This document is a Statement of Work (SOW) for the SERMC Notional IDIQ Activity (RMC 4002), a multi-item indefinite-delivery/indefinite-quantity (IDIQ) contract for nonskid deck replacement services on various U.S. Navy vessel classes.

The contract encompasses eight primary work items covering nonskid replacement for DDG-Class destroyers (Item 634-11-001), CG-Class cruisers (Item 634-11-002), LCS Freedom-Class ships (Item 634-11-003), and LHD-Class amphibious assault ships (Item 634-11-004), plus specialized application methods including hydroblasting (Item 634-11-005), abrasive blasting (Item 634-11-006), ablative nonskid installation (Item 634-11-007), and peel-and-stick nonskid application (Item 634-11-008). Each work item identifies specific deck locations and spaces requiring treatment, with work details to be specified in individual delivery orders. Performance requirements reference MIL-PRF-24667 nonskid specifications across various types (I, III, IV, V, XI) and compositions (G, PS), water jetting or abrasive blasting surface preparation per specification 009-032, deck marking verification with NAVAIR Field Office coordination, and operational drain testing per specification 009-071. All work requires pre-performance coordination meetings with Ship's Force Point of Contact 48 hours prior to start dates. The contract also includes Item 998-41-001 addressing hazardous waste management and disposal compliance with RCRA, federal hazardous materials transportation regulations, and 10 U.S.C. Section 7311, requiring proper categorization and documentation of Navy-generated, contractor-generated, and co-generated hazardous waste. No government-furnished materials are provided under any line item.

View the file

Other files

File Type Posted
EXHIBIT A DD FORM 1423 2.pdf PDF
Solicitation - N4002727R0004.pdf PDF
J-2 NONSKID ELINS ORDERING PERIODS 1 THROUGH 5.xlsx XLSX spreadsheet
S-1 Request for Specification Clarification.docx DOCX document
EXHIBIT A DD FORM 1423 3.pdf PDF
EXHIBIT A DD FORM 1423 4.pdf PDF
EXHIBIT A DD FORM 1423 1.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SHIP: SERMC NOTIONAL IDIQ ACTIVITY

(RMC 4002)

ITEM NO: 634-11-001

COAR: 26 PCN: SERV-L108

CMP: NONE

PLANNER: LAYNE, DERICK

SSP: SERM-NSKD-27-0001 1 of 3 ITEM NO: 634-11-001

1. SCOPE:

1.1 Title: Nonskid; replace (DDG Class-IDIQ)

1.2 Location of Work:

1.2.1 (As Per Delivery Order) Forecastle Deck, Bow to Frame 126

1.2.2 (As Per Delivery Order) Flight Deck and RAST Track Plate Tops, Frame 399 to Stern

1.2.3 (As Per Delivery Order) Flight Deck, Frame 370 to stern

1.2.4 (As Per Delivery Order) Helicopter Hanger No.1 (1-338-3-Q), including RAST Track Plate Tops

1.2.5 (As Per Delivery Order) Helicopter Hanger No.2 (1-338-8-Q), including RAST Track Plate Tops

1.2.6 (As Per Delivery Order) 01 Level, Frame 118 to 207, Port side Castleway/Passageway (01-118-4-L)

1.2.7 (As Per Delivery Order) 01 Level, Frame 118 to 207, Starboard side Castleway/Passageway (01-118-1-L)

1.2.8 (As Per Delivery Order) 01 Level, Frame 204 to 328, Port and Starboard Weather Deck

1.2.9 (As Per Delivery Order) 01 Level, Frame 204 to 370, Port and Starboard Weather Deck

1.2.10 (As Per Delivery Order) 02 Level, Frame 110 to 138, Port and Starboard Weather deck, Refueling At Sea (RAS) Station No.3 and No.4, including intermediate platforms

1.2.11 (As Per Delivery Order) Forward CIWS Magazine (02-112-2-M)

1.2.12 (As Per Delivery Order) 02 Level, Frame 193 to 228, Port and Starboard Weather deck

1.2.13 (As Per Delivery Order) 02 Level, Frame 228 to 237, Nulka Platform

1.2.14 (As Per Delivery Order) 02 Level, Frame 242 to 312, Port and Starboard Weather deck

1.2.15 (As Per Delivery Order) 02 Level, AFT VLS Deck, Frames 312 to

1.2.16 (As Per Delivery Order) 03 Level, Frame 145 to 193, Port and Starboard Weather deck

1.2.17 (As Per Delivery Order) 04 Level, Frame 140 to 176, Port and Starboard Weather deck, Including Bridge wings and Signal Bridge

1.2.18 (As Per Delivery Order) 05 Level, Frame 130 to 170, Port and Starboard Weather deck

1.2.19 (As Per Delivery Order) 06 Level, Frame 137 to 165, Port and Starboard Weather deck

SHIP: SERMC NOTIONAL IDIQ ACTIVITY (RMC 4002)

SSP: SERM-NSKD-27-0001 2 of 3 ITEM NO: 634-11-001

1.2.20 (As Per Delivery Order) Weapons & Aviation Ordnance Equipment Workshop (01-300-0-Q)

1.2.21 (As Per Delivery Order) Weapons Magazine (01-300-1-M)

1.2.22 (As Per Delivery Order) AFT CIWS Magazine No.2 (01-300-2-M)

1.2.23 (As Per Delivery Order) passageway (1-42-01-L)

1.2.24 (As Per Delivery Order) Torpedo Missile and Rocket Magazine (1-304-2-M)

1.2.25 (As Per Delivery Order) Fixed Gun Ammunition Rocket Magazine (1-318-2-M)

1.2.26 (As Per Delivery Order) Aviation Repair Shop (1-381-0-Q)

1.2.27 (As Per Delivery Order) General Workshop (2-200-2-Q)

1.2.28 (As Per Delivery Order) passageway (2-370-2-L)

1.2.29 (As Per Delivery Order) passageway (2-370-3-L)

1.2.30 (As Per Delivery Order) passageway (2-370-4-L)

1.2.31 (As Per Delivery Order) passageway (2-374-2-L)

1.2.32 (As Per Delivery Order) passageway (2-374-4-L)

1.2.33 (As Per Delivery Order) passageway (2-410-0-L)

1.2.34 (As Per Delivery Order) RAST Machinery Room (2-442-0-E)

1.2.35 (As Per Delivery Order) 5/54 Projectile Magazine (3-42-0-M)

1.2.36 (As Per Delivery Order) Powder Magazine Number One (3-62-1-M)

1.2.37 (As Per Delivery Order) 5/54 Powder Magazine Number One (3- 68-1-M)

1.2.38 (As Per Delivery Order) Powder Magazine Number 2 (3-68-2-M)

1.3 Identification:

1.3.1 Not Applicable.

2. REFERENCES:

2.1 Standard Items

3. REQUIREMENTS:

3.1 Conduct a meeting with Ship’s Force Point of Contact (SFPOC) 48 hours prior to the Period of Performance (POP) start date to coordinate a schedule for accomplishing the work of each space listed on the Delivery Order.

