as a tarpaulin over the load before entering surrounding streets. The contractor shall promptly clean up any materials that falls from trucks. The use of cell phones is prohibited on Grand Forks AFB while operating a motorized vehicle. Seat belts are required at all time while driving a vehicle. Base speed limits are strictly enforced, and violation(s) may result in suspended base driving privileges.
1.4.1.11 Equipment Condition
Equipment and vehicles used on base shall be safe and in good operating condition. The contracting officer (CO), CM, Base Safety, or designated representative, reserves the right to inspect any on-base equipment and reject such equipment if he/she considers it unsafe, in poor operating condition, or inappropriate for the work being performed.
1.4.1.12 Government Furnished Equipment
As a rule, the government will NOT furnish equipment/materials (GFE/GFM) except for equipment specified in the solicitation/RFP or elsewhere in these specifications. However, the government reserves the right to provide GFE/GFM for use on any delivery order. In such cases the delivery order shall contain, Schedule D, Schedule of Government Furnished Property listing GFE/GFM that pertain to the project. The contractor shall transport all GRE/GFM, if any, described on each delivery order from the government storage area to the work site indicated on the delivery order.
Once GFE/GFM are released to the contractor for transportation to the project site, the contractor shall assume the risk and responsibility for the loss or damage to GFE/GFM. The contractor shall follow the instructions of the CO or his/her authorized representative regarding the disposition of GFE/GFM not consumed in performance of this contract.
1.4.1.13 Airfield Security Requirements
The contractor shall comply with security regulations imposed by the installation commander and/or the agency responsible for the project location. Projects in restricted or controlled areas will require escorting by base personnel. Rules of entry will be established and directed to the contractor at the preconstruction meeting for associated projects. For specifics, refer to Section 19 for Base Entry Procedures and Airfield Requirements.
1.4.1.13.1 Special Provisions For Working On or Near the Airfield
By basic definition, all areas within the airfield fence are considered on the airfield. This is a restricted area, and entry can be gained by escort only or obtaining a flight line badge. Projects requiring airfield access
SECTION 01 14 00 Page 7 will have special provisions in the individual RFPs, in addition to what is contained in this section.
1.4.1.13.1.1 Coordination of Work
The contractor shall coordinate airfield work (design and construction) through the base operations, Security Forces, CM and the contracting officer (CO). The contractor shall contact Base Operations for daily construction restrictions involving the flight line, taxiway, and runway areas, and shall comply with DOD FAR SUP 252.236-7005, Airfield Safety Precautions, AFI 13-213, Airfield Management and Base Operations, Grand Forks AFBI 24-101.
1.4.1.13.1.2 Closures
All runway or taxiway closures will require the coordination of Base Operations through the CO not less than fourteen (14) calendar days prior to the requested closure, unless otherwise provided for in these specifications. The contractor will make the maximum utilization of time during the requested closure period, and schedule his/her operations in phases if necessary so as to minimize the effect of construction closures on normal base operations. Upon completing the work requiring the closure, the contractor shall immediately notify the CO so normal operations may resume.
1.4.1.13.1.3 Personnel Safety Precautions
Jet aircraft operating on the runways, taxiways, and aprons make the area of construction a zone of high level noise. The contractor shall take the necessary precautions, such as the use of ear plugs or muffs to prevent injury to the auditory systems of all personnel working in the area.
1.4.1.13.1.4 Restrictions
The government does not allow personal use vehicles inside the flight line fence. The contractor's employees and subcontractors shall park their personal vehicles in authorized parking lots outside the flight line fence. Personnel requiring entry to the flight line shall be escorted or possess a line badge. Contractor vehicles required in the performance of the work shall have a company sign (minimum size 6 inches by 18 inches) on both front doors. No contractor vehicles, equipment, or personnel shall be on or crossing any active runway or taxiway, except during construction period closures as outlined herein, or when the escort requests and gains clearance from the control tower. The contractor shall NOT open a trench unless material is on hand and ready for placing in the trench. As soon as practicable after placing material and obtaining approval for the work, the contractor shall backfill and compact trenches as required by the contract.
1.4.1.13.1.5 Cleanliness of Work Area
The contractor shall maintain the cleanliness of taxiway, runway, and apron pavements at all times in order to prevent foreign object damage (FOD).
