This document is an Amendment to Solicitation No. N4008024R2228 for the Renovation of Building 164 at the Naval Support Facility in Indian Head, Maryland. The key details are:
The purpose of this Amendment is to provide revised PPI Responses with changes highlighted in red and a corrected Price Proposal Form. The Proposal Due Date remains July 19, 2024 by 2PM ET. This is a small business set-aside solicitation for holders of the N4008021D0022/0023/0024/0025/0026/0027/0028/0029 Indefinite Delivery Quantity Contracts. The contract work involves the renovation of Building 164, including structural, architectural, mechanical, electrical, and plumbing systems. Additional details on specific requirements, technical specifications, and drawings are provided in the full solicitation documents available on SAM.gov.
View the file
Other files
Show all 41
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
R
PAGE OF PAGES
1 20
3 2. AMENDMENT/MODIFICATION
EFFECTIVE DATE
16-July-2024
4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY CODE N40080 7. ADMINISTERED BY (If other than item 6) CODE
NAVAL FACILITIES ENGINEERING SYS COMMAND
1314 HARWOOD STREET SE
WASHINGTON DC 20374
See Item 6
8. NAME AND ADDRESS OF CONT RACT OR (No., Street, County, State and Zip Code) X 9A. AMENDMENT OF SOLICITATION NO.
N4008024R2228
X 9B. DATED (SEE ITEM 11)
10-May-2024
10A. MOD. OF CONT RACT /ORDER NO.
10B. DATED (SEE ITEM 13)
CODE FACILIT Y CODE
11. T HIS ITEM ONLY APPLIES TO AMENDMENT S OF SOLICIT AT IONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegramwhich includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegramor letter, provided each telegramor letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. T HIS ITEM APPLIES ONLY TO MODIFICAT IONS OF CONT RACT S/ORDERS.
IT MODIFIES T HE CONT RACT /ORDER NO. AS DESCRIBED IN ITEM 14.
A. T HIS CHANGE ORDER IS ISSUED PURSUANT T O: (Specify authority) T HE CHANGES SET FORT H IN ITEM 14 ARE MADE IN T HE
CONT RACT ORDER NO. IN ITEM 10A.
B. T HE ABOVE NUMBERED CONT RACT /ORDER IS MODIFIED TO REFLECT T HE ADMINIST RAT IVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORT H IN ITEM 14, PURSUANT TO T HE AUT HORIT Y OF FAR 43.103(B).
C. T HIS SUPPLEMENT AL AGREEMENT IS ENT ERED INT O PURSUANT TO AUT HORIT Y OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPT ION OF AMENDMENT /MODIFICAT ION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
N40080-24-R-2228 Renovate Building 164, Naval Support Facility, Indian Head, Maryland.
The purpose for this Amendment is to:
1. Provide revised PPI Responses (changes in red)
2. Provide corrected Price Proposal Form 7.16.2024 (changes in red)
Proposal Due Date remains 19 July 2024 by 2PM (ET) CONTINUED ON PAGE 2
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONT RACT ING OFFICER (Type or print)
TEL: EMAIL:
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
15C. DATE SIGNED 16B. UNIT ED ST AT ES OF AMERICA
BY
(Signature of Contracting Officer)
16C. DATE SIGNED
EXCEPT ION TO SF 30
APPROVED BY OIRM 11-84
30-105-04 ST ANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
SOLICITATION NO.:
N4008024R2228 PROJECT TITLE/LOCATION: Indian Head, MD Renovate Building 164
PRE-PROPOSAL INQUIRY FORM (PPI FORM)
Question No.
Date Received
REFERENCE QUESTION GOVERNMENT RESPONSE
Posted on
Amend No.
Page Section Para.
1 6/3/2024 787 05 12 00
The subject specification section requires fabrication and erection of the structural steel by an AISC certified fabricator and erector. Such certifications are typically only held by large national fabricators and erectors constructing projects significantly larger than this project. The AISC certification in many cases cost prohibitive for small business fabricators and erectors to obtain and maintain. The AISC certification requirement excludes many highly qualified fabricators and erectors who routinely perform exemplary work on DOD projects. These are typically small businesses, minority businesses and service-disabled businesses that cannot compete due to the AISC requirement. Please confirm that the AISC certification requirement for the structural steel fabricator and erector can be waived.
The Government acknowledges that there are many qualified structural steel fabricators and erectors that are not certified by AISC. However, due to the complexity and historic nature of the work, the government is requiring the use of AISC certified contractors. In addition, it should be noted that there are aproximately 46 AISC certified fabricators in Maryland and Virginia, many of which are small businesses.
2 5/14/2024 162 01 31 23
Please clarify full-time supervisory personnel requirements with regards to the Superintendent, QC Manager, and Site Safety and Health Officer. How many individuals are required to fulfill these roles? Can multiple roles be performed by one person; or are three separate, full-time individuals required?
Due to the size and complexity of the project, it is required that each personnel be full-time, separate individuals, responsible for Superintendent, QC Manager, and Site Safety and Health Officer roles.
3 12-Jun
42000 2.2.2.4
Specification section 042000, paragraph 2.2.2.4 Salvaged brick states that in place of new brick, we are supposed to figure salvaged brick from foundries or industrial bldgs. In my 50 years’ experience in the masonry industry, I have never seen this before and have no idea how to find 35,000 used brick to match this bldg. In order to bid this job, we intend to use newly manufactured brick on all of the “new work,” including both interior and exterior brickwork. For the brick needed to infill areas in the existing walls, we are going to figure “set only” using brick from the demolition of the existing brick retaining wall; supplied by others, after it has been cleaned of mortar, washed and ready to use. Please confirm
Use of salvaged bricks and and other masonry units is required by Maryland SHPO for this project as detailed in the Contract documents. Contractor must use salvaged brick in place of new bricks or masonry units as required by the Contract documents. Bricks or masonry units may be salvaged from foundries or industrial buildings and/or reclaimed from on-site, project demolition work.