3.2 Accomplish the requirements of 009-032 of 2.1, including Table 2, Line 9, (Water Jetting), for MIL-PRF-24667 TYPE V, COMP G, for deck surfaces in the location listed in 1.2.1 through 1.2.5.

3.2.1 Provide a diagram showing equipment which must not be covered by nonskid, including but not limited to each tie-down, Baxter Bolt, pad eye, light, RAST track, deck drain, and water wash down system.

(V)(G) "“VISUAL INSPECTION OF AVIATION DECK MARKINGS”"

3.2.2 Each deck marking must be laid out with chalk lines. Contact the local NAVAIR Field Office via the SUPERVISOR, 24 hours prior, for

SSP: SERM-NSKD-27-0001 3 of 3 ITEM NO: 634-11-001 verification of each VLA and AVCERT deck marking prior to application of color topping.

3.3 Accomplish the requirements of 009-032 of 2.1, including Table 2, Line 21 (Water jetting), for MIL-PRF-24667 TYPE V, COMP G, for deck surfaces in each location listed in 1.2.6 through 1.2.10, and 1.2.15.

3.3.1 Provide a diagram showing equipment which must not be covered by nonskid, including but not limited to each tie-down, Baxter Bolt, pad eye, and deck drain.

3.4 Accomplish the requirements of 009-032 of 2.1, including Table 2, Line 21 (Water jetting), for MIL-PRF-24667 TYPE I, COMP G, for deck surfaces in each location listed in 1.2.11, 1.2.13, and 1.2.20 through 1.2.38.

3.4.1 Provide a diagram showing equipment which must not be covered by nonskid, including but not limited to each tie-down, Baxter Bolt, pad eye, and deck drain.

3.5 Accomplish the requirements of 009-032 of 2.1, including table 2, Line 22, for MIL-PRF-24667 TYPE XI, COMP PS, for the deck surfaces in location listed in 1.2.12, 1.2.14, and 1.2.16, through 1.2.19.

3.5.1 Provide a diagram showing equipment which must not be covered by nonskid, including but not limited to each tie-down, Baxter Bolt, pad eye, and deck drain.

3.6 Accomplish the requirements of 009-071 of 2.1, for an operational test of gravity drain piping for unobstructed flow.

(I)(G) "OR (V) (G) FINAL INSPECTION"

3.7 Accomplish a final visual inspection for each deck receiving new nonskid.

4. NOTES:

4.1 Ship’s Force Point of Contact shall be identified in each delivery order.

5. GOVERNMENT FURNISHED MATERIAL(GFM):

5.1 LLTM:

1. None.

5.2 PUSH MATERIAL:

1. None.

5.3 KITTED MATERIAL:

1. None.

ITEM NO: 634-11-002

COAR: 26 PCN: SERV-L110

CMP: NONE

PLANNER: LAYNE, DERICK

SSP: SERM-NSKD-27-0001 1 of 3 ITEM NO: 634-11-002

1. SCOPE:

1.1 Title: Nonskid; replace (CG Class - IDIQ)

1.2 Location of Work:

1.2.1 (As Per Delivery Order) Forecastle Deck, Bow to Frame 138

1.2.2 (As Per Delivery Order) Main Deck, Frame 454 to Stern

1.2.3 (As Per Delivery Order) Helicopter Hangar (02-292-2-Q), and RAST Track Plate Tops

1.2.4 (As Per Delivery Order) Flight Deck, 02 Level, Frame 346 to 418, including RAST Track Plate Tops

1.2.5 (As Per Delivery Order) Port Boat Deck, Frame 270 to 304

1.2.6 (As Per Delivery Order) Starboard Boat Deck, Frame 270 to 294

1.2.7 (As Per Delivery Order) Passageway (01-138-2-L)

1.2.8 (As Per Delivery Order) Passageway (01-138-3-L)

1.2.9 (As Per Delivery Order) 01 Level, Frame 174 to 409, Port Side

1.2.10 (As Per Delivery Order) 01 Level, Frame 174 to 409, Starboard Side

1.2.11 (As Per Delivery Order) 01 Level, Frame 409 to 472

1.2.12 (As Per Delivery Order) 04 Level, Frame 174 to 248

1.2.13 (As Per Delivery Order) 04 Level, Frame 289 to 346

1.2.14 (As Per Delivery Order), 03 Level, Frame 180 to 289

1.2.15 (As Per Delivery Order), Helicopter Repair Shop (02-276-01-Q)

1.2.16 (As Per Delivery Order) RAST Machinery Room (01-382-0-Q)

1.2.17 (As Per Delivery Order) Sonobuoy Storeroom (01-398-1-A)

1.2.18 (As Per Delivery Order) Windlass Room (1-0-0-E)

1.2.19 (As Per Delivery Order) 5/54 Loader Drum Room No. 1 (1-58-0- M)

1.2.20 (As Per Delivery Order) Torpedo Room No. 1 (1-390-1-M)

1.2.21 (As Per Delivery Order) Torpedo Room No. 2 (1-390-4-M)

1.2.22 (As Per Delivery Order) 5/54 Ammo Pallet Staging Room No.1 (2-58-0-Q)

1.2.23 (As Per Delivery Order) Reefer Machinery Room (2-220-4-Q)

1.2.24 (As Per (As Per Delivery Order) Filter Cleaning Shop (2-382- 4-Q)

1.2.25 (As Per Delivery Order) General Workshop (2-387-0-Q)

1.2.26 (As Per Delivery Order) Stores Handling Room (2-464-0-A)

