N33191-R-15-0403_CLIN_02.pdf
PDF 267 KB Posted
- Solicitation number
- N33191-15-R-0403
About this file
N33191-15-R-0403 CLIN 02 - SPEC
View the file
Other files
Show all 24
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation
APPROPRIATION: eSRM
BUILDING 61 NET ZERO FACILITY
At the
NSA SOUDA BAY, CRETE, GREECE
Project Number:1371339 (RM13-3002)
SUBMITTED BY:
FEAD/PWD Souda Bay
PSC 814 BOX 572
FPO AE, 09865
PREPARED BY:
MM GROUP CONSULTING ENGINEERS
APPROVED BY:
FEAD Director NSA Souda Bay, LT Andres Espinosa For Commander, NAVFAC EURAFSWA:
Date: July, 25, 2015
Date: July 8, 2015
9/16/2015 N33191-R-15-0403 CLIN 02 Page 1 of 78
BUILDING 61 ENERGY IMPROVEMENTS
NSA Souda, Crete, Greece
Small Project Table of Contents
Part 1 Proposal Forms and Documents
Part 2 General Requirements
Attachment A: Project-Specific Requirements
Part 3 Statement of Work / Project Program
Part 4 Minimum Materials, Engineering and Construction Requirements
Part 5 Prescriptive Technical Specifications
Part 6 Attachments
Preface
This Request for Proposal (RFP) consists of six parts.
Part 1 contains typical contractual forms, procedures, bidding instructions, bond information, clauses and wage decisions.
Part 2 contains general contract administrative and execution requirements including, but not limited to safety, design criteria & process, quality control, security, schedule, invoicing, temporary facilities, and design and construction oversight processes.
Part 2, Attachment A, contains project-specific general requirements that may either modify and/or supplement the corresponding standard paragraphs in the Part 2 "General Requirements" section.
Part 3 lists the project requirements, specific scope items, and expected quality level above and beyond those outlined in Part 4.
Part 4 contains Performance Specifications and minimum quality requirements.
Part 5, prescriptive specifications, is typically not used in this Small Project format.
Part 6 contains background project information, references, and other project-specific requirements.
9/16/2015 N33191-R-15-0403 CLIN 02 Page 2 of 78
Building 61 Net Zero Facility
SMALL PROJECT TEMPLATE - PART 1 PROPOSAL FORMS AND DOCUMENTS - Page 1
Part 1 Proposal Forms and Documents
Part 1 contains typical contractual procedures, bidding instructions, bond information, clauses and wage decisions. The Contract Specialist develops Part 1 in SPS.
9/16/2015 N33191-R-15-0403 CLIN 02 Page 3 of 78
SMALL PROJECT TEMPLATE - PART 2 GENERAL REQUIREMENTS - Page 1
Part 2 General Requirements
PART 2
GENERAL REQUIREMENTS
4/14
Table of Contents
1.0 DEFINITIONS
2.0 ORDER OF PRECEDENCE
3.0 POST AWARD KICKOFF MEETING (PAK)
4.0 DESIGN
5.0 FIRE PROTECTION AND LIFE SAFETY REQUIREMENTS
6.0 QUALITY CONTROL
7.0 SUBMITTAL PROCESS
8.0 SUPERVISION
9.0 SCHEDULE
10.0 BUDGET MANAGEMENT
11.0 PRECONSTRUCTION CONFERENCE
12.0 ACCESSIBILITY
13.0 CONTRACTOR'S PRODUCTION REPORTS
14.0 SCHEDULE OF PRICES
15.0 CONTRACTOR INVOICES
16.0 PROTECTION OF GOVERNMENT PROPERTY
17.0 EXISTING UNDERGROUND UTILITIES
18.0 LICENSES / PERMITS
19.0 CONTRACTOR WORK SITE
20.0 TEMPORARY UTILITIES
21.0 ENVIRONMENTAL CONTROLS AND PROTECTION
22.0 WASTE MANAGEMENT
23.0 RECORD DRAWINGS AND OPERATION & MAINTENANCE (O&M) DATA
24.0 WARRANTY
25.0 PERFORMANCE EVALUATIONS
26.0 WORK HOURS, ACCESS AND PASSES
27.0 SECURITY REQUIREMENTS
28.0 REQUIRED INSURANCE
29.0 PROPRIETARY RIGHTS
30.0 GOVERNMENT FURNISHED MATERIAL AND EQUIPMENT
31.0 ORAL MODIFICATION
32.0 NO WAIVER BY THE GOVERNMENT
33.0 EQUITABLE ADJUSTMENTS - WAIVER AND RELEASE OF CLAIMS
34.0 SAFETY AND OCCUPATIONAL HEALTH REQUIREMENTS
9/16/2015 N33191-R-15-0403 CLIN 02 Page 4 of 78
SMALL PROJECT TEMPLATE - PART 2 GENERAL REQUIREMENTS - Page 2
1.0 DEFINITIONS
As used throughout the contract, the following terms shall have the meaning set forth below:
Contracting Officer (KO): The individual designated to administer the contract.
Throughout this contract this individual will be responsible and possess the authority to act on behalf of the Government with respect to the specific contract.
Contracting Officer Representative (COR): The individual designated by the Contracting Officer as the authorized representative of the Contracting Officer. The COR is responsible for monitoring performance and technical management of the effort required and should be contacted regarding questions or problems of a technical nature.
Contractor: The term Contractor refers to both the prime Contractor and subcontractors, including the Designer of Record.
Designer of Record (DOR): Licensed architect/engineer working as subcontractor to or partner with prime Contractor who provides design for this contract.
Quality Control (QC): Contractor's system to control the quality of design, material, equipment and construction.