4 2-Jan
01 11 00
The documents state,"Prior to commencement of work, the contractor must engage a suitably licensed consulting firm to conduct a complete hazardous materials survey within limits of disturbance". Please confirm that this is the case.
Confirmed. 0004
July 2011
PROJECT TITLE/LOCATION: Indian Head, MD Renovate Building 164
PRE-PROPOSAL INQUIRY FORM (PPI FORM)
Question No.
Date Received
REFERENCE QUESTION GOVERNMENT RESPONSE
Posted on
Amend No.
Please confirm that the hazardous materials remediation pricing is to be provided after the consulting firm report has been submitted and reviewed since a hazardous materials report is not available at the time of bidding.
Contractor shall base their bid on the hazardous materials identified in the attached hazardous materials survey. Abatement / remediation costs for hazardous materials shall be determined based upon the proximity of identified hazardous substances and based on similar materials being potential hazardous substances. Any Contract changes for additional costs due to hazardous material abatement / remediation will be evaluated and processed on a case-by-case basis as outlined in the Contract documents.
6 Page 1 Summary of Work. 01 11
The documents make reference to replicate the administrative spaces current layout at Building 1480 (NSWC Dahlgren). Is this concept already built into the provided contract documents? If this is not the case, please provide us the Building 1480 layout for reference.
Contractor shall construct administrative spaces as set forth in the Contract documents.
Reference to Building 1480 (NSWC Dahlgren) shall be ignored by the Contractor.
General Requirement s
Can the Quality Control Manager & the Site Safety Health Officer be dual hatted?
No, Due to the size and complexity of the project, it is required that each personnel be full-time, separate individuals, responsible for Superintendent, QC Manager, and Site Safety and Health Officer roles.0004
8 CS-101, NOTE 9 Site plan CS-101 keynote 9 is missing on the site plan. Keynote 9 refers to concrete pavement. 0004
CS-101,
NOTES 2
AND 7, C-501
Site plan CS-101 keynotes 2 and 7 refer to incorrect detail on C-501. Please correct.
The keynotes 2 and 7, should refer to detail C5/C-501. 0004
6/13/2024 3 Solicitation 5
Notes " The contractor will be responsible for protection B154/B164 parking lot with temp. construction fence amd will not access the parking lot without written consent from the government. Under ii. B164 drawing 1. "No mention of B154/B164 parking lot". The protection reference is also noted under 01 11 00 1.2.1 par. 2.
There is an on-going, independent project to complete the construction of a new, asphalt parking lot in the location of the existing graveled parking lot between Buildings 154 and
164. This parking lot construction project is currently expected to be substantially complete prior to Building 164 being renovated. See annotated aerial photograph showing the approximate location of this new, asphalt parking lot.
11 6/13/2024 147 01 30 01.00
1.4.3 par. 2
States “The Audio Visual Package must be designed and incorporated into the FF&E package by the Contractor's ID and A/V Certified Technology Specialist-Design (CTS-D), as required”
- No audio visual package is noted in the drawings, please confirm if such will be required.
The A/V package is required and furnished by the Contractor per NSWC requirements. 0004
12 6/13/2024 499 01 58 00 1.3 par. 1
States " construct sign in accordance with project sign detail which can be download at www… There are multiple arrangement of those signs. The exterior signage for the project is noted on AS001. Please confirm besides the exterior signage required on the drawing. An exterior signage per detail on pg. 501, 502 and 503 is to be accounted and provided.
Specification Section 01 58 00 refers to the Construction Project Identification Sign that requires Plate 1USN, plates 3 and 4 Project Sign Details.
Drawing AS001 refers to NSWC IH permanet Building Signage additionally required for the project.
13 6/13/2024 541 01 78 24 Forms
The eOMSI forms are provided but under "In Scope" column those are noted no.
- Please confirm no items are required under the eOMSI.
- If that is not the case, for bidding purposes and administrative work please provide updated eOMSI with required items.
A sample of eOMSI is provided in the specification, but NAVFAC can provide an Excel file to the KTR, post-award.
PROJECT TITLE/LOCATION: Indian Head, MD Renovate Building 164
PRE-PROPOSAL INQUIRY FORM (PPI FORM)
Question No.
Date Received
REFERENCE QUESTION GOVERNMENT RESPONSE
Posted on
Amend No.
14 6/13/2024 553 01 78 30
1.1 SD-11 &
1.2 par. 1
Please confirm a final GIS (Geographic information System) drawing will be required, since this will required a site visit to set original and a final to note any field changes. Or clarify if the CADDs and original data/files (Appendix Items) will be provided just to account for one final GIS survey.
NAVFAC CM can provide GIS data and CADD files, post-award, upon request. 0004
15 6/13/2024 579 01 91 00.15 3.3.1 par. 2
It notes "Post construction endurance test" for cooling season and heating season. Depending on the completion test this might fall under just one or clarify whether both seasons are to be accounted separately.
Endurance test shall be performed for each season separately. 0004
17 6/13/2024 722 03 30 00
3.13.2.3 par
States "Test two cylinders at 7 days, two cylinders at 28 days, and hold two cylinders in reserve … For the entire project, take no less that five sets of samples and perform strength tests" Please clarify of after (5) sets if that will suffice or satisfy the requirement for the rest of the project.
As stated in paragraph 3.13.2.3, "Take samples for strength tests of each mix design of concrete placed each day not less than once a day, nor less than once for each 100 cubic yards of concrete for the first 500 cubic yards, then every 500 cubic yards thereafter, nor less than once for each 5000 square feet of surface area for slabs or walls." However, at least 5 sets of six cylinders must be tested for each mix design used in the project. Note, the specification is being revised to allow 4 inch by 8" cylinders. If 4x8 cylinders are used each strength test requires 3 samples, 9 total cylinders for each set of tests.
