17-R-3513_Technical_Questions_and_Answers.docx
DOCX document 14 KB Posted
- Attached to
- MARITIME SUPPORT VESSEL Federal contract opportunity
- Solicitation number
- N32205-17-R-3513
About this file
Questions and Answers 1
View the file
Other files for this federal contract opportunity
Show all 32
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
17-R-3515 C-Champion Replacement
Technical Questions and Answers
Question 1
Can any of the required client spaces (Conference room, Planning room, special secure office space, scan eagle ops space, tactical ops center, joint ops center, comms/server room, recreation space, and morale/rec tv room/lounge) be combined? If so, which ones?
Answer 1
A. Combining spaces is not preferred, but combining the Conference Room and Planning Room could be done if layout is careful. A retractable divider could be incorporated that would allow compartmenting of the room for use by occupants, but would NOT need to be sound proof nor a physical security barrier.
Question 2 Can any of the following spaces be combined for joint purpose, or is it required that each space is separate?
• 940 ft2 conference center
• 490 ft2 planning room
• 180 ft2 secure office space
• 120 ft2 Scan Eagle operations
• 500 ft2 tactical operations center • 500 ft2 joint operations center • 832 ft2 communications/server room • 490 ft2 recreation space
Answer 2
. 940 ft2 conference center (combine with Planning Room is acceptable, but not optimal) . 490 ft2 planning room (combine with Conference Room is acceptable, but not optimal) . 180 ft2 secure office space - no . 120 ft2 Scan Eagle operations - no . 500 ft2 tactical operations center -no . 500 ft2 joint operations center - no . 832 ft2 communications/server room - no . 490 ft2 recreation space - no