Amendment 2, Proposal Due date is 8/20/19 by 2:00 PM
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Amendment4_SF30.rtf | RTF text file | |
| RFP_Amendment_4,_NRL_43,_Replace_Emerg_Generator_Construction_Bundle.pdf | ||
| C.E.R._RFIs_Responses.doc | DOC document | |
| Amendment3_SF30.rtf | RTF text file | |
| RFP_Amendment_3,_NRL_43,_Replace_Emerg_Generator_Construction_Bundle.pdf | ||
| RFI_CLAIFICATIONS.docx | DOCX document | |
| RFP_Amendment_1,__N40080-19-R-5738,_NRL-43_Replace_Emerg_Generator.pdf | ||
| RFP_Amendment_2,__N40080-19-R-5738,_NRL-43_Replace_Emerg_Generator.pdf | ||
| Amendment2_SF30.rtf | RTF text file | |
| eOMSI.docx | DOCX document | |
| Solicitation_N40080-19-R-5738,_price_schedule.docx | DOCX document | |
| RFP_Amendment_1,__N40080-19-R-5738,_NRL-43_Replace_Emerg_Generator.pdf | ||
| Site_Visit_Sign-In_Sheet.pdf | ||
| N40080-19-R-5738,_NRL-43_RFI_Responses.xlsx | XLSX spreadsheet | |
| Amendment1_SF30.rtf | RTF text file | |
| NRL43_RFP.pdf | ||
| RFP__A59.pdf | ||
| A49_RFP.pdf | ||
| Solicitations_N40080-19-R-5738.docx | DOCX document |
Show all 19
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
IN REPLY
REFER TO
Code PRW22 August 14, 2019
AMENDMENT 02:
REQUEST FOR PROPOSAL NO. N40080-19-R-5738
8(A) Mechanical Multiple Award Construction Contract 8(a) Mechanical MACC
NAVFAC WASHINGTON
PROPOSED TASK ORDER:
NRL-43 Replace Emerg Generator_ Construction (Bundle)
Naval Research Laboratory, Washington, D.C.
AMENDMENT DATE: 14 AUGUST 2019
ISSUED BY: NAVAL FACILITIES WASHINGTON 1013 O
STREET, S.E.
WASHINGTON NAVY YARD
BUILDING 166 WASHINGTON,
D. C. 20374
Subj: Amendment 1 for Naval Research Laboratory (NRL)- NRL-43 Replace Emerg Generator_ Construction (Bundle), Washington DC.
The purpose of this amendment is to extent the proposal due date from 8/16/2019 to 8/20/2019 by 2:00
PM EST.
This will allow time for contractors and their affiliates to apply the RFI answers to their proposals.
If you have any questions or comments pertaining to this matter, please contact the Contract Specialist at (202) 685-8168.
Thank you, Jasmine M. Bowens
Contract Specialist NAVFAC Public Works Department Office: (202) 685-8168
DEPARTMENT OF THE NAVY
NAVAL FACILITIES ENGINEERING COMMAND WASHINGTON
1314 HARWOOD STREET SE
WASHINGTON NAVY YARD DC 20374-5018
| DEPARTMENT OF THE NAVY |
| AMENDMENT 02: |
| 2019-08-14T15:29:43-0400 | |
| BOWENS.JASMINE.M.1504694409 |