1.2.27 (As Per Delivery Order) 5/54 Loader Drum Room No.2 (2-482-0-

SSP: SERM-NSKD-27-0001 2 of 3 ITEM NO: 634-11-002

M)

1.2.28 (As Per Delivery Order) 5/54 Projectile Magazine No.1 (3-62- 0-M)

1.2.29 (As Per Delivery Order) Mk 26 Magazine No.1 (3-97-01-M)

1.2.30 (As Per Delivery Order) Pump Room No.2 & AC Machinery Room (3-398-0-E)

1.2.31 (As Per Delivery Order) Mk 26 Magazine No.2 (3-435-01-M)

1.2.32 (As Per Delivery Order) 5/54 Ammo Pallet Staging Room No.2 (3-464-0-Q)

1.2.33 (As Per Delivery Order) 5/54 Projectile Magazine No.2 (3-482- 0-M)

1.2.34 (As Per Delivery Order) 5/54 Powder Magazine No.3 (3-494-0-M)

1.3 Identification:

1.3.1 Not Applicable.

2. REFERENCES:

2.1 Standard Items

3. REQUIREMENTS:

3.1 Conduct a meeting with Ship’s Force Point of Contact (SFPOC) 48 hours prior to the Period of Performance (POP) start date to coordinate a schedule for accomplishing the work of each space listed on the Delivery Order.

3.2 Accomplish the requirements of 009-032 of 2.1, including Table 2, Line 9 (Water Jetting), for MIL-PRF-24667 TYPE V, COMP G, for each deck surface in the location listed in 1.2.1 and 1.2.2.

3.2.1 Provide a diagram showing equipment which must not be covered by nonskid, including but not limited to each tie-down, Baxter Bolt, pad eye, light, deck drain, and water wash down nozzle.

(I)(G) "VISUAL INSPECTION OF AVIATION DECK MARKINGS"

3.2.2 Each deck marking must be laid out with chalk lines. Contact the local NAVAIR Field Office via the SUPERVISOR, 24 hours prior, for verification of each VLA and AVCERT deck marking prior to application of color topping.

3.3 Accomplish the requirements of 009-032 of 2.1, including Table 2, Line 55 (Water Jetting), for MIL-PRF-24667 TYPE V, COMP G, for each deck surface in the location listed in 1.2.3 and 1.2.4.

3.3.1 Provide a diagram showing equipment which must not be covered by nonskid, including but not limited to each tie-down, Baxter Bolt, pad eye, light, RAST track, deck drain, and water wash down nozzle.

3.3.2 Apply each deck marking. Each deck marking must be laid out with chalk lines. Contact the local NAVAIR Field Office via the SUPERVISOR, 24 hours prior, for verification of each VLA and AVCERT deck marking prior to application of color topping.

3.4 Accomplish the requirements of 009-032 of 2.1, including Table 2, Line 60 (Water jetting), for MIL-PRF-24667 Type I, COMP G, for each deck surface in the location listed in 1.2.5 and 1.2.6.

SSP: SERM-NSKD-27-0001 3 of 3 ITEM NO: 634-11-002

3.4.1 Provide a diagram showing equipment which must not be covered by nonskid, including but not limited to each tie-down, Baxter Bolt, pad eye, deck drain, and water wash down nozzle.

3.5 Accomplish the requirements of 009-032 of 2.1, including Table 2, Line 21 (Water jetting), for MIL-PRF-24667 Type I, COMP G, for each deck surface in the location listed in 1.2.7 through 1.2.11 and 1.2.16 through 1.2.34.

3.5.1 Provide a diagram showing equipment which must not be covered by nonskid, including but not limited to each tie-down, Baxter Bolt, pad eye, deck drain, and water wash down nozzle.

3.6 Accomplish the requirements of 009-032 of 2.1, including Table 2, Line 61 (Water jetting), for MIL-PRF-24667 Type XI, COMP PS, for each deck surface in the location listed in 1.2.12 through 1.2.15.

3.6.1 Provide a diagram showing equipment which must not be covered by nonskid, including but not limited to each tie-down, Baxter Bolt, pad eye, deck drain, and water wash down nozzle.

3.7 Accomplish the requirements of 009-071 of 2.1, for an operational test of gravity drain piping for unobstructed flow.

(I)(G) "FINAL INSPECTION"

3.8 Accomplish a final visual inspection for each deck receiving new nonskid.

4. NOTES:

4.1 Ship’s Force Point of Contact shall be identified in each delivery order.

5. GOVERNMENT FURNISHED MATERIAL(GFM):

5.1 LLTM:

1. None.

5.2 PUSH MATERIAL:

1. None.

ITEM NO: 634-11-003

COAR: 26 PCN: SERV-L109

CMP: NONE

PLANNER: LAYNE, DERICK

SSP: SERM-NSKD-27-0001 1 of 3 ITEM NO: 634-11-003

1. SCOPE:

1.1 Title: Nonskid; replace (LCS Freedom Class - IDIQ)

1.2 Location of Work:

1.2.1 (As Per Delivery Order) Flight Deck

1.2.2 (As Per Delivery Order) Airborne Mission Zone (1-36-01-Q)

1.2.3 (As Per Delivery Order) Forecastle

1.2.4 (As Per Delivery Order) Boat Deck and Passageway (1-34-4-Q)

1.2.5 (As Per Delivery Order) Waterborne Mission Zone (3-65-0-Q)

1.2.6 (As Per Delivery Order) Reconfigurable Mission Space One (3- 45-0-Q)

1.2.7 (As Per Delivery Order) Reconfigurable Mission Space 2 (3-54- 0-Q)

1.2.8 (As Per Delivery Order) Mission Ordnance Magazine One (1-38-0- M)

1.2.9 (As Per Delivery Order) Mission Ordnance Magazine 2 (1-38-2-M)

1.2.10 (As Per Delivery Order) 01 Level Port and Starboard Bridge Wings

1.2.11 (As Per Delivery Order) 02 Level Frame 21-26

1.2.12 (As Per Delivery Order) 02 Level Frame 40 – 45

1.2.13 (As Per Delivery Order) 02 Level Frame 45 – 56

1.2.14 (As Per Delivery Order) 03 Level Frame 23-41

1.3 Identification:

1.3.1 Not Applicable.

2. REFERENCES:

2.1 Standard Items

3. REQUIREMENTS:

3.1 Conduct a meeting with Ship’s Force Point of Contact (SFPOC) 48 hours prior to the Period of Performance (POP) start date to coordinate a schedule for accomplishing the work of each space listed on the Delivery Order.