Quality Assurance (QA) Program: Government's program to evaluate the effectiveness of the Contractor's quality control. The Government's QA Program is not a substitute for the Contractor's QC Program.
Federal Holidays: New Year's Day, Martin Luther King Jr. Day, President's Day, Memorial Day, Independence Day; Labor Day, Columbus Day, Veterans Day, Thanksgiving Day, and Christmas Day.
Contract: Contract or task order.
2.0 ORDER OF PRECEDENCE
NFAS Clause 5252.236-9312. In the event of conflict or inconsistency between any of the below described portions of the confirmed contract, precedence shall be given in the following order:
a. Any portions of the proposal or final design that exceed the requirements of the solicitation..
1) Any portion of the proposal that exceeds the final design.
2) Any portion of the final design that exceeds the proposal.
3) Where portions within either the proposal or the final design conflict, the portion that most exceeds the requirements of the solicitation has precedence.
b. The requirements of the solicitation, in descending order of precedence:
9/16/2015 N33191-R-15-0403 CLIN 02 Page 5 of 78
SMALL PROJECT TEMPLATE - PART 2 GENERAL REQUIREMENTS - Page 3
1) Standard Form 1442, Price Schedule, and Davis Bacon wage rates.
2) Part 1 - Contract Clauses.
3) Part 2 - General Requirements.
4) Part 3 - Statement of Work/Project Program Requirements.
5) Part 6 - Attachments (excluding Concept Drawings).
6) Part 5 - Prescriptive Specifications, exclusive of performance specifications.
7) Part 4 - Minimum Materials, Engineering and Construction Requirements, exclusive of prescriptive specifications.
8) Part 6 - Attachments (including Concept Drawings).
3.0 POST AWARD KICKOFF MEETING (PAK)
Prior to commencement of design, and within 21 calendar days of award, meet with representatives of the Contracting Officer, installation and client to present the concept design for discussion and acceptance. The project team will develop a mutual understanding relative to the approved proposal, safety program, environmental permits and requirements, quality control procedures, and design and construction schedule.
During the meeting, Contractor shall propose and gain acceptance for any critical path work activities requiring advance submittal and approval. If the contract includes work on any fire protection system, including fire alarm and mass notification systems, the Contractor and the appropriate DOR shall meet with the NAVFAC Fire Protection Engineer (FPE) to establish clear expectations of fire protection requirements of the project.
The Contractor's key personnel shall attend at the expense of the Contractor. Key personnel are defined as the Project Manager, Superintendent, CQC representative(s), Safety Manager, DOR, major subcontractors and specialized supplementary personnel.
The PAK includes partnering, held during normal work hours with the non-labor -related costs shared by both parties. Partnering is a structured process, as well as philosophy of doing business with Contractors and clients that recognizes common goals through communication and teamwork. It helps create an environment where trust and teamwork prevent disputes, foster good working relationships to everyone's benefit, and facilitate the completion of a successful contract. If included in Attachment A, a Performance Assessment Plan that provides monthly performance feedback to the Contractor, will be discussed during the partnering session.
Key personnel will meet to identify strategies to ensure the project is carried to expeditious closure and turnover to the Client. Start the turnover process at the PAK Meeting utilizing the NAVFAC Red Zone (NRZ) Checklist and convene the Facility Turnover Meetings once the project has reached approximately 75% completion or 3 to 6 months prior to Beneficial Occupancy Date (BOD), whichever comes first. The Contracting Officer's Representative will lead the meetings and guide the discussions based on an agenda provided by the Government. The Facility Turnover effort shall fill
9/16/2015 N33191-R-15-0403 CLIN 02 Page 6 of 78
SMALL PROJECT TEMPLATE - PART 2 GENERAL REQUIREMENTS - Page 4 in the NRZ Checklist including Contractor, Client, and NAVFAC Checklist Items and assign a person to be responsible for each item and a due date. The Contracting Officer's Representative will facilitate the assignment of responsibilities and fill out the NRZ Checklist. The Contracting Officer's Representative shall develop a Plan of Action and Milestones (POAM) for the completion of all Contractor, Client, and NAVFAC Checklist items.
4.0 DESIGN
Design is the work necessary to ensure functionality, quality, and safety for critical facets of the project. Special coordination requirements, such as for phone, LAN and cable, are included in Attachment A.
a. Provide work in compliance with the following design standards and codes, as a minimum. Government standards listed in this RFP take precedence over industry standards.
b. This RFP references published standards, the titles of which can be found in the Unified Master Reference List (UMRL)on the Whole Building Design Guide at the Unified Facilities Guide Specification (UFGS) Website. The publications referenced form a part of this specification to the extent referenced.
The advisory provisions of all codes, requirements, and standards shall be mandatory; substitute words such as "must" or "required" for words such as "shall", "should", "may", or "recommended," wherever they appear. The results of these wording substitutions incorporate these code and standard statements as requirements. Reference to the "authority having jurisdiction" shall be interpreted to mean Contracting Officer or Contracting Officer Representative.
Comply with the required and advisory portions of the current edition of the standard at the time of contract solicitation.
The following list of codes and standards is not comprehensive and is augmented by other codes and standards referenced and cross-referenced in the RFP. Refer to Parts 3 and 4 for specific requirements within other UFC's.
