This is a Questions and Answers document for Navy solicitation N0018926QW220. The document addresses four key inquiries from potential contractors regarding classified information handling, past performance evaluation criteria, subcontracting permissions, and eligibility requirements.
The government clarified that contractors will not be responsible for safeguarding classified information at contractor-owned or leased facilities; all access to classified materials will occur strictly at government locations. Regarding past performance evaluation, the government confirmed that experience must have been performed within five years of the solicitation closing date and amended the solicitation to correct a previous three-year reference. The government confirmed that prime contractors may utilize established Joint Venture entities as subcontractors. Finally, in response to a question about 8(a) Tribal concerns submitting past performance references from affiliated companies, the government noted that this solicitation is set-aside for women-owned small business concerns under FAR clause 52.219-30, indicating the inquiring party may not meet the eligibility requirements for this opportunity.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Questions to Solicitation N0018926QW220
1. Question: The DRAFT 2254 included indicates that Secret level Safeguarding (Block 1b) is required in performance of this work. Can the government please clarify if the contractor will be responsible for safeguarding classified information at a contractor leased or owned location, or if all access to classified will be strictly at a government location.
Answer: The contractor will not be responsible for safeguarding classified information at a contractor leased or owned location. All access to classified information will be strictly at a government location.
2. Question: The RFP states that the past performance must be performed both within five
(5) years and three (3) years of the solicitation closing date. Can the government clarify which evaluation criteria is correct?
Answer: Past performance must have been performed within five (5) years of the solicitation closing date. The solicitation has been amended to change three years to five years.
3. Question: The solicitation permits subcontracting. Would the Government please confirm if a Quoter (Prime Contractor) is permitted to utilize an established Joint Venture (JV) entity as a subcontractor on its team?
Answer: Yes.
4. Question: Regarding the Past Performance volume, would the Government please confirm if an 8(a) Tribal Joint Venture (JV) member or a standalone 8(a) Tribal subcontractor is permitted to submit past performance references from an affiliated company (e.g., parent, subsidiary, or sister company), provided we demonstrate that the affiliate will have meaningful involvement in the performance of the resulting contract?"
Answer: We do not understand why you are asking this question because this acquisition is set-aside for women-owned small business concerns; see block 10 on the first page of the solicitation and FAR clause 52.219-30 in the solicitation.