18 6/13/2024 763 04 20 00 1.3.1.2 Mock up panel is noted as L-shape panel of minimum size 8 feet long by 6 feet high. For bidding purpose, please confirm one will be required only for the retaining wall.
This mock-up is for the building's wall types to illustrate the standard workmanship of the masonry representsed. It also will include the retaining wall.
19 6/13/2024 791 05 12 00 1.3 par. 1
States "Submit AISC structural steel fabricator quality certification". Due to the project site logistic and the potential for out of state contractors with the AISC Structural steel fabricator certification. Please advise if steel fabricator/contractor without the BU certification will be considered for this project since the work entails renovation and not new building.
The Government acknowledges that there are many qualified structural steel fabricators and erectors that are not certified by AISC. However, due to the complexity and historic nature of the work, the government is requiring the use of AISC certified contractors.
20 6/13/2024 819 05 40 00
1.2 SD-02 &
SD-05 &
1.6.2 (c.)
Per 1.4 "Load Bearing Cold-formed metal framing" and 1.6.2 "Sign and seal fabrication drawings by a registered professional engineer". Please confirm the section only pertain to cold-form metals use for structural purposes and not partition.
This section will represent load bearing cold formed metal, including partitions at the second floor where mezzanie decks are supported as well as exterior wall framing.
21 6/13/2024 885 06 41 16 1.5.2 par. 1
States “Prior to final approval of shop drawings, provide a full-size mock-up of a typical floor cabinet wall cabinet , including all components and hardware necessary to illustrate a completed unit with a minimum of one door and one drawer assembly.”
- Please confirm mockup will be require.
- If mock-up is required please confirm such it to be accounted
- Lastly, for bidding purposes clarify if a base cabinet and upper cabinet will suffice for the mock-up without countertop.
Provide the complete mock up per Specification Section 06 41 16, 1.5.2. 0004
PROJECT TITLE/LOCATION: Indian Head, MD Renovate Building 164
PRE-PROPOSAL INQUIRY FORM (PPI FORM)
Question No.
Date Received
REFERENCE QUESTION GOVERNMENT RESPONSE
Posted on
Amend No.
22 6/13/2024 908 07 05 23 1.3.1 par.1
States "The air barrier surface includes the top, bottom and sides of the envelope." The project is a renovation with existing historical members /items (i.e. repairing some of the existing windows or reusing brick that have been weathered with time. Please advise if all work related with the air barrier will be required for this project which may mean more work or fluid applied membrane to achieve "1.3.4 Pressure test."
Also noted under 07 27 10 subsection 1.3.7. If modeling was completed per design drawings, please confirm and or provide.
Confirmed. All work related to air-barrier is required.
We can provide any additional modeling completed at design, post-award.
23 6/13/2024 929 07 14 00 3.4.3 par.1 Per the drawing, the roof on this project is not a "flat roof" and have different roofing section and pitch. Per 3.4.3 and for bidding purposes, please advise if a flood test will be required
Low sloped roofing is not applicable. Flood testing for low sloped roofs are not needed.
Refer Specification Section 07 41 13 for inspection and leakage testing for the metal roofs.
24 6/13/2024 958 07 27 26 1.4.3 par.1
States "Provide a mock-up of the fluid applied membrane air barrier…Apply an area of not leas that 54 square feet."
- Please confirm such will be required.
- If so and for bidding purposes, please clarify if such can be applied on the “Masonry mock-up”.
Confirmed. Provide fluid applied air barrier for Masonry mock-up. 0004
25 6/13/2024 999 07 41 63 1.6.3 b.
States " Engineering services of an authorized engineer;
currently licensed in the geographical area where construction will take place, having a minimum of four years of experience as an engineer knowledgeable in roof wind design analysis, protocols and procedures for the MBMA RSDM; ASCE 7-16, UL 580 and FM 4474 FM wind design guide for metal roof systems." Please advise if calculations are to be included by PE within the geographical are of the project"
Confirmed. Provide a PE within the geographical area. 0004
26 6/13/2024 1080 07 81 00 1.2.1
States “Protect all structural steel, undersides of steel floors (if required) and steel roof decks (if required) with spray-applied fireproofing to a fire resistance hour-rating as indicated below, unless otherwise indicated.” During the site visit, it was noted that all structural members did not have any fireproofing. Additionally, the weathering of those member besides abatement might require abrasion such as sand blasting to clean members for new fireproofing to adhere to those members.
- Please confirm if all existing structural member are to be fireproof.
- Please advise if new structural members (include those under 05 40 00) are to be fireproof.
Per Specification Section 05 12 00, paragraph 2.6.2.1, structural steel must be cleaned to meet the requirements of SSPC SP 6/NACE No. 3, Commercial Blast Cleaning.
Per Specification Section 07 81 00 Section 1.2.2, there is a 0-hour fire resistsance rating for primary and secondary structural members; this section also indicates to provide 1 hour rating listed per UL 263 for structural members supporting occupancy separation fire barriers, vertically rated openings at stairwells and shafts as indicated.
Refer to Drawings LS001 and A-004 for additional information.
PROJECT TITLE/LOCATION: Indian Head, MD Renovate Building 164
PRE-PROPOSAL INQUIRY FORM (PPI FORM)
Question No.
Date Received
REFERENCE QUESTION GOVERNMENT RESPONSE
Posted on
Amend No.
27 6/13/2024 1087 07 81 00 3.6
States " The applied fireproofing shall be tested by an approved independent testing laboratory to be selected by the A/E and paid for by the Contractor." For bidding purposes, please advise allowance to carry for testing since such will be selected by A/E and contractor bidding price might reflect a different amount at a later date by A/E
Contractor can provide pricing for certified lab testing, with stated assumptions (& exclusions).