1) UFC 1-200-01, General Building Requirements
2) UFC 1-300-08, Criteria for Transfer and Acceptance of Military Real Property
3) FC 1-300-09N Navy and Marine Corps Design Procedures
4) UFC 3-560-01, Electrical Safety, O&M
5) UFC 3-600-01, Fire Protection Engineering for Facilities
6) UFC 1-200-02 High Performance and Sustainable Building Requirements
7) UFC 3-800-10N, Environmental Engineering for Facility Construction
8) UFC 4-010-01, DoD Minimum Antiterrorism Standards for Buildings
9/16/2015 N33191-R-15-0403 CLIN 02 Page 7 of 78
SMALL PROJECT TEMPLATE - PART 2 GENERAL REQUIREMENTS - Page 5
9) UFC 4-020-01, Security Engineering: Facilities Planning Manual
c. Part 3 contains the project description, functional and performance requirements, scope items, and expected quality levels that exceed Part 4. Part 4 identifies design criteria, verification requirements, and performance and quality requirements of products. See "Order of Precedence" paragraph in Part 2 for relationships between all parts of this RFP.
d. Provide professional registration and design signing and stamping requirements per requirements of FC 1-300-09N Navy and Marine Corps Design Procedures.
e. See Attachment A for project-specific submittal requirements.
f. Meet sustainability requirements per UFC 1-200-02 High Performance and Sustainable Building requirements and UFGS section 01 33 29.05 20 Sustainability Requirements for Design Build.
5.0 FIRE PROTECTION AND LIFE SAFETY REQUIREMENTS
Work shall comply with applicable criteria identified herein and Attachment A. Any project including work on means of egress, fire rated elements, Fire Suppression, Mass Notification, or Fire Alarm Systems shall require the services of a Registered Fire Protection Engineer per Attachment A.
a. Final Life Safety/Fire Protection Certification Documentation: Unless otherwise specified in Attachment A, provide certification that all life safety and fire protection features and systems have been installed in accordance with applicable criteria, the contract documents, approved submittals, and manufacturer's requirements. This certification shall summarize all life safety and fire protection features.
6.0 QUALITY CONTROL
Maintain quality control for and inspect all work under the contract. The DOR, as a member of the Contractor QC organization, shall remain directly involved during the construction process. For certain projects, the Quality Control Manager, Superintendent, and Site Safety and Health Officer may be combined - see paragraphs 6 and 34 in Attachment A. Further QC requirements are identified in Attachment A.
a. Submit a QC Plan for Government review and acceptance. The QC plan shall include the following:
1) NAMES, QUALIFICATIONS and RESPONSIBILITIES: For each person in the QC organization (design and construction).
2) OUTSIDE ORGANIZATIONS: Outside organizations, including architectural and consulting engineering firms and a description of the services these firms will provide.
3) INITIAL SUBMITTAL REGISTER (DESIGN & CONSTRUCTION): Include submittal reviewer, estimated date of delivery, and identify which design submittals require Government approval prior to construction, and which
9/16/2015 N33191-R-15-0403 CLIN 02 Page 8 of 78
SMALL PROJECT TEMPLATE - PART 2 GENERAL REQUIREMENTS - Page 6 construction submittals require DOR or Government approval prior to construction.
4) TESTING LABORATORIES: Accredited laboratories as applicable.
5) TESTING PLAN AND LOG: Tests required, referenced by specification paragraph number requiring the test, frequency, and person responsible for each test.
6) LIST OF DEFINABLE FEATURES: A Definable Feature of Work (DFOW) is a task, which is separate and distinct from other tasks, and has the same control requirements and work crews.
7) COMMUNICATION PLAN: Provide a plan for key decisions and possible problems the Contractor and Government may encounter during the design phase of the project. Communication Plan shall indicate the frequency of design meetings and what information is covered in those meetings, key design decision points tied to the Network Analysis Schedule and how the DOR plans to include the Government in those decisions, peer review procedures, interdisciplinary coordination, design review procedures, and comment resolution.
b. QC Manager Responsibilities:
1) Participate in the Post Award Kick-off, Partnering, Design Development and Coordination Meetings and Production Meetings.
2) Ensure that no construction begins before the DOR has signed and stamped the design for that segment of work, and design and construction submittals are approved as required in Attachment A and the QC Plan.
3) Immediately stop any work that does not comply with contract plans and specifications, and direct the removal and replacement of any defective work.
4) Prepare QC Reports.
5) Hold biweekly or as required by the Contracting officer, QC meetings with DOR, Superintendent and Government technical team; participation shall be suitable for the phase of work.
6) Ensure that safety inspections are performed. Attend weekly Toolbox meetings.
7) Maintain submittal log.
8) Maintain updated as-built drawings on site.
9) Maintain testing plan and log. Ensure that all testing is performed per contract.
10) Maintain deficiency log on site, noting dates deficiency identified, and date corrected.
9/16/2015 N33191-R-15-0403 CLIN 02 Page 9 of 78
SMALL PROJECT TEMPLATE - PART 2 GENERAL REQUIREMENTS - Page 7
11) Certify and sign statement on each invoice that all work to be paid under the invoice has been completed in accordance with contract requirements.
12) Perform Punch-out and Pre-final inspections, and participate in Final Inspections. Establish list of deficiencies; correct prior to the Final inspection.
13) Ensure that all required keys, operation and maintenance manuals, warranty certificates, and the As-built drawings are submitted to the Contracting Officer.
14) If Commissioning is part of work, engage Commissioning Authority (CxA), coordinate their oversight of Contractor's work and verify CxA's performance in accordance with UFGS section 01 45 00.05 20.
c. Use the Three Phases of Control process for construction QC.
1) Preparatory Phase: Review all applicable documents for compliance with all applicable laws, codes, regulations, and the requirements of the contract, including contract drawings and specifications. Determine requirements for testing and certification. Review submittal approvals for materials, equipment, shop drawings, and applicable methods of construction and installation. Include all Preparatory Phase items in the QC Report.
