LCC_20_Industry_Day _Engineering_Overview _FY17 _rev_2.pptx

PPTX presentation 3 MB Posted

Attached to
USS MT. WHITNEY Industry Day Federal contract opportunity
Solicitation number
N32205-16-R-4601
Issued by
Department of the Navy Military Sealift Command

About this file

Engineering Presentation

View the file

Other files for this federal contract opportunity

Other files attached to USS MT. WHITNEY Industry Day, newest first.
File Type Posted
Work_Items_0000 _0100_and_0900.pdf PDF
MTW_FY17_ESLP_Availability _Cover_Sheet_and_Work_Item_Index.docx.pdf PDF
Industry_Day_Agenda_02_Feb_2016.pdf PDF
Synopsis_of_Critical_Path_Items.docx DOCX document
MTW_Industry_Day_Reference_Example.zip ZIP file
LCC_20_Industry_Day _Contracting_Overview.pptm PPTM file

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USS MOUNT WHITNEY (LCC-20)

FY17 Industry Day – Engineering Overview provided, 02 Feb 2016

UNCLAS

Military Sealift Command MSC Delivers Overview

USS MT WHITNEY commissioned in 1971 Underwent first phase of Extended Service Life Program (ELSP) at Viktor Lenac Shipyard (Rijeka, Croatia) Jan 2015 – Sept 2015 ESLP designed to extend MTW service life to 2039 FY15 ESLP – HM&E upgrades (Assured Power) (complete) FY17 ESLP – C5I communication systems upgrades (CANES, NMT, CBSP) FY18 ESLP – HM&E upgrades and upkeep FY19 ESLP – Navigation/Bridge upgrades HM&E upgrades accomplished during FY15 ESLP Availability are expected to yield significant cost savings to the program and reduce the environmental impact to Gaeta

MSC Delivers List of Acronyms ESLP = Extended Service Life Program PSA = Post Shipyard Availability (short pier-side availability to address any incomplete or last minute maintenance items from the ROH/MTA) MTA = Mid-Term Availability (intermediate dry-docking, usually scheduled mid way of a 5 yr inspection cycle) ROH = Regular Overhaul (regular scheduled dry-docking at the beginning and end of a 5 year inspection cycle) DD = dry-docking SSTG = Ship’s Service Turbine Generator CIVMAR = Civilian Mariner OMT = Overhaul Management Team ACO = Administrative Contract Officer SOR = Senior Owner’s Rep, (Contract Officer’s Technical Representative, COTR), also Technical Person In-Charge

MSC Delivers 13 May 2016 – Issue Solicitation 29 May 2016 – Bidder’s Ship Check 18 Jun 2016 – Solicitation closes 20 Jun 2016 – Begin Technical and Price Evaluations 18 Jul 2016 – Receive Best and Final Proposals, (BaFP) (if needed) 31 Jul 2016 – Complete Evals of BaFP 16 Sep 2016 – Award Contract 04 Oct 2016 – Post Award Conference (at shipyard) 15 Dec 2016 – USS MT WHITNEY arrives shipyard 19 Dec 2016 – Navy and CIVMAR crew move-off MTW 29 Dec 2016 – Docking 09 May 2017 – Undocking 06 Jun 2017 – Navy and CIVMAR crew return to MTW 12 Jun 2017 – Base Contract Ends 13 Jun 2017 – Begin 30-day PSA 26 Jun 2017 – Dock Trials 30 Jun 2017 – Sea Trials 13 Jul 2017 – MTW departs shipyard and returns to Gaeta FY17 Key Milestones

Approximately 131 days on dock

Approximately 36 days Solicitation

Execution Base Contract Execution PSA Contract

MSC Delivers C5I Systems such as CANES, NMT, CBSP, DCGS-N INC 1, COMSEC Serial, KMI Spiral 2, ADNS INC III, ATIP. Equipment installation, configuration and testing will be accomplished by Gov Furnished - Alteration Installation Teams (AITs). Number of AITs on-sight may be as high as 50-100 persons.

Stern Tube Shaft and Stern Tube Bearing Liners (2), Propeller Shaft and Propeller Shaft Bearing Liner, Rudder Stock and Rudder Stock Bearing Liner, Stern Tube Assembly, Machine Lands for Stern Tube Bearing Carriers, and full re-alignment, (**planning, sequencing and coordination, critical**) Habitability Mods – Berthing Cubicles will be provided as GFM, “disassembled”, delivered to the shipyard in 40' ISO containers, (estimate 20-30 containers), will require assembly onsite.