28 6/13/2024 1099 07 92 00 1.7.3
States "Provide a mock-up of each type of sealant using materials, colors and techniques approved for the use on the project." Please confirm a mock up is to be provided for each type of sealant. Please clarify how many linear feet of each project will be required. Lastly, please advise if those can be applied on the Masonry mock up or substrate for mock-up is to be accounted - refer to 3.1 since this will affect testing.
Confirmed. Mock-up each sealant type. Linear feet of sealant is to be determined by contractor. It can be applied to the masonry mock-up given that the sealant adhesion, staining and compalilbility need to be tested.
29 6/13/2024 1105 07 92 00 3.1
States "Adhesion failures at any point require reverting back to 10 tests per 1000 LF as testing proceeds. Noncompliance of specified requirements constitutes a failure and requires reverting back to 10 test per 1000 LF as testing proceeds."
Please confirm section will applied and please clarify acceptable substrate to be use for testing.
Confirmed. This section is to be applied. The substrate for testing should be the part of the mock-up or construction the sealant is to be applied.
30 6/13/2024 1250 09 29 00 3.9 Please clarify if there are any shaft walls for this project since no wall partitions note those.
Refer to wall type 1Q on Drawing A-611. 0004
31 6/13/2024 1262 09 51 00 1.8
Please confirm spare tiles, from the same lot as those installed, of each color at the rate of 5 tiles for each 1000 tiles installed, with a minimum of 5 are to be provided or round to a full box for the ceiling tile. Including specialty tile ACT-2
Confirmed, provide spare tiles for all ceiling tile types as noted in Specification Section 09 51 00.
32 6/13/2024 1272 09 65 00 1.8
Please confirm extra flooring material of each color and pattern at the rate of 5 square feet for each 1000 square feet of sheet flooring installed and extra wall base material composed of 20 linear feet of each type, color and pattern are to be provided.
Confirmed, provide extra material for wall base in each color and pattern as noted in Specification Section 09 65 00.
33 6/13/2024 1273 09 65 00 3.2
States “Provide a smooth, true, level plane for surface preparation of the flooring, except where indicated as sloped.
Floor to be flat to within 3/16 inch in 10 feet. Prepare subfloor in accordance with flooring manufacturers recommended.”
During the site visit, it was noted spots were the concrete slab on grade has been saw cut and removed, and a floor unevenness of more than ½” from over time settling.
Additionally, the underpinning work will disturbed furthermore the existing concrete slab. The 3/16 might not be enough for a true level surface but please clarify if contractor is to provide a smooth surface for application only or true level plane.
Per the structural demolition drawings, the existing slab on grade is to be removed and a new slab installed for the entirety of the building.
Specification Section 09 65 00 only applies to resilient accessories as there is no resilient flooring in the project. The section will be updated accordingly.
PROJECT TITLE/LOCATION: Indian Head, MD Renovate Building 164
PRE-PROPOSAL INQUIRY FORM (PPI FORM)
Question No.
Date Received
REFERENCE QUESTION GOVERNMENT RESPONSE
Posted on
Amend No.
34 6/13/2024 1285 09 68 00 3.7.1 Please confirm "extra material from same dye lot for future maintenance... minimum of 5 percent of total square yards of each carpet type, pattern, and color" is to be provided.
Confirmed, provide extra material from same dye lot for each carpet type/pattern/color as noted in Specification Section 09 68 00.
35 6/13/2024 1310 09 90 00 1.12.3.1 Please confirm all sprinkler piping is to be prime and paint as noted. Additionally, clarify if pre-painted pipe will be allow as well to fulfill the requirement.
Per Specification Section 21 13 13, 3.6, color code mark exposed piping red. Factory painted piping is permitted.
36 6/13/2024 1329 10 14 00 1.2 Please confirm one sample will suffice for exterior signage Or clarify how many are to be provided.
Provide a sample for each type of sign. Refer to building signage elevation C3/A-201 and Drawing AS001.
37 6/13/2024 1329 10 14 00 1.7
Please confirm the following are to be provided, since AS001 only notes one: "3 extra interchangeable message panels and extra stock of the following: 1 message bars of each color and size for sign types 1. 1 pressure-sensitive letters in each color and size for sign type 1. 1 changeable message strips for sign type 1".
Confirmed, provide extra stock as noted in Specification Section 10 14 00. 0004
38 6/13/2024 1336 10 14 00 1.3
Please confirm the following are to provided for the interior signage, since there are (7) types of signage per I-503: "extra frames and extra stock of the following: 5 percent of each type of blank plates of each color and size for all sign types and changeable message strips. Provide paper inserts and one copy of the software for user produced signs and inserts after project completion"
Confirmed, provide extra stock as noted in Specification Section 10 14 00. 0004
39 6/13/2024 1368 14 24 23 1.4.1
States " 1.4.1 Periodic Elevator Certification Inspection and Testing Provide elevator mechanic to support NAVFAC QEI Certified Elevator Inspector in the periodic six-month and the annual Category 1 elevator certification inspection and testing. Perform Category 1 inspection and testing no greater than 30 days prior to the end of the warranty period. Perform all elevator certification testing in the presence of QEI Certified Elevator Inspector" Please clarify and confirm such time is to be allocated and accounted for from the installation elevator on site or after substantial completion. Additionally, please advise if (labor, materials and equipment) is to be included in the certification and testing certification (i.e. State of Maryland requirements).
Confirmed. Such time is to be accounted for on-site as well as substantial completion.
Yes, labor, materials and equipment to be included for testing and certification.
40 6/13/2024 1393 21 13 13 3.1
Please clarify if a full time Fire Protection QC specialist is required for the project. Or please confirm the preliminary and final test can be certified and witness by the engineer or record or PE sprinkler designer.