2) Initial Phase: Observe and inspect the initial portion of the work performed under a DFOW to establish the quality of the workmanship, resolve conflicts in construction, ensure that testing is done and certified as required, and to check all work procedures to ascertain the work is in conformance with required safety requirements. Record and report nonconforming work and work not of acceptable quality and requiring correction or rework. Include all Initial Phase items, along with initial phase checklist and, in the QC Report.
3) Follow-Up Phase: Occurs at the completion of each DFOW. Ensure the work is in compliance with contract requirements, quality of workmanship for all work is maintained, and all work performed meets safety requirements. Include all Follow-Up Phase items, including date, in the QC Report.
d. The QC Manager must possess a current certificate showing successful completion of the NAVFAC Contractor Quality Management (CQM) Training.
7.0 SUBMITTAL PROCESS
Provide to the Government submittals as listed. See Paragraph 4, DESIGN, and Attachment A for specific design and construction submittal format and approval and surveillance requirements. Design drawings may be prepared more like shop drawings to minimize construction submittals after final designs are approved. Therefore, the Contractor is encouraged to prepare and submit with the design drawings, appropriate connection, fabrication, layout, and product specific drawings.
a. QC Plan, prior to Design/Construction, may be phased.
b. Design and construction submittals, prior to construction, approved IAW QC
9/16/2015 N33191-R-15-0403 CLIN 02 Page 10 of 78
SMALL PROJECT TEMPLATE - PART 2 GENERAL REQUIREMENTS - Page 8
Plan, the DOR or QC Specialist is the approving authority for submittals unless otherwise indicated in Attachment A.
c. Sustainability Action Plan in accordance with UFGS 01 33 29.05 20 Sustainability Requirements
d. DOR-approved design and construction submittals identified in Attachment A for Government surveillance (typically Fire Protection system TAB and Life Safety submittals). Stamp the submittals "FOR SURVEILLANCE ONLY." Submit Surveillance submittals to the Government prior to starting work for that item.
Submittals required for surveillance will be returned only if corrective actions are required.
e. Material Safety Data Sheets (MSDS) as applicable.
f. Schedule: Provide detailed design schedule and preliminary construction schedule, due prior to PAK.
g. Environmental Protection Plan, prior to start of the work.
h. Contractor Safety Self-Evaluation Checklist.
i. Accident Reports - submit if incidence occurs.
j. Safety Submittals: Per Paragraph 34 and Attachment A, prior to construction.
k. Schedule of Prices, initial due 21 calendar days after award and a detailed due prior to construction.
l. Budget Management Summary: Per Attachment A.
m. Record Drawings, due at Beneficial Occupancy
n. Operation and Maintenance Information: Per Paragraph 23, Part 2 Attachment A, and Part 4. Due prior to testing as applicable, no later than 30 calendar days before Beneficial Occupancy.
o. Licenses and Permits: Per Attachment A and Part 4.
p. DD Form 1354: For all new construction, demolition, and any construction on an existing facility that adds new parts, items, or systems that are not maintenance or repair; e.g. replacement of windows, replacement of roofs, replacement of an exterior utility, adding an AC system, adding exterior lighting, the DOR shall prepare DD Form 1354 TRANSFER AND ACCEPTANCE OF MILITARY REAL PROPERTY, in accordance with UFC 1-300-08, available at http://65.204.17.188/report/doc_ufc.html . Submit form for Government approval a minimum of 30 calendar days prior to final acceptance of work.
q. High Performance and Sustainable Building (HPSB) compliance checklists in accordance with UFC 1-200-02, High Performance and Sustainable Building Requirements.
9/16/2015 N33191-R-15-0403 CLIN 02 Page 11 of 78
SMALL PROJECT TEMPLATE - PART 2 GENERAL REQUIREMENTS - Page 9
8.0 SUPERVISION
The Contractor shall have a supervisor fluent in English on the job site during working hours. Additional requirements per Attachment A.
9.0 SCHEDULE
Provide Design and Construction Schedule adequate for Contractor to efficiently manage project and for Government to efficiently manage QA and scheduling interfaces. Include construction phasing and any work restrictions (such as occupied spaces, special hours, potential work disruptions). Schedule shall contain DFOWs and dates for completion of each task including material procurement, and construction activities. Update the schedule at least monthly; use 3-week look-ahead for each QC meeting.
10.0 BUDGET MANAGEMENT
The Contractor shall be responsible for budget management throughout the entire project. It is the intent of the Government to partner with the Contractor to maximize project value while strictly controlling contract modifications and maintaining overall fiscal control. When required in Attachment A, develop a Budget Management System for each phase of the design.
11.0 PRECONSTRUCTION CONFERENCE
Prior to construction or demolition start, meet with representatives of the Contracting Officer to discuss and develop mutual understanding relative to administration of the safety programs, environmental issues, safety of building occupants and surrounding area, hazardous materials, waste disposal, construction QC procedures, construction schedule, labor provisions and other construction phase contract procedures. The Preconstruction Conference shall reinforce partnering philosophy initially established during the PAK.
12.0 ACCESSIBILITY
Provide barrier-free design in accordance with UFC 1-200-01, General Building Requirements.
13.0 CONTRACTOR'S PRODUCTION REPORTS
Submit Contractor Production Reports on forms furnished for this purpose. Complete the reports weekly unless otherwise requested by the Contracting Officer. Reports shall include:
a. Worker hours by classification, move-on and move-off of construction equipment furnished by the prime, subcontractor or the Government, and materials and equipment delivered to the site.
b. Safety meetings, checks and inspections.
9/16/2015 N33191-R-15-0403 CLIN 02 Page 12 of 78
SMALL PROJECT TEMPLATE - PART 2 GENERAL REQUIREMENTS - Page 10
c. Disposition of Construction Waste Material: Per Waste Management Plan and per Environmental Protection Plan.
d. Design and Construction Services: Including, but not necessarily limited to:
1) Check all Contract Documents for correctness and correlation. If the Contractor notes any discrepancy or ambiguity, immediately notify the COR.
