Bidders'_Questions_Log_PNW_as_of_14_June_2018.pdf

PDF 323 KB Posted

Attached to
Pacific North West CVN Private Sector Maintenance
Solicitation number
N00024-18-R-4300
Issued by

About this file

This document contains a bidder's questions log and related federal contract opportunity solicitation for providing maintenance, repair, and modernization efforts for CVN 68 Class and CVN 78 Class Aircraft Carriers home-ported in and visiting Bremerton, Washington. The bidder's questions log addresses inquiries on pricing requirements, availability schedules, historical labor rates, technical proposal instructions, and clarifications on contract clauses, CDRLs and attachments. The federal contract opportunity involves a cost plus incentive fee and award fee contract over five years, with an anticipated award date of November 2018 and completion by November 2023. The Naval Sea Systems Command seeks to maintain aircraft carriers at the Bremerton site currently under contract with General Dynamics - NASSCO. Market research found no small business set-aside was necessary.

Bidder's Questions

View the file

Other files

File Type Posted
PACNORWEST_Pre-Priced_Specs_6-13-18_R1.pdf PDF
N00024-18-R-4300_Amendment_0008.pdf PDF
ATTACHMENT_J-6_DATED_6-13-18_R1.docx DOCX document
N00024-18-R-4300_Conformed_through_Amendment_0008.pdf PDF
ATTACHMENT_J-6_DATED_6-6-18.docx DOCX document
N00024-18-R-4300_Amendment_0007.pdf PDF
N00024-18-R-4300_Conformed_through_Amendment_0007.pdf PDF
ATTACHMENT_J-6_DATED_6-5-18,_Amd_0007.docx DOCX document
Attachment_S_1_Cost_Exhibits_L001_thru_L008_Amd_0007.xlsx XLSX spreadsheet
Attachment_S_5_Cost_Exhibits_L001_thru_L008_Amd_0007.xlsx XLSX spreadsheet
N00024-18-R-4300_Conformed_through_Amendment_0006.pdf PDF
N00024-18-R-4300_Amendment_0006.pdf PDF
N00024-18-R-4300_Conformed_through_Amendment_0005.pdf PDF
N00024-18-R-4300_Amendment_0005.pdf PDF
N00024-18-R-4300_Amendment_0003.pdf PDF
Attachment_S_5_Cost_Exhibits_L001_thru_L008_updated.xlsx XLSX spreadsheet
Attachment_S_1_Cost_Exhibits_L001_thru_L008_updated.xlsx XLSX spreadsheet
N00024-18-R-4300_Amendment_0004.pdf PDF
PNW_CVN_PSM_CDRL_Package_5-21-18_updated.pdf PDF
DD254_for_N00024-18-R-4300_signed.pdf PDF
Copy_of_Bidders'_Questions_Log_PNW_as_of_22_MAY_2018.pdf PDF
F3_Delivery_Redelivery_Schedule.docx DOCX document
N00024-18-R-4300_0002.pdf PDF
N00024-18-R-4300_0001.pdf PDF
DD254_for_N00024-18-R-4300_signed.pdf PDF
Exhibit_A,_B,_and_C_DRAFT_PNW_CVN_PSM_CDRL_Package_2-2-18.pdf PDF
J_Attachments.zip ZIP file
N00024-18-R-4300_RFP.pdf PDF
S_Attachments.zip ZIP file
Show all 29

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOURCE SELECTION INFORMATION - SEE FAR 2.101 AND 3.104

1 3 4 5 6 7 16

NAVSEA

REFERE

NCE NO.

SOLICITATION

SECTION

SOLICITATION

PAGE CATEGORY/ TYPE GENERAL SUBJECT STATEMENT REQUIRING CLARIFICATION OR QUESTION STATUS (O/C)

ANSWER AMENDMENT

REQUIRED

(Y/N)

AMENDMENT

NUMBER

1 C 26 Descriptions & Specifications, Table C-1

Descriptions & Specifications, Table C-

The RFP statement of work calls out the use of NAVSSEA INST 9210.47B “Mixed Waste and PCB Waste Management” on Page 26.

The work scope found in Section L, Para.Ⅴ.C.10, Table L-6 clearly includes management of hazardous wastes (Work Item 077-11-001) resulting from the repair of ships. However, Special Provision “Non-Radioactive PCB Waste,” which implements the Toxic Substances Control Act (TSCA), is not included in the RFP. Should this be added? If not, please explain why the Government deems it is not needed.

C

No, NAVSEA Standard Items and/or Local Standard Items cover these requirements and adding them would be redundant.

