Amendment_0001_Q A.pdf

PDF 94 KB Posted

Attached to
AIR 6. 8. 5 Logistics Product Lifecycle Mgt Support
Solicitation number
N00421-14-R-0004
Issued by

About this file

Industry Questions and Answers

View the file

Other files

File Type Posted
RFP_Amendments_QA.pdf PDF
N000421-14-R-0004-0003.pdf PDF
Exhibit_A_CDRLS_dated_06-10-2014.PDF PDF
Attachment_P6_CLIN_Breakout_spreadsheet_Dated_09-June-2014.xls XLS spreadsheet
N00421-14-R-0004-0002.pdf PDF
Exhibit_B_FFP_Unit_Item__6_9_14.xls XLS spreadsheet
Attachment_13 MD _St.Mary's_05-2103_r.13.PDF PDF
N00421-14-R-0004-0001.pdf PDF
Attachment_P6_CLIN_Breakout_spreadsheet_Dated_03-June-2014.xls XLS spreadsheet
Attachment_P5_Past_Performance_Questionnaire_Package_for_Services_updated_5-20-14.doc DOC document
Attachment_12 _CA_Ventura_05-2071r.15.PDF PDF
Exhibit_B_FFP_Unit_Item__6_3_14.xls XLS spreadsheet
N00421-14-R-0004_Industry_Questions_and_Answers_06-04-14.pdf PDF
Attachment_04_FFP_CLIN_0005_Description.doc DOC document
Attachment_14 _CA _Kern_05-2043_r.16.PDF PDF
Exhibit_B_FFP_Item.xlsx XLSX spreadsheet
Attachment_P1_Workforce_Qualifications.xls XLS spreadsheet
Attachment_17 _NJ _Ocean_05-2351_r12.pdf PDF
ATTACHMENT_05_-_Baseline_Requirements_and_Definitions.doc DOC document
Attachment_15 _NC _Craven_05-2393_r14.pdf PDF
Attachment_10_Incurred_Cost_and_Progress_Reporting_CDRL_of_7-10-13_with_sample_data.xls XLS spreadsheet
Attachment_03 _Technical_Manual_Types.doc DOC document
Attachment_P4_Past_Performance_Matrix.doc DOC document
N00421-14-R-0004.pdf PDF
Attachment_04_FFP_CLIN_0005_Description.dot DOT file
Attachment_08_SAAR_Form_dd2875.pdf PDF
Attachment_16 _FL _Duval_05-2115_r13.pdf PDF
Attachment_12 _CA _Ventura_05-2072_r16.pdf PDF
Attachment_11_NMCI_Ordering_Procedure.doc DOC document
Attachment_07_IT_Positions_Process_for_Contractors.doc DOC document
Attachment_P6_CLIN_Breakout_spreadsheet_V7z_____11_Oct_2012_with_CIC.xls XLS spreadsheet
Attachment_P5_Past_Performance_Questionnaire_Package_for_Services.doc DOC document
Attachment_01_dd0254_DRAFT.pdf PDF
Attachment_18 _CA _San_Diego_05-2057_r14.pdf PDF
Exhibit_A-A001-008.PDF PDF
Attachment_14 _CA _Kern_05-2044_r16.pdf PDF
Attachment_13 _MD _St._Mary's_05-2104_r15.pdf PDF
Attachment_09_AIR7.4-7.2_Memo_dtd_16Oct_08_-_IT_Req.pdf PDF
Show all 38

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Amendment 0001

Industry Questions and Answers

Industry Question 1: Reference: Industry Question #33: Past Performance

Questionnaire and Due Date

Discussion: Originally the Past Performance questionnaires were to be sent out by

Offerors within two weeks of RFP release May 15th (May 29th). Since answers to questions were not posted until June 4th, it is likely that Offerors have submitted their questionnaires using the original Questionnaire format and sent them to Mr. Mattingly per the RFP instructions (Original RFP: Page 77).

Question: Please confirm that Past Performance Questionnaires that were processed in accordance with the original instructions, using the original questionnaire, is sufficient.

Government Response: Past Performance Questionnaires that were processed in accordance with the original instructions are sufficient.

Industry Question 2: Reference: Industry Question #64: Attachment P4 and Page 36 of

Amendment 0001

Discussion: “Attachment P4 will be deleted in a subsequent amendment to the RFP…”.

