This is Amendment 0002 to Solicitation N4002727R0004, issued by the Southeast Regional Maintenance Center (Navy) on November 19, 2026, with an effective date of November 19, 2026. The amendment addresses bidder questions and incorporates technical corrections related to ship maintenance and restoration work for Navy vessels.
The amendment answers eight bidder questions and incorporates ERRATA Number One and Revision 1 to Attachment J-2. Key clarifications include: the Government will provide access to electrical power at the pier, but the contractor must provide all equipment for connections; the contractor is responsible for all crane services and must comply with NSI 009-040 requirements; both Flight II and Flight IIA DDG Class configurations are covered by the ELIN pricing; paragraph references in work items have been corrected from 3.3.9 to 3.9; boat deck locations have been corrected from 1-34-4-Q to 1-31-4-Q; specified boat deck ELINs apply to the 01 Level only; and unit pricing should be based on work area ranges in Column B rather than estimated quantities in Column E. The amendment updates the list of attachments to include Attachment S-1 (Request for Specification Clarification), Attachment J-1 (Notional Work Items with ERRATA Number One), Attachment J-2 (ELIN Pricing for Ordering Periods 1-5 Revision 1), and Exhibit A (Contract Data Requirements List Form 1423). The offer receipt deadline was not extended by this amendment.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| J-2 NONSKID ELINS ORDERING PERIODS 1 THROUGH 5 (REV 1).xlsx | XLSX spreadsheet | |
| ERRATA Number One.pdf | ||
| Solicitation Amendment N4002727R00040001.pdf | ||
| EXHIBIT A DD FORM 1423 2.pdf | ||
| Solicitation - N4002727R0004.pdf | ||
| J-2 NONSKID ELINS ORDERING PERIODS 1 THROUGH 5.xlsx | XLSX spreadsheet | |
| S-1 Request for Specification Clarification.docx | DOCX document | |
| J-1 NOTIONAL WORK ITEMS.pdf | ||
| EXHIBIT A DD FORM 1423 3.pdf | ||
| EXHIBIT A DD FORM 1423 4.pdf | ||
| EXHIBIT A DD FORM 1423 1.pdf |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
R
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
16C. DATE SIGNED
Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBE
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
Section A - Solicitation/Contract Form
The following changes have been made:
Miscellaneous text in this section has been modified to:
The purpose of this amendment is to:
1. Answer Bidder's Questions 02 through 08
2. Incorporate ERRATA Number One
3. Incorporate Revision 1 to Attachment J-2
Will electrical power required to accomplish the work be provided by the Government or others, or is the Question 02:
contractor responsible for providing generators and associated power distribution equipment?
Yes, the Government will provide access to power at the pier. The contractor is required to request power need and Answer 02:
provide all required equipment to support connections to the bunker for contractor use.
Will crane services required to accomplish the work be provided by the Government or others, or should the Question 03:
contractor include crane services in its pricing?
Answer 03: No, the Government will not provide crane or crane services. The Contractor is responsible for any required crane services and shall comply with the requirements of NSI 009-040.
Question 04: For the DDG Class work identified in J-1 and J-2, please clarify whether the specified deck areas are based on Flight II or Flight IIA configurations, or whether both configurations are intended to be covered by the ELIN pricing.
Answer 04: Both configurations, Flight II and Flight IIA, are covered by the ELIN pricing.
Question 05: J-2, ELIN 0003AG references paragraph 3.3.9, which does not exist in J-1, Work Item 634-11-003 (LCS Freedom Class). Please clarify the intended paragraph and associated work requirements. This question also applies to the corresponding ELINs in Ordering Periods 2-5.
Paragraph 3.3.9 has been changed to Paragraph 3.9 on Attachment J-2 for ELINs 0003AG, 1003AG, Answer 05:
2003AG, 3003AG, and 4003AG.