Yes, a QFPE is required for project and must witness preliminary & final tests. 0004
41 6/13/2024 1440 22 00 00 3.8.1
It notes "the contractor has the option to perform a peppermint test in lieu of the smoke test". Please advise if "the final test shall include a smoke test" as noted for bidding purposes and in field coordination.
Drainage and vent systems final test must include a smoke test. 0004
PROJECT TITLE/LOCATION: Indian Head, MD Renovate Building 164
PRE-PROPOSAL INQUIRY FORM (PPI FORM)
Question No.
Date Received
REFERENCE QUESTION GOVERNMENT RESPONSE
Posted on
Amend No.
42 6/13/2024 1456 22 14 29 3.2.1
Notes to "Use a Fast Fourier Transform (FFT) analyzer to measure vibration levels." Please clarify if such test will be required for the sump pump which will required third party agency or clarify whether manufacturer data will suffice.
The contractor must comply with this requirement. Test is required. 0004
43 6/13/2024 26 23 05 15 2.1 & 3.9
States "Provide heat trace systems for pipes, valves, and fittings that are in accordance with IEEE 515 and the UL listed". Drawing EP705, panel 480/277 "HP-M2" notes a 20A Heat trace control panel. Please clarify the intent of the heat trace and location to confirm power requirements and wiring since 16 gage is noted in the specifications.
All exposed HVAC piping outside shall be heat traced. Pipe is above roof for AHU and above grade for chiller.
44 6/13/2024 66, 69 23 05 93
1.2 & 1.5.3.1 par. 8 & 3.3.3
States "DALT Field Work: Within 48 hours of COTR's selection, complete DALT field work on selected." There are no flags noted on the drawings provided. For bidding purposes please confirm only 20% will be tested or please specify how many and what sections will be required to be tested.
Yes, 20% shall be tested. 0004
45 6/13/2024 64 23 05 93
1.5.2.3 h (2) & j
For bidding purposes, please confirm additional visits are to be accounted: (1) season 1 & 2, (1) an 8 hr. DALT field visit, (3) near the end of TAB efforts
Yes, visits shall be accounted for per specification requirements. 0004
46 6/13/2024 131 23 07 00 3.4.3.3 Refer to the section and sheet drawing M-501. Please clarify insulation of pump only pertains to hydronic/HVAC system.
Additionally, confirm if the in line pump are to be insulated.
Yes, for chilled water pumps only. 0004
47 6/13/2024 299 23 25 00 2.7.3 Please confirm only (1) test Yes, one test per test type. 0004
48 6/13/2024 325 23 30 00 2.10.1 States "test and rate fans according to AMCA 210" Please confirm manufacturer reports will suffice.
Yes, manufacturer reports will suffice. 0004
49 6/13/2024 352 23 31 13
2.3.1 & 3.3.1.11
Section 2.3.1 Table show the minimum sheet metal gage/thickness. Section 3.3.1.11 Table show the minimum sheet metal gage/thickness for plenum construction. Please confirm thicker gage will only be required in plenum areas.
Specification Section 23 31 13 has been deleted. Reference 23 30 00 Section 2.9.1. 0004
50 6/13/2024 372 23 52 00 1.5
States" Submit spare parts data for each different item of material and equipment specified…" The eOMSI does not specific any equipment. Please clarify what spare parts are expected or need to be provided.
Data that shall be provided is a list of the parts recommended by the manufacturer to be replaced after 1 and 3 years of service.
51 6/13/2024 423 23 64 10 3.2
States "The Chiller Performance Test schedule must also allow the witnessing of the test by a Government Representative."
Since the chiller are tested at remoted locations depending on the manufacturer. Please advise if the witnessing can be waived and only manufacture factory test report provided. If not, please clarify for bidding purposes how many government representatives will be part of the factory testing and if accommodations are to be included.
Witness testing is required. NAVFAC to provide 2 (CxA, Acceptance) personnel and there is no acommodation requirement.
PROJECT TITLE/LOCATION: Indian Head, MD Renovate Building 164
PRE-PROPOSAL INQUIRY FORM (PPI FORM)
Question No.
Date Received
REFERENCE QUESTION GOVERNMENT RESPONSE
Posted on
Amend No.
52 6/13/2024 464 23 73 13 1.5 States "Ensure warranty is valid for at least 2 years from the date of project closeout". Please confirm 2 years to be provided only on Central station Air handling units
Spec was removed. Refer to 23 30 00 Section 2.11 for AHU's. Manufacturer standard warranty or a minimum of 1 year, whichever is greater, is required.
53 6/13/2024 489 23 81 00 3.7.1
States" Submit spare parts data for each equipment specified…." The eOMSI does not specific any equipment.
Please clarify what spare parts are expected or need to be provided.
Provide assumptions (and exclusions, if any) for these per for all the equipment shown on design design documents.
54 6/13/2024 501 25 05 11.21 1.7.1
States "1.7.1 Qualifications Provide a Cybersecurity Subject Matter Expert as the key person to implement and manage the cybersecurity related control systems of the project. This position requires that the individual currently meets IAM/IAT level II certification in accordance with DoDI 8570 Information Workforce Improvement Program. Individuals for this position should have experience securing DoD Systems and with Risk Management Framework. Control System experience is highly desirable. Submit the Cybersecurity. Please advise if a full time cybersecurity subject matter expert is required or on as need basis.
Confirmed. The full-time cybersecurity expert is required. 0004
55 6/13/2024 515 25 05 11.21 3.12.1
Refer to questions 66. Please advise if the 40 hours of technical support for cybersecurity testing of control systems can be perform by Cybersecurity Matter Expert or if a third party will be required.