However, Amendment 0001, Page 36, still references Attachment P4 and related requirements.

Question: Please confirm that the RFP will be amended to reflect the deletion of this attachment and any requirements related to this attachment.

Government Response: A subsequent amendment to the RFP will remove any remaining references to Attachment P4.

Industry Question 3: Reference: Industry Question #48, Amendment 0001, Page 31 and other references to page “Limitations”

Discussion: The answer to Industry Question #48 indicates that the page counts offered on page 31 are only “Suggestions”. However, in several instances throughout the RFP and Amendment 0001 the term “limitation” is used. Also certain items are “excluded from page count”. This indicates a page limit is in place. The term “suggestion” would give the offeror liberty to submit information far beyond the suggested page count.

Question: It is requested that the Government consider making the Amendment 0001

“suggested” page counts firm page limitations so that proposals received are consistent in the amount of content and remain balanced to facilitate a fair evaluation.

Government Response: The page counts cited in the RFP represent recommendations that the Government believes should be adequate for an offeror to craft its proposal response.

Industry Question 4: Reference: Attachment 6, Enclosure (1) Surveillance Activity

Checklist

Discussion: Performance Standards Metrics and Acceptable Quality Levels

Question: The Surveillance Activity Checklist does not specify the level of performance that is considered acceptable when performing tasks under this contract. Due to the accuracy required to produce highly precise deliverables to ensure the safety of our service men and women, will the Government please add the Performance Standards

Metrics and Acceptable Quality Levels expected to be achieved to the Enclosure (1)

Surveillance Activity Checklist.

Government Response: The Surveillance Activity Checklist will not be modified. This requirement is not a performance based services acquisition for which performance standard metrics and Acceptable Quality Levels would be identified in the RFP.

Industry Question 5: Reference: Amendment 0001, Section B

Discussion: Section B replacement

Question: Does the Government intend to issue a new Section B with the incorporated changes from Amendment 0001?

Government Response: The Government does not intend issue a new Section B as there is not a need for doing so.

Industry Question 6: Reference: Amendment 0001, Section H, 5252.216-9534 Task

Order Procedures, part (d), page 44

Discussion: This clause states “Labor rate (exclusive of fee) will be pre-established at the time of basic contract award for each labor category.”

Question: We assume that this clause refers to maximum bid rates only for the purposes of establishing task order ceiling, and during execution we will be permitted to bill all allowable costs incurred. Please confirm. If our assumption is incorrect, would the

Government please clarify the intent of this sentence?

Government Response: Section H clause 5252. 216-9534 (Task Order Procedures) will be revised to remove the phrase alluded to in this question in an upcoming amendment to the RFP.

Industry Question 7: Reference: Amendment 0001, Exhibit B – FFP Item

Discussion: Year 2 through 4 has a built-in Price per Unit escalation of 2.5%.

Question: Are Offerors required to use the escalation percentage provided in Exhibit B?

Government Response: Exhibit B will be updated via an upcoming RFP amendment to remove the built in per unit escalation.

Industry Question 8: Reference: Amendment 0001, Section I, 52.222-42 Statement of

Equivalent Rates for Federal Hires (May 1989), page 27

Discussion: The Computer Operator II in the chart on page 27 has an SCA Code of

14041. The description of a Computer Operator II provided in Section C (page 16) matches the SCA Directory of Occupations description of a Computer Operator II, which is SCA code 14042.

Question: Should the Computer Operator II on page 27 be mapped to 14042?

Government Response: The Government will provide an updated SCA code for this labor category in a subsequent amendment to the RFP.

Industry Question 9: Reference: Amendment 0001, Page 2, Summary of Changes (5), Attachment 4

Discussion: Section (5) states Attachment 04 FFP Item Description was revised.

Question: Would the Government please provide the modified attachment?

Government Response: The Government will provide an updated Attachment 04 on the

NAVAIR open solicitation website (Attachment 04 dated 06-03-2014). The updated

Attachment 04 has been posted on FBO website with RFP amendment 0001.

Industry Question 10: Reference: Amendment 0001, Section 4.6.2, Annual Level of

Effort BY SITE, pages 42-47

Discussion: In Year 1 and Year 2 of the table, the Contractor Site always comes before the Government Site when a category has both sites. In Year 3 and Year 4, the

Government Site comes first. This change makes the hours inconsistent from year to year. This reversal of Contractor/Government site begins with the “Analyst, Senior” category and ends with the “Technical Writer III” category.

