N0016426RGW20_005_SF30.pdf
PDF 605 KB Posted
- Attached to
- N0016426RGW20-PROCUREMENT OF DESIGN AND PRODUCTION OF FLAT RAILCARS-PSC 2220- NAICS 336510
- Solicitation number
- N0016426RGW20
About this file
This is Amendment 0005 to Solicitation N0016426RGW20, issued by NSWC Crane Warfare Center on 01 May 2026, extending the response due date from 13 March 2026 to 15 May 2026. The solicitation number is N0016426RGW20, and the contracting officer is Leslie A. Grabber-Heshelman.
The amendment provides revised requirement documents, updated answers to 35 previously posed questions, and extends the proposal closing date. Of the questions and answers, questions 21, 28, 29, 30, 33, and 34 were revised, with question 30 marked as no longer applicable due to obsolete facility requirements. The solicitation concerns the design, development, and production of Trident II AIM Flatcars for transporting weapons systems to three Strategic Weapons Facility locations (Atlantic, Pacific, and Eastern Range). Key technical requirements include an AAR-M1001 Section C compliant design with a maximum gross rail load of 286,000 pounds, lightweight target of 116,000 pounds, and end-of-car hydraulic cushioning. The contract structure includes CLINs 0001-0003 for development and production quantities (maximum 9 railcars total) and CLIN 0006 for delivery to three facility destinations. Pricing matrices for both CLINs are included with Year 1 through Year 5 time periods based on award date. The anticipated contract award date is no later than 5 March 2027. Government-furnished information including drawings (WS20972) and the Systems Requirement Document will be provided within 30 days of award. Offerors must acknowledge receipt of this amendment prior to the extended closing date.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| N0016426RGW20_003.pdf | ||
| Solicitation Amendment N0016426RGW200002.pdf | ||
| GFP.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
R
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER
NUMBER IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
15B. CONTRACTOR/OFFEROR
(Signature of person authorized to sign)
15C. DATE SIGNED 16B. UNITED STATES OF AMERICA
(Signature of Contracting Officer)
16C. DATE SIGNED
Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES
2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)
6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER
9B. DATED (SEE ITEM 11)
10A. MODIFICATION OF CONTRACT/ORDER NUMBE
10B. DATED (SEE ITEM 13)
CODE FACILITY CODE
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
Section A - Solicitation/Contract Form
The following changes have been made:
INFORMATION FROM TO
Response Due Date 13 Mar 2026 15 May 2026
Miscellaneous text in this section has been modified to:
Surveillance Criticality Designator (SCD) - A Due to system constraints the "From" date could not be updated.
The response "From" date should be 28 Mar 2026.
N0016426RGW200005
Section B - Supplies or Services & Prices or Costs
Miscellaneous text in this section has been modified to:
Questions and Answers
1. Will past performance on non- federal government contracts related to rail car design, testing and manufacture be acceptable and desired (state, local government and commercial)?
Answer: Yes.
2. How does the Government intend to evaluate delivery pricing under the Solicitation's Item 0006 and SOW Section 3.4.5?
Answer: The cost of the shipping should be considered for all 3 Strategic Weapons Facility locations. The exact location will be determined by available location prior to the delivery order. The Government will evaluate comparatively with respect to shipping location.
3. When the railcar is delivered, is it the Governments expectation the car will be a fully commissioned car and able to be towed or the car will not be fully commissioned, and transportation must occur using a method other than towing?
Answer: Fully commissioned and approved for use on rail with AAR.
4. Were any risk reduction contracts awarded prior to this effort? If so, can you provide the contract number and what data rights the Government owns?
Answer: No risk reduction contracts have been awarded prior to this effort.
5. For each order, will there be a Not-to-Exceed amount given for Shipping since shipping costs may vary? Who bears the risk or the rail carrier damage?
Answers: Shipping should be planned out by the vendor. Assumption of risk is in accordance with "Freight on Board" (FOB) terms.
6. Is there an incumbent for this requirement?
Answer: No.
7. What are the number of rail cars to be manufactured for development and production?
Answer: See Section B.
8. What is the minimum quantity for this IDIQ?
Answer: See Section B
9. What are the number of flat railcars for this contract?
Answer: See Section B.
10. After contract award, how long will it take the Technical Point of Contract to provide GFI.
Answer: 30 days.
11. What should be included in the Bill of Material (BOM)?
Answer: The BOM should be based on the final design of the railcar.
12. Is the end of railcar hydraulic cushioning required?
Answer: Yes. Defined in the Systems Requirement Document (SRD).
13. Please confirm that the design of the NSWC AIM Flatcar should be to AAR-M1001 Section C, part II, and not to any standards pertaining to tank cars.
Answer: Yes. Defined in the Systems Requirement Document (SRD).
14. Are there drawings for WS20972?
Answer: See the new GFI issued with current Solicitation Amendment.