Confirmed. Both are required. 0004
56 6/13/2024 515 to 610 25 05 11.21 At A
Attach. A
The table provided for the "Designer Control Correlation Identifiers" under classification, there are items noted as "Applicable, N/A, Impractical, Vendor to provide interconnection information, If system has capability and unless required by owner"
- Please advise if the table can be revised to remove items not pertaining to the project per the classification notes as NA or impractical. For bidding purposes this clarification will help to better determined the time associated with designer implementation. .
- Please clarify if items noted as “unless required by owner” will be revised and removed or clarify of those will be require for bidding purposes.
For bidding purposes, assume that this is a requirement. 0004
57 6/13/2024 631 25 05 11.23 3.12.1
Please advise if the 40 hours of technical support for cybersecurity testing of control systems can be perform by Cybersecurity Matter Expert or if a third party will be required.
Confirmed. Both are required. 0004
PROJECT TITLE/LOCATION: Indian Head, MD Renovate Building 164
PRE-PROPOSAL INQUIRY FORM (PPI FORM)
Question No.
Date Received
REFERENCE QUESTION GOVERNMENT RESPONSE
Posted on
Amend No.
58 6/13/2024 701 to 795 25 05 11.26 Att A
Attach. A
The table provided for the "Designer Control Correlation Identifiers" under classification, there are items noted as "Applicable, N/A, Impractical, If capability exist and unless required by system owner"
- Please advise if the table can be revised to remove items not pertaining to the project per the classification notes as NA or impractical. For bidding purposes this clarification will help to better determined the time associated with designer implementation. .
- Please clarify if items noted as “unless required by system owner” will be revised and removed or clarify of those will be require for bidding purposes.
For bidding purposes, assume that this is a requirement. 0004
59 6/13/2024 515, 633 &
25 11 21, 25 11 23 & 25 11 26
Please advise if a list of cybersecurity contractors vetted to performed work in the base or preferred vendor list can be provided.
The requested list will not be provided. Contractor is responsible for identifying and hiring a qualified cybersecurity contractor.
60 6/13/2024 813 25 10 10 2.3
This section details: hardware, hard drives, laptop, external drives, monitor keyboards, etc. to be provided. Please confirm all items noted on pg. 814, 815, 816 and 817 are to be provided.
Confirmed. 0004
61 6/13/2024 940 26 29 23 3.4.1.2 Please confirm 2 hours training session for (4) operation personnel will suffice under ASD.
Contractor must provide training per specification requirements. 0004
62 6/13/2024 1007 28 31 79 1.2.1A Please clarify if paragraph is meant for Bldg. 164 or please confirm Bldg. 154 is also to be included in the fire alarm design and pricing.
Intended to only be for B164, not including B154. 0004
63 6/13/2024 1034 28 31 76 2.20.1.4
States "…Do not mount antennas to any portion of the building roofing system. Sheet FA110 has note 3 indicating to be installed at the top of the exterior wall in conduit, which makes a reference to B5 on FA-502 for a roof detail. Please confirm antenna is not to be roof mounted and detail will be revise.
Drawing FA-502 Detail B4 is not a roof mounted detail. The detail indicates the antenna must be mounted above the roof level for unobstructed transmission. The detail indicates wall-mounting with clamps and supports along the wall. Roof/parapet shown for reference with respect to antenna.
64 6/13/2024 1043 28 31 76 3.10.3 Under spare parts b and c, additional items are noted as etc.
For bidding purpose, qualifications and quantifications. Please clarify what items are to be provided.
Specification Section 28 31 76 Section 3.10.3(b) and (c ) identify the items needed and quantities. The section indicates two of each type of notification appliances including speakers, strobes, and speaker/strobes. Similarly, the section indicates two of each type of initiating device to include manual pull stations, smoke detectors, CO detector, monitor module, control module, duct detector + housing.
65 6/13/2024 1047 31 11 00 3.3.1 & 3.3.2
3.3.1 "Tree removal" & 3.3.2 "grubbing" contain general notes for removal and disposal. Civil drawings fail to clearly show and identify all the existing flora, down trees on the north side and failing structures to be removed. Please confirm that those are not shown on the drawings are will need to be qualify and quantify by the contractor.
The contractor will be responsible for tree removal, clearing and grubbing to perform their work within the LOD.
66 6/13/2024 1052 31 23 00 1.6 Please clarify if any existing soils can be re-use. If not, please confirm all off site soil is to be tested as noted.
The on-site soil may be reused as Structural Fill provided that it does not contain organic matter or foreign debris, are not highly plastic, are not environmentally impacted, and conform to the criteria outlined in the construction documents.
Both on-site and off-site soil material must be tested to verify compliance with the construction documents.
PROJECT TITLE/LOCATION: Indian Head, MD Renovate Building 164
PRE-PROPOSAL INQUIRY FORM (PPI FORM)
Question No.
Date Received
REFERENCE QUESTION GOVERNMENT RESPONSE
Posted on
Amend No.
67 6/13/2024 1053 31 23 00 1.7.1 Please advise if a "drawings and calculations, certified by a registered professional engineered" will be required for the new associated retaining work .
Yes, the retaining wall final design must be certified by a professional engineer. 0004
68 6/13/2024 1193 33 11 00 3.3.1.7 Please confirm "tracer wire" is to be tested for continuity, since it might require a third party vendor.
Yes, the tracer wire must be tested for continuity. 0004
69 6/13/2024 1209 33 30 00 3.3.1.3 Please advise if CO if to witness the dye test. If so, please advise if 48 hours advance notice will suffice.
Yes, please advise Contracting Officer / CORT (CM) of dye test; 48 hours advance notice will suffice.
70 6/13/2024 1235 33 71 01 2.2.1
This spec. section is provided for overhead work and even noting wood poles. Sheet EP504 show electrical duct banks.
Sheet EP601 shows connection to existing utility poles. Please advise if overhead specification pertains to the project.
