Exec Milestones (Contractural)
| USS MASON DDG 87 DMP | Offerors are not to propose milestones highlighted in Orange. These milestones are calculated. | |||
| Offerors are to propose milestones highlighted in Blue in accordance with "Notes". Entering dates into the blue cells will allow the milestone spreadsheet to calculated the remaining interim milestones. | ||||
| System | Milestones (Calculated or Proposed) | Work Days Prior to "END OF AVAIL" Milestone | Notes | |
| Avail Start | Monday, February 03, 2020 | |||
| DOCK | Offeror to Propose Dock Dates IAW Specification 997-11-001 | |||
| Dry Dock Reports Due (No Later Than) | Sunday, December 31, 1899 | Reports due on the date in Column C or, if the date in Column C is on a weekend or Government holiday, due on the next Government business day following the date in Column C | ||
| UNDOCK | Offeror to Propose Undock Dates IAW Specification 997-11-001 | |||
| 20% Open and Inspect CFRs due | Saturday, April 18, 2020 | Reports due on the date in Column C or, if the date in Column C is on a weekend or Government holiday, due on the next Government business day following the date in Column C | ||
| 2 | 25% CONFERENCE | Tuesday, May 12, 2020 | Conference to be held on the next Wednesday following the date in Column C | |
| 40 | 50% CONFERENCE | Tuesday, August 18, 2020 | Conference to be held on the next Wednesday following the date in Column C | |
| 75% CONFERENCE | Monday, November 23, 2020 | Conference to be held on the next Wednesday following the date in Column C | ||
| HM&E T/O 1 to AIT (Oil Lab) | Monday, June 29, 2020 | 235 | ||
| HM&E T/O 2 to AIT (Aft Strng, Repair 3, 3 GTG) | Monday, July 13, 2020 | 225 | ||
| 2 F/O groups closed & ready (any two from grps 1 thru 6). Includes 70403K, 77829K impacts | Wednesday, July 15, 2020 | 223 | ||
| HM&E T/O 3 to AIT (CCS, Repair 5) | Monday, August 03, 2020 | 210 | ||
| 2 F/O groups closed & ready (any two from grps 1 thru 6). Includes 70403K, 77829K impacts | Wednesday, August 12, 2020 | 203 | ||
| CS TO 1 to AIT Begin | Friday, August 14, 2020 | 201 | ||
| HM&E T/O 4 to AIT (MER 1, AUX 1, Repair 2) | Monday, August 17, 2020 | 200 | ||
| HM&E T/O 5 to AIT (MER 2) | Friday, August 28, 2020 | 191 | ||
| ALL FO TANKS TURNED OVER, CONTINUE FCS Testing | Wednesday, September 09, 2020 | 183 | ||
| 21 | Firemain Restored | Friday, September 11, 2020 | 181 | |
| 13 | CS T/O 2 to AIT Begin | Friday, September 11, 2020 | 181 | |
| HM&E T/O 6 to AIT (Pot Water Sys per 71604) | Monday, September 14, 2020 | 180 | ||
| 39 | HM&E T/O 7 to AIT (70403K, 76253K & AHSSS Vent Mod) | Monday, October 05, 2020 | 165 | |
| Support Systems Restoration | Monday, October 19, 2020 | 155 | ||
| CS T/O 3 to AIT Begin | Friday, October 23, 2020 | 151 | ||
| CSSE Light Off | Friday, November 06, 2020 | 141 | ||
| HAB COMPLETE | Thursday, November 12, 2020 | 137 | ||
| Commence Crew Move Aboard | Friday, November 13, 2020 | 136 | ||
| Combat System T/O 4 to AIT | Friday, November 13, 2020 | 136 | ||
| 42 | Combat Systems AEGIS Light Off (ALO) | Friday, November 20, 2020 | 131 | |
| Engineering Plant Production Completion Date (PCD) | Friday, November 27, 2020 | 126 | ||
| Commence Hot Plant Testing | Monday, December 07, 2020 | 120 | ||
| Complete Hot Plant Testing | Friday, January 15, 2021 | 91 | ||
| LOA Start | Tuesday, February 16, 2021 | 69 | ||
| Fuel ship for sea trials | Tuesday, February 23, 2021 | 64 | ||
| Dock Trials | Wednesday, February 24, 2021 | 63 | ||
| 51 | Fast Cruise | Thursday, February 25, 2021 | 62 | |
| HM&E SEA TRIALS (CSST 1) | Monday, March 01, 2021 | 60 | ||
| Transit to NAVSTA | Friday, March 05, 2021 | 56 | ||
| KTR Contract Complete | Friday, March 05, 2021 | 56 | ||
| Availability Complete | Friday, May 21, 2021 | - Offeror to Propose "END OF AVAIL" milestone date no later than 20 May 2022 |
- Proposed date must be a Government Work Day
| END OF AVAIL (KEY EVENT) No Later than Date | Friday, May 21, 2021 |
| "Days Completed Early" for use in the Value Adjusted Total Evaluated Price Tradeoff (VATEP) Schedule Adjustment | 0 |
A+ Dates Rev9
| DDG-57 EDSRA 2013 A + DATES | |||||||||||||
| REV9 | 17-Apr-13 | ||||||||||||
| SUN | MON | TUE | WED | THU | FRI | SAT | SUN | MON | TUE | WED | THU | FRI | SAT |
| 3-Feb-13 | 4-Feb-13 | 5-Feb-13 | 6-Feb-13 | 7-Feb-13 | 8-Feb-13 | 9-Feb-13 | 10-Feb-13 | 11-Feb-13 | 12-Feb-13 | 13-Feb-13 | 14-Feb-13 | 15-Feb-13 | 16-Feb-13 |
| XST to BAE | |||||||||||||
| 17-Feb-13 | 18-Feb-13 | 19-Feb-13 | 20-Feb-13 | 21-Feb-13 | 22-Feb-13 | 23-Feb-13 | 24-Feb-13 | 25-Feb-13 | 26-Feb-13 | 27-Feb-13 | 28-Feb-13 | 1-Mar-13 | 2-Mar-13 |
| 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | ||
| 3-Mar-13 | 4-Mar-13 | 5-Mar-13 | 6-Mar-13 | 7-Mar-13 | 8-Mar-13 | 9-Mar-13 | 10-Mar-13 | 11-Mar-13 | 12-Mar-13 | 13-Mar-13 | 14-Mar-13 | 15-Mar-13 | 16-Mar-13 |
| Dock | |||||||||||||
| 13 | 14 | 15 | 16 | 17 | 18 | 19 | 20 | 21 | 22 | 23 | 24 | 25 | 26 |
| 17-Mar-13 | 18-Mar-13 | 19-Mar-13 | 20-Mar-13 | 21-Mar-13 | 22-Mar-13 | 23-Mar-13 | 24-Mar-13 | 25-Mar-13 | 26-Mar-13 | 27-Mar-13 | 28-Mar-13 | 29-Mar-13 | 30-Mar-13 |
| 27 | 28 | 29 | 30 | 31 | 32 | 33 | 34 | 35 | 36 | 37 | 38 | 39 | 40 |
| 31-Mar-13 | 1-Apr-13 | 2-Apr-13 | 3-Apr-13 | 4-Apr-13 | 5-Apr-13 | 6-Apr-13 | 7-Apr-13 | 8-Apr-13 | 9-Apr-13 | 10-Apr-13 | 11-Apr-13 | 12-Apr-13 | 13-Apr-13 |
| 25% Conf | |||||||||||||
| 41 | 42 | 43 | 44 | 45 | 46 | 47 | 48 | 49 | 50 | 51 | 52 | 53 | 54 |
| 14-Apr-13 | 15-Apr-13 | 16-Apr-13 | 17-Apr-13 | 18-Apr-13 | 19-Apr-13 | 20-Apr-13 | 21-Apr-13 | 22-Apr-13 | 23-Apr-13 | 24-Apr-13 | 25-Apr-13 | 26-Apr-13 | 27-Apr-13 |
| Turnover 1 | Turnover 2 | ||||||||||||
| 55 | 56 | 57 | 58 | 59 | 60 | 61 | 62 | 63 | 64 | 65 | 66 | 67 | 68 |
| 28-Apr-13 | 29-Apr-13 | 30-Apr-13 | 1-May-13 | 2-May-13 | 3-May-13 | 4-May-13 | 5-May-13 | 6-May-13 | 7-May-13 | 8-May-13 | 9-May-13 | 10-May-13 | 11-May-13 |
| Turnover 3 | #1 SWBD | #3 SWBD | #2 SWBD | ||||||||||
| 69 | 70 | 71 | 72 | 73 | 74 | 75 | 76 | 77 | 78 | 79 | 80 | 81 | 82 |
| 12-May-13 | 13-May-13 | 14-May-13 | 15-May-13 | 16-May-13 | 17-May-13 | 18-May-13 | 19-May-13 | 20-May-13 | 21-May-13 | 22-May-13 | 23-May-13 | 24-May-13 | 25-May-13 |
| Turnover 4 | Turnover 5 | ||||||||||||
| 83 | 84 | 85 | 86 | 87 | 88 | 89 | 90 | 91 | 92 | 93 | 94 | 95 | 96 |
| 26-May-13 | 27-May-13 | 28-May-13 | 29-May-13 | 30-May-13 | 31-May-13 | 1-Jun-13 | 2-Jun-13 | 3-Jun-13 | 4-Jun-13 | 5-Jun-13 | 6-Jun-13 | 7-Jun-13 | 8-Jun-13 |
| 2 FO Banks | Turnover 6 | ||||||||||||
| 97 | 98 | 99 | 100 | 101 | 102 | 103 | 104 | 105 | 106 | 107 | 108 | 109 | 110 |
| 9-Jun-13 | 10-Jun-13 | 11-Jun-13 | 12-Jun-13 | 13-Jun-13 | 14-Jun-13 | 15-Jun-13 | 16-Jun-13 | 17-Jun-13 | 18-Jun-13 | 19-Jun-13 | 20-Jun-13 | 21-Jun-13 | 22-Jun-13 |
| Turnover 7 | 50% Conf | 2 FO Banks | Undock | VCHT | |||||||||
| 111 | 112 | 113 | 114 | 115 | 116 | 117 | 118 | 119 | 120 | 121 | 122 | 123 | 124 |
| 23-Jun-13 | 24-Jun-13 | 25-Jun-13 | 26-Jun-13 | 27-Jun-13 | 28-Jun-13 | 29-Jun-13 | 30-Jun-13 | 1-Jul-13 | 2-Jul-13 | 3-Jul-13 | 4-Jul-13 | 5-Jul-13 | 6-Jul-13 |
| SW/CCS DK | PW | FM/AFFF/Halon/LP/HP/ENG Vent/MRG LO | LOFSP | 2 FO Banks | PH Dk BA/CHW/AC/Steer | ||||||||
| 125 | 126 | 127 | 128 | 129 | 130 | 131 | 132 | 133 | 134 | 135 | 136 | 137 | 138 |
