This is a Statement of Work (SOW) for nonskid replacement services on the LCS Freedom Class under SERMC Notional IDIQ Activity (RMC 4002), issued as Errata No. One to Item No. 634-11-003. The work encompasses replacement of nonskid surfaces across fourteen distinct ship locations including the Flight Deck, Airborne Mission Zone, Forecastle, Boat Deck, Passageway, Waterborne Mission Zone, Reconfigurable Mission Spaces, Mission Ordnance Magazines, and multiple bridge and frame areas.
The contractor must accomplish surface preparation and nonskid application per requirement 009-032, including water jetting to various MIL-PRF-24667 specifications and compositions depending on location: TYPE V COMP G for Flight Deck and Airborne Mission Zone (requirements 3.2 and 3.5); TYPE IV spray-on COMP G for Airborne Mission Zone and Forecastle through Waterborne Mission Zone (requirements 3.3 and 3.4); TYPE I COMP G for Reconfigurable Mission Spaces (requirement 3.6); and TYPE XI COMP PS for Reconfigurable Mission Spaces through bridge areas (requirements 3.7 and 3.8). For all locations, the contractor must provide diagrams identifying equipment to be excluded from nonskid coverage (tie-downs, Baxter Bolts, pad eyes, lights, drains, nozzles) and coordinate deck markings via chalk lines with NAVAIR Field Office verification 24 hours prior to color application. Additional requirements include conducting a pre-performance meeting with Ship's Force Point of Contact 48 hours before work commencement, performing operational testing of gravity drain piping per requirement 009-071, and conducting final visual inspection of treated decks. No government-furnished materials are provided; the contractor supplies all materials and labor.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Solicitation Amendment N4002727R00040002.pdf | ||
| J-2 NONSKID ELINS ORDERING PERIODS 1 THROUGH 5 (REV 1).xlsx | XLSX spreadsheet | |
| Solicitation Amendment N4002727R00040001.pdf | ||
| EXHIBIT A DD FORM 1423 2.pdf | ||
| Solicitation - N4002727R0004.pdf | ||
| J-2 NONSKID ELINS ORDERING PERIODS 1 THROUGH 5.xlsx | XLSX spreadsheet | |
| S-1 Request for Specification Clarification.docx | DOCX document | |
| J-1 NOTIONAL WORK ITEMS.pdf | ||
| EXHIBIT A DD FORM 1423 3.pdf | ||
| EXHIBIT A DD FORM 1423 4.pdf | ||
| EXHIBIT A DD FORM 1423 1.pdf |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SHIP: SERMC NOTIONAL IDIQ ACTIVITY
(RMC 4002)
ITEM NO: 634-11-003 (E1)
COAR: 26 PCN: SERV-L109
CMP: NONE
PLANNER: LAYNE, DERICK
SSP: SERM-NSKD-27-0001 1 of 3 ITEM NO: 634-11-003 ERRATA NO. One
1. SCOPE:
1.1 Title: Nonskid; replace (LCS Freedom Class - IDIQ)
1.2 Location of Work:
1.2.1 (As Per Delivery Order) Flight Deck
1.2.2 (As Per Delivery Order) Airborne Mission Zone (1-36-01-Q)
1.2.3 (As Per Delivery Order) Forecastle
1.2.4 (As Per Delivery Order) Boat Deck and Passageway (1-34-4-Q)1- 31-4-Q)
(E1)
1.2.5 (As Per Delivery Order) Waterborne Mission Zone (3-65-0-Q)
1.2.6 (As Per Delivery Order) Reconfigurable Mission Space One (3- 45-0-Q)
1.2.7 (As Per Delivery Order) Reconfigurable Mission Space 2 (3-54- 0-Q)
1.2.8 (As Per Delivery Order) Mission Ordnance Magazine One (1-38-0- M)
1.2.9 (As Per Delivery Order) Mission Ordnance Magazine 2 (1-38-2-M)
1.2.10 (As Per Delivery Order) 01 Level Port and Starboard Bridge Wings
1.2.11 (As Per Delivery Order) 02 Level Frame 21-26
1.2.12 (As Per Delivery Order) 02 Level Frame 40 – 45
1.2.13 (As Per Delivery Order) 02 Level Frame 45 – 56
1.2.14 (As Per Delivery Order) 03 Level Frame 23-41
1.3 Identification:
1.3.1 Not Applicable.
2. REFERENCES:
2.1 Standard Items
3. REQUIREMENTS:
3.1 Conduct a meeting with Ship’s Force Point of Contact (SFPOC) 48 hours prior to the Period of Performance (POP) start date to coordinate a schedule for accomplishing the work of each space listed on the Delivery Order.