2) Examine the work site as to conditions affecting the work. Field verify the site and scope of work, including but not limited to the measurement and location of all significant items required to perform the work. Failure by the Contractor to familiarize oneself with available information regarding these conditions shall not relieve the Contractor from the responsibility of successfully completing the work.
14.0 SCHEDULE OF PRICES
Submit on forms furnished by the Government. The initial schedule of prices may be preliminary for construction activities until the design is developed. Include a detailed breakdown of the contract price, with quantities for each kind of work. Include General Conditions, profit, and overhead in the unit prices. Break down into design and each construction category if stated in Attachment A. The Contractor may invoice for bonds once the Government has approved the bonds, however, no other requests for payment will be processed without an approved Schedule of Prices.
15.0 CONTRACTOR INVOICES
Contractor requests for payment shall conform and will be processed in accordance with the requirements of FAR 52.232-5 and FAR 52.232-27.
a. Content of Invoice: Requests for payment in accordance with the terms of the contract shall consist of the following: (If NFAS Clause 5252.232-9301 is present in the contract, documents shall be provided as attachments in Wide Area Workflow (WAWF). The maximum size limit per attachment is less than 2 megabytes, but you may have an unlimited number of attachments. If a document cannot be attached to WAWF due to system or size restrictions it shall be provided as instructed by the contracting officer). If NFAS Clause
5252.232.9301 is not present in the contract, follow the invoicing instructions provided in the contract.
1) Contractor's Invoice on NAVFAC Form 7300/30, which shall show, in summary form, the basis for arriving at the amount of the invoice.
2) Contractor's Monthly Estimate for Voucher (LANTNAVFACENGCOM Form 4-4330/110 (New 7/84)), with subcontractor and supplier payment certification.
3) Affidavit to accompany invoice (LANTDIV NORVA Form 4-4235/4 (Rev. 5/81)).
4) Updated copy of submittal register.
5) Updated copy of progress schedule. Furnish as specified in "FAR 52.236-15, 9/16/2015 N33191-R-15-0403 CLIN 02 Page 13 of 78
SMALL PROJECT TEMPLATE - PART 2 GENERAL REQUIREMENTS - Page 11
Schedules for Construction Contracts."
6) Network mathematical analysis.
7) Contractor Safety Self Evaluation Checklist (original)
8) Final release (for final payment only)
b. Payment:
1) Payment will be made on Contractor's submission of itemized requests and will be subject to reduction for overpayments or increased for underpayments from previous payments. The Government may withhold payment or reduce payments for the following:
a) Defects in material or workmanship.
b) Claims the Government may have against the Contractor under or in connection with this contract.
c) Contractor's failure to submit an updated schedule.
d) Payroll violations.
e) Unless otherwise adjusted, repayment to the Government upon demand for overpayments made to the Contractor.
2) Payments may be made for materials, stored off construction sites, under the following conditions:
a) Conditions described in Attachment A.
b) Materials adequately insured and protected from theft and exposure.
c) Materials not susceptible to deterioration or physical damage in storage or in transit to the job site are acceptable for progress payments. Items such as steel, machinery, pipe and fittings and electrical cable are acceptable, but items such as gypsum board; glass, insulation and wall covering are not.
d) Materials in transit to the job or storage site are not acceptable for payment.
e) Conditions specified in FAR 52.232-5(b) Payments Under Fixed Price Construction Contracts.
16.0 PROTECTION OF GOVERNMENT PROPERTY
Take special care to protect Government property. Return areas damaged as a result of construction under this contract to their original condition. In addition to FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements, perform the following:
9/16/2015 N33191-R-15-0403 CLIN 02 Page 14 of 78
SMALL PROJECT TEMPLATE - PART 2 GENERAL REQUIREMENTS - Page 12
a. Remove or alter existing work or facilities in such a manner as to prevent injury or damage to any portion of the existing work or facilities that remain.
b. Repair or replace portions of existing work altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work shall be in a condition equal to or better than that which existed before new work started.
c. Preserve the natural resources in accordance with the approved environmental protection plan.
17.0 EXISTING UNDERGROUND UTILITIES
Verify on-site utilities and have them marked out by a utility locator service prior to the start of construction. Where existing piping, utilities, oil and gas lines, and underground obstructions of any type that are to remain are indicated in locations to be traversed by new piping, ducts, and other work provided herein, and such are not indicated or specified to be removed, the elevations of the existing utilities and obstructions shall be determined before the new work is laid closer than the nearest manhole or other structure at which an adjustment in grade could be made. Obtain required dig permits and notify the Contracting Officer 21 calendar days prior to any excavation. Refer to Attachment A for specific station requirements.
18.0 LICENSES / PERMITS
Obtain all appointments, licenses, and permits required to perform work under this contract at no additional expense to the Government. See "Permits Record of Decision" (PROD) form for list of permits. Comply with all applicable local laws, and base regulations and procedures. Provide evidence of such permits and licenses to the Contracting Officer before work commences and at other times as requested by the Contracting Officer (see FAR 52.236-7, Permits and Responsibilities). Coordinate permit applications with Navy or local environmental office.
The contractor shall submit a complete PROD form with the first design submittal package. A blank PROD form can be obtained at the Download Tab of Part 6 of the NAVFAC Design-Build website at the following link http://ndbm.wbdg.org/system/html/6/453 . Contractor shall determine correct permit fees and pay said fees. Copies of all permits, permit applications, and the completed PROD form shall be forwarded to the Government's Civil Reviewer and Environmental Reviewer.