| 7-Jul-13 | 8-Jul-13 | 9-Jul-13 | 10-Jul-13 | 11-Jul-13 | 12-Jul-13 | 13-Jul-13 | 14-Jul-13 | 15-Jul-13 | 16-Jul-13 | 17-Jul-13 | 18-Jul-13 | 19-Jul-13 | 20-Jul-13 |
| CRP | 400HZ | DIU Cal | AHSS/JP5 | FUELING | |||||||||
| 139 | 140 | 141 | 142 | 143 | 144 | 145 | 146 | 147 | 148 | 149 | 150 | 151 | 152 |
| 21-Jul-13 | 22-Jul-13 | 23-Jul-13 | 24-Jul-13 | 25-Jul-13 | 26-Jul-13 | 27-Jul-13 | 28-Jul-13 | 29-Jul-13 | 30-Jul-13 | 31-Jul-13 | 1-Aug-13 | 2-Aug-13 | 3-Aug-13 |
| Hab Vent | FO Test Comp | COMX HPT | NAVSSI/67/73 | AHSS Vent Test | |||||||||
| 153 | 154 | 155 | 156 | 157 | 158 | 159 | 160 | 161 | 162 | 163 | 164 | 165 | 166 |
| 4-Aug-13 | 5-Aug-13 | 6-Aug-13 | 7-Aug-13 | 8-Aug-13 | 9-Aug-13 | 10-Aug-13 | 11-Aug-13 | 12-Aug-13 | 13-Aug-13 | 14-Aug-13 | 15-Aug-13 | 16-Aug-13 | 17-Aug-13 |
| 75% Conf | AHSS Cal | ALO | |||||||||||
| 167 | 168 | 169 | 170 | 171 | 172 | 173 | 174 | 175 | 176 | 177 | 178 | 179 | 180 |
| 18-Aug-13 | 19-Aug-13 | 20-Aug-13 | 21-Aug-13 | 22-Aug-13 | 23-Aug-13 | 24-Aug-13 | 25-Aug-13 | 26-Aug-13 | 27-Aug-13 | 28-Aug-13 | 29-Aug-13 | 30-Aug-13 | 31-Aug-13 |
| AHSS Cert | Hab T/O | ||||||||||||
| 181 | 182 | 183 | 184 | 185 | 186 | 187 | 188 | 189 | 190 | 191 | 192 | 193 | 194 |
| 1-Sep-13 | 2-Sep-13 | 3-Sep-13 | 4-Sep-13 | 5-Sep-13 | 6-Sep-13 | 7-Sep-13 | 8-Sep-13 | 9-Sep-13 | 10-Sep-13 | 11-Sep-13 | 12-Sep-13 | 13-Sep-13 | 14-Sep-13 |
| HPT COMP | PCD | Move NOB | LOA Prep | ||||||||||
| 195 | 196 | 197 | 198 | 199 | 200 | 201 | 202 | 203 | 204 | 205 | 206 | 207 | 208 |
| 15-Sep-13 | 16-Sep-13 | 17-Sep-13 | 18-Sep-13 | 19-Sep-13 | 20-Sep-13 | 21-Sep-13 | 22-Sep-13 | 23-Sep-13 | 24-Sep-13 | 25-Sep-13 | 26-Sep-13 | 27-Sep-13 | 28-Sep-13 |
| Fueling/JP5 | |||||||||||||
| 209 | 210 | 211 | 212 | 213 | 214 | 215 | 216 | 217 | 218 | 219 | 220 | 221 | 222 |
| 29-Sep-13 | 30-Sep-13 | 1-Oct-13 | 2-Oct-13 | 3-Oct-13 | 4-Oct-13 | 5-Oct-13 | 6-Oct-13 | 7-Oct-13 | 8-Oct-13 | 9-Oct-13 | 10-Oct-13 | 11-Oct-13 | 12-Oct-13 |
| LOA | LOA | LOA | LOA | LOA/DT | FC | Sea Trials | Sea Trials | Sea Trials | EOA |
&D
EquipCable Turnover R9
USS MITSCHER DDG-57
DDGM BF Critical Path Equipment/Cable Turnover, Power-up & Test Requirement Schedule
REV9, 17APR13
| Equipment | A + | Date | Comments |
| Turnover 1 | |||
| SPS-73 ISEA Disconnect SAOP for relocation | 26-Feb-13 | ||
| All Power Sources and Terminal Boxes for Equipment in A+45, A+55 & A+64 to also include new and upgraded sources.* | 44 | 17-Apr-13 | *To include but not limited to: LC11, 12, 13, 21, 23, 24, 25, 31, 32, 33, 34, 35, 41; PP 3-210-2, 2-299-1, 2-299-2, 01-129-2, 1-268-1, 1-288-1, 2-199-2, 3-219-2, 3-173-3, 4-131-1, 2-199-4, 2-219-1, 1-113-1, 3-116-1, 01-130-0, 1-157-2 as per SIDs. |
paul.r.jackson: Tim Gudge:
This is a list of all new or fully upgraded power panels that power 1st-3rd T/O equipment. Some will be removed and put in 4th T/O as they are secondary sources.
| GEDMS Mesh B (BSE B1-B10) | 44 | 17-Apr-13 | |
| GEDMS Mesh A BSEs and power cables affecting 1st Turnover IOUs* | 44 | 17-Apr-13 | *Mount BSE enclosure and provide J2 connector and cable for IOU power. Fiber not required until MESH A light-off. (BSE A03: J2: 3-210-2-1L-C) (BSE A10: J2: 3-210-2-1L-G) (BSE A04: J2 : LC25-1L-A8) |
robert.gudge: robert.gudge:
have to check power source.
| IOUs: 31, 32, 34, 42, 72, 82 | 44 | 17-Apr-13 | |
| USEs 31A, 31B, 32A, 32B, 34A, 34B, 42A, 72A, 82A & All Associated UPS, Relay Enclosures, Junction Boxes, and C/O Switches | 44 | 17-Apr-13 | |
| C-DR Boxes 12, 13, 14, 14A, 15, 15A, 16, 24, 37 | 44 | 17-Apr-13 | Install FDS ITB Modification Kit for the following ITB's; 12, 12A, 13, 13A, 14, 15, 16, 16A, 17, 17A, 25 & 25A. |
| Turnover 2 | |||
| UCCs 1 & 2 | 51 | 24-Apr-13 | |
| RSC DCC, C/O SW & Speaker | 51 | 24-Apr-13 | Hold Keyboard, 40" Monitor & Printer for later installation per SMR direction. |
| RSC Repair 5, C/O SW, Speaker & Access Cut | 51 | 24-Apr-13 | Hold Keyboard for later installation per SMR direction. |
| TIWS (CCS) | 51 | 24-Apr-13 | LAN Drop & Power Outlet |
| IOUs: 73, 74, 83, 84, 94 | 51 | 24-Apr-13 | |
| GEDMS Mesh A BSEs and power cables affecting 2nd Turnover IOUs* | 51 | 24-Apr-13 | *Mount BSE enclosure and provide J2 connector and cable for IOU power. Fiber not required until MESH A light-off. (BSE A09: J2: LC33-1L-H1) (BSE A06: J2: LC25-1L-A12) |
robert.gudge: robert.gudge:
have to check power source.
| C-DR Boxes 7, 8, 8A, 11, 25, 26, 31 | 51 | 24-Apr-13 | Install FDS ITB Modification Kit for the following ITB's; 7, 7A, 11, 11A, 26, & 26A. |
| USEs 73A, 74A, 74C, 83A, 83B, 84A, 94A & All Associated UPS, Relay Enclosures, Junction Boxes, and C/O Switches | 51 | 24-Apr-13 | |
| Turnover 3 | |||
| Electric Plant DIU 1 (Power/Network/Shipside Cabling) | 60 | 03-May-13 | |
| Propulsion DIU 4 (Power/Network/Shipside Cabling) | 60 | 03-May-13 | |
| UCC 3 | 60 | 03-May-13 | |
| ECs 1A, 1B (Power/Network/Shipside Cabling) | 60 | 03-May-13 | |
| FADC 1 | 60 | 03-May-13 | |
| RSC Repair 2, C/O SW, Speaker | 60 | 03-May-13 | Hold Keyboard for later installation per SMR direction. |
| TIWS (MER 1) | 60 | 03-May-13 | LAN Drop & Power Outlet |
| RSC CSMC, C/O SW, Speaker | 60 | 03-May-13 | Hold Keyboard for later installation per SMR direction. |
| Fire Detection System ITB Upgrade Electrical Mods & Cabling for IOUs in T/Os 1, 2, and 3. | 60 | 03-May-13 | |
| IOUs: 22, 33, 61, 62 | 60 | 03-May-13 | |
| GEDMS Mesh A BSEs and power cables affecting 3rd Turnover IOUs* | 60 | 03-May-13 | *Mount BSE enclosure and provide J2 connector and cable for IOU power. Fiber not required until MESH A light-off. (BSE A02: J2: (3-210-2-1L-D) |
robert.gudge: robert.gudge:
Have to check power source.
robert.gudge: robert.gudge:
have to check power source.
paul.r.jackson: Tim Gudge:
| This is a list of all new or fully upgraded power panels that power 1st-3rd T/O equipment. Some will be removed and put in 4th T/O as they are secondary sources. | C-DR Boxes 19, 21, 22, 23, 23A | 60 | 03-May-13 | Install FDS ITB Modification Kit for the following ITB's; 20, 20A, 22, 23, 23A, 24 & 24A. |
| USEs 22A, 33A, 61A, 62A & All Associated UPS, Relay Enclosures, Junction Boxes, and C/O Switches | 60 | 03-May-13 | ||
| F/O, L/O & CRP valves associated with SCD 71604K, Including electrical hook-up, in MER1 | 60 | 03-May-13 | 1A/1B F/O Filt/Sep Outlet, #1MRG Pur Suct/Fill, #1CRP Pur Suct/Fill | |
| #1 SWBD and related Load Centers and 1SF Special Frequency SWBD (2-Days) | 63 | 06-May-13 | Conduct all tie-ins and install Thermal Monitoring System | |
| #3 SWBD and related Load Centers and 2SF Special Frequency SWBD (2-Days) | 65 | 08-May-13 | Conduct all tie-ins and install Thermal Monitoring System | |
| #2 SWBD/1SA and any outstanding work/Final Ringout (2-Days, Ships's 60HZ PWR Secured) | 67 | 10-May-13 | Conduct all tie-ins and install Thermal Monitoring System | |
| Turnover 4 | ||||
| All Power Sources & Terminal Boxes for Equipment in A+73, A+83 and A+92* | 72 | 15-May-13 | *To include but not limited to: PP 02-167-1, 01-178-2, 2-116-1, 3-173-3, 2-48-1, 2-299-1, 3-258-1, 2-405-2, 1-143-2, 2-282-1, 3-256-2, 3-284-3, 04-154-2, 3-442-2, 3-442-1, 1-157-2, 03-142-2, 03-141-1, 03-154-2, 03-133-1, 03-129-1, 03-132-1, 03-130-1, 3-213-2, 3-255-1 as per SIDs. |
paul.r.jackson: Tim Gudge:
This is a list of all new or fully upgraded power panels that feed 4th-6th T/O equipment. Some will be added from the list in 1st T/O.