The contractor shall remove all materials and equipment to a safe distance from the runway as required by base operations.
1.4.1.13.1.6 Emergencies
There may be periods when the government, due to declared aircraft emergencies, will require the contractor to vacate the work site and move
SECTION 01 14 00 Page 8 his/her personnel and equipment a distance of several hundred feet away from the work site. Such removals, when ordered, will come on short notice and require expeditious action.
1.4.1.13.1.7 Airfield Security Restrictions
The government will not grant access to restricted areas for the contractor and/or subcontractors without a proper escort. Five (5) work days prior to commencing work, the contractor shall submit, in writing, a list of all personnel who will perform work in the restricted area.
1.4.1.13.1.8 Restricted Areas
The government will not grant access to restricted areas for the contractor and/or subcontractors without a proper escort. Five (5) work days prior to commencing work, the contractor shall submit, in writing, a list of all personnel who will perform work in the restricted area.
1.4.1.14 Base Entry Procedures
Security requirements for Air Force facilities under control of Grand Forks Air Force Base are specific and rigidly enforced. Levels of security include Restricted and Controlled areas. Differing degrees of security are enforced at each area. Minimum security requirements, common not only to each of these secure areas, are also required for entry onto Grand Forks AFB. Questions of clarification on locations or procedures for controlled/restricted areas contact Security Forces at 701 747-5351. These minimum requirements are outlined below.
Restricted areas are identified in GFAFBI 31-101 and include the Command Post (CP) and Mass Parking Area (MPA). Each area is fenced or conspicuously identified by posted signs.
Controlled areas include more than forty four user-controlled base facilities; only a few of which include all hangars, buildings, and communications facilities located within the base aircraft flight-line controlled area. Each of these areas is identified in GFAFBI 31-101 and each is conspicuously identified by posted signs. Work in this area will require the creation of a free zone so the contractor's personnel can work in the area without security escorts. Refer to the contract documents sheet C-001 SITE PLAN. Contractor personnel may need to be escorted from the perimeter of the controlled area to the free zone and back out.
1.4.1.14.1 Minimum Security Requirements
Visitor Passes: The Commercial Visitor Control Center will issue a SFMIS AF Form 75 (Visitor Pass) to the contractor and his/her employees upon completion of screening process for the duration of the contact. The screening process takes time, and the contractor shall visit the Commercial Visitor Control Center prior to expecting base entry to receive required forms and instruction on the application process, to include estimated time of receiving the visitor pass.
Although contractors will not be issued vehicles passes vehicles are subject to search while on the installation. Employee privately owned vehicles will not be allowed access to restricted/controlled areas without a free zone being established. Company vehicles will be allowed access to restricted/controlled areas. All Contractor vehicles should have markings
SECTION 01 14 00 Page 9 with the company name for quick identification of ownership and notification if they are involved in an incident.
The contractor shall ensure that his/her employees comply with all base traffic regulations and properly conduct themselves while on the base.
1.4.1.15 Personnel Entry Approval
Failure to obtain entry approval will not affect the contract price or time of completion.
1.4.1.16 No Smoking Policy
Smoking is prohibited within and outside of all buildings on installations under the cognizance of NAVFAC Midwest and Grand Forks Air Force Base except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The Base Civil Engineer Dept will identify designated smoking areas.
1.4.2 CONTRACTOR'S TEMPORARY FACILITIES
1.4.2.1 Administrative Field Office
Contractor's administrative field office shall be in good to new condition, and the exterior color must adhere to base standard color standards as stated previously in this section. Locations, if granted, shall be pre-approved by the CM/Base Civil Engineer through the CO. Storage of material/debris under the trailers is prohibited. Power and water will be provided by the government in reasonable quantities, and if they are reasonably available within proximity of the approved location.
Connections to existing government utilities shall be made by the contractor at no expense to the government. Modification of existing points of distribution from existing government infrastructure shall be approved prior to, and performed by the contractor at no expense to the government. Communication lines and service will not be provided by the government. The contractor shall utilize available commercial services in the area as necessary. The duration of such field office presence will be determined by the government upon request of the contractor.