3.2 Accomplish the requirements of 009-032 of 2.1, including Table 2, Line 9, (Water Jetting), for MIL-PRF-24667 TYPE V, COMP G, for each deck surface in the location listed in 1.2.1 and 1.2.2.

3.2.1 Provide a diagram showing equipment which must not be covered by nonskid, including but not limited to each tie-down, Baxter Bolt, pad eye, light, deck drain, and water wash down nozzle.

(V)(G) "VISUAL INSPECTION OF AVIATION DECK MARKINGS"

SSP: SERM-NSKD-27-0001 2 of 3 ITEM NO: 634-11-003

3.2.2 Each deck marking must be laid out with chalk lines. Contact the local NAVAIR Field Office via the SUPERVISOR, 24 hours prior, for verification of each VLA and AVCERT deck marking prior to application of color topping.

3.3 Accomplish the requirements of 009-032 of 2.1, including Table 2, Line 9, (Water Jetting), for MIL-PRF-24667 TYPE IV (spray on), COMP G, for the deck surface in the location listed in 1.2.2.

3.3.1 Provide a diagram showing equipment which must not be covered by nonskid, including but not limited to each tie-down, Baxter Bolt, pad eye, deck drain, and water wash down nozzle.

(V)(G) "VISUAL INSPECTION OF AVIATION DECK MARKINGS"

3.3.2 Each deck marking must be laid out with chalk lines. Contact the local NAVAIR Field Office via the SUPERVISOR, 24 hours prior, for verification of each VLA and AVCERT deck marking prior to application of color topping.

3.4 Accomplish the requirements of 009-032 of 2.1, including Table 2, Line 21, (Water Jetting), for MIL-PRF-24667 TYPE IV (spray on), COMP G, for each deck surface in the location listed in 1.2.3 through 1.2.5.

3.4.1 Provide a diagram showing equipment which must not be covered by nonskid, including but not limited to each tie-down, Baxter Bolt, pad eye, light, deck drain, and water wash down nozzle.

3.5 Accomplish the requirements of 009-032 of 2.1, including Table 2, Line 21, (Water Jetting), for MIL-PRF-24667 TYPE V, COMP G, for each deck surface in the location listed in 1.2.3 through 1.2.5.

3.5.1 Provide a diagram showing equipment which must not be covered by nonskid, including but not limited to each tie-down, Baxter Bolt, pad eye, light, deck drain, and water wash down nozzle.

3.6 Accomplish the requirements of 009-032 of 2.1, including Table 2, Line 21, (Water Jetting), for MIL-PRF-24667 TYPE 1, COMP G, for each deck surface in the location listed in 1.2.6 and 1.2.7.

3.6.1 Provide a diagram showing equipment which must not be covered by nonskid, including but not limited to each tie-down, Baxter Bolt, pad eye, light, deck drain, and water wash down nozzle.

3.7 Accomplish the requirements of 009-032 of 2.1, including Table 2, Line 22, (Water Jetting), for MIL-PRF-24667 TYPE XI, COMP PS, for each deck surface in the location listed in 1.2.6 through 1.2.9.

3.7.1 Provide a diagram showing equipment which must not be covered by nonskid, including but not limited to each tie-down, Baxter Bolt, pad eye, deck drain, and water wash down nozzle.

3.8 Accomplish the requirements of 009-032 of 2.1, including Table 2, Line 61, (Water Jetting), for MIL-PRF-24667 TYPE XI, COMP PS, for each deck surface in the location listed in 1.2.10 through 1.2.14.

3.8.1 Provide a diagram showing equipment which must not be covered by nonskid, including but not limited to each tie-down, Baxter Bolt, pad eye, deck drain, and water wash down nozzle.

3.9 Accomplish the requirements of 009-071 of 2.1, for an operational test of gravity drain piping for unobstructed flow.

(V)(G) "FINAL INSPECTION"

SSP: SERM-NSKD-27-0001 3 of 3 ITEM NO: 634-11-003

3.10 Accomplish a final visual inspection for each deck receiving new nonskid.

4. NOTES:

4.1 Ship’s Force Point of Contact shall be identified in each delivery order.

5. GOVERNMENT FURNISHED MATERIAL(GFM):

5.1 LLTM:

1. None.

5.2 PUSH MATERIAL:

1. None.

ITEM NO: 634-11-004

COAR: 26 PCN: SERV-L111

CMP: NONE

PLANNER: LAYNE, DERICK

SSP: SERM-NSKD-27-0001 1 of 3 ITEM NO: 634-11-004

1. SCOPE:

1.1 Title: Nonskid; replace (LHD Class - IDIQ)

1.2 Location of Work:

1.2.1 (As Per Delivery Order) Flight Deck

1.2.2 (As Per Delivery Order) Aircraft Hanger

1.2.3 (As Per Delivery Order) Aircraft Elevator Port Side (Frame 89 to 97)

1.2.4 (As Per Delivery Order) Aircraft Elevator STBD Side (Frame 114 to 121)

1.2.5 (As Per Delivery Order) Ramp (03 Level to Hanger Deck)

1.2.6 (AS Per Delivery Order) Ramp (Hanger Deck to 3rd Deck)

1.2.7 (As Per Delivery Order) Ramp (3rd Deck to 4th Deck)

1.2.8 (As Per Delivery Order) 3rd Deck Vehicle Stowage

1.2.9 (As Per Delivery Order) 4th Deck Vehicle Stowage

1.2.10 (As Per Delivery Order) I-10 Passageway 1-67-1-L

1.3 Identification:

1.3.1 Not Applicable.

2. REFERENCES:

2.1 Standard Items

3. REQUIREMENTS:

3.1 Conduct a meeting with Ship’s Force Point of Contact (SFPOC) 48 hours prior to the Period of Performance (POP) start date to coordinate a schedule for accomplishing the work of each space listed on the Delivery Order.

3.2 Accomplish the requirements of 009-032 of 2.1, including Table 2, Line 17, for the deck surface in the location listed in 1.2.1.

3.2.1 Provide a diagram showing equipment which must not be covered by nonskid, including but not limited to each tie-down, Baxter Bolt, pad eye, light, deck drain, and water wash down nozzle.