| Electric Plant DIUs 2 & 3 (Power/Network/Shipside Cabling) | 72 | 15-May-13 | |
| Propulsion DIU 5 (Power/Network/Shipside Cabling) | 72 | 15-May-13 | |
| UCC 4 | 72 | 15-May-13 | |
| RSC Repair 3, C/O SW, Speaker | 72 | 15-May-13 | Hold Keyboard for later installation per SMR direction. |
| ECs 2A, 2B (Power/Network/Shipside Cabling) | 72 | 15-May-13 | |
| FADCs 2 & 3 | 72 | 15-May-13 | |
| TIWS (MER 2) | 72 | 15-May-13 | LAN Drop & Power Outlet |
| Aft Steering Unit (ASU) | 72 | 15-May-13 | |
| Local Control Steering Units (LCUs 1 - 4) | 72 | 15-May-13 | |
| IOUs: 11, 13, 14, 41, 51, 81 | 72 | 15-May-13 | |
| C-DR Boxes 1, 10, 17, 27, 28, 28A, 30, 33, 34, 35, 36 | 72 | 15-May-13 | Install FDS ITB Modification Kit for the following ITB's; 1, 10, 18, 27, 27A, 28, & 30. |
| USE 11A, 13A, 14A, 41A, 51A, 81A & All Associated UPS, Relay Enclosures, Junction Boxes, and C/O Switches | 72 | 15-May-13 | |
| F/O, L/O & CRP valves associated with SCD 71604K, Including electrical hook-up, in MER2 | 72 | 15-May-13 | 2A/2B F/O Filt/Sep Outlet, #2MRG Pur Suct/Fill, #2CRP Pur Suct/Fill |
| Turnover 5 | |||
| Ship Control Console (SCC) | 81 | 24-May-13 | |
| BCCS | 81 | 24-May-13 | |
| HFS | 81 | 24-May-13 | |
| IBNS Racks 1, 2, including HS Firewall, UPS & C/O Switches | 81 | 24-May-13 | |
| IBNS Radar Rack | 81 | 24-May-13 | |
| Trigger/Video Amp/Nulka Processor | 81 | 24-May-13 | |
| IBNS NAV 1 computer (Pilot House) | 81 | 24-May-13 | |
| IBNS NAV 2 computer (Chart Room) | 81 | 24-May-13 | |
| IBNS NAV 3 computer (CIC) | 81 | 24-May-13 | |
| IBNS NAV 4 computer (CO's Laptop) | 81 | 24-May-13 | |
| SPS-73 SAOP, Ethernet SW, C/O SW & UPS | 81 | 24-May-13 | |
| NAVSSI Inputs to IBNS/SAOP | 81 | 24-May-13 | |
| ELS & LAN Drops/Receptacles | 81 | 24-May-13 | |
| RSC CIC & C/O Switch | 81 | 24-May-13 | Hold Keyboard for later installation per SMR direction. |
| Pilot House IBNS Trainer / RSC | 81 | 24-May-13 | Hold Keyboard, Training Monitors, Joystick & Cables for later installation per SMR direction. |
| IOUs: 21, 23, 53, 71, 91, 93 | 81 | 24-May-13 | |
| GEDMS Mesh A BSEs and power cables affecting 5th Turnover IOUs* | 81 | 24-May-13 | *Mount BSE enclosure and provide J2 connector and cable for IOU power. Fiber not required until MESH A light-off. (BSE A01: J2: (3-210-2-1L-A) (BSE A08: J2: LC33-1L-F) (BSE A07: J2; LC25-1L-A10) (BSE A05: J2: LC25-1L-A11) |
robert.gudge: robert.gudge:
Have to check power source.
robert.gudge: robert.gudge:
have to check power source.
paul.r.jackson: Tim Gudge:
| This is a list of all new or fully upgraded power panels that feed 4th-6th T/O equipment. Some will be added from the list in 1st T/O. | C-DR Boxes 4, 6, 5, 5A, 9, 18, 20, 32 | 81 | 24-May-13 | Install FDS ITB Modification Kit for the following ITB's; 2, 4, 5, 6, 8, 8A, 9, 19, 19A, 21, & 21A. |
| Oil Lab PC (SCD 70403K) | 81 | 24-May-13 | Includes all cabling, connections, Oil Lab PC, C-DR 40-43, SCD 70403K, | |
| 2 Fuel banks closed & ready to test (any two from groups 1 through 6) | 89 | 01-Jun-13 | Includes requirements of SCD 70403K and 77829K for those tanks (MOVs, XDCRs, Press SWs, Flow Meters, C-DR 40-43, TDRs, cabling, connections) | |
| Turnover 6 | ||||
| Continuous Thermal Monitoring System | 92 | 04-Jun-13 | ADACS unit in MER2, including power and all hook-ups | |
| GEDMS Maintenance Group | 92 | 04-Jun-13 | ||
| GEDMS Mesh A BSE A1-A10 Light Off | 92 | 04-Jun-13 | ||
| Turnover 7 | ||||
| SPS-73 ISEA Connectorize SAOP | 98 | 10-Jun-13 | ||
| DVSS - ALL VIROEs, CJBs, Cables (*) | 98 | 10-Jun-13 | ||
| IOU: 92 & Associated UPS, Relay Enclosure, Junction Boxes, and C/O Switches | 98 | 10-Jun-13 | ||
| C-DR Box 2 & 2A | 98 | 10-Jun-13 | ||
| 2 Fuel banks closed & ready to test (any two from groups 1 through 6) | 106 | 18-Jun-13 | Includes requirements of SCD 70403K and 77829K for those tanks (MOVs, XDCRs, Press SWs, Flow Meters, C-DR 40-43, TDRs, cabling, connections) | |
| CCS Deck COMPLETE | 113 | 25-Jun-13 | ||
| Potable Water System, incl Tanks, TBs, MOVs, TLIs & Modified Pump Controllers | 114 | 26-Jun-13 | ||
| Ventilation - Engineering, CPS Zone 4, Exhaust & Supply | 116 | 28-Jun-13 | E=SS01-150-1, SS01-150-3, ES01-146-1, ES01-146-3, SS2-203-1, ES01-191-1, SS3-251-2, ES01-258-2, SS2-262-2, SS2-270-1, ES01-243-1, ES01-255-2 |
CPS=SS01-301-2, SS01-305-2, ES01-308-2, ES01-309-2, ES01-308-4
| LO Filter Separator Purifier (SCD 76253K) | 119 | 01-Jul-13 | |
| Remaining fuel tank groups closed & ready to test - SCD 70403K COMPLETE | 120 | 02-Jul-13 | Includes requirements of SCD 70403K and 77829K for those tanks (MOVs, XDCRs, Press SWs, Flow Meters, C-DR 40-43, TDRs, cabling, connections) |
| All TLI's not previously turned over, Including Redundant, Radar/TDR and associated TBs, JP-5, all electrical work COMPLETE, SCDs 77829K/77269K COMPLETE | 120 | 02-Jul-13 | SCD 77829K, Includes all cabling, C-DR boxes, TBs, etc. from sensor/component to DIU (INCL OW, CRP & MRG due to DIU tie-ins) |
| Pilot House Deck COMPLETE | 123 | 05-Jul-13 | |
| AHSS Install Complete, Including Vent Mod | 131 | 13-Jul-13 | |
| Digital Indicators SCD 77427 COMPLETE | 138 | 20-Jul-13 | Placeholder |
| (*) Install all DVSS Cameras as directed by PMR |
| 70403 | Digital Fuel Fill Control System |
| 71604 | Machinery Control Station/Damage Control Station Upgrade |
| 71605 | Advanced Galley Mod |
| 71615 | Digital Video Surveillance System |
| 71726 | Full IBNS Upgrade |
| 71734 | Joint Biological Point Detect System |
| 77269 | Redundant TLI in GEN HD TK |
| 73088 | Gigabit Ethernet Data Multiplex System |
| 73622 | H2S Detector System in VCHT Rooms |
| 76034 | Emer JP5 Fill to #3 GEN HD TK |
| 76253 | Lube Oil Filter Separator Purifier |
| 76974 | Moriah WS HW For DDG Mod Plan |
| 77259 | EM Log Rpl AN/WSN-9(V)1 Digital Hybrid Speed Log (DHYSL) |
| 77427 | Digital Indicators |
| 77829 | Radar and TDR TLI's for DFM/JP5/PotWtr |
&P
Shipbd Test Major Milestone R9
| DDG 57 GEDMS/MCS/IBNS/DVSS/DFC INTEGRATED TEST SCHEDULE | |||||
| INTERNAL MAJOR MILESTONES - REV9, 19APR13 | |||||
| System | Scheduled | Revised (4/17/13) | Actual End | A+ Dates | |
| Ship Move to BAE | Thursday, February 07, 2013 | 2/7/13 | |||
| DOCK SHIP (Tentative) | Tuesday, March 05, 2013 | 3/5/13 | 1 | ||
| 1 | TURNOVER 1 | Wednesday, April 17, 2013 | 3/15/13 | 44 | |
| 2 | TURNOVER 2 | Wednesday, April 24, 2013 | 51 | ||
| 3 | GEDMS MESH B POWER UP/INITIAL SW LOAD (ISEA) | Monday, April 29, 2013 | 56 | ||
| 4 | DFC (LM2500) TRAINING (ISEA) | Wednesday, May 01, 2013 | 58 | ||
| 7 | TURNOVER 3 | Friday, May 03, 2013 | 60 | ||
| 6 | #1/3/2 SWBD/LC/1SF/2SF TIE-IN/CTM INSTALL - 6-11 MAY | Monday, May 06, 2013 | 63 | ||
| GEDMS TEMPORARY 3GMG (COMMS AVAILABLE)(ISEA) | Wednesday, May 08, 2013 | 65 | |||
| 8 | START FDS HARNESS CHECKS (T/O 1,2,3) (ISEA) | Wednesday, May 08, 2013 | 65 | ||
| 9 | TURNOVER 4 | Wednesday, May 15, 2013 | 72 | ||
| 10 | START FDS INITIAL POWER UP (ISEA) | Thursday, May 16, 2013 | 73 | ||
| 11 | MCS PWR UP/EC/MCS SW LOAD (INCL TIWS) (ISEA) | Thursday, May 16, 2013 | 73 | ||