Yes, the OHE pertains to this project. 0004
71 6/13/2024 1290 33 82 00 1.6.1.1
States " Provide outside plant design in accordance with RUS Bukk 1751F-643 for underground duct system design and for direct buried system design." Additionally, refer to TS100 note
1. Please confirm the intention is to run the data cable underground conduit only and not a duct bank.
Refer to detail C1 on Drawing T-506. Conduit should be in ductbank where indicated underground on Drawing TS100.
72 6/13/2024 LS001
Refer to the "Code compliance Site Plan" A Knox box is noted at the double door new entrance. There are no specification on such. Please advise if NAVFAC will furnish and install. Or clarify, if government to furnish and contractor to install. If contractor is to install, please provide cut sheet.
Key box is to be contractor furnished and contractor installed.
The location is shown on A-110.
73 6/13/2024 C-001
Survey note 6 states "Rice Associates has made a seep of the project site, however due to the abundance of conflicting records, and depiction of multiple parallel and crossing lines, the electromagnetic sweep was minimally successful" .
General note 3 states "The contractor is responsible for determining the exact location and depth of all existing utilities..." There is work outside (electrical/duct bank/sprinkler/french drain) and interior (underpinning and structural) that will required additional "test pits" to avoid any UXO from excavation. For bidding purposes please advise if an allowance for additional (5) TP can be included for all bidders -refer to sheet TS100 as well for work not surveyed.
Confirmed. Use this allowance due to the nature of this site and potential UXO in the area.
74 6/13/2024 TS100
Please provide as built civil drawing (site drawings) for B154 to evaluate surveying, new tele data conduit work and fencing.
Refer to the Civil site drawings. All data for surveying, comm, utility tie-ins, etc. should be verified by the contractor.
75 6/13/2024 TS100
Please advise if revised civil sheet drawings will be included for work associated on sheet TS100 in terms of limits of disturbance.
No additional civil drawings will be provided based off scope identified on Drawing TS100. 0004
PROJECT TITLE/LOCATION: Indian Head, MD Renovate Building 164
PRE-PROPOSAL INQUIRY FORM (PPI FORM)
Question No.
Date Received
REFERENCE QUESTION GOVERNMENT RESPONSE
Posted on
Amend No.
76 6/13/2024 SD205
Note 6 states "remove full height of pit wall, provide temporary support & shoring for existing columns. Note 9 on sheet S-110 also mention temporary supports. Please advise if another site visit can be schedule for shoring purposes and to bring underpinning contractors since no pictures were allow on site.
A second site visit was scheduled and completed on 27 June 2024 in order to allow additional contractor review of the existing site conditions. No additional site visits will be scheduled.
77 6/13/2024 A-003
Refer to sheet A-003 note 2 states "Concrete floor is an air barrier at grade and as such all concrete floor penetrations are to be sealed. Additionally, Refer additionally to RFI 41.
- For bidding purposes, please clarify or confirm if the concrete is to be sealed with the fluid membrane as well.
- If the floor is considered part of the air barrier, then all flooring will most likely will required to be self-leveled on top of the fluid applied membrane for flooring installation. The floor elevation might increase from ½” to ¾” depending on the location. Please confirm the intention is to have sealed floor and level floor. Confirm that design documents have been coordinated in this effort
Refer to the structural drawings and specifications for the new concrete slabs with liquid sealers. The slab elevation can be set to incorporate floor sealers and finishes given that it is new.
78 6/13/2024 AD-001
Refer to the "Historic Features" items 11, 12, 13, 14 and 15.
Those items are noted are restore and paint. Please confirm that is the intention, since those will required to be abated and abatement methods might damage to an extend those in order to be able to restore and paint.
Confirmed. Historic features are to be abated, and any existing damage or damage due to the abatement process shall be corrected during restoration, painted and reinstalled.
79 6/13/2024 A-110
Note 5 states "Reinstall restored existing oversized doors. But drawing also note door 113 (storefront) on the same location.
Additionally, refer to sheet A-423 detail 2, sheet A-313 note 32 and section details on A-533.
- Please clarify if doors are to be removed and disposed.
- Or confirm if doors are to be removed, restore and reinstall.
- If so, please provide further section details on the storefront in relation to existing doors for reinstallation (i.e. how are the doors and where to set the doors on the exterior masonry"
The existing overhead doors are to be removed, restored and reinstalled. They will then be bolted in a fixed open position. The storefront wall and operational storefront door is to be installed within the frame of the restored oversized door. Further details can be developed. These doors have been reviewed and approved by Maryland SHPO and will remain.
80 6/13/2024 A-110 Note 12 states "reinstall restored existing sliding doors". Also noted, sheet AD301 note 14. Those were not noted during the site visit. Please confirm or advise if note will be revised.
Note 12 is to remain. These doors have been reviewed and approved by Maryland SHPO. 0004
PROJECT TITLE/LOCATION: Indian Head, MD Renovate Building 164
PRE-PROPOSAL INQUIRY FORM (PPI FORM)
Question No.
Date Received
REFERENCE QUESTION GOVERNMENT RESPONSE
Posted on
Amend No.
81 6/13/2024 AD-001
On sheet AD-001 Note 15 states ". Locate hoist at entrance vestibule secure in place hoist to be inoperable." Sheet AD120 shows hoist crane location and states "Relocate crane in vestibule." Sheet A-110 & A-120 note 4 states "existing overhead crane to remain".
- Please clarify if the hoist crane is to remain in place or relocated, since work will involve abatement, scrapping and welding if relocated.
- If the hoist crane and beam is to be relocated, please confirm new location and please advise if new location will be reflected on revised structural drawings for connection points.
- Please advise color to be painted after restoration and MPI required.
The hoist is to be removed and restored per Drawing AD001. It is then to be relocated from its current postion shown on sheet Drawing AD120 (VIF) to the new vestibule shown on Drawings A110 and A120.
Interior Ferrous Metal: MPI INT 5.1M, Primer: MPI 76, Intermediate: MPI 1, Top coat: MPI 1, System DFT: 4.25 mils
Except for a small section adjacent to column K/2, the existing crane, crane rail, and rail support beams are to remain. The crane girder and hoist are to be relocated over the entrance vestibule as shown on Drawing A-120. Refer to Drawing SD-130 for the extent of the crane rail and rail support beam demolition. Refer to the other structural drawings, including but not limited to Drawings S-120, S-202, and S-532, for additional information.
82 6/13/2024 AD-120
Sheet AD-120, AD130, AD140, DA 201, AD202, AD 203, AD 301 note 18 states "Remove and save for reuse existing ventilator". Please confirm those are in working conditions.
Please provided cut sheet for bidding purposes.
These are existing historic ventilators indicated on Drawing AD001 as roof vents. These are to be restored and replaced. They are not operable.
83 6/13/2024 A-140
Note 8 states "Salvaged/refurbished ventilator (non-operable)." For bidding purposes, please provide cut sheet to find out if parts can be purchased to refurbished those ventilators.
These are existing historic ventilators indicated on Drawing AD001 as roof vents. These are to be restored and replaced. They are not operable.
84 6/13/2024 A-160
Note 3 states "under structure mounted projector/screen."
There is no specification provided for projector/screen. Please clarify if project will be provided by government or to be included in the FF& package. If provided by government and contractor install, please provide cut sheets for bidding purposes.
The projector and screen are not part of the FF&E package and will be provided by the Government.
85 6/13/2024 A-201
General Sheet note 1 states "After cleaning exterior masonry walls…" Please advise or clarify if all the exterior is to be clean.
If so, please confirm light power wash will suffice. If not, please provide guidance on chemicals or restrictions.
Refer to Specification Section 04 20 00 for cleaning. 0004
86 6/13/2024 I-110 & I-120
Note 1 states "Reclaimed historic RHB-1 to be applied as noted" at lobby 114 & corridor 204. During the site visit, it was noted that the brick for the retaining wall has been deteriorated for possible usage as reclaimed material. Please clarify if brick veneer or faux brick can be provided instead.
Please clarify if full wall height is to received the finish. Please provide or confirm wall height for bidding purposes.
Reclaimed historic brick RHB-1 to be applied to full height of wall in Lobby 114, refer to Drawing A-150 for Lobby 114 ceiling height. Brick to extend to underside of corrugated metal panels in Corridor 204, refer to Drawing A-310 for wall section detail. The intent is to use reclaimed historic brick in these areas as noted, if reclaimed historic brick is not suitable for use provide brick veneer for NAVFAC ID and IDOR review and approval.
87 6/13/2024 I-503
Note 4 states "Coordinate with user the correct name and title for all signs with inserts (s2)." For sampling purposes and pricing. Please advise the maximum total characters or letters for sign message.
Sign message to be determined, provide maximum total characters allowed at 3/4" capital letter height, flush left as noted in B1/I-503.
PROJECT TITLE/LOCATION: Indian Head, MD Renovate Building 164
PRE-PROPOSAL INQUIRY FORM (PPI FORM)
Question No.
Date Received
REFERENCE QUESTION GOVERNMENT RESPONSE
Posted on
Amend No.
88 6/13/2024 FX-001
Note 5 states " Contractor must obtain all required permits and approval from the AHJ (Authority Having Jurisdiction) prior commencing work." Note 9 on sheet FA001 also notes "Obtain approvals from the FPDOR...." Please clarify if the AHJ will be NAVFAC Professional Fire Engineer or whether the contractor is to account for a 3rd party and additional cost for badging and expenses to access the base.
Contractor is responsible for all base access/restricted access requirements to obtain any permits, approvals, etc.
89 6/13/2024 FA110
Please confirm no devices are to be install in the lactation room 109, since none are shown.
Appliance to be included in Room 109. 0004
90 6/13/2024 A532 A2 Note 10 This note indicates that insulated window on both interior and exterior of the wall. Please confirm if this is a typo as this should indicate the historic steel windows on the exterior
Confirmed. The Exterior winodow is the existing historic window to be restored. The interior window is an insulated window.
91 6/13/2024 A607 B1/D2 GL2 and GL3 appear on these details as well as on sheet 608.
Please confirm intent by listing two types of glazing
Refer to the Exterior Materials Legend on Drawing A-601 for Glazing types. 0004
92 6/13/2024 3 08 81 00
SD-04
Samples
Please confirm that GL3 is required to be both laminated and tempered. Laminated only will serve the design intent while keeping costs down
Confirmed. Provide GL3, tempered and laminated. 0004
93 6/13/2024 AD001 Note 1 What codes apply as stated to meet? This refers to energy efficiency per IECC. 0004 94 6/13/2024 8 08 81 00 2.3.1 Color must be gray for Low E? Please confirm intent Confirmed. 0004
95 6/13/2024 8 08 81 00 2.5 Please confirm need for fire rated glass spec. Our review shows no fire rated doors or walls with glazing
Confirmed. Fire-rated glazing is not required. 0004
96 6/13/2024 P-001
General Note C states "Furnish access doors for installation in walls and ceilings where access is required to concealed plumbing equipment, valves, controls and other devices."
Access panels are not shown in the architectural drawings.
For bidding purposes, please advise how many wall panels and how many ceiling panels to account in the bid.
Additionally, please clarify the rating on those access panels.
Access panel for each trap primer and for each valve above ceiling. Approx 15-20. Panels ratings to match rating of wall or ceiling where panel is installed.
97 6/13/2024 P-101
For demolition pricing, saw cutting and plumbing pricing purposes.
- Please provide slab thickness.
- The slab existing slab will be…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .