This service order describes routine maintenance requirements for two high pressure air compressors aboard the USNS Lewis and Clark. The contractor must provide a certified technician from the compressor manufacturer Sauer to perform a 2000-hour routine B maintenance on each compressor. This includes operational testing before and after maintenance is conducted. The contractor must replace any necessary components, document all work performed, and submit a service report to the Military Sealift Command. The location for the air compressors is in the auxiliary machinery room of the vessel. The solicitation number associated with the broader ship maintenance is N3220520R4091, issued by the Department of the Navy's Military Sealift Command for work aboard the USNS Lewis and Clark.

View the file

Other files for this federal contract opportunity

Other files attached to USNS LEWIS & CLARK ROH, newest first.
File Type Posted
LNC Solicitation Amend Discussions.docx DOCX document
COPY LNC SOLICITATION FINAL.docx DOCX document
USNS LEWIS CLARK AMEND 14.docx DOCX document
LNC ROH-DD MARCH 2021 COVER LETTER AND INDEX (3).doc DOC document
0104_A_QAWT Scuttle Repairs(1).docx DOCX document
0503_A_Cargo Pumproom Drain Piping Repairs(2).docx DOCX document
USNS LEWIS CLARK AMEND 0013.docx DOCX document
USNS LEWIS CLARK Amend 0012.docx DOCX document
USNS LEWIS CLARK AMEND 0011.docx DOCX document
Updated Work Item INDEX (2).doc DOC document
USNS LEWIS CLARK Amend 10.docx DOCX document
USNS LEWIS AND CLARK Amend 6.docx DOCX document
USNS LEWIS AND CLARK Amend 7.docx DOCX document
Clarification Question 9920.docx DOCX document
USNS LEWIS CLARK Amend 0009 F.docx DOCX document
0956_A_TAKE CCSI OVERHAULING SEA VALVES (5YR) (2).docx DOCX document
Clarification Question 9420.docx DOCX document
Clarification files Group 6.zip ZIP file
Updated Work Items.zip ZIP file
J2 Category A Items LNC (1).xls XLS spreadsheet
J 3 Category B Items LNC.xls XLS spreadsheet
USNS LEWIS CLARK Amend 0007.docx DOCX document
Clarification Questions Group 4.docx DOCX document
Clarification Question Group 3 Amend 0005.docx DOCX document
LNC Clarification Group 2 Amend 0004.docx DOCX document
LNC LIQUIDATED DAMAGES AMEND 0003.docx DOCX document
J - 2 Category A Items LNC (1).xls XLS spreadsheet
8194716_-.PDF PDF
Amendment 2 Clarification Group 1.docx DOCX document
8498620 TI-79 Gray Water Piping System Modifications.pdf PDF
0554_A_CARGO BRINE VALVES AND PIPING REPLACEMENT(1).docx DOCX document
8194692_-.PDF PDF
8194698_-.pdf PDF
J - 3 Category B Items LNC.xls XLS spreadsheet
8499057_-.pdf PDF
Clarification Questions.docx DOCX document
0503_A_Cargo Pumproom Drain Piping Repairs(1).docx DOCX document
7488761_C CMWD.pdf PDF
USNS LEWIS CLARK AMEND 0001.docx DOCX document
J-ATTACHMENTS LNC.zip ZIP file
L-4 LNC ROH21 J-A.pdf PDF
LEWIS CLARK SOLICITATION ROH.pdf PDF
Show all 42

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USNS LEWIS AND CLARK

(T-AKE 1)

MACHINERY, AUXILIARY SYSTEMSSERVICE ORDER
1/26/2020
ITEM NO: 502CATEGORY “A”MSC/N756/LSC

HPAC ROUTINE B MAINTENANCE

1.0 ABSTRACT:

1.1 This item describes the requirement for a qualified and certified Original Equipment Manufacturer (OEM) SAUER Air Compressor field service representative to perform Routine B Maintenance on the High Pressure Air Compressors.

2.0 REFERENCE:

2.1 Technical Manual T9551-A4-MMC-010 Air Compressor, Freshwater Cooled High Pressure WP5000

3.0 ITEM LOCATION/DESCRIPTION

3.1 Location/Quantity

3.1.1 Location: Auxiliary Machinery Room

3.1.2 Quantity: Two (2) High Pressure Air Compressors

4.0 GOVERNMENT FURNISHED EQUIPMENT/MATERIAL/SERVICES:

QTY
Part Number
Description
2
085821
2000 Hr. Routine B Maintenance Kit

5.0 NOTES

5.1 The Contractor and all Subcontractors, regardless of tier, must consult Military Sealift Command’s General Technical Requirements (GTRs) to determine applicability to this work item. The Contractor and all Subcontractors, regardless of tier, must comply with all applicable GTR requirements.

5.2 The Contractor and all Subcontractors shall review other work items under this contract to determine their effect on the work required by this item. Based on this review the Contractor shall plan and schedule work to minimize conflicts between work items.

5.3 THE USNS LEWIS AND CLARK ELECTRICAL COLOR CODING DOES NOT FOLLOW CONSISTENT COLOR SCHEME. THE SHIP IS KNOWN TO HAVE CURRENT CARRYING CONDUCTORS COLORED GREEN, BLUE, BLACK AND WHITE. THE CONTRACTOR SHALL ASSUME ALL ELECTRICAL CABLES ARE HOT UNTIL TESTED OTHERWISE. THE CONTRACTOR SHALL TEST ALL ELECTRICAL CABLES TO ENSURE THEY ARE DEAD PRIOR TO WORKING ON THE ITEM.

6.0 QUALITY ASSURANCE REQUIREMENTS: None additional

7.0 STATEMENT OF WORK REQUIRED:

7.1 Provide the services of a certified SAUER Air Compressor Original Equipment Manufacturer (OEM) field service technician to perform maintenance on High Pressure Air Compressors 1 and 2.

7.2 Operationally test each air compressor prior to maintenance verifying compressor functionality and identify any additional required work not addressed in this work item. Operational test will be conducted in the presence of the ship’s Chief Engineer, 1ST Engineer or their designated representative.

7.3 Perform 2000 hour Routine B Maintenance on HP Air Compressors 1 and 2.

7.4 Perform post maintenance operational test verifying the air compressors are operating as per the design operating parameters stated in reference 2.1. Operational test will be conducted in the presence of the ship’s Chief Engineer, 1ST Engineer or their designated representative.

7.5 Provide a detailed service report in PDF format to the MSCREP documenting components replaced, repairs conducted and results of the operational test.

7.6 Manufacturer’s Representative:

7.6.1 Provide the services of a certified SAUER Compressor Technical Representative. .

Sauer Compressors USA | North American Markets 245 Log Canoe Circle | Stevensville, MD 21666 Zack Barnes | Service Coordinator Main: 410-604-3142 | Direct: 410-200-4438

8.0 GENERAL REQUIREMENTS: None Additional