This is a Pre-Proposal Inquiry Form for solicitation N0025326Q0013, titled "Bldg. 1051 Replace Main Dry Valves," issued by the U.S. Navy. The document contains eleven pre-proposal questions with government responses addressing clarifications on scope, specifications, and requirements for the fire protection and breathing air systems work.

Key project requirements include replacement of wet-sprinkler alarm valves (1 quantity 8-inch and 3 quantities 6-inch) and dry-pipe alarm valves (2 quantities 6-inch), with Section I of the Statement of Work containing the correct quantities. The government estimates existing dry systems at 2,000-gallon capacity, requiring verification by a Fire Protection Engineer and Fire Protection Engineer-stamped hydraulic calculations. Contractors must provide shop drawings of riser changes and the nitrogen system. Replacement wet-sprinkler alarm valves must be the same generic type as existing valves but not necessarily identical models, with no alterations to the fire alarm system beyond what is necessary. Regarding the breathing air system, no piping outside the mechanical room shall be replaced; however, copper piping may be replaced with stainless steel (except the inlet air pipe to the air compressor). The air compressor upgrade from 10 HP to 15 HP is permissible if required to meet the 40 SCFM specification, with circuit upgrade costs included in the firm-fixed price. FAR Clause 52.225-9 (Buy American—Construction Materials) applies. Government responses reference UFC 3-240-02 Section 1-8 and applicable Washington-state Code (WAC) requirements for breathing air systems, and indicate that a revised Statement of Work correcting valve quantity discrepancies has been delivered to the contract specialist.

View the file

Other files

File Type Posted
C07_B1051_Att_13_PPI_Answers.pdf PDF
Solicitation Amendment N0025326Q00130002 SF 30.pdf PDF
Solicitation Amendment N0025326Q00130001 SF 30.pdf PDF
B1051_Att_12_SOW_Rev_1.pdf PDF
Solicitation - N0025326Q0013.pdf PDF
B1051_Att_02_Wage_Det.pdf PDF
B1051_Att_04_Guide_Environmental.pdf PDF
B1051_Att_07_Past_Perf.docx DOCX document
B1051_Att_09_PPI_Form.docx DOCX document
B1051_Att_06_Schedule_of_Values.xlsx XLSX spreadsheet
B1051_Att_08_Bid_Form.xlsx XLSX spreadsheet
B1051_Att_11_OSHA.pdf PDF
B1051_Att_03_Guide_Safety.pdf PDF
B1051_Att_05_Guide_OPSEC.pdf PDF
B1051_Att_12_SOW.pdf PDF
B1051_Att_10_Safety_Data.docx DOCX document
B1051_Att_01_Material_Equip.xlsx XLSX spreadsheet
Show all 17

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PRE-PROPOSAL INQUIRY FORM

SOLICITATION #: N0025326Q0013

TITLE: Bldg. 1051 Replace Main Dry Valves

E-mail form to: michelle.a.farrales.civ@us.navy.mil AND jason.b.gavinski.civ@us.navy.mil

Government Responses will be provided in red.

INQUIRIES:

1. Can the capacity (gallons) of the existing dry systems be provided, this will materially affect the correct type of nitrogen system required, if it can not be provided, is there a job walk scheduled or can one be scheduled?

SOW IV.2.C. gives Technical POC’s estimate for a 2000-gallon capacity, and a requirement for this to be checked by a Fire Protection Engineer. For context: the estimate was calculated from original construction drawings using pipe sizes (using sched. 40 black iron inner diameter actual values) and pipe lengths, then rounded up to the nearest “standard” equipment size.

2. Are the wet-sprinkler alarm valves required to be replaced with the same type of alarm valve, or can these be updated to riser-checks, or shotgun-style riser manifolds with check valves?

Same type, generically speaking. Identical models to the existing valves are not required.

The Government does not intend there to be any alterations to the fire alarm system other than what is strictly necessary to replace the alarm valves.

3. Is there any requirement to produce hydraulic calculations and/or record drawings of these fire sprinkler systems and/or riser detail drawings?

Provide shop drawings of the riser changes, and nitrogen system, and Fire Protection Engineer stamped hydraulic calculations for the existing dry pipe systems.

4. RFP States: "All materials and products provided by the Contractor in the performance of this contract shall be new and manufactured and assembled in the United States of America and shall meet or exceed the manufacturer’s specifications." - Please provide the FAR clause (Buy American) that this contract falls under.

This language is removed from the Statement of Work (SOW) and has officially incorporated FAR Clause 52.225-9 (Buy American—Construction Materials) via Amendment 0001.