(I)(G) "VISUAL INSPECTION OF AVIATION DECK MARKINGS"

3.2.2 Each deck marking must be laid out with chalk lines. Contact the local NAVAIR Field Office via the SUPERVISOR, 24 hours prior, for verification of each VLA and AVCERT deck marking prior to application of color topping.

3.3 Accomplish the requirements of 009-032 of 2.1, including Table 2, Line 9, for the deck surface in the location listed in 1.2.2.

3.3.1 Provide a diagram showing equipment which must not be covered by nonskid, including but not limited to each tie-down, Baxter Bolt, SSP: SERM-NSKD-27-0001 2 of 3 ITEM NO: 634-11-004 pad eye, light, deck drain, and water wash down nozzle.

(I)(G) "VISUAL INSPECTION OF AVIATION DECK MARKINGS"

3.3.2 Each deck marking must be laid out with chalk lines. Contact the local NAVAIR Field Office via the SUPERVISOR, 24 hours prior, for verification of each VLA and AVCERT deck marking prior to application of color topping.

3.4 Accomplish the requirements of 009-032 of 2.1, including Table 2, Line 55 (Water Jetting), for each deck surface in the location listed in

1.2.3 and 1.2.4.

3.4.1 Provide a diagram showing equipment which must not be covered by nonskid, including but not limited to each tie-down, Baxter Bolt, pad eye, and deck drain.

(I)(G) "VISUAL INSPECTION OF AVIATION DECK MARKINGS"

3.4.2 Each deck marking must be laid out with chalk lines. Contact the local NAVAIR Field Office via the SUPERVISOR, 24 hours prior, for verification of each VLA and AVCERT deck marking prior to application of color topping.

3.5 Accomplish the requirements of 009-032 of 2.1, including Table 2, Line 20B (Water Jetting), for each deck surface in the location listed in

1.2.5 through 1.2.7.

3.5.1 Provide a diagram showing equipment which must not be covered by nonskid, including but not limited to each tie-down, Baxter Bolt, and pad eye.

3.6 Accomplish the requirements of 009-032 of 2.1, including Table 2, Line 21 (Water Jetting), for MIL-PRF-24667 TYPE V, COMP G, for each deck surface in the location listed in 1.2.8 through 1.2.10.

3.6.1 Provide a diagram showing equipment which must not be covered by nonskid, including but not limited to each tie-down, Baxter Bolt, pad eye, and deck drain.

3.7 Accomplish the requirements of 009-071 of 2.1, for an operational test of each gravity drain for unobstructed flow.

(I)(G) "FINAL INSPECTION"

3.8 Accomplish a final visual inspection for each deck receiving new nonskid.

4. NOTES:

4.1 Ship’s Force Point of Contact shall be identified in each delivery order.

5. GOVERNMENT FURNISHED MATERIAL(GFM):

5.1 LLTM:

1. None.

5.2 PUSH MATERIAL:

SSP: SERM-NSKD-27-0001 3 of 3 ITEM NO: 634-11-004

ITEM NO: 634-11-005

COAR: 26 PCN: SERV-L113

CMP: NONE

PLANNER: LAYNE, DERICK

SSP: SERM-NSKD-27-0001 1 of 2 ITEM NO: 634-11-005

1. SCOPE:

1.1 Title: Nonskid; replace (Hydroblast - All Vessels - IDIQ)

1.2 Location of Work:

1.2.1 (As Per Delivery Order) Square feet in each location as designated by the SUPERVISOR

1.3 Identification:

1.3.1 Not Applicable.

2. REFERENCES:

2.1 Standard Items

3. REQUIREMENTS:

3.1 Conduct a meeting with Ship’s Force Point of Contact (SFPOC) 48 hours prior to the Period of Performance (POP) start date to coordinate a schedule for accomplishing the work for each space listed on the Delivery Order.

3.2 Accomplish the requirements of 009-032 of 2.1, including Table 2, Line 9 or Line 55 (Water Jetting), for MIL-PRF-24667 TYPE V COMP G, for each deck surface listed in 1.2.

3.2.1 Provide a diagram showing equipment which must not be covered by nonskid, including but not limited to each tie-down, Baxter Bolt, pad eye, light, RAST track, deck drain, and water wash down nozzle.

(I)(G) "VISUAL INSPECTION OF AVIATION DECK MARKINGS"

3.2.2 Each deck marking must be laid out with chalk lines. Contact the local NAVAIR Field Office via the SUPERVISOR, 24 hours prior, for verification of each VLA and AVCERT deck marking prior to application of color topping.

3.3 Accomplish the requirements of 009-032 of 2.1, including Table 2, Line 21 or Line 60 (Water Jetting), for MIL-PRF-24667 TYPE V COMP G, for each deck surface listed in 1.2.

3.3.1 Provide a diagram showing equipment which must not be covered by nonskid, including but not limited to each tie-down, Baxter Bolt, pad eye, light, deck drain, and water wash down nozzle.

3.4 Accomplish the requirements of 009-032 of 2.1, including Table 2, Line 21 or Line 60 (Water Jetting), for MIL-PRF-24667 TYPE I COMP G, for each deck surface listed in 1.2.

3.4.1 Provide a diagram showing equipment which must not be covered by nonskid, including but not limited to each tie-down, Baxter Bolt, pad eye, light, deck drain, and water wash down nozzle.

3.5 Accomplish the requirements of 009-032 of 2.1, including Table 2, Line 21 or Line 60 (Water Jetting), for MIL-PRF-24667 TYPE IV COMP G, for each deck surface listed in 1.2.

3.5.1 Provide a diagram showing equipment which must not be covered

SSP: SERM-NSKD-27-0001 2 of 2 ITEM NO: 634-11-005 by nonskid, including but not limited to each tie-down, Baxter Bolt, pad eye, deck drain, and water wash down nozzle.