15. What is the G-loading in conjunction with the requirement of the lightweight car of 116,000 pounds?
Answer: Please review Section 3.39 Figure 11 in SRD and the interface drawing Trident II AIM Flatcar /SSE Interface Dwg. 5681514.
16. On page 19 Section 3.12 of the SRD, correct?
Answer: Yes. Please review Section 3.39 Figure 11 in SRD and the interface drawing Trident II AIM Flatcar /SSE Interface Dwg. 5681514.
17. Will WS20972 be provided?
Answer: See the new GFI issued with current Solicitation Amendment.
18. Will the AIM Railcar Bulkhead, AIM Shipping Fixture, and Loading Tube as shown in the 'D5 AIM FLATCAR CARGO' figure of drawing 5681514 be provided as GFP for testing? Additionally, will all the hardware to attach the cargo structures to the flatcar be provided for testing?
Answer: Please review the GFP.
19. Is the government providing mechanical and fabrication drawings for the shipping fixture, bulkhead, and loading tube?
Current drawings provided do not have enough details to create CAD for analysis.
Answer: Please review the GFP.
20. What are the timelines for CLIN 0001 and CLIN 0002?
Answer: This can be negotiated.
21. What are the design criteria for the G forces/ strike-down load listed? Are they yield or ultimate?
Answer: This is listed in Trident II AIM Flatcar/SSE Interface Dwg. 5681514 in Figure 11 in the SRD.
Answer: Strike download did change but is listed in the updated SRD. Strike down load updated to 355 kips.
22. Is the 116,000 pounds lightweight critical given the Vertical G force requirement or is the overall capacity the critical element?
Answer: This is listed in Trident II AIM Flatcar/SSE Interface Dwg. 5681514 in Figure 11 in the SRD.
23. What is the maximum allowable length of the railcar?
Answer: Defined in the Systems Requirement Document (SRD).
24. Should max width of rail car fit within plate C? 10'-0" Recommended for max width with deck length of 68'.
Answer: Defined in Systems Requirement Document (SRD).
25. What is the preferred length of the rail car deck?
Answer: Defined in the Systems Requirement Document
26. What is to be done if the wheels, axles, bearings, side frames, truck bolsters, or span bolsters don't meet the G-loading criteria?
Answer: The system fails and redesign will be required.
27. What is the anticipated date of contract award?
Answer: The anticipated award date will be No Later Than 5 Mar 2027.
28. The empty weight of the car, resulting from the Gross Load Weight/Gross Rail Load requirement stated in Section 3.3.1, is not achievable.
Answer: The GRL is 286,000 lbs. The main focus is configuration 4.4. This will be the transportation load weight with the AIM that will be transported from site to site. Configuration 4.4 is listed at 186,800 lbs., therefore leaving 99,200 lbs. for the weight of JUST the flatcar to meet the 286,000 lb. GRL.
29. The Navy has requested a 68-foot car, the empty weight of the flatcar would be heavier than 80,000 lbs., thus resulting in an excess weight.
Answer: Configuration 4.1 thru 4.4 is the only transportation requirements so the max configuration load is 186,800 lbs. This leaves 99,200 lbs for the weight of JUST the flatcar. Regardless of this, if the design that the vendor creates is over that limit they will need to work with the railroad to put waivers in place so that the flatcar can still travel over the rail limiting the 286,000 lb gross load weight. Additionally, there are some specialized, higher-capacity cars that can handle a Gross Load Weight of 315,000 lbs, though their use might be restricted to specific routes capable of supporting such heavy loads.
30. In Drawing 5681514 on page 60 of 97 of the file "Drawings and SRD.pdf", Note 17 says that "Truck Axle Loads shall not exceed 60,000 lb. per axle in any load condition." To meet the axle load requirement, more than 4 axles are necessary.
Answer: The design DOESN'T have to be a 4-axle flatcar.
Answer: Question and answer above are no longer applicable because it is an obsolete facility requirement.
31.A 6-axle railcar cannot be designed due to the elimination of 3-axle truck bolsters by the rail industry. If the design changes to an 8-axle car, which uses commonly available components, the design of the railcar must be altered resulting in a change in the length specification, a change to the deck height and increase in weight of the railcar which will all exceed the current specifications.
Answer: This is defined in the SRD. This needs to meet the HxWxL requirements.
32.WS20972 and MIL-SPC-810. The specification refers to the securement of the load, but doesn't specifically say the equipment used to transport the load must be designed to these criteria. Please confirm the loadings specified in WS20972 document and MIL-SPC-810 apply to the securement of the load and not the vehicle itself.
Answer: Yes the loadings specified that WS20972 and MIL-SPC-810 apply to the securement of the load.
33. The SRD-500778 includes Configuration 5 requiring support of 249,500 lbs of cargo load, with Configurations 6 and 7 requiring 224,800 lbs. and 230,100 lbs. respectively. If the intended railcar design basis is a 286,000 lb. gross rail load platform, Configuration 5 would leave only 36,500 lbs. available for the car tare weight, which does not appear feasible for a compliant flatcar design. Also requesting Clarification regarding whether the new AIM Flatcar is intended to be limited to a 286,000 lb. gross rail load design, or Configurations 5, 6, and 7 load cases are to be interpreted differently than standard railcar cargo load/gross rail assumption.
Answer: If the design calls out for a higher GRL than 286,000 lbs. waivers can be discussed and that discussion can start. For more details, see previous comments about the load configurations. Configuration 4.4 is the main concern for the transportation load. 4.5 - 4.7 are used for storage and operational use at the facility.
34. At this time, the 286,000 lb. capacity requirement does not appear to be explicitly stated in the SOW text itself, 34.
Answer: Please see note 18 on Drawing 5681514. "ONLY LOAD CONFIGURATIONS 4.1 THRU 4.4 ARE USED FOR
TRANSPORTATION. OTHER LOADS ARE USED FOR STORAGE AND OPERATIONAL USE AT THE
FACILITY". Configuration 4.5 - 4.7 is just facility and storage requirements that will NOT leave the facility. They need to focus on configuration 4.4 as that is the main transportation weight for the cargo as it is in transit. In Configuration 4.4 the load is 216,800 lbs. With the max GRL at 186,000 lbs. this allows 99,200 lbs. for the weight of the flatcar itself.
35. Does the Government anticipate a heavier-duty design basis beyond a standard 286,000 lb. freight car platform?
Answer: The GRL is not listed in the SOW because it is a requirement and it is in the Systems Requirement Document
(SRD-500778).
End of Q&A
CLIN 0003 PRICING MATRIX
Quanti ty
Year
Year 2 Year 3 Year 4 Year 5
1 N/A xxxxxxxxxxxxxxxxxxxxx xxxx xxxxxxxxxxxxxxxxxxxxx xxxx xxxxxxxxxxxxxxxxxxxxx xxxx xxxxxxxxxxxxxxxxxxxxx xxxx
2 N/A
3 N/A
4 N/A
5 N/A
CLIN 0006 PRICING MATRIX
Destination Y ea r 1
Year 2 Year 3 Year 4 Year 5
Strategic Weapons Facility Atlantic (SWFLANT)
N /A xxxxxxxxxxxxxxxx xxxxxxxxx xxxxxxxxxxxxxxxx xxxxxxxxx xxxxxxxxxxxxxxxx xxxxxxxxx xxxxxxxxxxxxxxx xxxxxxxxxx
Strategic Weapons Facility Pacific (SWFPAC)
N /A
Eastern Range
(ER)
N /A
*Matrices to be completed by Offeror
Year 1 Time Period: Date of Award to 12 Months After Award **
Year 2 Time Period: 12 Months After Award to 24 Months After Award **
Year 3 Time Period: 24 Months After Award to 36 Months After Award **
Year 4 Time Period: 36 Months After Award to 48 Months After Award **
Year 5 Time Period: 48 Months After Award to 60 Months After Award **
** Actual dates will be included in the award document.
CONTRACT MINIMUM/MAXIMUM AMOUNTS
The contract maximum quantity of 9 includes ordering quantities from all CLINs with deliverables (CLINs 0001 through 0003, and 0006).
Section J - List of Attachments
The following attachments were added:
Summary of Changes of Requirements for Flat Railcar
| IDCode: J |
| Page: 1 |
| Pages: 9 |
| AmendNo: 0005 |
| EffDate: 01 May 2026 |
| ReqNo: See Continuation Sheet |
| ProjNo: |
| IssCode: N00164 |
| AdmCode: |
| IssuedBy: NSWC CRANE |
WARFARE CENTER, 300 HIGHWAY 361
CRANE, IN 47522-5001
UNITED STATES
Steven Junkins, Email: steven.l.junkins2.civ@us.navy.mil Telephone: 812-381-7148 AdminBy:
SCD: PAS:
| ContractorNameAdd: |
| Code: |
| FacCode: |
| SolChg: 1 |
| SolNo: N0016426RGW20 |
| SolDate: 21 Jan 2026 |
| AwardChg: Off |
| AwardNo: |
| AwardDate: |
| Amended: 1 |
| OffrExt: 1 |
| OffrNoEx: Off |
| NoCopies: 1 |
| ApprData: See Section G - Contract Administration Data |
| ChgeOrd: Off |
| ChgeOrder: |
| Modify: Off |
| SuppAgre: Off |
| SuppAuth: |
| ModOthr: Off |
| OthrSpec: |
| NoReq: Off |
| Require: Off |
| Copies: |
| Descript: The purpose of this amendment is to provide revised requirement documents, provide updated answers to previously posed questions, an extend the closing date for proposal receipt from 28 March 2026 to 18 May 2026. Please note that of the 35 Questions and Answers, question 21, 28, 29, 30, 33, and 34 were revised. Question 30 is no longer applicable. A Summary of Changes to Requirements has been added to Section J. |
| ContNameTitle: |
| CoNameTitle: Leslie A. Graber-Heshelman |
| ContDate: |
| CODate: 30 Apr 2026 |