5. Is any of the piping for the breathing air system to be replaced (aside from reconfiguration for new equipment)?

No piping of this system outside of the mechanical room shall be replaced.

6. Is there any outlined specialized flushing, degreasing, and certification parameters required to recertify the breathing air system for use?

E-mail form to: michelle.a.farrales.civ@us.navy.mil AND jason.b.gavinski.civ@us.navy.mil

Please reference UFC 3-240-02 Section 1-8, applicable Washington-state Code (WAC) requirements, for breathing air systems. The government has no special, localized requirements for the site.

7. Currently, the piping connecting the system is copper, which has the potential to oxidize over time and build up particulates. Stainless can also withstand aggressive heavy-duty cleaning procedures necessary to pass strict breathing air quality tests such as CGA G-7.1 Grade D Standards.

Would the gov't prefer to replace the piping with stainless steel - consistent with typical applications for Breathing Air Systems the Navy uses?

Replacement of copper pipe with stainless steel is generally permissible (see also response to #1 above), less the inlet air pipe to the air compressor. The inlet air pipe shall generally stay intact except for whatever minor modifications are needed to mate with the new air compressor.

8. Can pictures of the tank storage area lighting be provided?

Photos will be taken shortly after writing this response. However, given the present date (9/17), we don’t believe they will be cleared for release in time to be useful for the proposals. As a possibly useful clarification, the government does NOT require the new fixtures to match the existing ones.

9. Solicitation N0025326Q0013, Attachment 12 Statement of Work, Section IV.D (Air Compressor) and Section IV (Products) note that source power is 480VAC 3-phase 60Hz on the existing 10 HP-rated circuit, and that required capacity is 40 SCFM at 100 psig, oil-free package. Catalog oil-free packages that deliver 40 SCFM at 100 psig are 15 HP.

A 10 HP oil-free package is approximately 28 to 31 SCFM and will not meet 40 SCFM.

Please confirm whether offerors shall (a) furnish a 10 HP compressor on the existing circuit, (b) furnish a 15 HP compressor that meets 40 SCFM and include upgrade of the existing circuit in the firm-fixed price, or (c) another direction.

All specifications for this equipment were taken from existing, originally constructed equipment and original construction drawings. Basis of design specifications from original construction have not been preserved. An upgrade from 10HP to 15HP is permissible if that is indeed required to meet the SCFM specification of the existing unit.

10. Solicitation N0025326Q0013, Attachment 12 Statement of Work, Section IV.E

(Breathing Air Purifier) requires a package unit rated to deliver OSHA Grade D breathing air at 50 SCFM at 100 psig, with integrated CO, O2, and dew-point monitoring.

Regenerative plant purifiers of that capacity typically require approximately 60 SCFM inlet to deliver 50 SCFM outlet. The compressor in Section IV.D is specified at 40 SCFM. Please confirm the required compressor capacity so the purifier can deliver 50

E-mail form to: michelle.a.farrales.civ@us.navy.mil AND jason.b.gavinski.civ@us.navy.mil

SCFM Grade D, and whether a circuit upgrade is authorized if a larger compressor is required.

See also reply to #1. It is reasonable to conclude that the size of the filter unit was chosen from the standard size filtration units that were available at the time of original construction. The breathing air system design most likely factored in standard pressure and SCFM drops across the filtration unit rather than the system output being rated at the maximums of the filtration unit.

11. Solicitation N0025326Q0013, Attachment 12 Statement of Work, the valve quantities do not match. Section I requires replacement of 1 (qty.) 8-inch wet pipe alarm valve, 3 (qty.)

6-inch wet pipe alarm valves, and 2 (qty.) 6-inch dry pipe alarm valves (no 8-inch dry valve). Section IV.A–B lists 2 (qty.) 6-inch and 1 (qty.) 8-inch wet valves, and 2 (qty.) 6-inch and 1 (qty.) 8-inch dry valves. Section VI.2.C requires replacement of 2 (qty.) 6-inch dry pipe valves, 1 (qty.) 8-inch dry pipe valve, 2 (qty.) 6-inch wet alarm valves, and 1 (qty.) 8-inch wet alarm valve. Please confirm the exact quantity and size of wet pipe alarm valves and dry pipe alarm valves to furnish, including associated drain valves, and whether the 8-inch dry pipe valve is required.

Section I. of the SOW contains the correct quantities. A revised SOW correcting the other sections has been delivered to contract specialist and will be reposted accordingly.