| 13 | MCS/EC GRND ISO/SIG VERIFICATION/COLD TESTING(MER1) | Saturday, May 18, 2013 | 75 | ||
| 14 | TURNOVER 5 | Friday, May 24, 2013 | 81 | ||
| 16 | MCS/EC GRND ISO/SIG VERIFICATION/COLD TESTING(MER2) | Saturday, May 25, 2013 | 82 | ||
| 18 | START DC SENSOR TESTING (ISEA) | Monday, May 27, 2013 | 84 | ||
| 19 | IBNS POWER UP (ISEA) | Monday, May 27, 2013 | 84 | ||
| 21 | 2 FO TANK GROUPS TURNED OVER START TLI/FCS TESTING | Saturday, June 01, 2013 | 89 | ||
| 22 | TURNOVER 6 | Monday, June 03, 2013 | 91 | ||
| 24 | IBNS SIGNAL VERIFICATION/SW LOAD (ISEA) | Wednesday, June 05, 2013 | 93 | ||
| GEDMS MESH A POWER UP (ISEA) | Wednesday, June 05, 2013 | 93 | |||
| 23 | TURNOVER 7 | Monday, June 10, 2013 | 98 | ||
| 24 | 2 FO TANK GROUPS TURNED OVER CONT' TLI/FCS TESTING | Tuesday, June 18, 2013 | 106 | ||
| UNDOCK | Monday, June 03, 2013 | Thursday, June 20, 2013 | 108 | ||
| 20 | VCHT (TANKS/PIPING/PUMPS) | Friday, June 14, 2013 | Friday, June 21, 2013 | 109 | |
| 26 | SWS SYSTEM (PIPING/PUMPS/MOVs) | Tuesday, June 18, 2013 | Tuesday, June 25, 2013 | 113 | |
| DECK IN CCS COMPLETE | Tuesday, June 25, 2013 | 113 | |||
| POTWTR SYSTEM (PIPING/TANKS/PUMPS/MOVs) | Wednesday, June 19, 2013 | Wednesday, June 26, 2013 | 114 | ||
| 27 | FM/AFFF/HALON (PIPING/PUMPS/MOVs) | Friday, June 14, 2013 | Friday, June 28, 2013 | 116 | |
| 28 | VENT SYSTEM (FUELING/HPT, ENG/CPS-Z4) | Wednesday, June 19, 2013 | Friday, June 28, 2013 | 116 | |
| 29 | LP/HP AIR (PIPING/VALVES/COMPRESSORS) | Friday, June 21, 2013 | Friday, June 28, 2013 | 116 | |
| 30 | MRG LO SYSTEM (PIPING/MRGs/PUMPS/FILTERS/COOLERS) | Saturday, June 22, 2013 | Saturday, June 29, 2013 | 117 | |
| 31 | LO FILTER SEPARATOR PURIFIER | Saturday, June 22, 2013 | Monday, July 01, 2013 | 119 | |
| REMAINING FO TANKS TURNED OVER TO TEST | Tuesday, June 25, 2013 | Tuesday, July 02, 2013 | 120 | ||
| 32 | DECK IN PILOT HOUSE COMPLETE | Friday, July 05, 2013 | 123 | ||
| BLEED AIR (PIPING/VALVES) | Thursday, June 27, 2013 | Saturday, July 06, 2013 | 124 | ||
| 33 | STEERING (RUDDERS/RAMS/HPUs) | Thursday, June 27, 2013 | Saturday, July 06, 2013 | 124 | |
| 34 | AC PLANTS / CHILL WATER SYSTEM | Friday, June 28, 2013 | Saturday, July 06, 2013 | 124 | |
| EOSS VALIDATION (ISEA) | Wednesday, July 03, 2013 | Sunday, July 07, 2013 | 125 | ||
| 35 | CPP/CRP (PIPING/SHAFTS/PUMPS/HOPM/OD BOX) | Monday, June 24, 2013 | Sunday, July 07, 2013 | 125 | |
| FCS TRAINING FOR SHIPS FORCE (ISEA/NAG) | Wednesday, June 26, 2013 | Monday, July 08, 2013 | 126 | ||
| DVSS OPERATOR TRAINING (ISEA) | Friday, July 05, 2013 | Monday, July 08, 2013 | 126 | ||
| 36 | LUBE OIL FILTER SEPARATOR TRAINING (ISEA) | Wednesday, June 26, 2013 | Monday, July 08, 2013 | 126 | |
| 400HZ AVAILABLE | Tuesday, July 02, 2013 | Tuesday, July 09, 2013 | 127 | ||
| DIU CALIBRATIONS COMPLETE | Friday, July 05, 2013 | Friday, July 12, 2013 | 130 | ||
| AHSS SYSTEM COMPLETE (INCL VENT MOD) | Saturday, July 06, 2013 | Saturday, July 13, 2013 | 131 | ||
| JP5 (TANKS/TLIs/PIPING/PUMPS/FILTERS) | Saturday, July 06, 2013 | Saturday, July 13, 2013 | 131 | ||
| 37 | RSC TRAINING (ISEA) | Monday, July 01, 2013 | Monday, July 15, 2013 | 133 | |
| 38 | FUEL SHIP | Wednesday, July 03, 2013 | Wednesday, July 17, 2013 | 135 | |
| TIWS TRAINING (ISEA) | Tuesday, July 09, 2013 | Monday, July 22, 2013 | 140 | ||
| VENT SYSTEM (HAB, CPS-Z1-3) | Thursday, July 18, 2013 | Thursday, July 25, 2013 | 143 | ||
| 39 | F/O TESTING COMPLETE | Saturday, July 13, 2013 | Saturday, July 27, 2013 | 145 | |
| 40 | HOT PLANT TESTING COMMENCE | Monday, July 15, 2013 | Monday, July 29, 2013 | 147 | |
| 41 | NAVSSI/IFF/67/73 RADAR AVAILABLE FOR IBNS TESTING | Tuesday, July 23, 2013 | Tuesday, July 30, 2013 | 148 | |
| AHSS VENT VELOCITY TESTING (MSR/BIW) | Monday, July 15, 2013 | Wednesday, July 31, 2013 | 149 | ||
| 42 | AHSS CAL/TESTING/TRAINING (ISEA/OEM) | Thursday, August 01, 2013 | Thursday, August 15, 2013 | 164 | |
| AEGIS LIGHT OFF | Saturday, August 03, 2013 | Saturday, August 17, 2013 | 166 | ||
| 43 | AHSS CERTIFICATION (NHRC) | Monday, August 05, 2013 | Monday, August 19, 2013 | 168 | |
| 44 | HAB TURNOVER / MOVE ABOARD COMMENCE | Thursday, August 08, 2013 | Thursday, August 22, 2013 | 171 | |
| HOT PLANT TESTING COMPLETE | Wednesday, August 21, 2013 | Wednesday, September 04, 2013 | 184 | ||
| 46 | PCD | Thursday, August 22, 2013 | Thursday, September 05, 2013 | 185 | |
| 47 | SHIP MOVES TO NAVSTA | Friday, August 23, 2013 | Friday, September 06, 2013 | 186 | |
| 48 | SHIP LOA PREP | Monday, August 26, 2013 | Monday, September 09, 2013 | 189 | |
| MCS OVER THE SHOULDER TRAINING (ISEA ~5 days) | Monday, August 26, 2013 | Monday, September 09, 2013 | 189 | ||
| IBNS OPERATOR TRAINING | Tuesday, September 03, 2013 | Monday, September 16, 2013 | 196 | ||
| 49 | FUELING / RECEIVE JP5 | Thursday, September 05, 2013 | Thursday, September 19, 2013 | 199 | |
| IBNS IOS/IBNS OPERATOR TRAINING BUFFER | Monday, September 09, 2013 | Monday, September 23, 2013 | 203 | ||
| LOA | Monday, September 16, 2013 | Monday, September 30, 2013 | 210 | ||
| 51 | DOCK TRIALS | Friday, September 20, 2013 | Friday, October 04, 2013 | 214 | |
| 52 | FAST CRUISE | Saturday, September 21, 2013 | Saturday, October 05, 2013 | 215 | |
| 53 | SEA TRIALS | Tuesday, September 24, 2013 | Tuesday, October 08, 2013 | 218 | |
| IBNS TRAINING UNDERWAY | Tuesday, September 24, 2013 | Tuesday, October 08, 2013 | 218 | ||
| 54 | END OF AVAIL | Friday, September 27, 2013 | Friday, October 11, 2013 | 221 | |
| 55 | FINAL SOFTWARE LOAD | Post Sea Trials | |||
| 56 | TLI TESTING (FUELING AT SEA) | Post Sea Trials | |||
| FOLLOW-ON IBNS MAINTENANCE TRAINING (TBD) | Post Sea Trials |
GEDMS Checklist
| DDG61 GEDMS CHECKLIST | |||||||||
| BSE | BSE | IOU | C-DR | NEW | USE-A | USE-B | |||
| A1 | Weight Rm | B1 | Supply Strm 4 | 11 | 30 | ET Shop | 11A | ||
| A2 | DC Locker | B2 | Crew 5 | 13 | 28 | 28A | Load Center 1 | 13A | |
| A3 | PW 1-254-6-L | B3 | Supply Support | 14 | 27 | CO PW 02-154-1-L | 14A | ||
| A4 | PW 1-174-01-L | B4 | Pwr Convers Rm | 21 | 18 | Supply Strm 3 | |||
| A5 | CSMC | B5 | Crew 2 | 22 | 21 | EM Shop | 22A | ||
| A6 | PW 1-78-01-L | B6 | Fwd IC | 23 | 20 | PW 2-338-1-L | |||
| A7 | Sonar | B7 | AUX 1 | 31 | 12 & 13 | MER 2 | 31A | 31B | |
| A8 | Crew 1 | B8 | Supply Strm 1 | 32 | 16 | CCS | 32A | 32B | |
| A9 | MER 1 | B9 | Crew 4 | 33 | 23 | 23A | DC Locker | 33A | |
| A10 | Crew 3 | B10 | Crew 6 | 34 | 37 | MER 2 | 34A | 34B | |
| 41 | 17 | Aft IC | 41A | ||||||
| 42 | 24 | CSER 3 | 42A | ||||||
| 51 | 1 | Fwd IC | 51A | ||||||
| 53 | 5 | 5A | TR 2-116-1-T | ||||||
| 54 | 31 | MER 1 | 54A | ||||||
| 61 | 22 | Rep 3 | 61A | ||||||
| 62 | 19 | Aft Steering | 62A | ||||||
| 71 | 9 | Radio | |||||||
| 72 | 15 | Rep 5 | 72A | ||||||
| 73 | 26 | CSMC | 73A | ||||||
| 74 | 11 | MER 1 | 74A | 74C | |||||
| 81 | 10 | CSER 2 | 81A | ||||||
| 82 | 14 | 14A | OPS Office | 82A | |||||
| 83 | 8 | 8A | Aux 1 | 83A | |||||
| 84 | 25 | Admin | 84A | ||||||
| 91 | 6 | GSE Shop/Gage Cal | |||||||
| 92 | 2 | 2A | Sonar 3 | ||||||
| 93 | 4 | CSER 1 | |||||||
| 94 | 7 | Sec Force Locker | 94A | ||||||