2 C 26 Descriptions & Specifications, Table C-1

Descriptions & Specifications, Table C-

The RFP statement of work calls out the use of NAVSSEA INST 9210.47B “Mixed Waste and PCB Waste Management” on Page 26.

The work scope found in Section L, Para.V.C.10, Table L-6 clearly includes management of hazardous wastes (Work Item 077-11-001) resulting from the repair of ships. However, Special Provision “Hazardous Waste and PCB Waste,” which implements the (Implements TSCA, RCRA, and 10 USC 7311), is not included in the RFP. Should this be added? If not, please explain why the Government deems it is not needed.

C

No, NAVSEA Standard Items and/or Local Standard Items cover these requirements and adding them would be redundant.

3 C 26 Descriptions & Specifications, Table C-1

Descriptions & Specifications, Table C-

The RFP statement of work calls out the use of NAVSSEA INST 9210.47B “Mixed Waste and PCB Waste Management” on Page 26.

The work scope found in Section L, Para. V.C.10, Table L-6 clearly includes management of hazardous wastes (Work Item 077-11-001) resulting from the repair of ships. However, Special Provision, “Asbestos, PCBs and Other Regulated Substances,” which invokes OSHA and EPA notice requirements, is not included in the RFP. Should this be added? If not, please explain why the Government deems it is not needed.

C

No, NAVSEA Standard Items and/or Local Standard Items cover these requirements and adding them would be redundant.

4 I 113 CLAUSES Limitation of Liability The RFP contains the clause at 52.216-24 “Limitation of Government Liability.” Per FAR 16.603-4 this clause is only used in letter contracts. Given this is an IDIQ shouldn’t this clause be eliminated? C This was/will be addressed in Amendment 0003. Y 0003

5 C 69 CLAUSES Minimum Insurance Requirements The RFP contains a reference to the FAR clause at 52.228-5 “Insurance – Work on a Government Installation,” in the Section C provision referenced above, but the clause is not invoked in the contract. Is it the Government’s intention to invoke the clause by adding it to Section I Contract Clauses?

C This was/will be addressed in Amendment 0003. Y 0003

6 I 108 CLAUSES Liability and Insurance The RFP covers insurance for third party liability and property damage by including FAR 52.228-7, “Insurance – Liability to Third Parties,” but does not mention vessel coverage. FAR 217.7104 includes DFAR 252.217-7012 in the list of clauses to be added if the work is done under a Master Ship Repair contract. Should it be added to the Section I Contract Clauses?

C This was addressed in Amendment 0003. Y 0003

7 I 108 CLAUSES Safety and Health The RFP assumes a Master Ship Repair agreement will be in place (see page 90, under “Growth and New Work” and page 143, Section L). DFAR Clause 252.217-7015 is included in the list of clauses to be added if the work is done under a Master Ship Repair contract, per FAR 217.7104. Will the Government be adding this clause to Section I?

C This was addressed in Amendment 0003. Y 0003

8 L 157 Section L CIA WORK /PLANNING

On page 157, Section L, Table L-1 lists CIA, PIA and DPIA Execution Planning as all being CLIN 0007, however Section B shows CLIN 0009 as the DPIA Execution Planning CLIN. Similarly, Table L-3 shows CLIN 0008 for all Availability Execution efforts, but Section B identifies CLIN 0010 as the DPIA Execution CLIN. Additionally, the solicitation package does not appear to provide a notional package nor pre-priced items list associated with a CIA, so it is not apparent how to provide CIA pricing. Please clarify

C This was addressed in Amendment 0003. Y 0003

9 L 164 section L Work Item Hour and Material Summary

In the instructions for Section J-Exhibit L004 – Work Item Hour and Material Summary, the offeror is directed to “provide a separate Exhibit L004 for each CNO availability type”. Does the Government intend this to be for each CNO availability TYPE (DPIA and PIA) which would only require just one Exhibit L004 since the work items for both a DPIA and a PIA are included in the attachment S-1 provided with the solicitation? Does the Government instead intend this to be for each CNO AVAILABILITY (FY21 DPIA, FY21 PIA and FY23 DPIA) which would require three different Exhibit L004 worksheets?

C Yes, this requires a different Exhibit L0004 for each availablity.

10 J 164 J Historical /Proposed Rates Summary Schedule

In the instructions for Section J-Exhibit L005 – Historical /Proposed Rates Summary Schedule, the offeror is directed to provide historical rates for all Contractor Fiscal Years (CFY) from 2010 through 2015 and proposed rates for Government Fiscal Years (GFY) 2016 through 2021. However, Attachment S-1, worksheet L005 displays Historical Rate columns for CFY 2012 through 2017 as well as a column for GFY 2018 and proposed rates for GFY 2019 through 2024. Please clarify.

C This was/will be addressed in Amendment 0003. Y 0003

11 J 164 J Indirect Expense Schedules

In the instructions for Section J-Exhibit L006 – Indirect Expense Schedules, the offeror is directed to provide historical actuals for all Contractor Fiscal Years (CFY) from 2010 through 2015 and proposed rates for Government Fiscal Years (GFY) 2018 through 2023.

However, Attachment S-1, worksheet L006 displays Total Expense columns for CFY 2012 through 2018 and proposed rates for GFY 2019 through 2024. Please clarify

C This was/will be addressed in Amendment 0003. Y 0003

12 L 148 L FONT SIZE

In the proposal overview, it states that proposals must be prepared using the Arial typeface at a font size no smaller than 12-points. May smaller fonts or different fonts be used for headers, footers, exhibits, graphics, spreadsheets, and tables as long as they are easily readable?

C Offerors shall follow/adhere to the instructions within Section L of the RFP.

13 F 83 F Delivery/Redelivery Schedule In the Delivery/Redelivery Schedule for the Vessels table, the FY21 CVN 71 availability is listed as a CIA, however in all other listings of this availability it is shown as a DPIA. Please clarify. C This was addressed in Amendment 0001. Y 0001

14 C 19 CRDL'S RFP Section C Para. 3 references CDRLs A028 and A029 but these CDRLs are included in the Exhibit A B & C CDRLs Table of Contents on the ‘CDRLs NOT USED’ line. Were different CDRLs intended or should the references be removed? C

This was/will be addressed in Amendment 0003.

The reference to CDRLs A028 and A029 should be removed. These are CDRLs NOT USED nor are they applicable to paragraph 3 of section C.

FINAL SOLICITATION BIDDERS QUESTION

SOURCE SELECTION INFORMATION - SEE FAR 2.101 AND 3.104 6/14/2018

NAVSEA

REFERE

NCE NO.

SOLICITATION

SECTION

SOLICITATION

PAGE CATEGORY/ TYPE GENERAL SUBJECT STATEMENT REQUIRING CLARIFICATION OR QUESTION STATUS (O/C)

ANSWER AMENDMENT

REQUIRED

(Y/N)

AMENDMENT

NUMBER

15 I 146 I Proposal due-date Request clarification on the Proposal due-date discussed on page 146 of 188, paragraph I; Monday, 06/25/18 or Tuesday, 06/26/18? C This wass addressed in Amendment 0002. Y 0002

16 157 CIA Work Package Will a notional CIA Work Package be provided to facilitate pricing requested on page 157 of 188, paragraph 7., Table L-3? C The solictiationl provides all potential scope of work to be performed during execution of this anticatpated contract. With respect to that, for the purposes of proposal submission Offerors shall prepare a Table L-3 for the scope of work associated with PIA and DPIA.

17 157 CLIN'S Upon review of RFQ N00024-18-R-4300, should CLIN 0009 (page 6 of 188) be included in Table L-1 -Priced Execution Planning CLIN;

and should CLIN 0010 (page 6 of 188) be included in Table L-3 -Priced Accomplish Availability CLIN? C This was/will be addressed in Amendment 0003. Y 0003

18 8 & 173 AWARD DATE

Page 8 of the solicitation states “Offerors should utilize an award date of 16 November 2018 and completion 60 months from date of award, 15 November 2023.” The assumptions on page 173 state “Offerors should utilize an award date of 13 March 2019 and completion 60 months from date of award, 12 March 2024.” Please clarify the correct dates to use for purposes of estimating.

C This was/will be addressed in Amendment 0003. Y 0003

19 163 CLARIFICATION Page 163 references Attachment J-8 – Schedule of capped labor rates, while the document provided as part of the solicitation is J-7 – Capped Labor Rates. Please clarify which attachment number is correct. C This was/will be addressed in Amendment 0003. Y 0003

20 164 & 165 CLARIFICATION Pages 164 and 165, part (e ), (f) & (g) request historical rates from 2010 through 2015 and projected rates from 2016 through 2021.

Please clarify the correct dates that correspond with the S-1 and S-5 Cost Exhibits. C This was/will be addressed in Amendment 0003. Y 0003

21 171 & 172 CLARIFICATION Pages 171 and 172, part (e ), (f) & (g) request historical rates from 2010 through 2015 and projected rates from 2016 through 2021.

Please clarify the correct dates that correspond with the S-1 and S-5 Cost Exhibits. C This was/will be addressed in Amendment 0003. Y 0003

Hazardous Waste

Produced on Naval Vessels

Hazardous Waste

Produced on Naval Vessels

CLARIFICATION Upon review of paragraph 3.5 there are no quantities of hazardous waste listed for disposal. Is the intent for all hazardous waste to be disposed of by PSNS & IMF? C

The expected contractor hazardous waste for the PIA notional work specification 077-01-001 paragraph 3.5 is listed below. See note 4.1 of the work specification.

Cleaning Solvents 30 GAL Paints (Enamel, Latex, 35 GAL Epoxy, thinners, oil based, rubber paint, nonskid, lacquer, remover, varnishes) Sludge (Contaminated with 10 YDS a known hazardous waste)

Local Standard Item 099-06NW covers hazardous waste management for general contractor waste management requirements for Bremerton Naval Complex (BNC).

23 S-1 S-1 CLARIFICATION

Attachment S-1 states “Offeror to replicate cost exhibit L004 template and submit separate L004 exhibits for each type of CNO Availability contained in this solicitation.” However, the tab for Exhibit L004 shows both the PIA and DPIA. Should the L004 be revised to submit separate exhibits for the PIA and DPIA?

C The Offeror shall follow the instructions provided in the RFP and fill out the applicable Exhibit L004 for the applicable CNO Availability it is replicating. If the Offeror determines for formating and evaluatng purposes to hide the unapplicable rows/cells for each individual submittal it shall.

24 L 148 OVERVIEW The font size for proposal text is designated as Arial typeface at 12 point. Would it be permissible to use a font size of 8 point in tables and graphics as long as it remains legible? C Offerors shall follow/adhere to the instructions within Section L of the RFP.

25 L & J EXBT 164 Instructions for L007 in Section L indicate that the data is to be by GFY, but neither the instructions nor the Exhibit itself are clear as to the span of years to be included. Will the Government please confirm the span of years required to complete Section J-Exhibit L007? C This was/will be addressed in Amendment 0003, it should be FY19-FY24. Y 0003

26 L 174

A two-fold question regarding escalation: 1) Should escalation start in FY2017 or FY2018? The L-5 Table on pg. 174 indicates 2018, whereas the text on pg. 174 indicates 2017. 2) Are offerors to assume the material values in Tables L-6 & L-7 are in FY2017 dollars or FY2018 dollars? If we are to assume 2017 dollars, please provide FY2017 escalation data for table L-5. See below:

C This was/will be addressed in Amendment 0003. Y 0003

27 PRE-PRICED ITEM ATTACHMENT J6

Work Item 042-11-001 in the Pre-Priced attachment has varying Labor Hours in both the PIA and DPIA tables as compared to the hours for this WI in Tables L-6 and L-7 on pages 175 and 177 respectively. The question is two-fold: 1.What are the correct labor hours for Work Item 042-11-001? 2.Are offerors only to quote pricing for Work Item 042-11-001 in the Notional PIA/DPIA CLINs or just in the Pre-Priced section, or in both the Notional CLINs and in the Pre-Priced?

C

This was/will be addressed in Amendment 0003.

A revised Attachment J-6 will be provided in an amendment which will reflect updated DPIA & CMAV specifications and estimates. Labor hours for the DPIA pre-priced items and Table L-7 should match.

Y 0003

REFERE

NCE NO.

SOLICITATION

SECTION

SOLICITATION

PAGE CATEGORY/ TYPE GENERAL SUBJECT STATEMENT REQUIRING CLARIFICATION OR QUESTION STATUS (O/C)

ANSWER AMENDMENT

REQUIRED

(Y/N)

AMENDMENT

NUMBER

28 L 177 &180 TABLE L-6AND 7 CLARIFICATION

Are offerors to price PIA/DPIA Notional Work Item 813-11-001 in the PIA/DPIA Accomplish Availability CLINs or in the PIA/DPIA Execution Planning CLINs, or in both? The W.I. title is: ‘Advanced Planning….’, but this work item is listed in the Accomplish Availability CLIN Notional Work Package Tables. Please note that the notional labor hours for W.I. 813-11-001 differ from the hours for the Execution Planning CLINs for PIAs & DPIAs. Please verify the correct labor hours offerors are to quote and where. See below:

C

This was/will be addressed in Amendment 0003.

Table L-1 Man-Hours for CLIN 0007 for each Execution Planning item [5 total] will be revised to 24,352 to match the 813-11-001 advance planning specification in both the PIA and DPIA Notional Work Package Tables L-6 & L-7.

Y 0003

29 L 177 & 181 NOTIONAL WORK

PKG CLARIFICATION

Are adjustments required to any of the individual work items Man-hours or CFM material dollars listed in the L-6 and L-7 tables? Note that the totals at the bottom of the table vary from the actual math of the totals of the individual work items. Also note that the math for the totals of the work items by Man-hours & material dollars for both PIAs and DPIAs in the L004 Exhibits is correct. It appears rounding may be an issue in the L-6 & L-7 Tables’ totals. Please clarify.

C

This was/will be addressed in Amendment 0003.

Yes. Totals should be the following:

Table L-6 Totals: Man-hours 156,694 & CFM Material $2,630,464 Table L-7 Totals: CFM Material $5,873,966

30 EXHIBIT L007 CLARIFICATION Is Exhibit L007 proprietary to General Dynamics/NASSCO? The header on the exhibit included in the RFP would seem to indicate so.

Please clarify. C This was/will be addressed in Amendment 0003. Y 0003

31 C 19 CDRL'S Descriptions and Specifications The Statement of Work, paragraph 3, on page 19, requires CFSR, CPR, and IPMR reports (CDRL A032 and A088), in accordance with the applicable Contract Data Requirements List (CDRL) (CDRLs A028 and A029). A028 and A029 are not included in the Solicitation package and contractor believes CDRLs A032 and A088 are the correct requirements. Please clarify

C

This was/will be addressed in Amendment 0003.

Offeror's assumptions are correct. The reference to CDRLs A028 and A029 should be removed.

These are CDRLs NOT USED nor are they applicable to paragraph 3 of section C.

32 104 CDRL A068 SMALL BUSINESS

SUBCONTRACTING

On page 104 of the Solicitation, in the SMALL BUSINESS SUBCONTRCTING paragraph, reference is made to reporting requirements in accordance with Contract Data Requirements List (CDRL) (A068). CDRL A068 is not included in the Exhibits A, B, and C provided with the Solicitation. Please provide and correct the Table of Contents provided with the Exhibits A, B, and C.

C This was/will be addressed in Amendment 0003

33 Attachment J-6 Attachment J-6 CLARIFICATION The data provided in Attachment J-6 only includes the pre-determined Work Item, Work Item Description, Labor Hours and Material Dollars. As such the contractor is not able to determine if a deviation is warranted without the specifications and associated reference drawings. The contractor requests pre-determined Work Item specifications and associated reference drawings for Attachment J-6.

C

This was/will be addressed in Amendment 0003.

A revised J-6 will be provided. It will include each work specification that cannot be found in the notional DPIA work package. References will be provided.

Y 0003

34 Attachment J-1 Attachment J-1 CLARIFICATION

The contractor is not able to determine if a deviation is warranted without the associated reference drawings noted on the work items, a supporting example is PIA notional item 516-80- 001 paragraph 3.1 directs the contractor to accomplish the requirements of references

2.2 thru 2.4 ; the contractor cannot develop a labor & material estimate without the required references 2.2 thru 2.4. The contractor requests associated reference drawings for Attachment J1 notional PIA and DPIA Availability Work Package Work Items.

C References will be provided. Please request reference from the names listed in the solictiation.

35 144 NWP Notional Work Package Requests Paragraph states that offers interested must request a NOTIONAL WORK PACKAGE (NWP) and attachments J1 & J4 will not be attached in the solicitation. There was attachments J1 & J4 NWP in the solicitation provided by the Govt. Are these attachments current and to be used in this solicitation? If not can the most recent J1 & J4 (NWP) be provided.

C Attachment J-4 was/will be addressed in Amendment 0003. Attachment J-1 provided is current.

36 8 Direct and Indirect Cap This paragraph identifies the Award date as 16NOV18 with the completion date of 15NOV23. Then on page 173 of the Cost Assumptions Proposal the Award date is identified as 13MAR19 with the completion date of 12MAR2024. Please identify which award and completion date is correct.

C This was/will be addressed in Amendment 0003. Y 0003

37 21 & 173 IAPA Page 21, paragraph 9 identifies (175) work items over a 12 month period. Page 173, paragraph 4 identifies (60) work items over a 12 month period. Please clarify the amount of work items that will be involved with the IAPA. C This was/will be addressed in Amendment 0003. Y 0003

38 TABLE L2 157 IAPA MANHOURS Page 157 Table L2 only provides CLIN 0001 Man-hours for FY20. However, Section B CLIN 0001 pricing requirement on page 2 details FY19-FY24. Please provide CLIN 0001 Man-hours for FY19, 21, 22, 23, and 24. C This was/will be addressed in Amendment 0003. Y 0003

39 8 CLARIFICATION References work site located at NWRMC in San Diego, CA. Please clarify if NWRMC has operations in San Diego. C

This was/will be addressed in Amendment 0003.

Reference to "Southwest Regional Maintenance Center (SWRMC)" was/will be revised to "Northwest Regional Maintenance Center (NWRMC)". Inaddition, the location was/will be revised from San Diego, CA to Bremerton, WA.

Y 0003

40 TABLE L1 157 CLARIFICATION CLIN Numbers in L1 table for DPIA's do not match the CLIN Numbers in Section B for Execution Planning DPIA. C This was/will be addressed in Amendment 0003. Y 0003

REFERE

NCE NO.

SOLICITATION

SECTION

SOLICITATION

PAGE CATEGORY/ TYPE GENERAL SUBJECT STATEMENT REQUIRING CLARIFICATION OR QUESTION STATUS (O/C)

ANSWER AMENDMENT

REQUIRED

(Y/N)

AMENDMENT

NUMBER

41 TABLE L3 157 CLARIFICATION CLIN Numbers in L3 table for DPIA's do not match the CLIN Numbers in Section B for Accomplish DPIA C This was/will be addressed in Amendment 0003. Y 0003

42 159 HISTORICAL LABOR CLARIFICATION Historical labor, OH, G&A and other proposed rates for the last four corporate fiscal years plus year-to date actuals. Will the government require this data on a company level or a corporate level? C This is not a Government decision as it is applicable to the individual Offeror and its processes.

43 148 PAST PERFORMANCE CLARIFICATION Please clarify what the page limits are, if any, for Volume III. Past Performance. C There is no page count for Volume III, Past Performance.

44 150 MAN HOUR

PROJECTIONS CLARIFICATION

The RFP states "The offeror shall also utilize the Notional Work Packages for PIA Work Items and the availability schedule in Section F for man-hour projections, in responding to the Technical Proposals." Please confirm whether the projections are only to include the PIA Work Items, or both the PIA and DPIA work items

C This was/will be addressed in Amendment 0003.

The projections are for both the Notional Work Packages for PIA and DPIA.

Y 0003

45 161 Pre-Determined Work Item Estimate CLARIFICATION

RFP Section L, Pre-Determined Work Item Estimate provides the option for the offeror to deviate from the Government’s estimate for the pre-determined work items in attachment J-6. However, no work specs or references have been provided for any of the PIA or DPIA work items listed in attachment J-6. Please provide.

C

This was/will be addressed in Amendment 0003.

A revised J-6 will be provided. It will include each work specification that cannot be found in the notional DPIA work package. References will be provided.

Y 0003

46 161 WAF/OSHE CLARIFICATION

Work item 042-11-001 is listed in the PIA and DPIA notional packages and RFP Section L, Tables L-6 and L-7 as “Scheduling, Progressing and Associated Reports; provide”. However, in attachment J-6 Pre-Priced Item list 042-11-001 is listed as OSHE requirements. Please clarify.

C This was/will be addressed in Amendment 0003.

A revised J-6 will be provided with the correct items.

46 106 CLAUSE'S Service contract Reporting Requirements (OCT 2016)

NNS notes that the prescription for this clause states that “The contracting officer shall insert the clause at 52.204-14, Service contract Reporting Requirements, in solicitations and contracts for services (including construction) that meet or exceed the thresholds at 4.1703, except for indefinite-delivery contracts. NNS understands that this clause is not required for “actions entirely funded by DoD, …..”. Will this clause be removed from the requirements?

C This is not a service contract therefore, 52.204-14 is not applicable.

47 107 CLAUSE'S Protest After Award Only the basic version of the clause is included in the Contract. OFFEROR understands that the prescription for the clause indicates that the ALT I version of the clause should be inserted when the solicitation or contract contemplated by the Government is a cost-reimbursement contract. Will the RFP be amended to include Alt I in the requirements?

C Agreed 52.233-3 ALT I was added in Amendment 0004 Y 0004

48 107 CLAUSE'S Limitation of Liability – Services (Feb 1997)

The clause 52.246-24 for Limitation of Liability - High Value items is currently included in the RFP. The SOW includes services delivered as part of the contract, however the RFP does not include the clause FAR 52.246-25 for Limitation of Liability for Services.

Should this clause be included based on the prescription at 46.805?

C This is not a service contract therefore, 52.246-25 is not applicable.

49 Exhibit L006 Indirect Expense Schedules 164 Sect. L & Sect. J Exhibits Sect. L & Sect. J Exhibits

OFFEROR noticed there are conflicting pricing documents and instructions within Section L and the Attachments. 1. In Section J, Attachment S-1 – Exhibit L006 Indirect Expense Schedules: The table for CFY requires Total Expenses be provided for years 2012 – 2018 while the instructions in Section L, Page 164, Para. V.B. 3. f: Instructions for Section J-Exhibit L006- Indirect Expense Schedules requests the date range of 2010 – 2015. Will the Government please clarify the date range required for the proposal? 2. In Section J, Attachment S-1 – Exhibit L006 Indirect Expense Schedules: The table for GFY requires total proposed cost range (2019 – 2024), while the instructions in Section L, Page 164, Para. V.B. 3. f: Instructions for Section J-Exhibit L006- Indirect Expense Schedules request the date range of 2018 through 2023. Will the Government please clarify the date range required for the proposal?

C This was/will be addressed in Amendment 0003. Y 0003

50 Sect J Exhibit L005 164 & 159 Sect. L & Sect. J Exhibits Exh L005 Historical/Proposed Rates Summary Schedule

Will the Government please review the following RFP observations and provide range of dates required in the proposal? 1. In Section J, Attachment S-1, Exhibit L005- Historical/Proposed Rates Summary Schedule: The table requires data for CFY 2012 – 2018 while the instructions in Section L, Para.V.B.3.e requests the CFY date range of 2010 – 2015. Will the Government please clarify the date range required for the proposal? 2. In Section J, Attachment S-1, Exhibit L005 – Historical/Proposed Rates Summary Schedule: The table for the GFY Proposed Rates requires a range from 2019 – 2024 while the instructions in Section L requests data from 2016 – 2021. 3.

Further Page 159, Paragraph IV states Historical labor, overhead, G&A and other proposed rates for the last four corporate fiscal years plus year-to-date actuals and for indirect accounts, provide historical base/expense pool data as well as rates. Will the Government please clarify how this instruction relates to Exhibit L005?

C This was/will be addressed in Amendment 0003. Y 0003

51 146 CLAUSES Info. Assurance Contractor Training.

and Cert. (Jan 2008)

The Contractor understands the prescription for the subject DFAR Clause to be for acquisitions that include contractor information assurance functional services for DoD information systems as described in DoD 8570.01-M, or that require any appropriately cleared contractor personnel to access a DoD information system to perform contract duties. Please provide work specifications that require information assurance type services? If there are no such services in the SOW, does the Government intend to remove this clause?

C Agreed this is not applicable and was removed in Amendment 0004. Y 0004

52 L 157 CIA CLINS PRICING Please provide the period of performance (PoP) for the CIA planning CLIN. Is the PoP consistent with the hours requested to be priced? C This RFP was developed to provide an overarching idea of potential any potential CIA work will be addressed at the Order level for the purposes of this RFP Offerors shall follow the RFP instructions for PIA, DPIA, and IAPA only.

REFERE

NCE NO.

SOLICITATION

SECTION

SOLICITATION

PAGE CATEGORY/ TYPE GENERAL SUBJECT STATEMENT REQUIRING CLARIFICATION OR QUESTION STATUS (O/C)

ANSWER AMENDMENT

REQUIRED

(Y/N)

AMENDMENT

NUMBER

53 116 Warranty of Supplies of a Complex Nature (May 2001)

The contractor understands the clause is prescribed for solicitations and contracts for the delivery of complex items “when a fixed-price supply or research and development contract is contemplated and the use of the warranty clause has been approved under agency procedures.” Is the Government anticipating awarding orders that are either fixed price or R&D? If not, should this clause be removed?

C Agree, this is not applicable and was removed in Amendment 0004. Y 0004

54 CLAUSES Qualifying Country Sources as Subcontractors (DEC 2017)

The clause referenced above lists the qualifying countries from which the OFFEROR may buy supplies and services and augments the requirements of 252.225-7001 which is incorporated by reference in the RFP. OFFEROR understands the prescription at 225.11 to state that the subject clause is to be included when 252.225-7001 is included. Does the Government intend on adding 252.225-7002 to the requirements?

C Agree, this was added in Amendment 0004. Y 0004

55 J EXHBIT Integrated Program Management Report (IPMR)

The OFFEROR notes that the Government intends to provide a tailored down DID for each availability if Applicable. Can the Government provide examples of a tailored down DID for each type of availability? Also, will the Government please provide parameters for determining applicability?

C This information will be addressed at the individual ordering level.

56 J-1 139 Notional Work Package Requests C References will be provided. Please request reference from the names listed in the solictiation.

57 J-1 229 Notional Work Package Requests C References will be provided. Please request reference from the names listed in the solictiation.

58 L

The instructions appear to conflict.

Will the Navy clarify if Offerors are expected to price the FY23 CVN 76 DPIA beyond the RFP’s completion date of 12 March 2024?

C

Yes, offers are expected to price the CVN 76 DPIA FY23 through availability completion.

59 CLAUSES Prohibition of Hexavalent Chromium (Jun 2013

The OFFEROR notes that there is an exception at 223.7304 to the prescription for this clause which states “The prohibition in 223.7303 does not apply to— (a) Legacy systems and their related parts, subsystems, and components that already contain hexavalent chromium.

However, alternatives to hexavalent chromium shall be considered by the appropriate official during system modifications, follow-on procurements of legacy systems, or maintenance procedure updates and (b) Additional sustainment related contracts (e.g., parts, services) for a system in which use of hexavalent chromium was previously approved.” Is the contractor correct to consider the CVN 68 class ships to be and/or contain legacy systems? If so, will the Government consider removing this clause?

C

This was/will be addressed in Amendment 0004.

Y 0004

60 Section J ATTACHMENT J-6 Is it the Government's intent for Bidders to price all DPIA Notional Work items as Pre-Priced? Will the J-6 Table for the PIA Pre-Priced Work Items be modified to include all PIA Notional Work Items as Pre-Priced in a forthcoming Amendment? O

It is not the Government's intent for Bidders to price all DPIA Notional Work Items as pre-priced items. Amendment 0008 revised the Amendment J-6 and pre-priced work specifications will be sent upon request to biiders via AMRDEC.

Y 0008

The OFFEROR notes there are Government specification contained in the proposal. Will the Government please provide the following North West requirement documents as they have the potential to impact pricing?

099-01NW (01/11/2017)

099-02NW (07/01/2016)

099-03NW (02/10/2017)

099-04NW (01/11/2017)

009-05NW (01/11/2017)

099-06NW (01/11/2017)

099-07NW (01/11/2017)

099-10NW (05/25/2017)

099-60NW (03/08/2016) Referenced in work item 813-11-001 paragraph 2.1 (page 139)

The OFFEROR notes there are Government specification contained in the proposal. Will the Government please provide the following North West requirement documents as they have the potential to impact pricing?

099-01NW (01/11/2017)

099-02NW (07/01/2016)

099-03NW (02/10/2017)

099-04NW (01/11/2017)

009-05NW (01/11/2017)

099-06NW (01/11/2017)

099-07NW (01/11/2017)

099-10NW (05/25/2017)

099-60NW (03/08/2016) Referenced in work item 813-11-001 paragraph 2.1 (Page 229)

REFERE

NCE NO.

SOLICITATION

SECTION

SOLICITATION

PAGE CATEGORY/ TYPE GENERAL SUBJECT STATEMENT REQUIRING CLARIFICATION OR QUESTION STATUS (O/C)

ANSWER AMENDMENT

REQUIRED

(Y/N)

AMENDMENT

NUMBER

61 Section J ATTACHMENT J-6

Based upon all the requested and received information the Government sent list of 6 spec items and the file name identifies it as being for a DPIA. However, only one of the six work items is in the original J-6 DPIA Pre-Priced Item List, two are listed just in the DPIA Notional Work Package but have a different title and specs than the work item in the notional package, two are not in either the J-6 or the Notional Work package and one item, Flight Deck Non-Skid, has an item by the same name as an item in the Notional Package but with a different work item number and the work item specs are very different. 042-27-001 - Accountability of Manhour and Material Reservation - (not in original J-6 Pre-Priced list or Notional Work Package)

167-11-005 - Quick Acting Watertight Door 01-44-4; replace - (Item number in DPIA Notional Work Package with different title - AESS No. 13 Watertight Ballistic Hatch; repair)

634-21-001 - Hangar Bay No. 3 Non-Skid; replace - (Item number in DPIA Notional Work Package with different title - Flight Deck Nonskid; replace)

634-21-002 - Flight Deck Nonskid; replace - (work item number not listed in J-6 nor Notional Work Package, but Notional has same title for work item 634-21-001)

634-21-003 - Flight Deck Landing Area Nonskid; replace - (not in original J-6 Pre-Priced list or Notional Work Package)

982-32-001 - in original J-6 Pre-Priced list

O

Was addressed via Amendment 0008.

Y 0008