This solicitation requests proposals for operation and maintenance of inactive vessels in Bremerton and a detachment in San Diego. Proposals are due by 5:00 PM on June 16, 2022. The solicitation was released by the Department of the Navy Naval Sea Systems Command. Offerors must provide all necessary services to operate and maintain the inactive vessels, including inspection and testing of fire and flood detection systems according to provided Navy standards. Inspections will cover circuit testing, alarm functionality, sensor placement and operation, and documentation of any discrepancies. The selected contractor will be responsible for maintenance and repair of all fire and flood protection equipment onboard the vessels.

View the file

Other files

File Type Posted
Attachment J2 Cost Element Summary Spreadsheets Rev 2.xlsx XLSX spreadsheet
BREMERTON CDRL 033-036 Rev1.pdf PDF
Attachment J-1 Pre-Proposal Information Form Rev 4.xlsx XLSX spreadsheet
BREMERTON CDRL 017-020 Rev1.pdf PDF
BREMERTON CDRL 049-052 Rev1.pdf PDF
BREMERTON CDRL 009-012 Rev1.pdf PDF
BREMERTON CDRL 041-044 Rev1.pdf PDF
BREMERTON CDRL 001-004 Rev1.pdf PDF
BREMERTON CDRL 013-016 Rev1.pdf PDF
BREMERTON CDRL 045-048 Rev1.pdf PDF
Bremerton Solicitation Rev 4.pdf PDF
BREMERTON CDRL 025-028 Rev1.pdf PDF
BREMERTON CDRL 037-040 Rev1.pdf PDF
BREMERTON CDRL 021-024 Rev1.pdf PDF
BREMERTON CDRL 005-008 Rev1.pdf PDF
BREMERTON CDRL 053-055 Rev1.pdf PDF
BREMERTON CDRL 029-032 Rev1.pdf PDF
Amendment 003.pdf PDF
BREMERTON ATTACHMENT J-2 Cost Element Summary Spreadsheets Rev 2.xlsx XLSX spreadsheet
BREMERTON ATTACHMENT J-1 Pre-Proposal Information Form Rev 2.xlsx XLSX spreadsheet
BREMERTON ATTACHMENT J-9 Government Furnished Vehicles.xlsx XLSX spreadsheet
BREMERTON ATTACHMENT J-20 - Quality Assurance Surveillance Plan.pdf PDF
BREMERTON ATTACHMENT J-2 Cost Element Summary Spreadsheets.xlsx XLSX spreadsheet
BREMERTON CDRL 021-024.pdf PDF
BREMERTON ATTACHMENT J-7 Janitorial Task and Frequency Chart.xlsx XLSX spreadsheet
BREMERTON CDRL 017-020.pdf PDF
BREMERTON CDRL 001-004.pdf PDF
BREMERTON CDRL 033-036.pdf PDF
BREMERTON ATTACHMENT J-14 Integrity Inspection.docx DOCX document
BREMERTON ATTACHMENT J-11 Cathodic Protection.docx DOCX document
BREMERTON CDRL 013-016.pdf PDF
BREMERTON CDRL 025-028.pdf PDF
BREMERTON ATTACHMENT J-10 TOOLS MATERIAL.xls XLS spreadsheet
BREMERTON ATTACHMENT J-3 List of assigned Vessels.xls XLS spreadsheet
BREMERTON CDRL 037-040.pdf PDF
BREMERTON CDRL 005-008.pdf PDF
BREMERTON ATTACHMENT J-4 Tank Soundings Template.xls XLS spreadsheet
BREMERTON ATTACHMENT J-6 History Folder Index.docx DOCX document
BREMERTON CDRL 009-012.pdf PDF
BREMERTON ATTACHMENT J-21 DD254 (BREMERTON).pdf PDF
BREMERTON ATTACHMENT J-8 GFE FROM ERP.xls XLS spreadsheet
BREMERTON CDRL 029-032.pdf PDF
BREMERTON ATTACHMENT J-1 Pre-Proposal Information Form.xlsx XLSX spreadsheet
BREMERTON CDRL 045-048.pdf PDF
BREMERTON CDRL 053-055.pdf PDF
BREMERTON ATTACHMENT J-22 INACTSHIPMAINTO BREMERTON Organizational Chart_.pdf PDF
BREMERTON ATTACHMENT J-16 Security Report.doc DOC document
BREMERTON ATTACHMENT J-19 PCB Inventory.doc DOC document
BREMERTON ATTACHMENT J-5 Repair Request Work Order (RRWO)(sample).docx DOCX document
BREMERTON CDRL 049-052.pdf PDF
Show 40 more