| DELETED: | IOU 12 / C-DR29 IOU 52 / C-DR3 |
Tota # of USE = 26
HM&E Turnovers
| USSMASON DDG87 FY20 DMP Hull/Mechanical and Electrical (HM&E) Turnovers | |||
| Equipment | A+ Contractor turnover to AIT | A+ AIT turnover to test team | Equipment |
| Contractor Responsible | 03-Feb-20 | AIT Responsible | |
| 18-Feb-20 | SPS-73 ISEA Disconnect SAOP for relocation. ISEA to disconnect prior to Contractor rigging | ||
| 26-Mar-20 | Remove all FODMS IOUs (29 total) and ship as directed by drawing. Ripout 12, 13, 52, 61, 73, 81 and 91 foundations. | ||
| MSR HM&E T/O 1 | 29-Jun-20 | 13-Jul-20 | AIT T/O 1 GEDMS Mesh B and MG |
| Complete all contractor work for SA70403 in oil lab. | 29-Jun-20 | 13-Jul-20 | All Power Sources and Terminal Boxes for Equipment in TO 1, TO 2 and TO 3 to also include new and upgraded sources.* |
| 13-Jul-20 | GEDMS Mesh B (BSE B1-B10) and power cables at least one power source has to be available* | ||
| 13-Jul-20 | Install GEDMS Maintenance Group. Removed MG will be shipped as directed by drawing. Install while access cut to Aft IC is open | ||
| MSR HM&E T/O 2 (Aft Strng, Repair 3 & #3 GTG) | 13-Jul-20 | 03-Aug-20 | AIT T/O 2 (Aft Strng, Repair 3 & #3 GTG) |
| Aft Steering Unit (ASU) | 13-Jul-20 | 03-Aug-20 | (Power/Network/Shipside Cabling) |
| Repair 3 foundations installed, equipment loaded and painted iaw spec item | 13-Jul-20 | 03-Aug-20 | RSC Repair 3, UPS, C/O SW, Hold Keyboard for later installation per SMR direction. |
| Local Control Steering Units (LCUs 1 - 4) | 13-Jul-20 | 03-Aug-20 | (Power/Network/Shipside Cabling) |
| Electric Plant DIU 3 | 13-Jul-20 | 03-Aug-20 | (Power/Network/Shipside Cabling) to include FADC #3 |
| 03-Aug-20 | All Power Sources & Terminal Boxes for Equipment in TO 4, TO 5 and TO 6 as per SIDs. | ||
| 03-Aug-20 | Install IOUs: 21, 22, 23, 41 and 62. IIUs 122, 162. C-DR 122, 141 and 162. USE-162B. All associated work related to these IOUs/IIUs/USEs/C-DR boxes | ||
| 2 Fuel groups closed & ready to test (any two from groups 1 through 6). Includes requirements of SA70403K and SA77829K for those tanks (MOVs, XDCRs, Press SWs, Flow Meters, TDRs | 15-Jul-20 | 29-Jul-20 | Includes requirements of SA70403K and SA77829K for those tanks (MOVs, XDCRs, Press SWs, Flow Meters, TDRs, cabling, connections) |
| MSR T/O 3 (CCS & Repair 5) | 03-Aug-20 | 17-Aug-20 | AIT T/O 3 (CCS & Repair 5) |
| CCS & Repair 5 foundations complete and equipment set in place, spaces painted IAW work item. Deck work to be completed while test team is working in MER 1 and 2. | 03-Aug-20 | 17-Aug-20 | Complete SA71604 wiring in CCS, including vent control panels, RSC DCC, UPS and C/O SW. Hold Keyboard, 40" Monitor & Printer for later installation per SMR direction. TIWS (CCS) LAN Drop & Power Outlet |
| SA74012, 77419, 83894 and 89925 complete within CCS | 03-Aug-20 | 17-Aug-20 | |
| 17-Aug-20 | RSC Repair 5, UPS, and C/O SW. Hold Keyboard for later installation per SMR direction. | ||
| 17-Aug-20 | SA70403K complete in Oil Lab, includes all cabling, connections for Oil Lab PC | ||
| 17-Aug-20 | Install IOUs 32, 33, 42, 72. IIUs 132, 142, 172 and 173. C-DRs 132,142, 172 and 173. USE 132B. All associated work related to these IOUs/IIUs/USEs/C-DR boxes | ||
| 2 Fuel groups closed & ready to test (any two from groups 1 through 6). Includes requirements of SA70403K and SA77829K for those tanks (MOVs, XDCRs, Press SWs, Flow Meters, TDRs | 12-Aug-20 | 26-Aug-20 | Includes requirements of SA70403K and SA77829K for those tanks (MOVs, XDCRs, Press SWs, Flow Meters, TDRs, cabling, connections) |
| MSR T/O 4 (MER 1, AUX 1 & Repair 2) | 17-Aug-20 | 28-Aug-20 | AIT T/O 4 (MER 1, AUX 1 & Repair 2) |
| Electric Plant DIU 1 AUX 1 | 17-Aug-20 | 28-Aug-20 | (Power/Network/Shipside Cabling) to include FADC #1 |
| Propulsion DIU 4, UCC 3, ECU 1A and 1B in MER 1; foundations installed, equipment loaded and painted iaw spec item | 17-Aug-20 | 28-Aug-20 | (Power/Network/Shipside Cabling) |
| Repair 2 foundations installed, equipment loaded and painted iaw spec item | 17-Aug-20 | 28-Aug-20 | RSC Repair 2, C/O SW and UPS. Hold Keyboard for later installation per SMR direction. |
| F/O, L/O & CRP valves associated with SA71604K in MER1. 1A/1B F/O Filt/Sep Outlet, #1MRG Pur Suct/Fill, #1CRP Pur Suct/Fill | 17-Aug-20 | 28-Aug-20 | Electrical hook-up of valves associated with SA71604K in MER 1 |
| SA 71605 Galley foundations, piping and electrical complete that impact MER 1 overhead | 17-Aug-20 | ||
| 28-Aug-20 | Install IOUs 71, 74, 82, 83 and 84. IIUs 174, 182 and 183. USEs 174B and 183B. C-DRs 174, 182 and 183. All associated work related to these IOUs/IIUs/USEs/C-DR boxes | ||
| MSR T/O 5 (MER 2) | 28-Aug-20 | 14-Sep-20 | AIT T/O 5 (MER 2) |
| Electric Plant DIU 2, Propulsion DIU 5, UCC 4, ECU 2A and 2B in MER 2; foundations installed, equipment loaded and painted iaw spec item | 28-Aug-20 | 14-Sep-20 | AIT (Power/Network/Shipside Cabling) to include FADC #2 |
| F/O, L/O & CRP valves associated with SCD 71604K in MER2. 2A/2B F/O Filt/Sep Outlet, #2MRG Pur Suct/Fill, #2CRP Pur Suct/Fill | 28-Aug-20 | 14-Sep-20 | AIT (Power/Network/Shipside Cabling) |
| 14-Sep-20 | Install IOU 31 and 51; IIU 131, 134 and 151; C-DR 131, 134 and 151; USE 131B. All associated work related to these IOUs/IIUs/USEs/C-DR boxes | ||
| 14-Sep-20 | ADACS unit in MER2, including power and all hook-ups | ||
| 2 Fuel groups closed & ready to test (any two from groups 1 through 6). Includes requirements of SA70403K and SA77829K for those tanks (MOVs, XDCRs, Press SWs, Flow Meters, TDRs | 09-Sep-20 | 23-Sep-20 | Includes requirements of SA70403K and SA77829K for those tanks (MOVs, XDCRs, Press SWs, Flow Meters, TDRs, cabling, connections) |
| MSR T/O 6 (71604 Potable Water) | 14-Sep-20 | 28-Sep-20 | AIT T/O 6 |
| Complete all work under SA71604 and 77829 for Potable Water system, incl Tanks, TBs, MOVs, TLIs. | 14-Sep-20 | 28-Sep-20 | AIT (Power/Network/Shipside Cabling) Modified PW Pump Controllers |
| 28-Sep-20 | GEDMS Mesh A BSEs (A1-A10) and power cables at least one power source has to be available* | ||
| 28-Sep-20 | Install IOUs 53, 92, 93 and 94. IIU 194. C-DR 194. All associated work related to these IOUs/IIUs/USEs/C-DR boxes | ||
| 28-Sep-20 | SA 71604 and 77829K, Includes all cabling, C-DR boxes, TBs, etc. from sensor/component to DIU for PW system, all electrical work complete | ||
| MSR T/O 7 (70403K, 76253K, 71604 AHSS Vent Mod) | 5-Oct-20 | 19-Oct-20 | AIT T/O 7 (AHSS, DVSS, Dig Indicators) |
| LO Filter Separator Purifier (SA 76253K) complete | 05-Oct-20 | 19-Oct-20 | AIT (Power/Network/Shipside Cabling) |
| AHSS Vent Mod SA71604 dwg 500-8659958 complete | 05-Oct-20 | 19-Oct-20 | AHSS Install Complete |
| 19-Oct-20 | SA71615 DVSS Complete - ALL VIROEs, Cables (*) Install all DVSS Cameras as directed by SMR | ||
| 19-Oct-20 | SA 70403, 71604 and 77829K, Includes all cabling, C-DR boxes, TBs, etc. from sensor/component to DIU (INCL OW, CRP & MRG due to DIU tie-ins) and associated TBs, JP-5, all electrical work complete | ||
| 19-Oct-20 | Digital Indicators SCD 77427 complete except CS spaces | ||
