Q_AND_A_Responses_3.docx

DOCX document 33 KB Posted

Attached to
USNS ROBERT E. PEARY: Regular Overhaul/Dry-Docking Federal contract opportunity
Solicitation number
N32205-18-R-4250
Issued by
Department of the Navy Military Sealift Command

About this file

Responses to questions asked #3

View the file

Other files for this federal contract opportunity

Other files attached to USNS ROBERT E. PEARY: Regular Overhaul/Dry-Docking, newest first.
File Type Posted
0941_A_FW_Stern_Tube_Lubrication_System_Installation_T-ALT_403__Rev_1.doc DOC document
N32205-18-R-4250_Amendment_0004.docx DOCX document
0013_A_PROJECT_PLANNING_AND_MONITORING_(REP_FY18_only_19March18).docx DOCX document
N32205-18-R-4250_Amendment_3.docx DOCX document
0030_B_CONTINUATION_OF_SERVICES_REV_FEB_14.doc DOC document
Revised_J_-_3_Category_B_Items_PEARY_Rev__1.xls XLS spreadsheet
N32205-18-R-4250_Amendment_2.docx DOCX document
Revised_PEARY__WI_Index_ROH_DD_2018.doc DOC document
0024_NSP_Physical_Security_at_Private_Contractor's_Facility__MARCH_2017_..__(2).doc DOC document
Revised_J_-_2_Category_A_Items_PEARY_Rev__1.xls XLS spreadsheet
8498002_-_Stern_Tube_Fresh_Water_(Closed_Loop)_with_Piping_in_Overhead_o.._.pdf PDF
N32205-18-R-4250_Amendment_0001.docx DOCX document
Work_Item_1001_reference_page_2_5363431_M.pdf PDF
Q_AND_A_Responses_2.docx DOCX document
0556A_REV_Steering_Gear_Preventive_Maintenance_7-10_Year.doc DOC document
0105A_REV_Preservation_of_House_Rev_1.docx DOCX document
PEARY_SOLICITATION_2018_ROHDD.docx DOCX document
Q_AND_A_Responses_1.docx DOCX document
J_-_14_Technical_Data_Non-Disclosure.docx DOCX document
J_-_2_Category_A_Items_PEARY.xls XLS spreadsheet
N32205-18-R-4250.docx DOCX document
J_-_11_Dry_Dock_Evaluation_Form.docx DOCX document
J_-_10_Interport_Differential.doc DOC document
J_-_12_Past_Performance_Data.doc DOC document
J_-_7_MSC_Ship_Repair_Facility_Survey.doc DOC document
J_-_9_Disclosure_of_Lobbying_Activities_SF-LLL.doc DOC document
J_-_3_Category_B_Items_PEARY.xls XLS spreadsheet
J_-_13__PAST_PERFORMANCE_QUESTIONNAIRE.docx DOCX document
J_-_8_Request_for_Spec_Clarification.doc DOC document
J_-_14_Technical_Data_Non-Disclosure.docx DOCX document
SYNOPSIS_N32205-18-R-4250_USNS_ROBERT_E._PEARY.docx DOCX document
Show all 31

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

MILITARY SEALIFT COMMAND

N32205-18-R-4250

QUESTIONS AND ANSWERS #3

The following are answers to questions received from potential offerors. The answers provide clarification only and DO NOT constitute an amendment to the solicitation.

Question #1

SPECIFICATION ITEM NO.: 0520

PARAGRAPH / SECTION NO: 1.1, 3.1.2, 3.2.2, 4.0, 7.5, 7.7, 7.8, 7.9,

TITLE: HTFW Cooler Cleaning and Gasket Change (T-ALT 426)

QUESTION:

Paragraphs 1.1 and 3.1.2 gives the number of coolers as (2). Paragraph 7.5 gives the number of coolers as (3).

Please advise the number of coolers to be worked.

Paragraphs 3.2.2 and 7.8 indicates the materials are contractor supplied. Paragraph 4.0 indicates the materials are GFM.

Please confirm who is to supply.

Bill of materials gives the total quantity of gaskets to be (324). Paragraphs 7.7, 7.8 and 7.9 gives the quantity as (318).

Please advise the correct quantity.

ANSWER:

COOLERS=2

GASKETS=GFM

GASKET QTY= 318

Question #2 TITLE: MISC. Items for Clafirication QUESTION: WI 113.7.1- What amount of hazmat must be removed from the containers to the temporary containers?

WI 113.3.2.1 & 7.7.9- Per Q&A #1, since the original AC units are being reinstalled, does the contractor still need to provide new units?

WI 605-Liferaft certifications are for the USNS Byrd. Please provide certifications for the USNS Peary.

WI 519 & 520- The spec states 1 unit, but also gives a gasket quantity over 1000. Please clarify the number of plates to be serviced in both work items.

WI 941 reference 2.1.1 is listed as 530-8495285 Rev A, the drawing provided is 530-8496453 Rev -. Please provide correct drawing.

General- Has annual servicing of the SCBA compressor and fill station already been completed?