For example, in the North Island column:

Yr 1 Yr 2 Yr 3 Yr 4

Analyst, Senior (Ctr Site) 1280 1286 1695 1703

Analyst, Senior (Govt Site) 1678 1686 1293 1299

Technical Writer III (Ctr Site) 0 0 1515 1523

Technical Writer III (Govt Site) 1500 1508 0 0

Question: Will the Government please correct years 3 and 4 of the Level of Effort table?

Government Response: The Government will provide an updated LOE chart in a subsequent amendment to the RFP.

Industry Question 11: Amendment 0001, Attachment P6

Discussion: Attachment P6 only has one column (G) for each labor category’s hourly rate. Most Offerors will have different rates for each location.

Question: We assume the Government will allow Offerors to insert a “Rate” column for each location. Please confirm.

Government Response: The Government will provide an updated Attachment P6 in a subsequent amendment to the RFP.

Industry Question 12: Reference: Amendment 0001, Attachment P6

Discussion: The Summary tab of Attachment P6 has a rate column (G) and hours columns (H, J, L, N, P, R, T, V, AE) that are not needed for a Summary worksheet. The

Summary sheet should only be a summation of each year’s costs.

Question: Would the Government please allow Offerors/Subs to hide the Rate and Hours columns on the Summary worksheet?

Government Response: Yes.

Industry Question 13: Reference: Amendment 0001, Attachment P6

Discussion: Instruction #5 states the worksheets should be formatted for printing on letter-size paper, without requiring “adjustments.”

Question: For ease of evaluation, would the Government allow the worksheets to be printed on 11x17 so all columns could print on a single sheet?

Government Response: The Government will allow the "worksheets" to be printed in

11x17 papers.

Industry Question 14: Reference: Amendment 0001, Attachment P6

Discussion: Instruction #15(g) states to enter the subcontractor fully burdened cost including fixed fee. Instruction #15(j) also states to enter the subcontractor fixed fee rate.

Question: By entering the fully burdened cost including fee in the Subcontractor rate section, we assume cell G399 would be zero. Please confirm.

Government Response: The cell G399 is for the prime to enter its proposed fee on subcontractor Labor.

Industry Question 15: In the updated Attachment P6, the way the labor categories are presented, there is not a way to separate hours between Government Site and Contractor

Site. The way it is presented, the contractor would have to enter a very complicated formula into the file to separate the hours by site to generate the separate Overheads.

Would the Government please clarify how to separate hours between the Government and Contractor Site Labor Categories based on the Annual Level of Effort Site table in section 4.6.2 of Section L.

Government Response: The offeror may add additional rows for the contractor site labor categories.

Industry Questions and Answers

From

Original RFP Released

Industry Question 17: RFP Pg. 68-69, 5252.209-9513 OCI, the attachment is not identified.

Please provide the attachment. Which volume shall we place our OCI answer – Volume I?

Government Response: A company needing to provide information regarding OCI issues should do so in Volume 1 of its proposal.

Industry Question 92: Reference: RFP Exhibit A, CDRL A005, Block 16

Discussion: CDRL does not reflect the software specification changes that were made to Section

6.7.2 and 6.7.3.

Please advise if the CDRL text will be modified to match the SOW text for this section.

Government Response: The Government will provide an updated Exhibit A CDRLS in a subsequent amendment to the RFP.

Industry Question 93: Reference: RFP Exhibit A, CDRL A006

Discussion: The information in the CDRL is incomplete and does not provide the information needed to prepare and deliver the QPP. The contract reference in Block 5 is incorrect and should read “SOW para 7.2”.

Will the Government please provide a completed/corrected CDRL A006?

Industry Question 94: Reference: RFP, Exhibit A, CDRL A008

Discussion: Numerous changes have been made to this CDRL since the pre-solicitation CDRL was reviewed. The RFP CDRL no longer reflects Section 10.0 of the RFP SOW. For example, the date of first submission of the SDP IS 90 DACA per Section 10.1 not AS REQ as indicated in Block 12 and the Block 5 contract reference should be SOW para 10.0. Also the Block 15 totals do not match the required distribution quantities.

Please advise if CDRL A008 will be updated to match Section 10.0 of the RFP SOW, specifically Blocks C, 5-5, and 10-16.