007_Item_103_RFC_Answer.docx

DOCX document 27 KB Posted

Attached to
USNS BIG HORN Regular Overhaul and Dry Dock (ROH-DD)
Solicitation number
N32205-15-R-1011
Issued by

About this file

007 Item 103 RFC Answer

View the file

Other files

File Type Posted
J-3_Category_B_Items_BIG_HORN_Revised_11-9-15.xlsx XLSX spreadsheet
Amedment_0003.doc DOC document
J-2_Category_A_Items_BIG_HORN_Revised_11-9-15.xlsx XLSX spreadsheet
N32205-15-R-1011 _Amendment_2.pdf PDF
UPDATED_J-10 _BIG_HORN_15-R-1011.pdf PDF
009_Item_110_RFC_Answer.docx DOCX document
005_Item_203_RFC_Answer.docx DOCX document
008_Item_512_RFC_Answer.docx DOCX document
006_Item_506_RFC_Answer.docx DOCX document
001_Section_B_RFC_Answer.docx DOCX document
004_Item_508_RFC_Answer.docx DOCX document
003_Item_204_RFC_Answer.docx DOCX document
002_Item_203_RFC_Answer.docx DOCX document
Conformed_Copy_of_Solicitation_through_Amendment_1_-BIG_HORN_N32205-15-R-1011.pdf PDF
Amendment_1-BIG_HORN_N32205-15-R-1011.pdf PDF
SF_33_p1_BIG_HORN_Released.pdf PDF
JnA_BIG_HORN_N32205-15-R-1011-CA-Signed_Redacted_FedBizOps.pdf PDF
J-6_WI_015_CDRL.pdf PDF
J-7_MSC_Ship_Repair_Facility_Survey.docx DOCX document
J-2_Category_A_Items_BIG_HORN.xlsx XLSX spreadsheet
BIG_HORN_Scheduled_Government_Furnished_Property.xls XLS spreadsheet
J-12_Past_Performance_Data.docx DOCX document
LAR_FY15_Interport_Differentials_(3-2-15).xls XLS spreadsheet
J-9_Disclosure_of_Lobbying_Activities_SF-LLL.docx DOCX document
J-8_Request_for_Spec_Clarification.docx DOCX document
BIG_HORN_Solicitation.doc DOC document
J-11_Dry_Dock_Evaluation_Form.docx DOCX document
J-13__PAST_PERFORMANCE_QUESTIONNAIRE.docx DOCX document
J-3_Category_B_Items_BIG_HORN.xlsx XLSX spreadsheet
J-14_Technical_Data_Non-Disclosure_BIG_HORN.docx DOCX document
Show all 30

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

N32205-15-R-1011

USNS BIG HORN (T-AO 198)

REQUEST FOR SPECIFICATION CLARIFICATION

DATE: ___10 September 2015_________________

NAME OF CONTRACTOR: ___ _______________

SPECIFICATION ITEM NO.: ____103_________________

PARAGRAPH / SECTION NO:____various________________

TITLE: ____Pump Room Bilge Preservation _

QUESTION:

Paragraph 3.1.1 states to perform 1000 sq ft of mechanical cleaning and 7500 sq ft of resurfacing/ preservation.

Paragraph 3.1.2 states to perform 500 sq ft of mechanical cleaning and 5000 sq ft of resurfacing/ preservation

Reading these line items would lead us to presume that we would be doing spot power tooling, spot coats, cleaning/ washing and painting a full coat to the entire area.

Paragraph 7.2.2 states to perform surface preparation to a WJ-2 standard, SC-2 Condition to all areas of the bilge and 4” up and stations, brackets and anything attached to the bilge, then perform power tooling on inaccessible areas to water blasting to an SP-11 standard

Reading this line would lead us to presume that we are to UHP blast the entire area and power tooling any inaccessible areas to an SP-11 standard.

Paragraph 7.2.6 states to apply the following coating system to all of the prepared surfaces of the tank deck overhead.

What is the real intent of this item?

ANSWER:

The real intent of this item is to water jet blast the entire bilge areas identified in paragraph 3.0. There may be some areas of mechanical cleaning which is stated in paragraph 3.0 as 1000 sq ft and 500 sq ft respectively. The entire bilge will be cleaned, primed and painted.

Para 7.2.6 Should read “ apply the following coating system to all prepared surfaces of this Work Item.”

ATTACHMENT J - 8