ANSWER:

1. WI 113.7.1: Two 10’ x 8’ Walk in units

2. WI 113.3.2.1 & 7.7.9: KTR provide new AC units, retain old just in case.

3. WI 605: Disregard BYRD certs provided as reference. Company that provides serviced expected to issue PEARY certs.

4. WI 519 & 520: WI-519- GFM will be enough material to do 1 heat exchanger, the rest will be turned over to S/F as spares.

WI-520 2 Coolers to be addressed #1 & #2 (#3 is already complete).

5. WI 941 Latest drawing submitted to KO via SEPCOR

6. The servicing of the SCBA is covered in WI-502

Question #3

SPECIFICATION ITEM NO.: 0565

PARAGRAPH / SECTION NO: 1.1, 3.1.2 and 4.1 TITLE: #1 Fuel Oil Cooler Cleaning and Gasket Replacement

QUESTION:

Paragraph 1.1 describes work to be performed on #1 and #2 coolers. Paragraph 3.1.2 gives the quantity as One (1) cooler.

Please confirm number of coolers to be worked.

Paragraph 4.1 is the same bill of materials as given for item 0564. Messrs. Phex informs us that these coolers have (61) plates each.

Is the GFM list incorrect?

ANSWER:

COOLERS=2

GFM=NEW GASKETED PLATES P/N-9814056

FOR WI-564

New gasketed plates will be GFM P/N-9816400

Question #4

SPECIFICATION ITEM NO.: 0572

PARAGRAPH / SECTION NO: 2.3

TITLE: Brine and Defrost Pump and Motor Overhauls

QUESTION:

Could you please provide specified tech manual T9516-BN-MMC-01A

ANSWER: Will be provided separately to each offeror.

Question #5

SPECIFICATION ITEM NO.: 030

PARAGRAPH / SECTION NO: 7.6, 7.7 and 7.8

TITLE: Continuation of services

QUESTION:

Paragraphs 7.6, 7.7 and 7.8 do not match the Category “B” Contractor Price Breakdown Sheet.

We request that the discrepancy be rectified and new documents issued.

ANSWER: A revised J-3 will be sent out separately.

Question #6

SPECIFICATION ITEM NO.: Miscellaneous

PARAGRAPH / SECTION NO: Miscellaneous

TITLE: MISC. Items for Clarification

QUESTION:

WI 013.7.17 C&D- SOW calls for these two turnovers to occur 16 days prior to dock trials. Generally this amount is significantly less. Please clarify if this is the true intent.

WI 559.2.1 & 4.2.1- GFM states that the BOM in reference 2.1 will be provided as GFM, but the drawing states that it will be IAF. Which is correct?

WI 560.2.1 & 4.2.1- GFM states that the BOM in reference 2.1 will be provided as GFM, but the drawing states that it will be IAF. Which is correct?

ANSWER:

WI 013.7.17 C&D: GE has testing to do that require Crew move-aboard/Machinery-turnover 16 days in advance as no changes to the plant (to include Engine Room & AMR machinery) can occur during testing, all work must be complete.

WI 559.2.1 & 4.2.1- Material will be GFM with the exception of gaskets

WI 560.2.1 & 4.2.1- Material will be GFM with the exception of gaskets

Question #7

SPECIFICATION ITEM NO.: __941___________

PARAGRAPH / SECTION NO:___3.2.1_________________

TITLE: Freshwater (closed loop) Stern Tube Lubrication System

QUESTION:

This item was amended to use a different drawing for reference 2.1.1, however, the verbiage in the specification no longer seems to match the reference and we cannot determine what material is required. For example, para 3.2.1.a says that the Wartsila parts kit contains all the electrical components in the bill of materials list on ref 2.1.1 sheet 14 but the list of electrical material is on page 1 and there is no bill of materials at all on page 14. Para 3.2.1.b says another Wartsila kit contains various piping components in the BOM on sheet 6 but sheet 6 contains only a list of label plates. Piping components are listed on page 18 but the numbers in the spec do not correspond to those in the BOM (spec says fittings through F-64 are included but the BOM ends at F-61). Paragraphs c and d are equally confusing. Para c refers to a partial list of unidentified material which may or may not be included in the Wartsila kit (we believe this is actually supposed to be structural material as it was previously listed on page 1 but, again, the numbers do not match). Paragraph d refers to the list of label plates on page 6 but the material seems to be pipe. Please clarify the material required for this item.

ANSWER:

1.1.1Bill of Materials (Contractor Furnished):
a.Wartsila Parts Kit: WDI002115-001 - QTY 1 Kit

Note: This parts kit contains all the electrical closed loop components in the bill of materials listed on reference 2.1.1 sheet 1/2. Items 1-67,

b. Wartsila Parts Kit: WDI002115-002 –QTY 1 Kit Note: This parts kit contains the following parts listed in the bill of materials on reference 2.1.1 sheet 18: V-1 through V-9 and F1 through 61.

c.Provide Items 1 through 12 listed in the bill of materials on reference 2.1.1 sheet 2.
d.Provide Items P2 through P6 listed in the bill of materials on reference 2.1.1 sheet 18.
e.Provide labels on sheet 6 of ref. 2.1.1
f.Provide cable tags on sheet 17 of ref 2.1.1