3.6 Accomplish the requirements of 009-071 of 2.1, for an operational test of each gravity drain for unobstructed flow.

(V)(G) "FINAL INSPECTION"

3.7 Accomplish a final visual inspection for each deck receiving new nonskid.

4. NOTES:

4.1 Ship’s Force Point of Contact shall be identified in each delivery order.

5. GOVERNMENT FURNISHED MATERIAL(GFM):

5.1 LLTM:

1. None.

5.2 PUSH MATERIAL:

1. None.

ITEM NO: 634-11-006

COAR: 26 PCN: SERV-L116

CMP: NONE

PLANNER: LAYNE, DERICK

SSP: SERM-NSKD-27-0001 1 of 2 ITEM NO: 634-11-006

1. SCOPE:

1.1 Title: Nonskid; replace (Abrasive Blast - All Vessels - IDIQ)

1.2 Location of Work:

1.2.1 (As Per Delivery Order) Square feet in each location as designated by the SUPERVISOR

1.3 Identification:

1.3.1 Not Applicable.

2. REFERENCES:

2.1 Standard Items

3. REQUIREMENTS:

3.1 Conduct a meeting with Ship’s Force Point of Contact (SFPOC) 48 hours prior to the Period of Performance (POP) start date to coordinate a schedule for accomplishing the work for each space listed on the Delivery Order.

3.2 Accomplish the requirements of 009-032 of 2.1, including Table 2, Line 9 or Line 55 (Abrasive Blast), for MIL-PRF-24667 TYPE V COMP G, for each deck surface listed in 1.2.

3.2.1 Provide a diagram showing equipment which must not be covered by nonskid, including but not limited to each tie-down, Baxter Bolt, pad eye, light, RAST track, deck drain, and water wash down nozzle.

(I)(G) "VISUAL INSPECTION OF AVIATION DECK MARKINGS"

3.2.2 Each deck marking must be laid out with chalk lines. Contact the local NAVAIR Field Office via the SUPERVISOR, 24 hours prior, for verification of each VLA and AVCERT deck marking prior to application of color topping.

3.3 Accomplish the requirements of 009-032 of 2.1, including Table 2, Line 21 or Line 60 (Abrasive Blast), for MIL-PRF-24667 TYPE V COMP G, for each deck surface listed in 1.2.

3.3.1 Provide a diagram showing equipment which must not be covered by nonskid, including but not limited to each tie-down, Baxter Bolt, pad eye, light, deck drain, and water wash down nozzle.

3.4 Accomplish the requirements of 009-032 of 2.1, including Table 2, Line 21 or Line 60 (Abrasive Blast), for MIL-PRF-24667 TYPE I COMP G, for each deck surface listed in 1.2.

3.4.1 Provide a diagram showing equipment which must not be covered by nonskid, including but not limited to each tie-down, Baxter Bolt, pad eye, light, deck drain, and water wash down nozzle.

3.5 Accomplish the requirements of 009-032 of 2.1, including Table 2, Line 21 or Line 60 (Abrasive Blast), for MIL-PRF-24667 TYPE IV COMP G, for each deck surface listed in 1.2.

3.5.1 Provide a diagram showing equipment which must not be covered

SSP: SERM-NSKD-27-0001 2 of 2 ITEM NO: 634-11-006 by nonskid, including but not limited to each tie-down, Baxter Bolt, pad eye, deck drain, and water wash down nozzle.

3.6 Accomplish the requirements of 009-071 of 2.1, for an operational test of each gravity drain for unobstructed flow.

(V)(G) "FINAL INSPECTION"

3.7 Accomplish a final visual inspection for each deck receiving new nonskid.

4. NOTES:

4.1 Ship’s Force Point of Contact shall be identified in each delivery order.

5. GOVERNMENT FURNISHED MATERIAL(GFM):

5.1 LLTM:

1. None.

5.2 PUSH MATERIAL:

1. None.

ITEM NO: 634-11-007

COAR: 26 PCN: SERV-L121

CMP: NONE

PLANNER: LAYNE, DERICK

SSP: SERM-NSKD-27-0001 1 of 2 ITEM NO: 634-11-007

1. SCOPE:

1.1 Title: Ablative Nonskid; replace (All Vessels - IDIQ)

1.2 Location of Work:

1.2.1 (As Per Delivery Order) square feet in locations as designated by the SUPERVISOR

1.3 Identification:

1.3.1 Ablative Deck Covering FLAMEMASTER E340F

1.3.2 Ablative Nonskid FLAMEMASTER E340F NS

1.3.3 Nonskid Membrane, MIL-PRF-24667, Type III

1.3.4 MIL-PRF-3135 Underlayment

2. REFERENCES:

2.1 Standard Items

3. REQUIREMENTS:

3.1 Conduct a meeting with Ship’s Force Point of Contact (SFPOC) 48 hours prior to the Period of Performance (POP) start date to coordinate a schedule for accomplishing the work of each space listed on the Delivery Order.

3.2 Accomplish the requirements of 009-032 of 2.1, including Table 2, Line 9 or Line 55, Column A and B, to remove existing and install new Ablative deck covering and Ablative nonskid for each launcher blast pad, including each associated deck surface receiving nonskid deck covering in each location listed in 1.2

3.2.1 Install new material listed in 1.3.1 and 1.3.2 to each surface prepared in 3.2 in accordance with manufacturer’s instructions.

3.2.2 Provide a diagram showing equipment which must not be covered by nonskid, including but not limited to each tie-down, Baxter Bolt, pad eye, light, deck drain, and water wash down nozzle.

3.2.3 Each deck marking must be laid out with chalk lines. Contact the local NAVAIR Field Office via the SUPERVISOR, 24 hours prior, for verification of each VLA and AVCERT deck marking prior to application of color topping.

3.3 Accomplish the requirements of 009-032 of 2.1, including Table 2, Line 21 or Line 60, Column A and B, to remove existing and install new Ablative deck covering and Ablative nonskid for each launcher blast pad, including each associated deck surface receiving nonskid deck covering in location listed in 1.2.

3.3.1 Install new material listed in 1.3.1 and 1.3.2 to each surface prepared in 3.3 in accordance with manufacturer’s instructions.

3.3.2 Provide a diagram showing equipment which must not be covered by nonskid, including but not limited to each tie-down, Baxter Bolt, pad eye, deck drain, and water wash down nozzle.

SSP: SERM-NSKD-27-0001 2 of 2 ITEM NO: 634-11-007

3.4 Accomplish the requirements of 009-032 of 2.1, including Table 2, Line 9 or Line 55, Column A and B, to remove existing and install new Ablative nonskid to Ablative deck covering for each launcher blast pad, including each associated deck surface receiving nonskid deck covering in location listed in 1.2.

3.4.1 Install new material listed in 1.3.2 to each surface prepared in 3.4 in accordance with manufacturer’s instructions.