Latest 50 of 95 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Periodicity:

Spec Code:

Berthed At:

Quarter:

NSTM 50 INSPECTION GUIDELINES

FF1

Insp Date:

TDL

Remarks N/A

NO

YES

Description Item Check continuity of each heat, smoke and flood alarm circuit at the control panel. Record results below. Are all readings satisfactory?

Have all other discrepancies been reported? If not report them here.

F/F Continuity FWD Draft:

AFT Draft:

List:

Comments:

Inspector Inspector Inspection Manager Circuit Continuity Test Results SW No.

Cir Type K Ohm Test Location Sat Unsat SW No.

Cir Type K Ohm Test Location Sat Unsat Sat Unsat Sat Unsat Sat Unsat Sat Unsat Sat Unsat Sat Unsat Sat Unsat Sat Unsat Sat Unsat Sat Unsat Sat Unsat Sat Unsat Sat Unsat Sat Unsat Sat Unsat Sat Unsat Sat Unsat Sat Unsat Sat Unsat Sat Unsat Sat Unsat Sat Unsat Sat Unsat Sat Unsat Sat Unsat Sat Unsat Sat Unsat Sat Unsat

Attachment 12 NSTM 50 INSPECTION GUIDELINES - Discrepancy Listing Spec Code:

Line Item # Location Discrepancy Discovery Dt Correction Dt

Berthed At:

Quarter:

NSTM 50 INSPECTION GUIDELINES

FF2

Insp Date:

TDL

Remarks N/A

NO

YES

Description Item Audible alarm and alarm light are activated by the test switch?

Is the power available light energized at all times except during continuity testing ?

Does test switch indicate proper vessel and alarm on remote monitoring computer; can alarm be silenced from remote monitoring computer?

Have all other discrepancies been reported? If not report them here.

Fire Panel FWD Draft:

AFT Draft:

List:

Comments:

Inspector Inspector Inspection Manager

Line Item # Location Discrepancy

Berthed At:

Quarter:

NSTM 50 INSPECTION GUIDELINES

FF3

Insp Date:

TDL

Remarks N/A

NO

YES

Description Item Activate all flooding sensors by tipping floats or shorting probes to check for proper operation.

Are sensor cutout switches numbered and chart present? Do cutouts isolate alarms circuit as indicated on chart?

All sensors operated mannually indicate proper vessel and location on remote monitoring systems.

Are Fire/Flood sensors correctly located in respect to electrical power and water tight sub-division of a ship?

Visual and audible alarms activate when the sensor is actuated.

Each fire wire heat sensor is activated.

Each smoke detector is activated using canned smoke to ensure its proper operation.

Have all other discrepancies been reported? If not report them here.

Flood Tip Float (MOB B) FWD Draft:

AFT Draft:

List:

Comments:

Inspector

Line Item # Location Discrepancy

Berthed At:

Quarter:

NSTM 50 INSPECTION GUIDELINES

FF4

Insp Date:

TDL

Remarks N/A

NO

YES

Description Item Visual and audible alarms activate when the sensor is actuated.

Activate all flooding sensors by tipping floats or shorting probes to check for proper operation.

Are sensor cutout switches numbered and chart present? Do cutouts isolate alarms circuit as indicated on chart?

All sensors operated mannually indicate proper vessel and location on remote monitoring systems.

Are Fire/Flood sensors correctly located in respect to electrical power and water tight sub-division of a ship?

Each heat sensor is activated using a hot air gun to ensure its proper operation. (exercise extreme caution to prevent damage to heat dectecting element due to overheating) Each smoke detector is activated using canned smoke to ensure its proper operation.

Have all other discrepancies been reported? If not report them here.

Flood Tip Float (Non MOB B) FWD Draft:

AFT Draft:

List:

Comments:

Inspector

Line Item # Location Discrepancy