Contractor is exclusively responsible for his full compliance with patent laws and shall affirm that the company is licensed to use equipment and processes the company shall employ in this project.
19.0 CONTRACTOR WORK SITE
Limit use of the premises for work and for storage of material and equipment associated with the contract. Unless otherwise specified or separately agreed to, Government owned material handling equipment, transportation equipment or general tools will not be
9/16/2015 N33191-R-15-0403 CLIN 02 Page 15 of 78
SMALL PROJECT TEMPLATE - PART 2 GENERAL REQUIREMENTS - Page 13 available for Contractor's use. Clean work area daily and after completion of the work, removing all loose debris and disposing of all non-permanent materials IAW the contractor's Waste Management Plan.
a. Temporary Facilities: The Contractor may provide his own office facilities;
coordinate and obtain advance approval from the Contracting Officer. Provide and maintain suitable sanitary facilities within the construction limits of the contract. Dispose of sanitary waste in accordance with the applicable laws, and local regulation.
b. Contractor-Furnished Equipment: Equipment is subject to the inspection and approval of the Contracting Officer, prior to and during the life of the contract. All equipment and vehicles shall display readily visible Contractor identification markings. Relocate stored Contractor equipment which may interfere with operations of the Government or with others on-site.
c. Contractor-furnished Material: Protect and secure products stored at this site.
1) All replacement units, parts, components, and materials to be used in the maintenance, repair and alteration of facilities and equipment shall be new and compatible with the existing equipment on which it is to be used, and shall comply with applicable local Government, commercial, or industrial standards as well as Underwriter's Laboratories, Inc., and National Electrical Manufacturers Association as applicable.
2) In addition, submit a current certificate recognized by the State or local authority that states the Contractor has completed at least 10 hours of training in backflow preventer installations.
20.0 TEMPORARY UTILITIES
a. The Government will provide water and power in reasonable quantities at the prevailing rates.
b. All labor, material, and equipment necessary to affect temporary utility tie-ins, including transformers if necessary, shall be at the expense of the Contractor and under the surveillance of the Contracting Officer.
c. The Contractor shall be responsible for any damages to Government, private or public facilities and property that may result from the installation and removal of these temporary utility tie-ins. Corrections and repairs shall be made at the Contractor's expense.
d. The actual location and installation of the temporary tie-in, together with any interruptions of utilities systems, shall be identified and approved by the Contracting Officer prior to execution. Notify the COR and Station Utilities 15 calendar days prior to any tie-ins.
e. Permanent utility systems, when indicated, will be available for tie-in.
9/16/2015 N33191-R-15-0403 CLIN 02 Page 16 of 78
SMALL PROJECT TEMPLATE - PART 2 GENERAL REQUIREMENTS - Page 14
f. Telephone and Data Service: Make arrangements with local telephone company, NMCI and other pertinent base communication departments.
g. Maintain utility services to existing facilities surrounding the site at all times during construction.
h. Contractor shall install and certify back flow preventers on all connections to the potable water supply system.
21.0 ENVIRONMENTAL CONTROLS AND PROTECTION
Unforeseen Hazardous Conditions: Do not disturb hazardous materials and report condition immediately to the Contracting Officer potentially hazardous conditions that are uncovered or the Contractor becomes aware of that have not been identified in the RFP.
This includes hazardous components and materials and contamination (see UFC 3-800-10N, Environmental Engineering for Facility Construction, for more information).
This includes conditions that are not only hazardous to humans but wildlife, marine life and the environment. Stop work in the area of the questionable material or condition until identification and direction is provided.
22.0 WASTE MANAGEMENT
Develop a Waste Management Plan that identifies all recyclable material and disposal methods for all material. Contractor shall reduce, recycle or salvage as much waste material as possible with a goal of diverting at least 50% of construction waste from landfill. Address waste reduction, recycling and salvage as part of the waste management plan. Report volume or weight of disposed and recycled materials to the Government.
Report destination of debris diverted from disposal. The Contractor is responsible for removing and disposing of all waste materials generated. Consider all material recyclable or reusable, unless clearly demonstrated the material requiring disposal is waste material.
23.0 RECORD DRAWINGS AND OPERATION & MAINTENANCE (O&M)
DATA
Furnish hard copy and electronic format for all as-built and O&M information. Record drawings shall incorporate all changes to the approved final design. Provide O&M data for as-built products, materials, and equipment, including data sheets, test reports, warranties, certificates, list of spare parts suppliers for all pieces of equipment, and approved construction submittals. Refer to Attachment A.
24.0 WARRANTY
Warrant all materials and work for not less than one year after final acceptance of the work, except as otherwise indicated in this RFP. If required to provide remedial repair of previously installed work due to latent defect or unacceptable work performance, warrant the repaired work for one year after the completion and acceptance of the repair. For
9/16/2015 N33191-R-15-0403 CLIN 02 Page 17 of 78
SMALL PROJECT TEMPLATE - PART 2 GENERAL REQUIREMENTS - Page 15 warranted items, furnish the manufacturers' original written warranty accompanied by a copy of the supplier's receipt showing place of purchase, telephone number of supplier, address, delivery order number if applicable, and ticket number.
25.0 PERFORMANCE EVALUATIONS
The evaluation will take into account all aspects of the Contractor's performance, including evaluations from Performance Assessment Plans when included in Attachment A. Performance evaluations may be completed any time during the contract. The Government will provide a copy of the performance evaluation and an opportunity to discuss the evaluation. The performance evaluations will have an impact on the award of future contracts.