3.2 Accomplish the requirements of 009-032 of 2.1, including Table 2, Line 9, (Water Jetting), for MIL-PRF-24667 TYPE V, COMP G, for each deck surface in the location listed in 1.2.1 and 1.2.2.
3.2.1 Provide a diagram showing equipment which must not be covered by nonskid, including but not limited to each tie-down, Baxter Bolt, pad eye, light, deck drain, and water wash down nozzle.
(V)(G) "VISUAL INSPECTION OF AVIATION DECK MARKINGS"
SHIP: SERMC NOTIONAL IDIQ ACTIVITY (RMC 4002)
SSP: SERM-NSKD-27-0001 2 of 3 ITEM NO: 634-11-003 ERRATA NO. One
3.2.2 Each deck marking must be laid out with chalk lines. Contact the local NAVAIR Field Office via the SUPERVISOR, 24 hours prior, for verification of each VLA and AVCERT deck marking prior to application of color topping.
3.3 Accomplish the requirements of 009-032 of 2.1, including Table 2, Line 9, (Water Jetting), for MIL-PRF-24667 TYPE IV (spray on), COMP G, for the deck surface in the location listed in 1.2.2.
3.3.1 Provide a diagram showing equipment which must not be covered by nonskid, including but not limited to each tie-down, Baxter Bolt, pad eye, deck drain, and water wash down nozzle.
(V)(G) "VISUAL INSPECTION OF AVIATION DECK MARKINGS"
3.3.2 Each deck marking must be laid out with chalk lines. Contact the local NAVAIR Field Office via the SUPERVISOR, 24 hours prior, for verification of each VLA and AVCERT deck marking prior to application of color topping.
3.4 Accomplish the requirements of 009-032 of 2.1, including Table 2, Line 21, (Water Jetting), for MIL-PRF-24667 TYPE IV (spray on), COMP G, for each deck surface in the location listed in 1.2.3 through 1.2.5.
3.4.1 Provide a diagram showing equipment which must not be covered by nonskid, including but not limited to each tie-down, Baxter Bolt, pad eye, light, deck drain, and water wash down nozzle.
3.5 Accomplish the requirements of 009-032 of 2.1, including Table 2, Line 21, (Water Jetting), for MIL-PRF-24667 TYPE V, COMP G, for each deck surface in the location listed in 1.2.3 through 1.2.5.
3.5.1 Provide a diagram showing equipment which must not be covered by nonskid, including but not limited to each tie-down, Baxter Bolt, pad eye, light, deck drain, and water wash down nozzle.
3.6 Accomplish the requirements of 009-032 of 2.1, including Table 2, Line 21, (Water Jetting), for MIL-PRF-24667 TYPE 1, COMP G, for each deck surface in the location listed in 1.2.6 and 1.2.7.
3.6.1 Provide a diagram showing equipment which must not be covered by nonskid, including but not limited to each tie-down, Baxter Bolt, pad eye, light, deck drain, and water wash down nozzle.
3.7 Accomplish the requirements of 009-032 of 2.1, including Table 2, Line 22, (Water Jetting), for MIL-PRF-24667 TYPE XI, COMP PS, for each deck surface in the location listed in 1.2.6 through 1.2.9.
3.7.1 Provide a diagram showing equipment which must not be covered by nonskid, including but not limited to each tie-down, Baxter Bolt, pad eye, deck drain, and water wash down nozzle.
3.8 Accomplish the requirements of 009-032 of 2.1, including Table 2, Line 61, (Water Jetting), for MIL-PRF-24667 TYPE XI, COMP PS, for each deck surface in the location listed in 1.2.10 through 1.2.14.
3.8.1 Provide a diagram showing equipment which must not be covered by nonskid, including but not limited to each tie-down, Baxter Bolt, pad eye, deck drain, and water wash down nozzle.
3.9 Accomplish the requirements of 009-071 of 2.1, for an operational test of gravity drain piping for unobstructed flow.
SHIP: SERMC NOTIONAL IDIQ ACTIVITY (RMC 4002)
SSP: SERM-NSKD-27-0001 3 of 3 ITEM NO: 634-11-003 ERRATA NO. One
(V)(G) "FINAL INSPECTION"
3.10 Accomplish a final visual inspection for each deck receiving new nonskid.
4. NOTES:
4.1 Ship’s Force Point of Contact shall be identified in each delivery order.
5. GOVERNMENT FURNISHED MATERIAL(GFM):
5.1 LLTM:
1. None.
5.2 PUSH MATERIAL:
1. None.
5.3 KITTED MATERIAL:
1. None.