J-3 Category B Items.xlsx
XLSX spreadsheet 18 KB Posted
- Attached to
- USNS GUADALUPE FY20 ROH Federal contract opportunity
- Solicitation number
- N3220520R4005
About this file
This document contains a Category B items spreadsheet and related solicitation for the USNS GUADALUPE FY20 ROH. The spreadsheet lists various work items and materials required for overhauling the ship including physical security, continuation of services, steel replacement, miscellaneous piping replacement, drydocking and undocking the vessel, and pintle bearing replacement. Estimated quantities, unit prices, labor hours, material costs and total prices are provided. The solicitation seeks these Category B work items and materials in support of the overhaul and repair of the USNS GUADALUPE under solicitation number N3220520R4005 issued by the Department of the Navy Military Sealift Command. Responses are due in accordance with the terms of the solicitation.
View the file
Other files for this federal contract opportunity
Show all 40
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Cat B Items
| USNS GUADALUPE (T-AO 200) FY20 ROH/DD | |||||||||||||||
| GENERAL REQUIREMENT | QTY | UI | Unit Price | Total | PRIME Contractor | SUBCONTRACTOR | OTHER COSTS | ||||||||
| ITEM NO. | TITLE CAT B ITEM | PRIME L/H | LABOR PRICE | MATERIAL PRICE | SUB L/H | LABOR PRICE | MATERIAL PRICE | Total Labor Hours | Total Material | TOTAL PRICE | |||||
| CATEGORY "B" | |||||||||||||||
| 025 | PHYSICAL SECURITY AT CONTRACTOR'S FACILITY | ||||||||||||||
| 7.11 | Cost to Establish Condition Bravo | 1 | DAY | ||||||||||||
| 7.12 | Cost to Establish Condition Charlie | 1 | DAY | ||||||||||||
| 7.13 | Cost to Establish Condition Delta | 1 | DAY | ||||||||||||
| 7.11 | Daily Rate to Maintain Condition Bravo | 1 | DAY | ||||||||||||
| 7.12 | Daily Rate to Maintain Condition Charlie | 1 | DAY | ||||||||||||
| 7.13 | Daily Rate to Maintain Condition Delta | 1 | DAY | ||||||||||||
| WI 025 Sub-Total | |||||||||||||||
| 030 | CONTINUATION OF SERVICES | QTY | UI | Unit Price | Total | PRIME L/H | LABOR PRICE | MATERIAL PRICE | SUB L/H | LABOR PRICE | MATERIAL PRICE | Total Labor Hours | Total Material | TOTAL PRICE | |
| 7.1 | Parent work item 010 “Overhaul Management Team Services”. | 30 | DAYS | ||||||||||||
| 7.2 | Parent work item 011” General Services for the Ship” | 30 | DAYS | ||||||||||||
| 7.3 | Parent work item 012 “Telephone Services | 30 | DAYS | ||||||||||||
| 7.4 | Parent work item 013 “Project Planning and Monitoring” | 30 | DAYS | ||||||||||||
| 7.5 | Parent work item 016 “Fire Protection and Ship’s Safety” | 30 | DAYS | ||||||||||||
| 7.6 | Shipboard Access and Security | 30 | DAYS | ||||||||||||
| 7.7 | Parent work item 020 “Gas Free Certificates” | 30 | DAYS | ||||||||||||
| 7.8 | 30 | DAYS | |||||||||||||
| WI 030 Sub-Total | |||||||||||||||
| 112 | STEEL REPLACEMENT | QTY | UI | Unit Price | Total | PRIME L/H | LABOR PRICE | MATERIAL PRICE | SUB L/H | LABOR PRICE | MATERIAL PRICE | Total Labor Hours | Total Material | TOTAL PRICE | |