26.0 WORK HOURS, ACCESS AND PASSES
All Contractor employees, including subcontractors, and subcontractors' employees, suppliers, and suppliers' employees shall be required to comply with the Installation Security Requirements regarding personnel, vehicle, and equipment security passes and access the jobsite. Nothing in the contract shall be construed in any way to limit the authority of the Commanding Officer to prescribe new, or to enforce existing security regulations governing the admission or exclusion of persons and the conduct of persons while aboard the station, including but not limited to, the rights of search of all persons or vehicles aboard the station.
Coordinate with the Contracting Officer for specific security and access requirements.
a. Access to Buildings/ Occupied Buildings: The Contractor may work in or around existing occupied buildings. The Contractor is responsible, via the Contracting Officer, to obtain access to building and facilities and arrange for them to be opened and closed. Do not enter the building(s) without prior approval of the Contracting Officer. Keep the existing buildings and their contents secure at all times. Provide temporary closures as required to maintain security. Contract personnel will not be permitted in security-regulated buildings or areas unless cleared by the Security Officer.
b. Passes and Badges: Contractor employees and representatives performing work under this contract are required to be either United States citizens or documented legal residents (status verified by prime contractor). All Contractor employees shall obtain the required employee and vehicle passes. Failure to obtain security and base access passes shall not be a cause for contract performance time extension. The Contractor shall immediately turn in all terminated employee's badges to the issuing office.
1) Personnel will be issued appropriate identification badges when the Contractor submits, in writing on company letterhead, a list indicating that all individuals are bona fide employees. Employees shall complete questionnaires and other forms as required for security. Allow 14 calendar days for background checks and processing. The list shall contain the following information:
a) Name of employee
9/16/2015 N33191-R-15-0403 CLIN 02 Page 18 of 78
SMALL PROJECT TEMPLATE - PART 2 GENERAL REQUIREMENTS - Page 16
b) Social Security Number
c) Date of Birth
d) Place of Birth
e) Citizenship, Statement of (U.S.) or proof of documented legal residency
f) Employment Eligibility Verification Form (DHS FORM I-9). This form is available at http://uscis.gov/graphics/formsfee/forms/files/I-9.pdf
c. Contractor Vehicles: All vehicles shall display a valid license plate and safety inspection sticker, if applicable, and shall be maintained in good repair. The company name shall be displayed in a clearly visible manner and size on each Contractor vehicle used in the course of work. Registration, proof of insurance and driver's licenses are required to obtain a station vehicle pass.
d. Work Hours: Unless otherwise indicated, work will be located on a Government compound, military installation, or station. Contractor work hours shall be between 0730 and 1630 Monday through Friday, or as indicated in Attachment A. Obtain advance approval from the Contracting Officer for Contractor personnel to remain on site beyond normal working hours. Notify the Contracting Officer at least 48 hours in advance to obtain approval for access to the jobsite or work outside of normal working hours or on Saturday, Sunday, and Federal Holidays.
e. Contractor Personnel: Provide the Contracting Officer the name(s) of the supervisory person(s) authorized to act for the Contractor. Provide, and update as required, a list of the key personnel for the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency.
f. Contractor employees shall conduct themselves in a proper, efficient, courteous and businesslike manner. Remove from the site any individual whose continued employment is deemed by the Contracting Officer to be contrary to the public interest or inconsistent with the best interests of National Security.
27.0 SECURITY REQUIREMENTS
All security requirements apply to all subcontractors and suppliers associated with this contract. Special or extraordinary security requirements are identified in Attachment A.
In addition to special or extraordinary security requirements, comply with the following:
a. Do not publicly disclose any information concerning any aspect of the materials or services relating to this contract, without prior written approval of the Contracting Officer.
b. Do not disclose or cause to be disseminated any information concerning the operations of the activity’s security or interrupt the continuity of its operations.
c. Do not disclose any information to any person not entitled to receive it. Failure
9/16/2015 N33191-R-15-0403 CLIN 02 Page 19 of 78
SMALL PROJECT TEMPLATE - PART 2 GENERAL REQUIREMENTS - Page 17 to safeguard any classified information that may come to the Contractor or any person under his control, may subject the Contractor, his agents or employees to criminal liability under 18 U.S.C., Sections 793 and 798.
d. Direct to the Contracting Officer and or Installation Security Officer for resolution all inquiries, comments or complaints arising from any matter observed, experienced, or learned as a result of or in connection with the performance of this contract, the resolution of which may require the dissemination of official information.
e. Coordinate photography requirements with the Contracting Office. All areas are prohibiting photographing without Government Escort.
Deviations from or violations of any of the provisions of this paragraph, will, in addition to all other criminal and civil remedies provided by law, subject the Contractor to immediate termination for default and withdrawal of the Government’s acceptance and approval of employment of the individuals involved.
28.0 REQUIRED INSURANCE
Within 15 calendar days after award, furnish the Contracting Officer a Certificate of Insurance as evidence of the following insurance coverage amounts not less than the amount specified below in accordance with FAR Clause 52.228-5, Insurance Work On A Government Installation:
a. Comprehensive General Liability: $500,000 per occurrence.
b. Automobile Liability: $200,000 per person, $500,000 per occurrence for bodily injury; $20,000 per occurrence for property damage.
c. Worker's Compensation: As required by Federal and State Worker’s compensation and occupational disease and other laws.
d. Employer’s Liability Coverage: $100,000, except in states where worker’s compensation may not be written by private carriers.
e. Others as required by state or host nation law.
f. Above insurance coverage’s are to extend to Contractor personnel operating Government owned equipment and vehicles.
g. The Certificate of Insurance shall provide for 30 calendar days written notice to the Contracting Officer by the insurance company prior to cancellation or material change in policy coverage. Other requirements and information are contained in Attachment A.