| 19-Oct-20 | Install IOUs 11, 14, IIUs 111, 114, C-DRs 111, 114. Complete all associated work related to these IOUs/IIUs/USEs/C-DR boxes | ||
| HM&E SHIPALT Equipment in Combat Systems MOD Spaces, dates are CS Turnover dates | |||
| Contractor Complete | Date | Date | AIT Complete |
| Aft IC Gyro- SA80612 ICAS complete (Leave cable run to CSER 3 hanging until CANES Rack in place) | 14-Aug-20 | ||
| CIC- SA71604 work complete | 18-Sep-20 | 06-Nov-20 | RADAR 2- SA71726 Trigger/Video Amp installed and wired |
| CIC- SA71726 work complete | 18-Sep-20 | 06-Nov-20 | CIC- SA77427 and SA71726 work complete |
| RADAR 1- SA71726 work complete | 25-Sep-20 | 13-Nov-20 | RADAR 1- SA71726 working complete. IBNS Rack 2 wiring including HS Firewall, UPS & C/O Switches |
| Pilot House- all SA71604 mods complete | 23-Oct-20 | 20-Nov-20 | Pilot House- all SA71604, SA77427 work complete |
| Pilot House- SA71726 SPS-73 SAOP install. (ISEA deliver to Contractor) | 23-Oct-20 | 20-Nov-20 | Pilot House- SA71726, SPS-73 ISEA Connectorize SAOP Ethernet SW, C/O SW & UPS |
| Pilot House- SA71726 work complete | 23-Oct-20 | 20-Nov-20 | Pilot House- SA71726 work complete. Hold Keyboard, Training Monitors, Joystick & Cables for later installation per SMR direction. |
| Pilot House- SA77419 Textile ducting work complete | 23-Oct-20 | 20-Nov-20 | Pilot House- complete all SA77427 mods |
| Pilot House- Painted and deck complete iaw work item | 23-Oct-20 | 20-Nov-20 | |
| CSMC- SA71604 work complete | 30-Oct-20 | 20-Nov-20 | CSMC- SA73091K (BSE A5), SA84226K and SA71604K work complete. Hold Keyboard for later installation per SMR direction. |
| Array Room #1- SA71726 mods complete | 06-Nov-20 | 20-Nov-20 | Array Room 1- SA71726 work complete |
| 14-Aug-20 | Aft IC Gyro 3-300-0-C, SA73091(IOU41, IIU141, CDR 17/141 and MG) and SA77427 complete. | ||
| 14-Aug-20 | Fwd IC Gyro 4-94-0-C, SA73091(IOU51, IIU151, CDR1/151) and SA77427 complete | ||
| 18-Sep-20 | CSER 3 1-300-0-C, SA73091 complete (IOU42, IIU142, CDR 24/142) | ||
| 18-Sep-20 | CSER 2 2-126-2-C, SA73091 complete (CDR10) | ||
| 18-Sep-20 | CIC- SA71604 work complete including RSC, UPS & C/O Switch. Hold Keyboard for later installation per SMR direction. | ||
| 25-Sep-20 | Communications Center 2-126-1-C, SA73091(IOU71, CDR9) and SA77427 complete | ||
| 02-Oct-20 | CSER 1 2-53-1-C, SA73091(IOU93, CDR4) and SA77427 complete | ||
| 16-Oct-20 | SONAR Control 2-50-2-C, SA77427 complete | ||
| 16-Oct-20 | SONAR 3 3-18-0-Q, SA73091 complete (IOU92, CDR2/2A) | ||
| 16-Oct-20 | SONAR 1 1-18-0-Q, SA73091 complete (BSE A7) | ||
| 06-Nov-20 | Power Supply / Conversion Rm 3-126-2-Q, SA73091 complete | ||
| 06-Nov-20 | CSER 4 03-142-1-C, SA73091 complete (IOU 11, IIU 111, CDR 29,30, 111) | ||
| 06-Nov-20 | Chart Room- SA77427 and SA71726 complete, IBNS NAV 2 computer | ||
| 06-Nov-20 | Electric Load Center 03-142-2-Q, SA73091 complete (CDR28) | ||
| 20-Nov-20 | XO Cabin- SA77427 complete | ||
| 20-Nov-20 | CO Cabin- SA77427, 71726 complete; IBNS NAV 4 computer (CO's Laptop), install prior to HAB Turnover |
CS Turnovers
| USS MASON DDG87 FY20 DMP Combat Systems (CS) Turnovers | ||||||||||||
| A+ MSR T/O to AIT Date | AIT/MSR Complete to support testing | SUPPORT SERVICES: Gray Fill Indicates Services Required | ||||||||||
| COMPARTMENT NUMBER | COMPARTMENT NAME | A+ Contractor turnover to AIT | 3-Feb-20 | 60 Hz | 400 Hz | Vent | ECW | Chill Water | Fire Main | Dry Air | HP Air | LP Air |
| TURNOVER 1 | ||||
| 4-94-0-C | IC & Gyro Room #1 (FWD) | 14-Aug-20 | 6-Nov-20 | |
| 3-300-0-C | IC & Gyro Room #2 (AFT) | 14-Aug-20 | 6-Nov-20 | |
| 3-126-2-Q | Power Supply/Conversion Room | 6-Nov-20 | 6-Nov-20 | |
| 3-319-0-Q | Power Conversion Room | 6-Nov-20 | 6-Nov-20 | |
| 4-42-0-Q | Sonar Cooling Equipment Room | 6-Nov-20 | 6-Nov-20 | |
| 4-126-0-E | Auxiliary Machinery Room #1 | 6-Nov-20 | 6-Nov-20 | SWS |
| TURNOVER 2 | ||||
| 2-220-1-Q | SNAP II Computer Room (LAN Room) | 11-Sep-20 | 20-Nov-20 | |
| 2-126-2-C | CSER #2 | 18-Sep-20 | 6-Nov-20 | |
| 1-300-0-C | CSER #3 | 18-Sep-20 | 6-Nov-20 | |
| 1-126-0-C | Combat Information Center (CIC) | 18-Sep-20 | 6-Nov-20 | |
| 03-128-0-C | Radar Room #1 | 25-Sep-20 | 13-Nov-20 | |
| 2-126-1-C | Communications Center (Radio) | 25-Sep-20 | 20-Nov-20 | |
| 03-142-0-C | Radar Room #2 | 2-Oct-20 | 6-Nov-20 | |
| 2-53-1-C | CSER #1 | 2-Oct-20 | 6-Nov-20 | |
| 1-18-0-Q | Sonar Equipment Room #1 | 16-Oct-20 | 13-Nov-20 | |
| 2-18-0-Q | Sonar Equipment Room #2 | 16-Oct-20 | 13-Nov-20 | |
| 3-18-0-Q | Sonar Equipment Room #3 | 16-Oct-20 | 13-Nov-20 | |
| 2-50-2-C | Sonar Control Room | 16-Oct-20 | 13-Nov-20 | |
| 2.5-78-0-M | VLS Magazine #1 (FWD) | 16-Oct-20 | 20-Nov-20 | |
| 2-338-0-M | VLS Magazine #2 (AFT) | 16-Oct-20 | 20-Nov-20 | |
| 2-153-2-C | Tomahawk Equipment Room | 6-Nov-20 | 20-Nov-20 | |
| TURNOVER 3 | ||||
| 06-157-0-T | Mast and Access Trunk | 23-Oct-20 | 20-Nov-20 | |
| 04-130-0-C | Pilot House | 23-Oct-20 | 20-Nov-20 | |
| 05-131-0-Q | Director Equipment Room #1 | 23-Oct-20 | 20-Nov-20 | |
| 01-274-1-C | Radar Room #3 | 30-Oct-20 | 13-Nov-20 | |
| 01-130-0-Q | Combat Systems Maintenance Central | 30-Oct-20 | 20-Nov-20 | |
| 03-142-1-C | CSER #4 | 6-Nov-20 | 20-Nov-20 | |
| 1-46-0-M | 5"/54 Loader Drum & Fan Room | 6-Nov-20 | 20-Nov-20 | |
| 01-130-2-C | SSES | 6-Nov-20 | 20-Nov-20 | |
| 1-314-0-C | CSER 3 Annex | 6-Nov-20 | 20-Nov-20 | |
| 03-128-1-Q | SPY Array Room #1 (FWD/STBD) | 6-Nov-20 | 20-Nov-20 | |
| 03-128-2-Q | SPY Array Room #2 (FWD/PORT) | 6-Nov-20 | 20-Nov-20 | |
| 03-158-3-Q | SPY Array Room #3 (AFT/STBD) | 6-Nov-20 | 20-Nov-20 | |
| 03-158-2-Q | SPY Array Room #4 (AFT/PORT) | 6-Nov-20 | 20-Nov-20 | |
| 02-112-0-Q | CIWS Workshop #1 | 6-Nov-20 | 20-Nov-20 | |
| 2-458-0-Q | MFTA Winch Room | 6-Nov-20 | 20-Nov-20 | |
| 03-112-0-C | CIWS Control Room #1 | 6-Nov-20 | 20-Nov-20 | |
| TURNOVER 4 | ||||
| 1-78-1-Q | VLS Fan Room fwd | 13-Nov-20 | 13-Nov-20 | |
| 1-78-2-Q | VLS Fan Room fwd | 13-Nov-20 | 13-Nov-20 | |
| 3-362-0-Q | VLS Fan Room aft | 13-Nov-20 | 13-Nov-20 | |
| 04-150-0-C | Chart Room (w/4) | 13-Nov-20 | 20-Nov-20 | |
| 1-268-0-C | CCS (VLS Alarms) | 13-Nov-20 | 20-Nov-20 | |
| 2-157-1-C | Radio Transmitter Room | 20-Nov-20 | 20-Nov-20 | |
| 01-300-0-Q | CIWS Wpn & Avn Ord Eqpt Wks | 20-Nov-20 | 20-Nov-20 | |
| 02-299-0-C | CIWS Control Room#2 | 20-Nov-20 | 20-Nov-20 | |
| 03-142-2-Q | Electric Load Center #1 | 20-Nov-20 | 20-Nov-20 | |
| Fwd 03 lvl, Aft 05 lvl | AN/SPY-1 Antenna Arrays | 20-Nov-20 | 20-Nov-20 | |
| 04-272-0-Q | Director Equipment Room #2 | 20-Nov-20 | 20-Nov-20 | |
| 03-282-0-Q | Director Equipment Room #3 | 20-Nov-20 | 20-Nov-20 | |
| 01-330-0-Q | VLS Service Interface Room (AFT) | 20-Nov-20 | 20-Nov-20 | |
| 1-97-2-Q | VLS Service Interface Room (FWD) | 20-Nov-20 | 20-Nov-20 | |
| TURNOVER 5 | ||||
| 02 LVL FR 338-370 | Missile Deck (AFT) | 20-Nov-20 | 20-Nov-20 | |
| 01 LVL FR 78-110 | Missile Deck (FWD) | 20-Nov-20 | 20-Nov-20 | |
| 01-(46-78)-0-M | 5"/54 CAL Gun Mount (MT 51) | 20-Nov-20 | 20-Nov-20 | |
| 06-150-0/Deck | FCS Director #1 | 20-Nov-20 | 20-Nov-20 | |