3.4.2 Provide a diagram showing equipment which must not be covered by nonskid, including but not limited to each tie-down, Baxter Bolt, pad eye, light, deck drain, and water wash down nozzle.

3.5 Accomplish the requirements of 009-032 of 2.1, including Table 2, Line 21 or Line 60, Column A and B, to remove existing and install new Ablative nonskid to Ablative deck covering for each launcher blast pad, including each associated deck surface receiving nonskid deck covering in location listed in 1.2.

3.5.1 Install new material listed in 1.3.2 to each surface prepared in 3.5 in accordance with manufacturer’s instructions.

3.5.2 Provide a diagram showing equipment which must not be covered by nonskid, including but not limited to each tie-down, Baxter Bolt, pad eye, light, deck drain, and water wash down nozzle.

3.6 Install new material listed in 1.3.3 to smooth the deck, in accordance with manufacturer’s instruction.

3.7 Install new material listed in 1.3.4 to fill low spots in the deck and or slope the deck to each deck drain, in accordance with manufacturer’s instruction.

3.8 Accomplish the requirements of 009-071 of 2.1, for an operational test of gravity drain piping for unobstructed flow.

(V)(G) "FINAL INSPECTION"

3.9 Accomplish a final visual inspection for each deck receiving new nonskid.

4. NOTES:

4.1 Ship’s Force Point of Contact shall be identified in each delivery order.

5. GOVERNMENT FURNISHED MATERIAL(GFM):

5.1 LLTM:

1. None.

5.2 PUSH MATERIAL:

1. None.

ITEM NO: 634-11-008

COAR: 26 PCN: SERV-L117

CMP: NONE

PLANNER: LAYNE, DERICK

SSP: SERM-NSKD-27-0001 1 of 1 ITEM NO: 634-11-008

1. SCOPE:

1.1 Title: Peel and Stick Nonksid; replace (All Vessels - IDIQ)

1.2 Location of Work:

1.2.1 (As Per Delivery Order) square feet in each location as designated by the SUPERVISOR

1.3 Identification:

1.3.1 Not Applicable.

2. REFERENCES:

2.1 Standard Items

3. REQUIREMENTS:

3.1 Conduct a meeting with Ship’s Force Point of Contact (SFPOC) 48 hours prior to the Period of Performance (POP) start date to coordinate a schedule for accomplishing the work of each space listed on the Delivery Order.

3.2 Accomplish the requirements of 009-026 of 2.1, including Attachment G, for each location listed in 1.2.

3.2.1 Accomplish the requirements of 009-032 of 2.1, Table 2, Line 22 or 61.

3.3 Accomplish the requirements of 009-071 of 2.1, for an operational test of gravity drain piping for unobstructed flow.

(V)(G) "FINAL INSPECTION"

3.4 Accomplish a final visual inspection for each deck receiving new nonskid.

4. NOTES:

4.1 Ship’s Force Point of Contact shall be identified in each delivery order.

5. GOVERNMENT FURNISHED MATERIAL(GFM):

5.1 LLTM:

1. None.

5.2 PUSH MATERIAL:

1. None.

ITEM NO: 998-41-001

COAR: 26 PCN: SERV-L118

CMP: NONE

PLANNER: LAYNE, DERICK

SSP: SERM-NSKD-27-0001 1 of 5 ITEM NO: 998-41-001

1. SCOPE:

1.1 Title: Hazardous Waste Produced on Naval Vessel; control

1.2 Location of Work:

1.2.1 Throughout the Ship

1.3 Identification:

1.3.1 Not Applicable

2. REFERENCES:

2.1 Resource Conservation and Recovery Act, (RCRA) Compliance Monitoring

2.2 49 U.S.C. 5103, Federal Hazardous Materials Transportation Act

2.3 Applicable Hazardous Waste, Manifest Form

2.4 10 U.S.C., 7311 Repair or Maintenance of Naval Vessels: Handling of Hazardous Waste

3. REQUIREMENTS:

3.1 Manage and dispose of each hazardous waste listed in 3.5 in accordance with 2.1 and 2.2.

3.1.1 When a Navy generator number is required by this Work Item, submit the original of 2.3 to the SUPERVISOR for assignment of Environmental Protection Agency (EPA) or delegated state environmental agency identification number.

3.1.2 Manage and transport for Navy disposal, Navy-generated

hazardous waste listed in 3.5 in accordance with 2.1 and 2.2, as designated by the SUPERVISOR.

3.1.3 Submit one legible copy, in hard copy or approved

transferrable media, of 2.3 signed by the owner or operator of the disposal facility to the SUPERVISOR within 48 hours of receipt from owner or operator of disposal facility.

3.2 Complete documentation required by 2.1 and 2.2, using EPA or delegated state environmental agency identification number in accordance with 2.4.

3.2.1 Documentation related to hazardous waste generated solely by the physical actions of Ship's Force or Navy employees (termed Navy- Generated Hazardous Waste) on board the vessel must only bear a generator identification number issued to the Navy pursuant to applicable law. The contractor must obtain SUPERVISOR'S concurrence with the categorization of the waste as Navy-generated before completion of the manifest. The manifest prepared must be presented to the SUPERVISOR for completion after the hazardous waste has been identified.

3.2.2 Documentation related to hazardous waste generated solely by the physical actions of contractor personnel (termed Contractor- Generated Hazardous Waste) must bear a generator identification number issued to the contractor pursuant to applicable law.

SSP: SERM-NSKD-27-0001 2 of 5 ITEM NO: 998-41-001

Regardless of the presence of other material in or on the shipboard systems or structure which may have qualified a waste stream as hazardous, where the contractor performs work on a system or structure using materials (whether or not the use of such materials was specified by the Navy) which by themselves would cause the waste from such work to be a hazardous waste, documentation related to such waste must only bear a generator number issued to the contractor.