Steel Replacement various tanks, voids, bilges, side-shell, fan rooms, boiler foundation, reduction gear foundation, stern tube, etc.

5.

FY17 – Major Work Items

MSC Delivers

5. Bulkhead 118, Stern Tube Shaft Seal

6. Potable Water Delivery & Heating System Replacement

7. Gym Relocation

8. Install GFM Incinerator

9. Anti-Roll Tank Removal (convert to storeroom)

10. Lower Engineroom: (busy area) Steel repairs inside the Oily Waste Holding Tank and the Waste Oil Tank, (WI 0113) Steel repairs to the engineroom inner bottom plating, (WI 0115) Steel repairs to the engineroom machinery foundations, (WI 0109) Steel repairs to the Red Gear foundation, (WI 0202) Remove/test the sea valves in this area, (WI 0902) paint the bilges, (WI 0506)

FY17 – Major Work Items - continued

MSC Delivers

11. Docking, ABS Surveys and Vessel Incline

12. Coating Renewal of Ballast Tanks, Potable Water Tanks, CHT Tanks, Reserve Feedwater Tanks

13. Shaft Alley:

Steel repairs to Bulkhead 118, (WI 0118) Stern Tube Renewal, (WI 0912) Propulsion Shaft Alignment, (WI 0920)

14. Installation of new ‘Rudder to Rudder Stock’ Packing Gland, (WI 0918)

15. Rig 1C S/S Turbine Generator from ship to shore for disassembly and cleaning

16. Install GFM RHIB Davit Assembly on Stbd Sponson

FY17 – Major Work Items - continued

MSC Delivers MTW Shafting Arrangement

MSC Delivers

Shell Plate Renewal

MSC Delivers

MSC Delivers

MSC Delivers Many of the hab spaces are located below the 4th deck and consist of multi-berthing, open-space living quarters and associated wet spaces.

Spaces will require all furniture & outfitting to be removed and replaced with new.

MSC will provide almost all of the furniture associated with these spaces as Government Furnished Material (GFM).

Berthing Cubicles will be provided “disassembled”, delivered to the shipyard in 40' ISO containers, (estimate 20-30 containers). Will require substantial Lay Down area. Will require assembly onsite. MSC will provide assembly instructions with the furniture.

In accordance with associated drawings, most spaces will require new piping, new lighting, new electrical power, new bulkheads, new HVAC ducting and new decking.

Habitability Mods

MSC Delivers Living Spaces

Group 1 - MSC (5-37-1, 5-37-2, 5-37-3, 5-37-4, 5-36-8, 5-34-2) Group 2 - MSC (5-64-1, 5-69-1, 5-70-1) Group 3 - MSC (5-98-0) Group 4 - MSC (6-98-0) Group 5 - MSC (5-109-0) Group 6 - NAVY (4-18-0, 4-25-1) Group 7 - NAVY (5-18-0, 5-26-0) Group 8 - NAVY (5-40-2, 5-42-2) Group 9 - NAVY (5-40-0, 5-42-1) Group 10 – NAVY (5-67-0, 5-72-2, 5-68-2)

Each 'Group' below is separated into a different Work Items Wet Spaces

Group 1 - MSC (5-30-2-L) Group 2 - MSC (5-64-5-L) Group 3 - MSC (5-101-1-L) & (5-103-2-L) & (5-98-2-L) Group 4 - N/A Group 5 - MSC (5-112-2-L) Group 6 - NAVY (4-18-3-L) Group 7 - NAVY (5-24-2-L) Group 8 - NAVY (5-40-4-L) Group 9 - NAVY (5-40-1-L) Group 10 - NAVY (5-64-2-L) & (5-64-6-L) Habitability Mods

MSC Delivers LCC-20 Program Points of Contact Washington DC:

Daniel Glod (MSC/N10) MTW Contract Specialist Tel: (202) 685-5954, Email: daniel.glod@navy.mil Seamus Hunt (MSC/N72) MTW Lead Design Engineer Tel: (202) 685-5237, Email: seamus.p.hunt@navy.mil Marc Bromante (MSC/N74) MTW FY17 Senior Owner’s Rep Tel: (202) 685-5036, Email: marc.bromante@navy.mil Norfolk, Va:

Michelle Knox (MSC/N10) MTW Contract Officer Tel: (757) 443-2902, Email: michelle.r.knox@navy.mil Rick Albert (MSC/N74) MTW ESLP Project Officer Tel: (757) 443-5957, Email: rick.albert@navy.mil Gaeta Italy:

Mike Brown (MSC/PM4CM1) MTW Principal Port Engineer (PPE) Tel: Email: michael.t.brown1@navy.mil