For projects which require removal of asbestos containing materials the Asbestos Contractor or Subcontractor, as the case may be shall provide occurrence-based liability
9/16/2015 N33191-R-15-0403 CLIN 02 Page 20 of 78
SMALL PROJECT TEMPLATE - PART 2 GENERAL REQUIREMENTS - Page 18 insurance with asbestos coverage’s in an amount not less than $1,000,000 and shall name the Government and PQP as additional insured’s.
29.0 PROPRIETARY RIGHTS
All field notes, design drawings, specifications, and other documents collected and produced as part of this contract shall be considered property of the Government. These data shall not be used, in whole or part, published or unpublished, as a part of any technical or non-technical presentation without written pre-approval of the Contracting Officer.
30.0 GOVERNMENT FURNISHED MATERIAL AND EQUIPMENT
If applicable, the Government will furnish the materials and equipment for installation by the Contractor pursuant to contract clause FAR 52.245-2, Government Property (Fixed Price Contracts). Notify the Contracting Officer in writing at least 15 calendar days before the materials and equipment are required. Pick up materials and equipment no later than 30 calendar days after such date. When materials and equipment are not picked up by the 30th day, the Contractor will be charged for storage at the prevailing rate. The Contracting Officer will specify the location of materials and equipment and the delivery location.
31.0 ORAL MODIFICATION
No oral statement by any person other than the Contracting Officer, as provided in the contract clause entitled, "CHANGES AND CHANGED CONDITIONS," will in any manner or degree modify or otherwise affect the terms of this contract.
32.0 NO WAIVER BY THE GOVERNMENT
The failure of the Government in any one or more instances to insist upon strict performance to any of the terms of this contract or to exercise any option herein conferred shall not be construed as a wavier or relinquishment to any extent of the right to assert or rely upon such terms or options on any future occasion.
33.0 EQUITABLE ADJUSTMENTS - WAIVER AND RELEASE OF
CLAIMS
a. Whenever the Contractor submits a claim for equitable adjustment under a clause which provides for equitable adjustment of the contract, such claim shall include all types of adjustments in the total amounts to which the clause entitles the Contractor, including, but not limited to, adjustment arising out of delays or disruptions.
b. Except as the parties may otherwise expressly agree, the Contractor shall be deemed to have waived: (1) any adjustments to which he otherwise might be entitled under the clause where such claim fails to request such adjustments; and
9/16/2015 N33191-R-15-0403 CLIN 02 Page 21 of 78
SMALL PROJECT TEMPLATE - PART 2 GENERAL REQUIREMENTS - Page 19
(2) any increase in the amount of equitable adjustments additional to those requested in its claim.
c. The Contractor agrees that, if required by the Contracting Officer, it shall execute a release, in form and substance satisfactory to the Contracting Officer, as part of the supplemental agreement setting forth the aforesaid equitable adjustment.
The Contractor further agrees that such release shall discharge the Government, including its officers, agents, and employees, from any further claims, including, but not limited to, further claims arising out of delays or disruptions caused by the aforesaid change.
34.0 SAFETY AND OCCUPATIONAL HEALTH REQUIREMENTS
a. References: The publications listed below form a part of this specification to the extent referenced. Use current version of referenced requirements at the time of contract solicitation. The publications are referred to within the text by the basic designation only.
AMERICAN NATIONAL STANDARDS INSTITUTE (ANSI)
ANSI Z359.1, Safety Requirements for Personal Fall Arrest System, Subsystems and Components ANSI A10.32, Fall Protection systems for Construction and Demolition Operations ANSI A10.6, Demolition Operations ANSI Z9.2, Fundamentals Governing the Design and Operation of Local Exhaust Systems ANSI Z88.2, Respiratory Protection ANSI Z358.1, Emergency Eyewash and Shower Equipment
ASME INTERNATIONAL (ASME)
ASME B30.22, Articulating Boom Cranes ASME B30.3, Construction Tower Cranes ASME B30.5, Mobile and Locomotive Cranes ASME B30.8, Floating Cranes and Floating Derricks
AMERICAN SOCIETY OF TESTING AND MATERIALS (ASTM)
ASTM Standards on Lead-Based Paint Abatement in Buildings ASTM E 1368, Visual Inspection of Asbestos Abatement Projects
DEPARTMENT OF DEFENSE (DoD) MIL-STD-1472F, Military Standard, Human Engineering Design Criteria for Military Systems, Equipment and Facilities DoD-HDBK 743A, Anthropometry of US Military Personnel
DEFENSE LOGISTICS AGENCY (DLA)
DLA 4145.25, Storage and Handling of Compressed Gases and Liquids in Cylinders
EPA Standards and Documents - General 15 U.S.C. 2601 - Toxic Substances Control Act EPA Title X - The Residential Lead Based Paint Hazard Reduction Act
9/16/2015 N33191-R-15-0403 CLIN 02 Page 22 of 78
SMALL PROJECT TEMPLATE - PART 2 GENERAL REQUIREMENTS - Page 20
EPA & HUD - Lead Safe Work Practices HUD Guidelines, Guidelines for the Evaluation and Control of Lead Based Paint Hazards in Housing
ENVIRONMENTAL FINAL GOVERNING STANDARDS FOR GREECE (FGS)
(May 2014)
NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)
NFPA 241, Safeguarding Construction, Alteration, and Demolition Operations NFPA 51B, Fire Prevention During Welding, Cutting, and Other Hot Work NFPA 70, National Electrical Code NFPA 70E, Electrical Safety in the Workplace
NSA SOUDA BAY STORMWATER POLLUTION PREVENTION PLAN (SWPPP)
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 Safety -- Safety and Health Requirements (2014 Edition)
UNITED FACILITIES CRITERIA (UFC)
UFC 3-560-01, Electrical Safety, O&M
U.S.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .