N00024-25-R-2301_Bidders Questions_A0003.xlsx
XLSX spreadsheet 22 KB Posted
- Solicitation number
- N00024-25-R-2301
About this file
This document is a Bidders Questions file for Solicitation N00024-25-R-2301, addressing Post Shakedown Availabilities (PSAs) for DDG 51 Class Ships at Norfolk, VA. The file contains seven questions and corresponding government responses related to solicitation details, with amendments issued to clarify and correct various sections. Key clarifications include updates to Attachment S-2 work items, confirmation that the Master Program Schedule can be an appendix excluded from page limits, and resolution of performance period discrepancies.
The solicitation, issued by the Naval Sea Systems Command (NAVSEA), seeks a contractor to perform PSAs for DDG 124 and DDG 127, with periods of performance spanning from 30-June 2026 to 30-Sep-2026 and 30-May-2027 to 31-Aug-2027. The government has specified a 16-week (112-day) PSA, with the last two weeks dedicated to Ship's Force LOA and PRTs. The NAICS code for this procurement is 336611 (Ship Building and Repairing), and contractors were provided opportunities to seek clarification on schedule, work items, and proposal requirements through this Q&A process.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| N00024-25-R-2301_A0004.pdf | ||
| N00024-25-R-2301_Bidders Questions_A0004.xlsx | XLSX spreadsheet | |
| N00024-25-R-2301_A0003.pdf | ||
| N00024-25-R-2301_A0002.pdf | ||
| N00024-25-R-2301_Bidders Questions_A0002.xlsx | XLSX spreadsheet | |
| N00024-25-R-2301_Bidders Questions_A0001.xlsx | XLSX spreadsheet | |
| S-2 work packages_A0001.xlsx | XLSX spreadsheet | |
| N00024-25-R-2301_A0001.pdf | ||
| S-1 - Bidders Questions Form.xlsx | XLSX spreadsheet | |
| S-2 work packages.xlsx | XLSX spreadsheet | |
| S-3 - Cost Exhibits.xlsx | XLSX spreadsheet | |
| S-4 - Compliance Checklist.docx | DOCX document | |
| S-5 - Contractor Award Announcement Information.docx | DOCX document | |
| Exhibit A_PSA RFP Preliminary CDRLS.pdf | ||
| N00024-25-R-2301.pdf | ||
| J-1 Testing Index and Test Numbering System for DDG 51 and Follow Ships.pdf |
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| Question Number | Date Submitted | Question Source: (RFP, attachment #, GFI title, etc.) | Page number and paragraph header from source | Question | Government Response | Posted |
| 1 | 4/18/25 | Section L | Page 102 of 116 | Section L page 102 of 116 states Attachment S-5 contains a historical work package containing work items…... However the S-5 received is a Contractor Award Announcement. We did receive S-2, Work Package, but this is only a list of work items. Please provide all the work items listed in the S-2 | The Government has amended the Solicitation to correct this section to show Attachment S-2. | Amendment 0001 |
| 2 | 4/18/25 | Section L | Page 102 of 116 | Section L page 102 of 116 lists 6 work items the contractor is to discuss. Number (6), 262-11-001 is NOT listed in the S-2, Work Items. Please delete item 262-11-001 from page 102 or provide the work item. | Number (6) 262-11-0001 has been added to Attachment S-2. | Amendment 0001 |
| 3 | 4/18/25 | Section L | Page 100 | Section L, page 100, Tab A requires a master program schedule. Is this schedule to be based on the work items listed in Attachment S-2? | The Master Program Schedule is based on the work package S-2. | Amendment 0001 |
| 4 | 4/28/25 | Section L | Page 102 of 116 | Upon receipt of this solicitation package, we requested missing work items, Attachment S-2. Without this information, we are unable to write to the requirements of the solicitation. We again request the S-2 and respectfully request at least a 2 week extension after receipt of the missing information. | Attachment S-2 has been updated and the Government has extended the proposal due date. | Amendment 0001 |
| 5 | 5/1/25 | Section L | Page 100 of 116 | Per RFP instructions, Teaming Agreements, Facility Utilization Loading Charts, Man-Power Loading Charts, Craft/Trade Staffing Plan and Resumes shall be provided as an Appendix and not included in the page limit. Please verify that the Master Program Schedule can also be provided as an Appendix to Volume I and be excluded from the page limit. | Yes. The Master Program Schedule can be provided as an Appendix to Volume I and be excluded from the page limit. | Amendment 0002 |
| 6 | 5/7/25 | Section F | Page 49 of 116 | Section F-2 of the proposal states, “For purposes of the offeror’s proposal, the offeror shall estimate a 16 week (112 day) PSA, with the last two (2) weeks being dedicated to Ship’s Force LOA and PRTs. The offeror shall plan for and man a maximum three (3) week, PrePSA or “smart start” period prior to the 112 day availability to accomplish care and protection, erection of staging, and early start on critical path items agreed upon with the government.” The estimated 112 days appears to be in contradiction to the Section F DELIVERY INFORMATION Dates, 30-JUNE 2026 TO 30-SEP-2026 and 30-MAY-2027 TO 31-AUG-2027, which are 92 days and 93 days, respectively. |
| The Government has adjudicated Section F to show the full 112 days. | Amendment 0003 | ||||||
| 7 | 5/7/25 | Section F | Page 49 of 116 | Please clarify if offerors are to base the schedule off the Section F Periods of Performance, or the 16 week (112 day) estimate. Please also clarify if the end of availability date provided with the period of performance should include the 2 weeks dedicated to Ship’s Force LOA and PRTs, or if those two weeks will be performed after the contractor’s delivery date (end of availability). | Offerors are to base the schedule off the Section F Periods of Performance. The two weeks dedicated to Ship's Force LOA and PRTs is not included in the POP as this two weeks starts after PSA end. | Amendment 0003 |
File details come from the government source that posted it. Updated .