| 05-280-0/Deck | FCS Director #2 | 20-Nov-20 | 20-Nov-20 | |
| 04-292-0/Deck | FCS Director #3 | 20-Nov-20 | 20-Nov-20 | |
| 01-(247-257) | SVTT (STBD) | 20-Nov-20 | 20-Nov-20 | |
| 01-(240-250) | SVTT (PORT) | 20-Nov-20 | 20-Nov-20 | |
| 2-450-1-Q | NIXIE Room | 20-Nov-20 | 20-Nov-20 | |
| 02-(200-220)-1 | Decoy Launchers (STBD) | 20-Nov-20 | 20-Nov-20 | |
| 02-(200-220)-2 | Decoy Launchers (PORT) | 20-Nov-20 | 20-Nov-20 | |
| 02-(220-237) | NULKA Launchers (PORT) | 20-Nov-20 | 20-Nov-20 | |
| 02-(220-237) | NULKA Launchers (STBD) | 20-Nov-20 | 20-Nov-20 | |
| 03-(142-158)-3 | EW Array SLQ-32 (STBD) | 20-Nov-20 | 20-Nov-20 | |
| 03-(142-158)-4 | EW Array SLQ-32 (PORT) | 20-Nov-20 | 20-Nov-20 | |
| 03-(112-128)-0 | CIWS (MT 21) FWD | 20-Nov-20 | 20-Nov-20 | |
| 02-(300-316)-0 | CIWS (MT 22) AFT | 20-Nov-20 | 20-Nov-20 | |
| 2-442-6-Q | Bathythermograph Room | 20-Nov-20 | 20-Nov-20 | |
| 0 1/2-28-0-Q | Dome Equipment Room | 20-Nov-20 | 20-Nov-20 | |
| 1-304-2-M | Torpedo, Missile & Rocket Mag | 20-Nov-20 | 20-Nov-20 |
GEDMS SA73091 breakout
| Spaces affected: | BSE | IOU | IIU | USE B | C-DR | New C-DR | Turnover | Date |
| Turnover 1 | ||||||||
| 4-370-6-A SUPPLY DEPARTMENT STRM NO. 4 - TCB 1A delete, install new foundation | B1 | TO1 | 13-Jul-20 | |||||
| 3-310-2–L CREW LIVING SPACE NO. 5 - TCB 2a swap with BSE B2 no foundation change | B2 | TO1 | 13-Jul-20 | |||||
| 3-220-2-Q SUPPLY SUPPORT CENTER - TCB 3A swap with BSE B3 no foundation change | B3 | TO1 | 13-Jul-20 | |||||
| 3-126-2-Q POWER SUPPLY/CONVERSION ROOM - TCB 4A swap with BSE B4 no foundation change | B4 | TO1 | 13-Jul-20 | |||||
| 3-97-02-L CREW LIVING SPACE NO. 2 - TCB 5A delete, install BSE B5 on port side | B5 | TO1 | 13-Jul-20 | |||||
| 4-94-0–C IC & GYRO ROOM NO. 1 - TCB 6A swap with BSE B6 no foundation change | B6 | TO1 | 13-Jul-20 | |||||
| 4-126-0-E AUXILIARY MACHINERY ROOM NO. 1 - TCB 7A delete BSE B7 will be in AUX 1 | B7 | TO1 | 13-Jul-20 | |||||
| 3-220-01-A SUPPLY DEPARTMENT STRM NO. 1 - TCB 8A swap with BSE B8 no foundation change | B8 | TO1 | 13-Jul-20 | |||||
| 3-300-1-L CREW LIVING SPACE NO. 4 - TCB 9A swap with BSE B9 no foundation change | B9 | TO1 | 13-Jul-20 | |||||
| 3-338-3-L CREW LIVING SPACE NO. 4 - TCB 10A delete foundation and BSE B10 new foundation | B10 | TO1 | 13-Jul-20 | |||||
| 3-300-0-C Aft Gyro 2 MG swap, no foundation work MUST RETAIN ALL MOUNTING HARDWARE | TO1 | 13-Jul-20 | ||||||
| Turnover 2 | ||||||||
| 4-370-5-A SUPPLY DEPARTMENT STOREROOM NO.3 | 21 | 18 | TO2 | 3-Aug-20 | ||||
| 2-378-2-A AVIATION STOREROOM # 1 | 22 | 122 | 21 | 122 | TO2 | 3-Aug-20 | ||
| 2-338-1-L PASSAGE | 23 | 20 | TO2 | 3-Aug-20 | ||||
| 3-300-0-C IC & GYRO ROOM NO. 2 | 41 | 141 | 17 | 141 | TO2 | 3-Aug-20 | ||
| 4-442-0-E STEERING GEAR ROOM | 62 | 162 | 162B | 19 | 162 | TO2 | 3-Aug-20 | |
| Turnover 3 | ||||||||
| 1-268-0-C CCS | 32 | 132 | 16 | 132 | TO3 | 17-Aug-20 | ||
| 1-258-3-Q ENGINEERING LOG ROOM | 132B | TO3 | 17-Aug-20 | |||||
| 1-330-0-A DAMAGE CONTROL EQUIPMENT LOCKER | 33 | 23/23A | TO3 | 17-Aug-20 | ||||
| 1-300-0-C CSER 3 | 42 | 142 | 24 | 142 | TO3 | 17-Aug-20 | ||
| 1-206-3-A REPAIR 5 | 72 | 172 | 15 | 172 | TO3 | 17-Aug-20 | ||
| 01-130-0-Q CSMC | 173 | 26 | 173 | TO3 | 17-Aug-20 | |||
| Turnover 4 | ||||||||
| 2-126-1-C COMMUNICATIONS CENTER | 71 | 9 | TO4 | 28-Aug-20 | ||||
| 4-174-0-E ENGINE ROOM NO. 1 | 74 | 174 | 174B | 11 | 174 | TO4 | 28-Aug-20 | |
| 1-158-4-Q COMBAT SYSTEM OFFICE (switchboard room) | 82 | 182 | 14 | 182 | TO4 | 28-Aug-20 | ||
| 4-126-0-E AUX 1 | 83 | 183 | 183B | 8/8A | 183 | TO4 | 28-Aug-20 | |
| 01-110-01-Q TECHNICAL LIBRARY ANNEX | 84 | 25 | TO4 | 28-Aug-20 | ||||
| Turnover 5 | ||||||||
| 4-254-0-E ENGINE ROOM NO. 2 | 31 | 131/134 | 131B | 12*13*37 | 131,134 | TO5 | 14-Sep-20 | |
| 4-94-0-C IC & GYRO ROOM NO. 1 | 51 | 151 | 1 | 151 | TO5 | 14-Sep-20 | ||
| Turnover 6 | ||||||||
| 3-116-1-T ACCESS TRUNK | TO6 | 28-Sep-20 | ||||||
| 3-116-1-T ACCESS TRUNK | 53 | 5/5A | TO6 | 28-Sep-20 | ||||
| 3-18-0-Q SONAR EQUIPMENT ROOM NO. 3 | 92 | 2/2A | TO6 | 28-Sep-20 | ||||
| 2-53-1-C CSER 1 | 93 | 4 | TO6 | 28-Sep-20 | ||||
| 1-94-1-A REPAIR 2 | 94 | 194 | 7 | 194 | TO6 | 28-Sep-20 | ||
| 2-381-1-Q ELECTRIC SHOP - TCB 1 swap with BSE A1 no foundation change | A1 | TO6 | 28-Sep-20 | |||||
| 01-338-2-Q SWITCHBOARD ROOM #3 - install BSE A2 (Pway 01-309-2-L delete TCB 2 completely | A2 | TO6 | 28-Sep-20 | |||||
| 1-254-6-L PASSAGEWAY - TCB 3 swap with BSE A3 no foundation change | A3 | TO6 | 28-Sep-20 | |||||
| 1-174-1-L PASSAGEWAY - install BSE A4 (1-174-0-L CPO MESSROOM & LOUNGE - delete TCB 4) | A4 | TO6 | 28-Sep-20 | |||||
| 01-130-0-Q CSMC - delete TCB 5, install BSE A5 new foundation | A5 | TO6 | 28-Sep-20 | |||||
| 1-78-2-Q SHIPS OFFICE - TCB 6 swap with BSE A6 no foundation change | A6 | TO6 | 28-Sep-20 | |||||
| 1-18-0-Q SONAR EQUIPMENT ROOM NO. 1 - TCB 7 swap with BSE A7 no foundation change | A7 | TO6 | 28-Sep-20 | |||||
| 3-116-1-T ACCESS TRUNK- delete TCB 8, install BSE A8 foundation (slides forward) | A8 | TO6 | 28-Sep-20 | |||||
| 4-174-0-E ENGINE ROOM NO. 1 - delete TCB 9, install BSE A9 new foundation move (needed) | A9 | TO6 | 28-Sep-20 | |||||
| 3-338-1-L CREW LIVING SPACE #6 - TCB 10 delete, install BSE A10 modify foundation | A10 | TO6 | 28-Sep-20 | |||||
| Turnover 7 | ||||||||
| 03-142-1-Q CSER 4 | 11 | 111 | 29/30 | 111 | TO7 | 19-Oct-20 | ||
| 03-142-2-Q ELECTRIC LOAD CENTER NO. 1 | 28 | TO7 | 19-Oct-20 | |||||
| 02-154-1-L PASSAGE | 14 | 27 | TO7 | 19-Oct-20 | ||||
| 02-133-1-L PASSAGE | 114 | 114 | TO7 | 19-Oct-20 | ||||
| 2-410-2-A REPAIR 3 | 22 | TO7 | 19-Oct-20 | |||||
| 2-126-2-C CSER 2 | 10 | TO7 | 19-Oct-20 | |||||
| .5-42-1-A INERT GAS CYLINDER STOREROOM | 6 | TO7 | 19-Oct-20 |
| Following IOUs are deleted. Ripout completed | 26-Mar-20 |
| IOU 12 | 26-Mar-20 |
| IOU 13 | 26-Mar-20 |
| IOU 52 | 26-Mar-20 |
| IOU 61 | 26-Mar-20 |
| IOU 73 | 26-Mar-20 |
| IOU 81 | 26-Mar-20 |
| IOU 91 | 26-Mar-20 |
&14USS MASON DDG-87 FY20
DMP GEDMS SA73091 BREAKOUT SCHEDULE&18
ALO CRS
| USS OSCAR AUSTIN DDG79 FY18 DMP AEGIS Light Off Compartment Release Schedule | |||||||||||||||
| COMPARTMENT NUMBER | COMPARTMENT NAME | MSR turnover to AIT | Date | A = SOA | 8-Jan-18 | SUPPORT SERVICES: Gray Fill Indicates Services Required | |||||||||
| 60 Hz | 400 Hz | A/C | ECW | Chill Water | Fire Main | Dry Air | HP Air | LP Air | |||||||
| 4-94-0-C | IC & Gyro Room #1 (FWD) | 158 | 15-Jun-18 | 93 | 207 | 3-Aug-18 | |||||||||
| 3-300-0-C | IC & Gyro Room #2 (AFT) | 158 | 15-Jun-18 | 93 | 207 | 3-Aug-18 | |||||||||
| 03-128-0-C | Radar Room #1 | 200 | 27-Jul-18 | 66 | 221 | 17-Aug-18 | |||||||||
| 06-157-0-T | Mast and Access Trunk | 221 | 17-Aug-18 | 70 | 235 | 31-Aug-18 | |||||||||
| 03-142-0-C | Radar Room #2 | 207 | 3-Aug-18 | 63 | 235 | 31-Aug-18 | |||||||||
| 2-53-1-C | CSER #1 | 207 | 3-Aug-18 | 63 | 235 | 31-Aug-18 | |||||||||
| 2-126-2-C | CSER #2 | 193 | 20-Jul-18 | 62 | 241 | 6-Sep-18 | |||||||||
| 1-300-0-C | CSER #3 | 193 | 20-Jul-18 | 62 | 241 | 6-Sep-18 | |||||||||