Question 06: J-2, ELIN 0003AG identifies Boat Deck and Passageway 1-31-4-Q, whereas J-1, Work Item 634-11-003, paragraph 1.2.4 identifies Boat Deck and Passageway 1-34-4-Q. Please confirm the correct location. This question also applies to the corresponding ELINs in Ordering Periods 2-5.
Attachment J-2 identifies the correct location of 1-31-4-Q. ERRATA Number One is incorporated to modify Answer 06:
Work Item 634-11-003, Paragraph 1.2.4, Boat and Deck Passageway from 1-34-4-Q to 1-31-4-Q.
J-2, ELINs 0002AE and 0002AF identify the port and starboard boat decks between Frames 270-304 and Question 07:
270-294, respectively. Boat decks within these frame ranges exist on both the 01 and 02 levels and vary in size. Please clarify which deck level, or whether both levels, are intended to be included in each ELIN. This question also applies to the corresponding ELINs in Ordering Periods 2-5.
ELINs 0002AE, 0002AF, 1002AE, 1002AF, 2002AE, 2002AF, 3002AE, 3002AF, 4002AE, and 4002AF are Answer 07:
for the 01 Level only.
N4002727R00040002
The following ELINs in Ordering Period 1 of J-2 show differences between the square footage ranges in Question 08:
Column B and the estimated quantities in Column E. The same differences appear in the corresponding ELINs in Ordering Periods 2-5. 0001BR, 0001BS, 0002BM, 0002BN, 0003AX, 0003AY, 0005AE, 0005AF, 0005AH, 0005AJ, 0006AE, 0006AF, 0006AH, and 0006AJ. For example, ELIN 0001BR identifies work areas of 51-250 SF in Column B but lists an estimated quantity of 500 SF in Column E. Please clarify what square footage offerors should use to develop the unit price for each ELIN. Should we base the unit price on the work-area range in Column B or on the estimated quantity in Column E?
Unit pricing should be based on the work area range in Column B. Answer 08:
Section J - List of Attachments
Miscellaneous text in this section has been modified to:
The following document(s), exhibit(s), and other attachment(s) form a part of this solicitation:
Attachment S-1 Request for Specification Clarification
The following document(s), exhibit(s), and other attachment(s) form a part of this solicitation:
Attachment J-1 Notional Work Items, including ERRATA Number One
Attachment J-2 ELIN Pricing, Ordering Periods 1, 2, 3, 4, and 5 (Revision 1)
Exhibit A Contract Data Requirements List (CDRL) Form 1423
| IDCode: J |
| Page: 1 |
| Pages: 4 |
| AmendNo: 0002 |
| EffDate: 19 Nov 2026 |
| ReqNo: See Continuation Sheet |
| ProjNo: |
| IssCode: N40027 |
| AdmCode: |
| IssuedBy: SOUTHEAST REGIONAL MAINT CENTER |
PO BOX 280057, MAYPORT FL 32228-0057
MAYPORT, FL 32228-0057
UNITED STATES
Danielle Fujio-White, Email: danielle.b.fujio-white.civ@us.navy.mil AdminBy:
SCD: PAS:
| ContractorNameAdd: |
| Code: |
| FacCode: |
| SolChg: 1 |
| SolNo: N4002727R0004 |
| SolDate: 30 Oct 2026 |
| AwardChg: Off |
| AwardNo: |
| AwardDate: |
| Amended: 1 |
| OffrExt: Off |
| OffrNoEx: 1 |
| NoCopies: 1 |
| ApprData: See Section G - Contract Administration Data |
| ChgeOrd: Off |
| ChgeOrder: |
| Modify: Off |
| SuppAgre: Off |
| SuppAuth: |
| ModOthr: Off |
| OthrSpec: |
| NoReq: Off |
| Require: Off |
| Copies: |
| Descript: See Page 2, SF 30 Block 14 Continuation Page |
| ContNameTitle: |
| CoNameTitle: Danielle B. Fujio-White |
| ContDate: |
| CODate: 19 Nov 2026 |
File details come from the government source that posted it. Updated .