3.2.3 Documentation related to hazardous waste generated by the combined physical actions of Navy and contractor personnel (termed Co-Generated Hazardous Waste) must bear a generator identification number issued to the contractor pursuant to applicable law and must also cite in the remarks block a generator identification number issued to the Navy pursuant to applicable law. When the contractor merely drains a system and such drainage creates hazardous waste or the contractor performs work on system or structure using materials which by themselves would not cause the waste from such work to be hazardous waste but such work nonetheless creates a hazardous waste, documentation related to such waste must bear a generator identification number issued to the contractor and must also cite in the remarks block a generator identification number issued to the Navy. The contractor must sign the generator certification on the Uniform Hazardous Waste Manifest whenever use of the manifest is required for disposal. The contractor must obtain SUPERVISOR's concurrence with the categorization of the wastes as co-generated before completion of the manifest. Each manifest prepared must be presented to the SUPERVISOR for completion after the hazardous waste has been identified.

3.3 If the contractor, while performing work at a Government facility, cannot obtain a separate generator identification number from the state in which the availability will be performed, the contractor must notify the SUPERVISOR within three business days of receipt of written notification by the state. After obtaining approval of the SUPERVISOR, the contractor must use the Navy site generator identification number and insert in the remarks block the contractor generator identification number issued for the site where his main facilities are located.

3.4 If, for availabilities at a contractor-owned or controlled facility, the Navy cannot obtain a separate generator identification number for use at a contractor facility, the Navy must notify the contractor within 3 business days of receipt of notification by the state. The contractor must dispose of hazardous waste in accordance with 2.1, 2.2, and 3.2.3.

3.5 Hazardous waste, as listed in 2.1, expected to be produced during performance of this Job Order:

TYPE NAVY

AMOUNT

CO-GENERATED CONTRACTOR

Acid Solutions (may include spent sulfamic, citric chromic, nitric, sulfuric, hydrochloric, etc.)

0 0 0

SSP: SERM-NSKD-27-0001 3 of 5 ITEM NO: 998-41-001

Ethylene Glycol (Antifreeze)

0 0 0

Sodium Hydroxide 0 0 0

Cleaning Solvents 0 0 0

Sodium Phosphates (Tri, Bi, or Mono)

0 0 0

Fluorocarbons 0 0 0

Morpholine 0 0 0

Sodium Chromates 0 0 0

Hydrazine 0 0 0

Carbohydrazide 0 0 0

Methyl Ethyl Ketone

0 0 0

Spent Abrasive Blast Material (contaminated with a known hazardous waste)

0 0 0

Trichloroethane 0 0 0

Miscellaneous Chemicals (Ignitable)

0 0 0

Miscellaneous Chemicals (Corrosive)

0 0 0

Miscellaneous Chemicals (TCLP Toxic)

0 0 0

Miscellaneous Chemicals (Reactive)

0 0 0

Oil (Synthetic) 0 0 0

Paints (Enamel, Latex, Epoxy, thinners, oil based, rubber paint, nonskid, lacquer, remover, varnishes

0 0 0

Paints (May include lead, cadmium, or chrome)

0 0 0

Paint Strippers 0 0 0

SSP: SERM-NSKD-27-0001 4 of 5 ITEM NO: 998-41-001

(phenols, lead, chromium)

Sludge (Contaminated with a known hazardous waste)

0 0 0

Wool Felt (contaminated with chromium and PCB's)

0 0 0

Ventilation Debris/Residue (heavy metals, e.g., cadmium, chromium)

0 0 0

Human Waste 0 0 0

Bilge Water 0 0 0

3.6 Notify the SUPERVISOR at least one working day prior to shipment of hazardous waste for disposal.

3.7 Submit one legible copy, in hard copy or approved transferrable media, of a report identifying type, amount, and disposal cost of waste listed in 3.5 that was removed during the performance of this Job Order to the SUPERVISOR.

3.7.1 The report must include analysis or other method used to identify the waste and state whether each listed waste was hazardous (with generator assignment), non-hazardous, or did not exist.

3.7.1.1 Chemical analysis must be accomplished by a laboratory with a state or EPA approved quality assurance program.

3.7.2 The contractor must make an effort to minimize hazardous waste generation by reducing the volume or toxicity by neutralizing, recycling, or otherwise removing it from the requirements of Subtitle C of 2.1 and include a description of such efforts in the report.

4. NOTES:

4.1 The waste listed in 3.5 is based on the best information available at the time of preparation of the solicitation. Hazardous waste generated during the actual performance of the work may vary in type or amount from waste listed in 3.5 which may result in renegotiation for credit or increase pursuant to Paragraph (b) of 2.4. The contractor is expected to use best management practice to identify and dispose of all hazardous waste. Some of the substances listed in 3.5 may be neutralized, recycled, or otherwise removed from the requirements of Subtitle C of

2.1. Inclusion of these substances in the waste listed in 3.5 does not preclude the contractor from taking action consistent with 2.1 to reduce or eliminate the hazardous constituents of any waste required to be disposed of under the contract in accordance with 2.2. Processes that add hazardous constituents to the bilges may require that bilge water be disposed of as a hazardous waste.

4.1.1 The types and amounts of wastes listed in 3.5 are estimates of waste to be disposed of under this contract as required by 2.4. They are not estimates of the amount of the work involved in generating

SSP: SERM-NSKD-27-0001 5 of 5 ITEM NO: 998-41-001 that waste. The work requirements of each individual Work Item specify the actual work to be accomplished.

4.2 Hazardous wastes are determined by one or more of the following methods:

4.2.1 Chemical analysis which shows that the material

characteristics of ignitability, corrosivity, reactivity, and/or toxicity (Toxicity Characteristic Leachate Procedure - TCLP) exceed the limits for that material in 40 CFR 261.20 Subpart C.

4.2.2 Reference to a Material Safety Data Sheet (MSDS).

4.2.3 Applying knowledge of the hazardous characteristics of the waste in light of the materials or the process used.

4.3 Asbestos, bilge water, oil/water including sludge, debris and other contaminants, sludge which includes solids and sludge from ballast tanks, CHT tanks, voids, oily waste tanks, fuel ballast tanks, fuel oil tanks, skegs (West coast), PCB's (Maryland), etc., apply only in those states listing them as hazardous waste. When an availability is to be performed in a state where these items are hazardous waste, an estimate of the amount to be generated must be included in 3.5.

4.4 Nothing contained in this Work Item must relieve the contractor from complying with applicable federal, state, and local laws, codes, ordinances, and regulations, including the obtaining of licenses and permits in connection with hazardous waste handling and disposal in the performance of this contract.

5. GOVERNMENT FURNISHED MATERIAL (GFM):

5.1 LLTM:

1. None.

5.2 PUSH MATERIAL:

1. None.