N0017418R00170001.docx
DOCX document 35 KB Posted
- Attached to
- Multiple Launch Rocket System (MLRS) M26 Rocket Motor Reclamation and Flight Testing Federal contract opportunity
- Solicitation number
- N0017418R0017
About this file
N0017418R00170001 Solicitation amendment
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| PRB_Case_Number_027_ExhibitA_CDRLs.pdf | ||
| PRB_Case_Number_027_Attachment8_SF1408Survey.pdf | ||
| N0017418R0017-RFP_Final.pdf | ||
| PRB_Case_Number_027_Attachment3_PastPerformanceMatrix.doc | DOC document | |
| PRB_Case_Number_027_Attachment6_DemilCert.pdf | ||
| PRB_Case_Number_027_Attachment1_CAP.doc | DOC document | |
| PRB_Case_Number_027_Attachment4_QASP.docx | DOCX document | |
| PRB_Case_Number_027_Attachment5_CostSummaryFormat.xlsx | XLSX spreadsheet | |
| PRB_Case_Number_027_Attachment2_PastPerformanceQuest.doc | DOC document | |
| PRB_Case_Number_027_Attachment7_GFP.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
N0017418R0017
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
The following items are applicable to this modification:
SUMMARY OF CHANGES (REVISED)
SUMMARY OF CHANGES
The purpose of this amendment is to 1) address questions from an Offeror, and 2) address a request for an extension.
1. Questions received by an offeror are as follows:
a. Shall we assume that the Period of Performance clock starts when the five (5) Loaded MLRS M26 Rocket Pods are received on the Contractor’s dock?
b. Please identify the location from where the GFM MLRS M26 Rocket Pods are shipping.
The answers are as follows:
a. The Period of Performance (POP) clock starts at the date of contract award. It is anticipated that the GFM shipment will commence as early as the issuance of the contract(s); it is also anticipated that the shipment will take approximately 120 days, at most, from the date of commencement to arrive at the Contractor’s facility. The estimated POP duration is simply an estimate.
b. The GFM will be shipping from the Letterkenny Munitions Center, located in Chamberburg, PA.
2. A 30-day extension has been requested by an Offeror. The Government finds that a 30-day extension is not in the best interest of the Government.
3. All other terms and conditions remain unchanged.
4. Please direct any questions to Ashleigh Bowie, ashleigh.bowie@navy.mil.
(End of Summary of Changes) image1.wmf