| 1-126-0-C | Combat Information Center | 193 | 20-Jul-18 | 62 | 241 | 6-Sep-18 | |||||||||
| 05-131-0-Q | Director Equipment Room #1 | 228 | 24-Aug-18 | 58 | 241 | 6-Sep-18 | |||||||||
| 2-50-2-C | Sonar Control Room | 221 | 17-Aug-18 | 58 | 241 | 6-Sep-18 | |||||||||
| 1-18-0-Q | Sonar Equipment Room #1 | 221 | 17-Aug-18 | 42 | 228 | 24-Aug-18 | |||||||||
| 2-18-0-Q | Sonar Equipment Room #2 | 221 | 17-Aug-18 | 42 | 228 | 24-Aug-18 | |||||||||
| 3-18-0-Q | Sonar Equipment Room #3 | 221 | 17-Aug-18 | 42 | 228 | 24-Aug-18 | |||||||||
| 01-130-2-C | SSES | 242 | 7-Sep-18 | 46 | 241 | 6-Sep-18 | |||||||||
| 2-220-1-Q | SNAP II Computer Room (LAN Room) | 186 | 13-Jul-18 | 25 | 221 | 17-Aug-18 | |||||||||
| 03-128-1-Q | SPY Array Room #1 (FWD/STBD) | 242 | 7-Sep-18 | 25 | 221 | 17-Aug-18 | |||||||||
| 03-128-2-Q | SPY Array Room #2 (FWD/PORT) | 242 | 7-Sep-18 | 25 | 221 | 17-Aug-18 | |||||||||
| 03-158-3-Q | SPY Array Room #3 (AFT/STBD) | 242 | 7-Sep-18 | 25 | 221 | 17-Aug-18 | |||||||||
| 03-158-2-Q | SPY Array Room #4 (AFT/PORT) | 242 | 7-Sep-18 | 25 | 221 | 17-Aug-18 | |||||||||
| 01-130-0-Q | Combat Systems Maintenance Central | 235 | 31-Aug-18 | 25 | 221 | 17-Aug-18 | |||||||||
| 2-126-1-C | Communications Center | 200 | 27-Jul-18 | 39 | 235 | 31-Aug-18 | |||||||||
| 3-126-2-Q | Power Supply/Conversion Room | 242 | 7-Sep-18 | 9 | 207 | 3-Aug-18 | |||||||||
| 3-319-0-Q | Power Conversion Room | 242 | 7-Sep-18 | 9 | 207 | 3-Aug-18 | |||||||||
| 4-42-0-Q | Sonar Cooling Equipment Room | 242 | 7-Sep-18 | 9 | 207 | 3-Aug-18 | |||||||||
| 4-126-0-E | Auxiliary Machinery Room #1 | 242 | 7-Sep-18 | 9 | 207 | 3-Aug-18 | |||||||||
| 1-78-1-Q | VLS Fan Room fwd | 249 | 14-Sep-18 | 28 | 228 | 24-Aug-18 | |||||||||
| 1-78-2-Q | VLS Fan Room fwd | 249 | 14-Sep-18 | 28 | 228 | 24-Aug-18 | |||||||||
| 3-362-0-Q | VLS Fan Room aft | 249 | 14-Sep-18 | 28 | 228 | 24-Aug-18 | |||||||||
| 04-130-0-C | Pilot House | 228 | 24-Aug-18 | 23 | 228 | 24-Aug-18 | |||||||||
| 2-338-0-M | VLS Magazine #2 (AFT) | 242 | 7-Sep-18 | 22 | 228 | 24-Aug-18 | |||||||||
| 2.5-78-0-M | VLS Magazine #1 (FWD) | 242 | 7-Sep-18 | 22 | 228 | 24-Aug-18 | |||||||||
| 02-112-0-Q | CIWS Workshop #1 | 242 | 7-Sep-18 | 14 | 221 | 17-Aug-18 | |||||||||
| 2-153-2-C | Tomahawk Equipment Room | 221 | 17-Aug-18 | 14 | 221 | 17-Aug-18 | |||||||||
| 03-142-1-C | CSER #4 | 242 | 7-Sep-18 | 7 | 221 | 17-Aug-18 | |||||||||
| 04-150-0-C | Chart Room (w/4) | 249 | 14-Sep-18 | 7 | 221 | 17-Aug-18 | |||||||||
| 03-142-2-Q | Electric Load Center #1 | 256 | 21-Sep-18 | 21 | 235 | 31-Aug-18 | |||||||||
| 01-274-1-C | Radar Room #3 | 235 | 31-Aug-18 | 21 | 235 | 31-Aug-18 | |||||||||
| 03-112-0-C | CIWS Control Room #1 | 242 | 7-Sep-18 | 21 | 235 | 31-Aug-18 | |||||||||
| 1-46-0-M | 5"/54 Loader Drum & Fan Room | 242 | 7-Sep-18 | 21 | 235 | 31-Aug-18 | |||||||||
| 2-458-0-Q | MFTA Winch Room | 256 | 21-Sep-18 | 13 | 228 | 24-Aug-18 | |||||||||
| 2-157-1-C | Radio Transmitter Room | 256 | 21-Sep-18 | 11 | 228 | 24-Aug-18 | |||||||||
| 01-300-0-Q | CIWS Wpn & Avn Ord Eqpt Wks | 256 | 21-Sep-18 | 11 | 228 | 24-Aug-18 | |||||||||
| 02-299-0-C | CIWS Control Room#2 | 256 | 21-Sep-18 | 11 | 228 | 24-Aug-18 | |||||||||
| 1-314-0-C | CSER 3 Annex | 242 | 7-Sep-18 | 21 | 241 | 6-Sep-18 | |||||||||
| 1-268-0-C | CCS (VLS Alarms) | 249 | 14-Sep-18 | 7 | 235 | 31-Aug-18 | |||||||||
| Fwd 03 lvl, Aft 05 lvl | AN/SPY-1 Antenna Arrays | 256 | 21-Sep-18 | 0 | 235 | 31-Aug-18 | |||||||||
| 04-272-0-Q | Director Equipment Room #2 | 256 | 21-Sep-18 | 0 | 235 | 31-Aug-18 | |||||||||
| 03-282-0-Q | Director Equipment Room #3 | 256 | 21-Sep-18 | 0 | 235 | 31-Aug-18 | |||||||||
| 1-97-2-Q | VLS Service Interface Room (FWD) | 256 | 21-Sep-18 | 0 | 235 | 31-Aug-18 | |||||||||
| 02 LVL FR 338-370 | Missile Deck (AFT) | 256 | 21-Sep-18 | 0 | 235 | 31-Aug-18 | |||||||||
| 01 LVL FR 78-110 | Missile Deck (FWD) | 256 | 21-Sep-18 | 0 | 235 | 31-Aug-18 | |||||||||
| 01-(46-78)-0-M | 5"/54 CAL Gun Mount (MT 51) | 256 | 21-Sep-18 | 0 | 235 | 31-Aug-18 | |||||||||
| 06-150-0/Deck | FCS Director #1 | 256 | 21-Sep-18 | 0 | 235 | 31-Aug-18 | |||||||||
| 05-280-0/Deck | FCS Director #2 | 256 | 21-Sep-18 | 0 | 235 | 31-Aug-18 | |||||||||
| 04-292-0/Deck | FCS Director #3 | 256 | 21-Sep-18 | 0 | 235 | 31-Aug-18 | |||||||||
| 01-(247-257) | SVTT (STBD) | 256 | 21-Sep-18 | 0 | 241 | 6-Sep-18 | |||||||||
| 01-(240-250) | SVTT (PORT) | 256 | 21-Sep-18 | 0 | 241 | 6-Sep-18 | |||||||||
| 2-450-1-Q | NIXIE Room | 256 | 21-Sep-18 | 0 | 241 | 6-Sep-18 | |||||||||
| 02-(200-220)-1 | Decoy Launchers (STBD) | 256 | 21-Sep-18 | 0 | 241 | 6-Sep-18 | |||||||||
| 02-(200-220)-2 | Decoy Launchers (PORT) | 256 | 21-Sep-18 | 0 | 241 | 6-Sep-18 | |||||||||
| 02-(220-237) | NULKA Launchers (PORT) | 256 | 21-Sep-18 | 0 | 241 | 6-Sep-18 | |||||||||
| 02-(220-237) | NULKA Launchers (STBD) | 256 | 21-Sep-18 | 0 | 241 | 6-Sep-18 | |||||||||
| 03-(142-158)-3 | EW Array SLQ-32 (STBD) | 256 | 21-Sep-18 | 0 | 241 | 6-Sep-18 | |||||||||
| 03-(142-158)-4 | EW Array SLQ-32 (PORT) | 256 | 21-Sep-18 | 0 | 241 | 6-Sep-18 | |||||||||
| 03-(112-128)-0 | CIWS (MT 21) FWD | 256 | 21-Sep-18 | 0 | 241 | 6-Sep-18 | |||||||||
| 02-(300-316)-0 | CIWS (MT 22) AFT | 256 | 21-Sep-18 | 0 | 241 | 6-Sep-18 | |||||||||
| 2-442-6-Q | Bathythermograph Room | 256 | 21-Sep-18 | 0 | 241 | 6-Sep-18 | |||||||||
| 0 1/2-28-0-Q | Dome Equipment Room | 256 | 21-Sep-18 | 0 | 241 | 6-Sep-18 | |||||||||
| 1-304-2-M | Torpedo, Missile & Rocket Mag | 256 | 21-Sep-18 | 0 | 241 | 6-Sep-18 | |||||||||
| 01-110-3-Q | Fan Room PZ #1 | 224 | 20-Aug-18 | 200 | 27-Jul-18 | ||||||||||
| 01-126-3-Q | Fan Room PZ #2 |
Mike Kraft: Mike Kraft:
| supply AUX 1 fan SS 01-150-1 | 224 | 20-Aug-18 | 200 | 27-Jul-18 | |||
| 01-158-0-Q | Fan Room PZ #2 | 224 | 20-Aug-18 | 200 | 27-Jul-18 | ||
| 01-190-1-Q | Fan Room PZ #2 | 224 | 20-Aug-18 | 200 | 27-Jul-18 | ||
| 01-200-2-Q | Fan Room PZ #2 |
Mike Kraft: Mike Kraft:
| supplies MER 1 fan SS 2-203-1 | 224 | 20-Aug-18 | 200 | 27-Jul-18 |
| 01-240-01-Q | Fan Room PZ #3 |
Mike Kraft: Mike Kraft:
| supply for MER2 (fans SS 262-2 and SS 2-270-1) and AUX 2 (SS 3-251-2) | 224 | 20-Aug-18 | 200 | 27-Jul-18 |
| 01-300-2-Q | Fan Room |
Mike Kraft: Mike Kraft:
| Aft VCHT supply fan 4-330-1 ? | 224 | 20-Aug-18 | 200 | 27-Jul-18 |
| 01-338-3-Q | Fan Room |
Mike Kraft: Mike Kraft:
supplies #3GTG and aft steering Mike Kraft: Mike Kraft:
supply AUX 1 fan SS 01-150-1 Mike Kraft: Mike Kraft:
supplies MER 1 fan SS 2-203-1 Mike Kraft: Mike Kraft:
| supply for MER2 (fans SS 262-2 and SS 2-270-1) and AUX 2 (SS 3-251-2) | 224 | 20-Aug-18 | 200 | 27-Jul-18 | |||
| 01-338-4-Q | Fan Room | 224 | 20-Aug-18 | 200 | 27-Jul-18 | ||
| 03-142-3-Q | Fan Room | 224 | 20-Aug-18 | 200 | 27-Jul-18 | ||
| 03-142-4-Q | Fan Room | 224 | 20-Aug-18 | 200 | 27-Jul-18 | ||
| 03-152-2-Q | Fan Room | 224 | 20-Aug-18 | 200 | 27-Jul-18 | ||
| 2-42-2-Q | Fan Room | 224 | 20-Aug-18 | 200 | 27-Jul-18 | ||
| 2-430-1-Q | Fan Room | 224 | 20-Aug-18 | 200 | 27-Jul-18 | ||
| 3-164-2-Q | Fan Room | 224 | 20-Aug-18 | 200 | 27-Jul-18 |
Conf day calc
| 347 | 87 | 174 | 260 | |
| KTR days | 20 | 25% | 50% | 75% |