| 3.1.1 | Approx 10,000 Pounds of structure steel plate | 10000 | LBS | ||||||||||||
| 3.1.2 | Approx 5,000 Pounds of rolled structure shapes | 5000 | LBS | ||||||||||||
| 3.3.3 | Approx fifty(50) feet of weld 6" long or less cracks | 50 | FT | ||||||||||||
| 3.3.4 | Approx. fifty (50) 7”-12” long cracks. | 50 | FT | ||||||||||||
| 3.3.5 | Approx. twenty (20) sounding tube striker plates | 20 | EA | ||||||||||||
| WI 112 Sub-Total | |||||||||||||||
| 113 | MISCELLANEOUS PIPING REPLACE | QTY | UI | Unit Price | Total | PRIME L/H | LABOR PRICE | MATERIAL PRICE | SUB L/H | LABOR PRICE | MATERIAL PRICE | Total Labor Hours | Total Material | TOTAL PRICE | |
| 3.1.2.1 | Sixty (60) linear feet of eight inch Schedule 80 steel pipe | 60 | FT | ||||||||||||
| 3.1.2.2 | Eight (8) eight inch flanges four bolt 150# flat face, socket welded | 8 | EA | ||||||||||||
| 3.1.2.3 | Four (4) eight inch 90 degree elbows | 4 | EA | ||||||||||||
| 3.1.2.4 | Eighty (80) linear feet of six inch Schedule 80 steel pipe | 80 | FT | ||||||||||||
| 3.1.2.5 | Eight (8) six inch flanges four bolt 150# flat face, socket welded | 8 | EA | ||||||||||||
| 3.1.2.6 | Four (4) six inch 90 degree elbows | 4 | EA | ||||||||||||
| 3.1.2.7 | Eighty (80) linear feet of five inch Schedule 80 steel pipe | 80 | FT | ||||||||||||
| 3.1.2.8 | Eight (8) five inch flanges four bolt 150# flat face, socket welded | 8 | EA | ||||||||||||
| 3.1.2.9 | Four (4) five inch 90 degree elbows | 4 | EA | ||||||||||||
| 3.1.2.10 | Eighty (80) linear feet of three inch Schedule 40 steel pipe | 80 | FT | ||||||||||||
| 3.1.2.11 | Eight (8) three inch flanges four bolt 150# flat face, socket welded | 8 | EA | ||||||||||||
| 3.1.2.12 | Four (4) three inch 90 degree elbows | 4 | EA | ||||||||||||
| 3.1.2.13 | Eighty (80) linear feet of two and a half inch Schedule 40 steel pipe | 80 | FT | ||||||||||||
| 3.1.2.14 | Eight (8) two and a half inch flanges four bolt 150# flat face, socket welded | 8 | EA | ||||||||||||
| 3.1.2.15 | Four (4) two and a half inch 90 degree elbows | 4 | EA | ||||||||||||
| WI 113 Sub-Total | |||||||||||||||
| 901 | DRYDOCKING AND UNDOCKING VESSEL | QTY | UI | Unit Price | Total | PRIME L/H | LABOR PRICE | MATERIAL PRICE | SUB L/H | LABOR PRICE | MATERIAL PRICE | Total Labor Hours | Total Material | TOTAL PRICE | |
| 7.1 | Submit unit price per day up to a maximum of 15 days to continue all services in accordance with parent item if directed | 15 | DAYS | ||||||||||||
| WI 901 Sub-Total | |||||||||||||||
| 914 | PINTLE BEARINGS | QTY | UI | Unit Price | Total | PRIME L/H | LABOR PRICE | MATERIAL PRICE | SUB L/H | LABOR PRICE | MATERIAL PRICE | Total Labor Hours | Total Material | TOTAL PRICE | |
| 8.1.1 | Replacement of the Starboard Rudder Upper and Lower Pintle Bearings | 1 | Upper and Lower Bearing | ||||||||||||
| WI 914 Sub-Total | |||||||||||||||
| TOTAL |
&"Times New Roman,Regular"&10USNS LEROY GRUMMAN (TAO-195)
| &"Times New Roman,Bold"&14 | |
| CATEGORY "B" ITEMS | &"Times New Roman,Regular"&10N3220519R4011 |
ATTACHMENT J-3
File details come from the government source that posted it. Updated .