1.4.2.2 Dumpsters
Equip dumpsters with secure covers and they shall be the standard base color dark bronze SW6006. The cover shall be closed at all times, except when being loaded with trash and debris. Locate dumpsters behind the construction fence or out of the public view. Empty site dumpsters when they become 90 of full capacity, or as needed to allow full closure of the covers. All other exterior trash containers shall be dark bronze SW6006 utilized in the construct site area. Locate the trash containers behind the construction fence or out of the public view. Empty trash containers as required to prevent over filling. Large demolition normally requires a large dumpster without lids-these are acceptable but shall not have debris higher than the sides before emptying. Ensure mandated recyclable material (paper, glass, and cardboard, etc) is collected and taken to the recycling center at Bldg 672.
1.4.2.3 Temporary Sanitation Facilities
All temporary sewer and sanitation facilities shall be self-contained units
SECTION 01 14 00 Page 10 with both urinals and stool capabilities. Ventilate the units to control odors and fumes and empty and clean them at least once a week or more often if required by the Contracting Officer. The doors shall be self-closing.
The exterior of the unit will match the base standard (antique linen), unless the facility is behind the construction fence or out of the public view.
1.4.3 CONSTRUCTION SITE MAINTENANCE, SAFETY FENCE, AND CONSTRUCTION FENCE
The construction site must be kept neat, clean, and free of debris. Clean up shall be performed at the end of each work day in conjunction with a complete general clean up at the end of the project. Cut grass (to include weeds) within the construction and storage sites to maintain a maximum height of 4 inch or less. Trim grass around fences and other obstructions where a mower cannot reach. Grass and/or weeds allowed to grow on stockpiled earth is not acceptable at any height. Contractor identification signs are not required, however if the contractor chooses to erect signs at construction sites, they will be in compliance with base requirements and color scheme and approved by the CM/Base Civil Engineer before being erected.
The contractor shall also provide a temporary safety fence (with gates as applicable) and warning signs at the construction site prior to the start of work to protect the public from construction activities. The safety fence will match the base standard (dark brown) (or bright orange where it protects excavated areas), high density polyethylene grid or approved equal, a minimum of 42 inches high, supported and tightly secured to steel posts located on minimum 10 foot centers. The contractor must remove the fence from the work site upon completion of the contract. The fence shall be maintained to avoid sagging and a general state of disrepair while it is deployed on the construction site.
The contractor shall install fences to isolate construction sites as required by the RFP. The construction fence shall be constructed of galvanized chain-link type metal or approved equal, a minimum of 2.13 m (7 feet) high, supported, and tightly secured to steel posts located on minimum 3 m (10 feet) centers. The construction fence shall be covered with dark brown fabric securely attached to the fence with 1"x2"x6' wood batten strips on both sides five feet on center for the purpose of obscuring view of the site.
1.4.4 ERadioactive Materials and Equipment
Contractors bringing radioactive materials or devices containing radioactive sources onto Grand Forks AFB must have prior approval from the Wing Radiation Safety Officer (RSO), at Bioenvironmental Engineering (701) 747-5596. In addition, the contractor must submit the following documentation to the Wing RSO for review 30 days prior to bringing materials on base:
a. The name and type of equipment.
b. The type and size of radiation source.
c. The dates and locations of the equipment's usage.
d. The radiological controls that the Contractor will use while operating the equipment.
e. Copy of the Nuclear Regulatory Commission License Agreement State
SECTION 01 14 00 Page 11
License, along with any amendments, covering the radioactive material to be used.
f. Copy of the user's qualification and radiation safety training.
g. Radiation dosimetry results from the prior calendar year.
h. Statement of expected use (use rate) of radioactive materials or devices for the length of the contract.
i. Statement of storage and security requirements.
j. Copies of the last two leak checks (if applicable).
Under no circumstances will a contractor use an unlicensed radioactive source/device on Grand Forks AFB. Contractors bringing radioactive materials on Air Force installations or conduct operations using radioactive materials on Air Force installations must receive written approval by the installation commander or their appointee. To get this approval, the contractor must send a request to the installation RSO at least 30 calendar days before bringing the materials onto the installation. For contractors these requirements must be included in the statement of work. The contractor should direct any questions regarding his responsibility on this issue to the Wing RSO prior to the starting of any work. Because the Air Force considers contracts involving radioactive materials a hazardous items contract, the provisions of AFI40-201, chapter 3 will also apply.
1.4.5 Working Hours
The standard hours of work on Grand Forks Air Force Base are from 0800 to 1630 hours; Monday through Friday, excluding…