The file's text, extracted by GovTribe without its formatting.
N0002417R4429
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
AMENDMENT 0001
The purpose of Amendment 0001 is to:
-Section C, add Paragraph 3.5 "Milestone Definitions" -Section I, revise FAR Clause 52.211-11 Liquidated Damages -Section J, revise Attachment J-3 Execution Milestones and Key Event Dates -Sections L & M, revise the Interport Differential amount for Pascagoula, MS -Section M, delete "management" under Factor 2 - Technical Capabilities
Specific changes are outlined in red below.
SECTION C - DESCRIPTIONS AND SPECIFICATIONS
The following have been modified:
SCOPE OF WORK
1. GENERAL REQUIREMENTS
0. The Contractor under the direction of the Regional Maintenance Center (RMC) and as an independent Contractor and not as an agent of the Government, shall furnish the material, support (electrical, crane, rigging, etc.) and facilities (except those furnished by the Government under express provisions of this contract) and provide the management, technical, procurement, production, testing and quality assurance necessary to prepare and accomplish the repair and alteration of the USS MESA VERDE (LPD 19) FY18 Dry-Docking Phased Maintenance Availability (DPMA) in accordance with the requirements stated in this Section, the Work Item Specifications and Work Item Plans, Drawings, and Other References, the Delivery Schedule, and all other terms and conditions set forth in this contract. Category I NAVSEA FY17 Standard Items through CHG 2 identified under Attachment J-1 are applicable to all items without further reference. Category II NAVSEA FY17 Standard Items through CHG 2 are applicable when invoked and/or referenced in individual work items specified in Attachment J-1.
NAVSEA Standard items may be found at:
http://www.navsea.navy.mil/Home/RMC/CNRMC/OurPrograms/SSRAC/NSI.aspx
0. The Contractor shall accomplish planning and scheduling to ensure a rational, integrated and timely plan for receipt, storage and installation of Government Furnished Material as identified in work item specifications, and for accomplishment of production work.
0. The Contractor shall provide an integrated milestone plan for the availability. These milestones will include a schedule of key events necessary to meet the contract delivery dates. A critical path analysis and a milestone schedule shall be used to measure schedule accomplishment of the functions and elements required to successfully complete the repair and alteration of USS MESA VERDE (LPD 19) FY18 DPMA within the availability dates herein.
0. INTEGRATED PRODUCTION SCHEDULE DEVELOPMENT, UPDATE, AND REVIEWS –
In support of NAVSEA Standard Item requirements and to confirm the contractor has all available input for development of the Integrated Production Schedule, including the development of the Integrated Work Package, Production Schedule, Integration of O, I and D level Work, Integration of AIT and SHIPALT requirements and any other contractor assigned or Third Party work scheduled for accomplishment concurrent with the CNO availability, the contractor shall, with the Regional Maintenance Center (RMC), conduct the Work Package Execution Review (WPER). The WPER will take place at the RMC located at the vessel’s homeport. The RMC will schedule the WPER per the Joint Fleet Maintenance Manual (JFMM) Milestones either as a separate event or concurrent with an Integrated Project Team Development (IPTD) event no later than A-30 for CNO availabilities. This review shall be accomplished following the JFFM, Volume II, Integrated Fleet Maintenance requirements including the Critical Time Period, First 100 Hour Plan. Final 100 Hour plan and identify any schedule or scope impact. See Appendix E of the JFMM II-I-2E-1. The JFMM can be found at http://www.submepp.navy.mil/jfmm/index.htm.
The Contractor shall formally present its Integrated Production Schedule to the Navy Supervisory Authority (NSA) at the WPER, Start of the Availability, 25% complete conference, 50% complete conference, 75% complete conference, production completion meetings, and for pre Sea Trials requirements. The Integrated Production Schedule shall include Alteration Installation Teams (AIT), Government-Contracted Third Party Maintenance Providers, Ship's Force, Commercial Industrial Services (CIS), and Fleet Maintenance Activity (FMA) work to the maximum extent this information is available. At each meeting, the contractor shall present and explain, at minimum, the following information:
3. The Contractor's latest, Government approved, Integrated Production Schedule created in full compliance with Standard Item 009-60.
3. The Contractor's current progress in preparing for and/or executing the Availability in accordance with their Integrated Production Schedule. The Contractor shall provide an explanation and mitigation plan for any preparation or execution delays in comparison to their Integrated Production Schedule.
1. The Contractor's plan shall describe opportunities for schedule acceleration (at no cost to the Government unless directly related to a Government caused delay) and potential risks and mitigations to remaining schedule attainment.
0. Wherever the term “Job Order” is used in this solicitation/award, it also means “Contract.”
0. The Contractor shall report and recommend corrective action during contract performance for those deficiencies discovered which are not covered by the work specifications. As found conditions, needed repairs and corrective action reports will be submitted to the Government in the form of a Condition Found Report (CFR). The Contractor's conditions found reporting shall be in accordance with that set forth in Standard Item 009-01.
0. The Navy may send a site inspection team to perform an inspection of the contractor's facility prior to arrival of the vessel
0. GOVERNMENT FURNISHED MATERIAL: Government Furnished Material (GFM) cited in the solicitation will be shipped to the contractor’s facility. The successful offeror is to coordinate delivery of Government Furnished Material with the Project Manager. Government property permanently removed from a vessel that requires a Property Administrator's disposition instructions shall be properly prepared for shipment and be delivered as directed by the Property Administrator. GFM will be listed in paragraph 5 of the Work Item(s).
0. QUALITY ASSURANCE
8. QUALITY ASSURANCE PROGRAM - The Contractor shall provide and maintain a quality assurance program acceptable to the Government, and shall perform or have performed the inspections and tests pursuant to that program to substantiate that the material and workmanship provided pursuant to the job order conform to the drawings, specifications, job orders, and contract requirements listed herein. The Contractor's quality assurance program shall be in accordance with that set forth in Standard Item 009-04. In addition to its rights under Clause 252.217-7005, Inspection and Manner of Doing Work (Jul 2009), the Government shall have the right to deem work or material furnished by the Contractor to be incomplete and not in accordance with the requirements of the job order by reason of the Contractor's failure to comply with the requirements of its quality assurance program and, as such, the Contractor shall not be entitled to progress payments for said work and material.
8. Quality Assurance Surveillance Plan (QASP) - The Contractor shall meet the performance/acceptable quality level requirements for each deliverable/assessment area in the QASP, Attachment J-5. There will be monetary deductions based on unfavorable contractor performance as stated in the QASP. There is no maximum dollar limit to the deductions which can be assessed against the Contractor for failing to meet the performance/acceptable quality level requirements.
0. IDENTIFICATION OF CONDITION FOUND - In accordance with the requirements of NAVSEA Standard Item 009-01, the contractor shall identify needed repairs and recommend corrective action during contract performance for work/deficiencies discovered which are not covered by the existing work package. For conditions to impact the critical path(s) /controlling item(s), the contractor shall notify the government via electronic media within 24-hours of discovery. This initial notification need not include all content required for a Condition Found Report (CFR), but must include a description of the condition/deficiency and an estimated timeframe for the offeror's professional recommendation for resolution, which shall not exceed five (5) working days as specified below. Recommended repairs and corrective actions shall be submitted to the Government in the form of a CFR (intended to represent the "Work Request" described in DFARS 252.217-7028, Over and Above Work (Dec 1991)) per CDRL A002.
1.10.1 CONDITION FOUND NOTIFICATION TO GOVERNMENT
CFRs shall be submitted through the Navy Maintenance Database Re-platform (NMDR) within five (5) working days of discovery of the condition. At a minimum, the CFR will include the following:
(1) Identify contract, ship, and hull number
(2) Serialized by CFR number
(3) Identification of the applicable Work Item number
(4) Date requirement was discovered
(5) Description of the work requirement
(6) Specific location of the work
(7) Recommendation for corrective action
(8) Recommendation for the appropriate/best time to accomplish the work (i.e. during current availability with or without schedule change, future CNO or Continuous Maintenance Availability). Provide supporting rationale for the recommendation, such as cost efficiencies, availability of work force, availability of material, premium expenditures, etc.
(9) Identification of related changes, if any, to the internal milestones and production and contract completion dates.
1.10.2 GOVERNMENT REVIEW AND RESPONSE TO CFR
The Maintenance Team will review the CFR. If the CFR is inadequate or incomplete, it will be rejected with time continuing to accrue (relative to five (5) working day requirement). As appropriate, the Government and contractor will need to meet, conduct ship checks and/or discuss the recommendation for corrective action further to determine the full scope of work required prior to final approval of the CFR. The contractor's accuracy reflected in the CFRs submitted may be evaluated in CPARS and utilized for past performance ratings on future requirements. Additionally, deductions may be assessed in accordance with Attachment J-5, QASP.
1.11 REQUEST FOR CONTRACT CHANGE (RCC)
In the event a growth requirement or new work is validated and fully scoped, the Government may generate a Request for Contract Change (RCC) and the ACO may request a firm fixed price proposal from the contractor.
The contractor shall provide all Change Order Price Analysis (COPA) proposals to the ACO in response to RCCs within seven (7) calendar days. A contractor’s COPA shall remain valid for a minimum of 14 calendar days, unless otherwise specified on an individual RCC by the ACO; if another timeline is specified by the Government on an individual RCC, the contractor’s COPA shall remain valid for that amount of time. A COPA addressing a change to the FFP contract shall include at a minimum:
| a. | Labor hours to be performed by the Prime Contractor | | __________ | | | |
| b. | Subcontractor Quote (If applicable) | * | | $__________ | | |
| c. | Material Quote (If applicable)** | | | | $__________ | |
| d. | Mark-up (If applicable) | | | | | $__________ |
*Subcontractor quotes shall include labor hours, labor rate, material (part number, description, unit cost, quantity, total cost, and vendor quotes for each line item), and tiered subcontractor quotes (if applicable)
** Material quote shall include the part number, description, unit cost, quantities, total cost, and vendor quotes for each line item
Note 1: Labor hours for both prime and subcontract shall be provided broken down by trade and labor mix.
Note 2: The required documentation must accompany the COPA for the COPA to be considered submitted to the ACO. See Attachment J-5, QASP, for deductions associated with late or invalid COPA submittals.
If circumstances arise where the contractor is unable to submit a COPA within seven (7) calendar days, the contractor shall notify the ACO in writing of the specific circumstances and provide a revised date in which a COPA proposal will be submitted. Additional time needed to complete a COPA may be granted solely at the discretion of the ACO. The new timeframe granted, solely at the discretion of the ACO which may differ from the contractor’s request, shall be met by the contractor. Deductions may be assessed in accordance with Attachment J-5, QASP.
0. NAVY MAINTENANCE DATABASE (NMD): The Contractor shall use NMD for the submission of Condition Found Reports throughout the administration of this contract. NMD is located at https://mfom.sscno.nmci.navy.mil/MFOM/DodStatement.aspx.
0. ORGANIZATION CHART AND EMPLOYEE ROSTER:
1. ORGANIZATION CHART - Within 30 days of contract award, submit a chart detailing each management, technical, engineering and production position from the highest company level to the lowest supervisory level. Include descriptions of each position describing the duties, responsibilities, authority and names of the individuals filling the positions. The organizational chart must represent the facility that will perform the work.
1. EMPLOYEE ROSTER: After receipt of award and prior to starting work aboard the vessel, the contractor must submit a list of employees who will work aboard ship to the Commanding Officer of the ship via the NSA Security Office. The list should be on company letterhead, include each employee's name and security clearance when required, and bear the signature of a company official.
0. AUTHORIZED CHANGES ONLY BY THE CONTRACTING OFFICER – No order, statement, or conduct of Government personnel who visit the Contractor's facilities or in any other manner communicates with Contractor personnel during the performance of this contract shall constitute a change under the "Changes" clause of this contract. The Contractor shall not comply with any order, direction or request of Government personnel unless it is issued in writing and signed by the Contracting Officer, or is pursuant to specific authority otherwise included as a part of this contract. The Contracting Officer is the only person authorized to approve changes in any of the requirements of this contract and, notwithstanding provisions contained elsewhere in this contract, the said authority remains solely the Contracting Officer's. In the event the contractor effects any change at the direction of any person other than the Contracting Officer, the change will be considered to have been made without authority and no adjustment will be made in the contract price to cover any increase in charges incurred as a result thereof.
1. LOCATION: Government facilities are not available for this requirement. All work shall be completed at the contractor’s facilities.
2.1 DRYDOCK CERTIFICATION - The dry-docking of all vessels shall be accomplished in dry docks certified in accordance with MIL-STD-1625D(SH) dated 27 August 2009.
3. SCHEDULE: USS MESA VERDE must be delivered, mission-ready, no later than 03 May 2019.
3.1: MILESTONES: In addition to the contract completion date of 03 May 2019, the Government has established execution dates for the milestones identified in Attachment J-3.
3.1.1 - Reserved
3.1.2 - If any milestone event is not accomplished by the date provided, and the failure to accomplish any such milestone event does not arise from a cause beyond the control and without fault or negligence of the Contractor, such failure may be deemed to constitute a failure to perform this contract in accordance with its terms within the meaning of subparagraph (a)(1)(ii) of the clause of this contract entitled "DEFAULT” (DFARS 252.217-7009).
3.1.3 - Reserved
3.1.4- The Contractor shall schedule the performance of all items in the USS MESA VERDE (LPD 19) FY18 DPMA work package, including work items included as both Base and Option items, so as to permit a contract scope increase up to 94,048 “hours” and $1,506,656 in “material” to be performed as "Additional Requirements" (including growth and new work). “Material,” as defined for the application of this paragraph, is defined as physical deliverable materials, exclusive of prime and subcontractor labor. “Hours,” as defined for the application of this paragraph is to include both prime and subcontract labor hours. The contractor agrees that these Additional Requirements, if ordered, shall be performed concurrently with the aforementioned work items, during the contract period of performance, without impacting, accelerating, or causing delay or disruption to the work required by the aforementioned work items, to any other Government contract, or to any other work in progress for the Government.
The "Additional Requirements," if required, shall be ordered during the contract period of performance, as may be modified, on the following schedule:
0. No more than 75% of the hours or material following the 25% schedule point the availability (as measured in days between the “Start Availability” and “End of Availability” milestones in Attachment J-3).
0. No more than 50% of the hours or material following the 50% schedule point the availability (as measured in days between the “Start Availability” and “End of Availability” milestones in Attachment J-3).
0. No more than 25% of the hours or material following the 75% schedule point the availability (as measured in days between the “Start Availability” and “End of Availability” milestones in Attachment J-3).
3.2. DELAYS / DISRUPTIONS: The contractor shall coordinate the work effort with the NSA Project Manager on a daily basis to prevent changing situations from causing delays and disruptions. Disruption due to minor delays in obtaining access to spaces and operation of equipment are to be expected. A minor delay is defined as eight (8) hours or less. These disruptions are considered normal rather than unusual occurrences during the performance of tasks ordered under this contract. If, during contract performance, delays greater than those indicated above are encountered, the Contractor shall immediately verbally notify the Project Manager and Contracting Officer, followed by a written statement within 24 hours after occurrence of delay, stating time of impact, reason for delay, duration of impact, number of people affected, action taken to properly schedule the work, action taken to minimize impact, and the names of the Government person(s) contacted.
3.3 - SCHEDULE AND ASSOCIATED REPORTS: The proposed scheduling of work, resources, key events and milestones submitted by the Contractor in accordance with Standard Item 009-60 during the course of contract performance shall not be materially different from the Schedule and Associated Reports provided in the Contractor’s technical proposal.
3.4 MILESTONES FOR CERTAIN REPORTS (Quality Assurance Plan (QASP) Attachment J-5 Deliverable 2): The contractor shall complete the necessary work associated with the following reports and submit to the Government the required reports in the necessary format and containing the required information as specified in the Work Item no later than A+61.
| Work Item |
| Description |
| Report Paragraph Number |
| Report Type |
Reports Due On or Before the First 20% of the Docking Duration, as specified by the docking date in Attachment J-3
| 110-11-001 |
| Underwater Hull and Appendages; inspect |
| 3.4.2 |
| Visual |
| 163-11-002 |
| Sea Chest; inspect and repair |
| 3.3.2 |
| Visual |
| 243-11-002 |
| Stern Tube Shaft Seal; overhaul |
| 3.2.2.1 |
| Visual with OEM assist |
| 3.2.4.4 |
| Visual & Measurement |
| 243-11-005 |
| Starboard Propulsion Shafting; inspect and repair |
| 3.3.2.1 |
| Visual |
| 243-12-003 |
| Port Propulsion Shafting; inspect and repair |
| 3.3.2.1 |
| Visual |
| 244-11-001 |
| Outboard Propulsion Shafting (Starboard), Bearing Clearance Measurement; perform |
| 3.1.1 |
| Measurement |
Measurement
Measurement
| 244-12-003 |
| Outboard Propulsion Shafting (Port), Bearing Clearance Measurement; accomplish |
| 3.2.3 |
| Visual & |
Measurement
Measurement
| 245-11-001 |
| Controllable Pitch Propeller (CPP) Blade; repair and assess |
| 3.3.4 |
| Torque |
| 245-11-004 |
| Controllable Pitch Propeller (CPP) Starboard Valve Rod |
Assembly; repair
Measurement
| 245-12-003 |
| Controllable Pitch Propeller (CPP) Port Valve Rod Assembly; |
repair
Measurement
| 520-10-001 |
| Sea Valve; repair and replace |
| 3.1.1 |
| Pre-Op Test |
| 529-11-004 |
| Main and Secondary Drainage Valves; repair |
| 3.1.1 |
| Pre-Op Test |
| 529-11-005 |
| Main and Secondary Drainage Valves; replace |
| 3.4.1 |
| Visual |
| 562-11-001 |
| Rudderstock Seal Assembly (PORT and STBD); repair |
| 3.2.1.1 |
| Visual |
| 562-11-003 |
| Rudder Stock Bearing; replace |
| 3.5.1.1 |
| Visual |
Measurement
| 631-31-001 |
| Underwater Hull; preserve |
| 3.4.5.2 |
| Visual |
| 633-21-001 |
| Impressed Current Cathodic Protection System Reference |
Electrode Assembly; replace
| 3.2.1 |
| Pre-Op Test, Visual |
Reports Due On or Before the First 20% of the Avail Duration, as specified in Attachment J-3
| 138-11-001 |
| Flight Deck Catwalk; preserve |
| 3.2.1 |
| Visual |
| 241-11-001 |
| Main Reduction Gear (MRG) Turning Gear; overhaul |
| 3.6.4 |
| Visual & |
Measurement
| 259-11-001 |
| Propulsion Gas Turbine Exhaust Duct No. One; repair |
| 3.4.2 |
| Visual & NDT |
| 259-11-004 |
| Gas Turbine Air Intake Perforated Sheathing; preserve |
| 3.3.1 |
| Visual |
| 261-11-001 |
| Quick Closing Valve Remote Pull Cable; replace |
| 3.2.1 |
| Inspection |
| 262-11-001 |
| Main Lube Oil Cooler Clean and Inspect |
| 3.4.3 |
| Repair Recommendations |
| 262-41-001 |
| Lube Oil Service Pump; overhaul |
| 3.3.3.1 |
| Inspection |
| 262-42-001 |
| Lube Oil Service Pump; overhaul |
| 3.3.3.1 |
| Inspection |
| 304-11-001 |
| Multiple Cable Penetrator (MCP); repair |
| 3.1.1 |
| Inspection |
| 311-21-001 |
| Ship Service Diesel Generator (SSDG) No.One, "D" Level 8,000 |
Hour Maintenance; accomplish
| 3.4.8 |
| Inspection of 3.4.1, 3.4.3, & 3.4.4 |
| 311-23-002 |
| Title: Ship Service Diesel Generator (SSDG) No.3, "D" Level |
8,000 Hour Maintenance; accomplish
| 3.4.8 |
| Inspection of 3.4.1, 3.4.3, & 3.4.4 |
| 311-23-003 |
| Number 3 Ship Service Diesel Generator Intake Air Cooler; |
repair
| 311-26-001 |
| Cylinder Head Cap Plug, No.6 Ship Service Diesel Generator |
Engine(SSDGE); replace
| 3.6.3.1 |
| Visual & Measurements |
| 311-26-003 |
| Ship Service Diesel Generator (SSDG) No.6, "D" Level 8,000 |
Hour Maintenance; accomplish
| 3.4.8 |
| Inspection of 3.4.1, 3.4.3, & 3.4.4 |
| 521-11-001 |
| Firemain Valve; repair |
| 3.1.1 |
| Pre-Op |
| 524-21-001 |
| Auxiliary Machinery Seawater Pump; repair |
| 3.3.3.2 |
| Visual & Measurements |
| 529-11-001 |
| Ballast Valves; repair |
| 3.1.1 |
| Pre-Op |
| 529-61-001 |
| Deballast Air Compressor (DBAC) NO. 2, Class B Overhaul; |
accomplish
| 529-61-002 |
| Deballast Air Compressor (DBAC) No. One, Class B Overhaul; |
accomplish
| 529-61-004 |
| Deballast Air Compressor (DBAC) No. 3, Class B Overhaul; |
accomplish
| 529-61-005 |
| Deballast Air Compressor (DBAC) No. 5, Class B Overhaul; |
accomplish
| 529-61-006 |
| Deballast Air Compressor (DBAC) No. 4, Class B Overhaul; |
accomplish
| 533-11-001 |
| Potable Water Pump No. 4; overhaul |
| 3.4.1.1 |
| Visual |
| 541-12-003 |
| Hellan Strainer; replace |
| 3.1.2 |
| Pre-Op & Visual |
| 553-10-001 |
| Nitrogen Generator/Compressor No. One and No. 2; overhaul and |
system clean
| 581-11-002 |
| Anchor and Anchor Chain; inspect and preserve |
| 3.4.11 |
| Inspection |
| 584-21-001 |
| Stern Gate Upper and Lower Hydraulic Cylinder Assembly; |
repair
| 588-11-001 |
| Thrust Roller, Deck Edge Aircraft Elevator; repair |
| 3.2.2 |
| Inspection |
| 588-11-003 |
| Port Aircraft Elevator Lockbar; repair |
| 3.1.2 |
| Inspection |
| 623-11-002 |
| Starboard (Stbd) Accommodation Ladder; repair |
| 3.1.1 |
| Visual |
This listing is not all-inclusive of reports to be provided by the Contractor.
3.5 Milestone Definitions. The following milestones shall be considered achieved (certified) if all work associated with each of the key events as identified in the WIs below are completed in their entirety (no Contractor caused exceptions allowed), accepted, and certified by the SUPERVISOR.
(a) Undocking. Prior to undocking, the following Work Items must be complete in their entirety (no contractor caused exceptions allowed), accepted, and certified by the SUPERVISOR:
| 110-11-001 |
| Underwater Hull Inspection and Repair; accomplish |
| 123-10-001 |
| Tanks and Voids Open, Pump, Clean and Gas Free; accomplish |
| 123-10-002 |
| Fresh Water/Water Mist Storage Tank; repair and preserve |
| 123-11-001 |
| Fuel Oil Overflow Storage Tank; repair |
| 123-11-002 |
| Fuel Oil Storage Tank; preserve |
| 123-11-003 |
| Auxiliary Fuel Oil Service Tank; preserve |
| 123-11-004 |
| Fuel Oil Storage Tank Clad Weld; accomplish |
| 123-12-001 |
| JP-5 Tank; repair |
| 123-12-002 |
| JP-5 Tank; preserve |
| 123-14-001 |
| Potable Water Tank; repair and preserve |
| 123-14-003 |
| Water Mist Fire Extinguishing Storage Tank; repair |
| 123-15-001 |
| SSDG Used Lube Oil Tank; repair |
| 123-15-002 |
| Lube Oil Tank; repair |
| 123-16-003 |
| Ballast Tank; repair |
| 123-16-004 |
| Ballast Tank; repair |
| 123-16-006 |
| Ballast Tank; repair |
| 123-16-007 |
| Ballast Tank; clad weld, repair and preserve |
| 123-16-009 |
| Ballast Tank; repair |
| 123-16-011 |
| Ballast Tank; repair |
| 123-16-014 |
| Ballast Tank; repair and preserve |
| 123-17-001 |
| Contaminated Oil Tank; repair |
| 123-17-002 |
| Contaminated Oil Tank; repair |
| 123-17-003 |
| Contaminated Oil Tank; repair |
| 123-17-004 |
| Contaminated Oil Tank Clad Weld; accomplish |
| 123-17-008 |
| Contaminated Oil Tank; repair and preserve |
| 163-11-001 |
| Sea Chest; repair |
| 167-90-002 |
| ShipAlt LPD17-82448K, SternGate Corrosion Mod to IC Sys; accomplish |
| 233-11-002 |
| 1A Main Propulsion Diesel Engine (MPDE) Air Intake System; replace |
| 233-11-004 |
| Main Propulsion Diesel Engine (MPDE) Turbocharger; clean and inspect |
| 233-11-005 |
| Main Propulsion Diesel Engine (MPDE) Sequential Turbocharger Valve; replace old valves with new valves and gaskets |
| 233-11-006 |
| Main Propulsion Diesel Engine (MPDE) Air Start Distributor and Main Air Start Control Valve; clean and inspect |
| 233-11-007 |
| Main Propulsion Diesel Engine (MPDE); overhaul |
| 233-11-008 |
| 1A Main Propulsion Diesel Engine (MPDE), Fuel Oil Injection Pump and Fuel Oil Injection Pump Drive; overhaul |
| 233-11-009 |
| Main Propulsion Diesel Engine (MPDE) Intercooler; clean and inspect |
| 233-11-010 |
| Main Propulsion Diesel Engine (MPDE), Flexible Coupling; inspect and repair |
| 233-11-011 |
| Number 1A Main Propulsion Diesel Engine (MPDE) Crankcase Vacuum Fan and Impeller; repair |
| 233-11-012 |
| Number 1A Main Propulsion Diesel Engine (MPDE) Vibration Damper; repair |
| 233-12-002 |
| 1B Main Propulsion Diesel Engine (MPDE) Air Intake System; replace |
| 233-12-003 |
| 1B Main Propulsion Diesel Engine (MPDE), Fuel Oil Injection Pump and Fuel Oil Injection Pump Drive; overhaul |
| 233-12-004 |
| Main Propulsion Diesel Engine (MPDE) Turbocharger; clean and inspect |
| 233-12-006 |
| Main Propulsion Diesel Engine (MPDE) Sequential Turbocharger Valve; replace old valves with new valves and gaskets |
| 233-12-007 |
| Main Propulsion Diesel Engine (MPDE) Air Start Distributor and Main Air Start Control Valve; clean and inspect |
| 233-12-009 |
| Main Propulsion Diesel Engine (MPDE); overhaul |
| 233-12-010 |
| Main Propulsion Diesel Engine (MPDE) Intercooler; clean and inspect |
| 233-12-011 |
| Number 1B Main Propulsion Diesel Engine (MPDE) Crankcase Vacuum Fan and Impeller; repair |
| 233-12-013 |
| Main Propulsion Diesel Engine (MPDE) Vibration Damper; repair |
| 233-13-002 |
| 2A Main Propulsion Diesel Engine (MPDE), Fuel Oil Injection Pump and Fuel Oil Injection Pump Drive; overhaul |
| 233-13-003 |
| Main Propulsion Diesel Engine (MPDE) Turbocharger; clean and inspect |
| 233-13-004 |
| Main Propulsion Diesel Engine (MPDE) Vibration Damper; repair |
| 233-13-005 |
| Main Propulsion Diesel Engine (MPDE) Sequential Turbocharger Valve; replace old valves with new valves and gaskets |
| 233-13-006 |
| Main Propulsion Diesel Engine (MPDE); overhaul |
| 233-13-007 |
| Main Propulsion Diesel Engine (MPDE) Flexible Coupling; repair |
| 233-13-008 |
| Main Propulsion Diesel Engine (MPDE) Intercooler; clean and inspect |
| 233-13-009 |
| Number 2A Main Propulsion Diesel Engine (MPDE) Crankcase Vacuum Fan and Impeller; repair |
| 233-13-011 |
| Number 2A Main Propulsion Diesel Engine (MPDE) Air Intake Pre-Heater; replace |
| 233-14-002 |
| 2B Main Propulsion Diesel Engine (MPDE), Fuel Oil Injection Pump and Fuel Oil Injection Pump Drive; overhaul |
| 233-14-003 |
| Main Propulsion Diesel Engine (MPDE) Turbocharger; clean and inspect |
| 233-14-004 |
| Main Propulsion Diesel Engine (MPDE) Vibration Damper; repair |
| 233-14-005 |
| Main Propulsion Diesel Engine (MPDE) Sequential Turbocharger Valve; replace old valves with new valves and gaskets |
| 233-14-006 |
| Main Propulsion Diesel Engine (MPDE); overhaul |
| 233-14-007 |
| Main Propulsion Diesel Engine (MPDE) Intercooler; clean and inspect |
| 233-14-009 |
| Number 2B Main Propulsion Diesel Engine (MPDE) Crankcase Vacuum Fan and Impeller; repair |
| 233-14-011 |
| Number 2B Main Propulsion Diesel Engine (MPDE) Air Intake Pre-Heater; replace |
| 233-14-012 |
| Main Propulsion Diesel Engine (MPDE) Spare Cylinder Head and Components; clean and inspect |
| 241-11-001 |
| Main Reduction Gear Foundation Chock; inspect and repair |
| 241-11-002 |
| Number One Main Reduction Gear (MRG) Attached Lube Oil Pump Foundation; repair |
| 241-12-001 |
| Number 2 Main Reduction Gear (MRG) Attached Lube Oil Pump Foundation; repair |
| 241-90-001 |
| ShipAlt LPD17-82232K, LPD 17 Class Flame Arrestor Relocation; accomplish |
| 243-10-001 |
| Main Propulsion Shafting Forward Boss Fairing; repair |
| 243-11-001 |
| Starboard Stern Tube Shaft Seal; overhaul |
| 243-11-002 |
| Propulsion Shafting; inspect and repair |
| 243-12-001 |
| Port Stern Tube Shaft Seal; overhaul |
| 243-12-002 |
| Propulsion Shafting; inspect and repair |
| 243-80-001 |
| ShipAlt LPD17-84077D, Modify Port and Starboard Shaft Bossing Sections; accomplish |
| 244-11-001 |
| Main Propulsion Line Shaft Bearing Alignment; accomplish |
| 244-11-002 |
| Outboard Propulsion Shafting, Bearing Clearance Measurement; accomplish |
| 244-11-003 |
| Propulsion Shaft and Bearing Alignment; Assess |
| 244-12-001 |
| Outboard Propulsion Shafting, Bearing Clearance Measurement; accomplish |
| 244-12-002 |
| Propulsion Shaft and Bearing Alignment; assess |
| 245-11-001 |
| Controllable Pitch Propeller (CPP) Hub; replace |
| 245-11-002 |
| Controllable Pitch Propeller (CPP) Oil Distribution (OD) Box; replace |
| 245-11-003 |
| Controllable Pitch Propeller (CPP) Valve Rod Assembly; repair |
| 245-11-004 |
| Controllable Pitch Propeller (CPP) Blade; inspect and repair |
| 245-11-005 |
| Number One Main Reduction Gear (MRG) Controllable Pitch Propeller (CPP) Attached Pump Foundation; repair |
| 245-12-001 |
| Controllable Pitch Propeller (CPP) Hub; replace |
| 245-12-002 |
| Controllable Pitch Propeller (CPP) Oil Distribution (OD) Box; replace |
| 245-12-003 |
| Controllable Pitch Propeller (CPP) Valve Rod Assembly; repair |
| 245-12-004 |
| Controllable Pitch Propeller (CPP) Blade; inspect and repair |
| 245-12-005 |
| Number 2 Main Reduction Gear (MRG) Controllable Pitch Propeller (CPP) Attached Pump Foundation; repair |
| 256-61-001 |
| Number 1A Main Propulsion Diesel Engine (MPDE) Central Freshwater (CFW) Heat Exchanger; clean and inspect |
| 256-61-002 |
| Number 1B Main Propulsion Diesel Engine (MPDE) Central Freshwater (CFW) Heat Exchanger; clean and inspect |
| 259-11-001 |
| Main Propulsion Diesel Engine (MPDE), Exhaust Fastener and Exhaust Bellow; replace |
| 259-12-001 |
| Main Propulsion Diesel Engine (MPDE), Exhaust Expansion Joint and Exhaust Fastener; replace |
| 259-13-001 |
| Main Propulsion Diesel Engine (MPDE), Exhaust Expansion Joint and Exhaust Fastener; replace |
| 259-14-001 |
| Main Propulsion Diesel Engine (MPDE), Exhaust Expansion Joint and Exhaust Fastener; replace |
| 259-80-001 |
| ShipAlt LPD17-88788D, Main Propulsion Diesel Engine (MPDE) Expansion Joint Replacement; accomplish |
| 262-11-001 |
| Lube Oil Piping; repair |
| 262-11-002 |
| Lube Oil Piping; repair |
| 262-12-001 |
| 2B Main Propulsion Diesel Engine Lube Oil Filter Differential Pressure Gauge Tubing; repair |
| 262-12-002 |
| 2A Main Propulsion Diesel Engine (MPDE) Lube Oil Cooler Inlet Pressure Gauge Tubing; repair |
| 262-90-001 |
| ShipAlt LPD17-79652K, Main Propulsion Diesel Engine Filter Modification; accomplish |
| 262-90-002 |
| ShipAlt LPD17-78278K, Main Propulsion Diesel Engine Lube Oil Pump Crossover Piping Modification; accomplish |
| 264-11-002 |
| Number 2A MPDE Rocker Lube Oil Gage Piping; replace |
| 264-31-001 |
| Main Reduction Gear Lube Oil Purifier Heater; replace |
| 264-31-002 |
| Main Reduction Gear Lube Oil Purifier Heater; replace |
| 299-21-001 |
| Main Propulsion Diesel Engine Hydraulic Hand Pump; repair |
| 311-21-002 |
| Ship's Service Diesel Generator (SSDG) Exhaust Fastener; replace |
| 311-21-004 |
| Ships Service Diesel Generator (SSDG) Aftercooler; repair |
| 311-21-005 |
| Number One Ship's Service Diesel Generator (SSDG) Fuel Oil Heat Exchanger; clean and inspect |
| 311-21-006 |
| Ship's Service Diesel Generator (SSDG) Top End Overhaul; accomplish |
| 311-22-002 |
| Ship's Service Diesel Generator (SSDG) Exhaust Expansion Joint and Exhaust Fastener; replace |
| 311-22-003 |
| Ships Service Diesel Generator (SSDG) Aftercooler; repair |
| 311-22-004 |
| Number 2 Ship's Service Diesel Generator (SSDG) Air Inlet Shutoff Valve; replace |
| 311-22-005 |
| Number 2 Ship's Service Diesel Generator (SSDG) Fuel Oil Heat Exchanger; clean and inspect |
| 311-23-003 |
| Ships Service Diesel Generator (SSDG) Aftercooler; repair |
| 311-23-004 |
| Ship's Service Diesel Generator (SSDG) Exhaust Fastener; replace |
| 311-23-005 |
| Number 3 Ship's Service Diesel Generator (SSDG) Fuel Oil Heat Exchanger; clean and inspect |
| 311-23-006 |
| Ship's Service Diesel Generator (SSDG) Top End Overhaul; accomplish |
| 311-24-002 |
| Number 4 Ship's Service Diesel Generator (SSDG) Air Inlet Shutoff Valve; replace |
| 311-24-003 |
| Ships Service Diesel Generator (SSDG) Aftercooler; repair |
| 311-24-004 |
| Ship's Service Diesel Generator (SSDG) Exhaust Expansion Joint and Exhaust Fastener; replace |
| 311-24-005 |
| Number 4 Ship's Service Diesel Generator (SSDG) Fuel Oil Heat Exchanger; clean and inspect |
| 311-25-003 |
| Ships Service Diesel Generator (SSDG) Aftercooler; repair |
| 311-25-004 |
| Ship's Service Diesel Generator (SSDG) Exhaust Expansion Joint and Exhaust Fastener; replace |
| 311-25-005 |
| Number 5 Ship's Service Diesel Generator (SSDG) Fuel Oil Heat Exchanger; clean and inspect |
| 311-25-006 |
| Ship's Service Diesel Generator (SSDG) Top End Overhaul; accomplish |
| 453-48-001 |
| SPS-48E Antenna; replace |
| 506-11-001 |
| Vent Tank Sounds and Overflow Piping; repair |
| 512-90-003 |
| ShipAlt LPD17-82469K, Ship Service Diesel Generator (SSDG) Ventilation Modification; accomplish |
| 520-11-001 |
| Sea Valve; repair and replace |
| 521-11-001 |
| Firemain Piping System; repair |
| 521-90-001 |
| ShipAlt LPD17-81157.01K Auxiliary Sea Water System Valve Replace; accomplish |
| 521-90-002 |
| ShipAlt LPD17-81157.02K Auxiliary Sea Water System Valve Replace; accomplish |
| 521-90-003 |
| ShipAlt LPD17-85606.05K, 85606.06K, 85606.09K, 85606.11K, Firemain Branch Piping Modifications; accomplish |
| 524-11-001 |
| Auxiliary Sea Water System (ASW) Piping; chemical clean (Optional) |
| 524-90-001 |
| ShipAlt LPD17-81157.04K Auxiliary Seawater System Valve Replace; accomplish |
| 524-90-002 |
| ShipAlt LPD17-81157.03K Auxiliary Seawater System Valve Replace; accomplish |
| 524-90-003 |
| ShipAlt LPD17-81415K Ship's Service Diesel Generator (SSDG) Auxiliary Seawater System Piping Upgrade; accomplish |
| 532-90-001 |
| ShipAlt LPD17-82460K SPS-48E Expansion Tank Relocation; accomplish |
| 536-11-001 |
| Number 1A Main Propulsion Diesel Engine (MPDE) Jacket Water (JW) Keep Warm Pump and Motor; repair |
| 536-11-002 |
| Number 1B Main Propulsion Diesel Engine (MPDE) Jacket Water (JW) Keep Warm Pump and Motor; repair |
| 536-11-003 |
| Number 2A Main Propulsion Diesel Engine (MPDE) Jacket Water (JW) Keep Warm Pump and Motor; repair |
| 536-11-004 |
| Number 2B Main Propulsion Diesel Engine (MPDE) Jacket Water (JW) Keep Warm Pump and Motor; repair |
| 536-12-002 |
| Number 1B Main Propulsion Diesel Engine Jacket Water Heater; replace |
| 555-51-001 |
| Water Mist Firefighting (WMFF) Valve and Actuator; repair |
| 555-51-002 |
| Water Mist Firefighting (WMFF) Pump; repair |
| 555-80-001 |
| ShipAlt LPD17-80860D, Watermist Fire Extinguishing System Pump Modification; accomplish |
| 561-80-002 |
| ShipAlt LPD17-83657D, Steering Gear Tiller Modification; accomplish |
| 562-11-001 |
| Rudder Bearing Seal and Rudderstock Seal; repair |
| 584-21-001 |
| Lower Stern Gate Gasket; replace |
| 584-21-002 |
| Stern Gate Upper and Lower Hydraulic Cylinder Assembly; repair |
| 631-31-001 |
| Underwater Hull; preserve |
| 631-41-001 |
| Freeboard; preserve |
| 633-21-001 |
| Impressed Current Cathodic Protection (ICCP) System; repair |
| 633-21-002 |
| Impressed Current Cathodic Protection (ICCP) System; repair |
| 980-90-003 |
| ShipAlt LPD19-MA 81842K MIDE Bulkhead Shaft Seal Installation Alteration Installation Team (AIT) Support Service; provide |
(b) Crew Move Aboard. This milestone is considered achieved if all contracted work that impacts habitability spaces and habitability support systems is completed in its entirety (no contractor caused exceptions allowed), certified, and accepted by the SUPERVISOR. Completion of habitability spaces shall be evidenced by closeout of spaces per NAVSEA Standard item 009-81. Key areas of concern are: safety of the crew, sanitation and serviceability of food preparation, serving, and eating areas; livability of berthing and sanitary spaces; cleanliness.
1. The following is the list of Work Items that must be completed in its entirety (no contractor exceptions allowed), certified, and accepted by the SUPERVISOR for Crew Move Aboard:
| 110-11-001 |
| Underwater Hull Inspection and Repair; accomplish |
| 120-11-002 |
| Bulkhead; repair |
| 120-11-004 |
| Bulkhead; repair |
| 120-11-008 |
| Longitudinal Bulkhead; repair |
| 123-10-001 |
| Tanks and Voids Open, Pump, Clean and Gas Free; accomplish |
| 123-10-002 |
| Fresh Water/Water Mist Storage Tank; repair and preserve |
| 123-11-001 |
| Fuel Oil Overflow Storage Tank; repair |
| 123-11-002 |
| Fuel Oil Storage Tank; preserve |
| 123-11-003 |
| Auxiliary Fuel Oil Service Tank; preserve |
| 123-11-004 |
| Fuel Oil Storage Tank Clad Weld; accomplish |
| 123-12-001 |
| JP-5 Tank; repair |
| 123-12-002 |
| JP-5 Tank; preserve |
| 123-14-001 |
| Potable Water Tank; repair and preserve |
| 123-14-003 |
| Water Mist Fire Extinguishing Storage Tank; repair |
| 123-15-001 |
| SSDG Used Lube Oil Tank; repair |
| 123-15-002 |
| Lube Oil Tank; repair |
| 123-16-003 |
| Ballast Tank; repair |
| 123-16-004 |
| Ballast Tank; repair |
| 123-16-006 |
| Ballast Tank; repair |
| 123-16-007 |
| Ballast Tank; clad weld, repair and preserve |
| 123-16-009 |
| Ballast Tank; repair |
| 123-16-011 |
| Ballast Tank; repair |
| 123-16-014 |
| Ballast Tank; repair and preserve |
| 123-17-001 |
| Contaminated Oil Tank; repair |
| 123-17-002 |
| Contaminated Oil Tank; repair |
| 123-17-003 |
| Contaminated Oil Tank; repair |
| 123-17-004 |
| Contaminated Oil Tank Clad Weld; accomplish |
| 123-17-008 |
| Contaminated Oil Tank; repair and preserve |
| 123-19-001 |
| Vacuum Collection, Holding and Transfer (VCHT) Tank; preserve |
| 123-19-002 |
| Vacuum Collection, Holding and Transfer (VCHT) Tank; repair |
| 123-19-003 |
| Plumbing Waste Tank; repair and preserve |
| 123-21-002 |
| Accessible Void; repair and preserve |
| 123-21-003 |
| Accessible Void; preserve (touch up) |
| 163-11-001 |
| Sea Chest; repair |
| 167-90-002 |
| ShipAlt LPD17-82448K, SternGate Corrosion Mod to IC Sys; accomplish |
| 171-90-001 |
| ShipAlt LPD17-83023K, IFF Ring Hinged Access Mod; accomplish |
| 233-11-002 |
| 1A Main Propulsion Diesel Engine (MPDE) Air Intake System; replace |
| 233-11-004 |
| Main Propulsion Diesel Engine (MPDE) Turbocharger; clean and inspect |
| 233-11-005 |
| Main Propulsion Diesel Engine (MPDE) Sequential Turbocharger Valve; replace old valves with new valves and gaskets |
| 233-11-006 |
| Main Propulsion Diesel Engine (MPDE) Air Start Distributor and Main Air Start Control Valve; clean and inspect |
| 233-11-007 |
| Main Propulsion Diesel Engine (MPDE); overhaul |
| 233-11-008 |
| 1A Main Propulsion Diesel Engine (MPDE), Fuel Oil Injection Pump and Fuel Oil Injection Pump Drive; overhaul |
| 233-11-009 |
| Main Propulsion Diesel Engine (MPDE) Intercooler; clean and inspect |
| 233-11-010 |
| Main Propulsion Diesel Engine (MPDE), Flexible Coupling; inspect and repair |
| 233-11-011 |
| Number 1A Main Propulsion Diesel Engine (MPDE) Crankcase Vacuum Fan and Impeller; repair |
| 233-11-012 |
| Number 1A Main Propulsion Diesel Engine (MPDE) Vibration Damper; repair |
| 233-12-002 |
| 1B Main Propulsion Diesel Engine (MPDE) Air Intake System; replace |
| 233-12-003 |
| 1B Main Propulsion Diesel Engine (MPDE), Fuel Oil Injection Pump and Fuel Oil Injection Pump Drive; overhaul |
| 233-12-004 |
| Main Propulsion Diesel Engine (MPDE) Turbocharger; clean and inspect |
| 233-12-006 |
| Main Propulsion Diesel Engine (MPDE) Sequential Turbocharger Valve; replace old valves with new valves and gaskets |
| 233-12-007 |
| Main Propulsion Diesel Engine (MPDE) Air Start Distributor and Main Air Start Control Valve; clean and inspect |
| 233-12-009 |
| Main Propulsion Diesel Engine (MPDE); overhaul |
| 233-12-010 |
| Main Propulsion Diesel Engine (MPDE) Intercooler; clean and inspect |
| 233-12-011 |
| Number 1B Main Propulsion Diesel Engine (MPDE) Crankcase Vacuum Fan and Impeller; repair |
| 233-12-013 |
| Main Propulsion Diesel Engine (MPDE) Vibration Damper; repair |
| 233-13-002 |
| 2A Main Propulsion Diesel Engine (MPDE), Fuel Oil Injection Pump and Fuel Oil Injection Pump Drive; overhaul |
| 233-13-003 |
| Main Propulsion Diesel Engine (MPDE) Turbocharger; clean and inspect |
| 233-13-004 |
| Main Propulsion Diesel Engine (MPDE) Vibration Damper; repair |
| 233-13-005 |
| Main Propulsion Diesel Engine (MPDE) Sequential Turbocharger Valve; replace old valves with new valves and gaskets |
| 233-13-006 |
| Main Propulsion Diesel Engine (MPDE); overhaul |
| 233-13-007 |
| Main Propulsion Diesel Engine (MPDE) Flexible Coupling; repair |
| 233-13-008 |
| Main Propulsion Diesel Engine (MPDE) Intercooler; clean and inspect |
| 233-13-009 |
| Number 2A Main Propulsion Diesel Engine (MPDE) Crankcase Vacuum Fan and Impeller; repair |
| 233-13-011 |
| Number 2A Main Propulsion Diesel Engine (MPDE) Air Intake Pre-Heater; replace |
| 233-14-002 |
| 2B Main Propulsion Diesel Engine (MPDE), Fuel Oil Injection Pump and Fuel Oil Injection Pump Drive; overhaul |
| 233-14-003 |
| Main Propulsion Diesel Engine (MPDE) Turbocharger; clean and inspect |
| 233-14-004 |
| Main Propulsion Diesel Engine (MPDE) Vibration Damper; repair |
| 233-14-005 |
| Main Propulsion Diesel Engine (MPDE) Sequential Turbocharger Valve; replace old valves with new valves and gaskets |
| 233-14-006 |
| Main Propulsion Diesel Engine (MPDE); overhaul |
| 233-14-007 |
| Main Propulsion Diesel Engine (MPDE) Intercooler; clean and inspect |
| 233-14-009 |
| Number 2B Main Propulsion Diesel Engine (MPDE) Crankcase Vacuum Fan and Impeller; repair |
| 233-14-011 |
| Number 2B Main Propulsion Diesel Engine (MPDE) Air Intake Pre-Heater; replace |
| 233-14-012 |
| Main Propulsion Diesel Engine (MPDE) Spare Cylinder Head and Components; clean and inspect |
| 241-11-001 |
| Main Reduction Gear Foundation Chock; inspect and repair |
| 241-11-002 |
| Number One Main Reduction Gear (MRG) Attached Lube Oil Pump Foundation; repair |
| 241-12-001 |
| Number 2 Main Reduction Gear (MRG) Attached Lube Oil Pump Foundation; repair |
| 241-90-001 |
| ShipAlt LPD17-82232K, LPD 17 Class Flame Arrestor Relocation; accomplish |
| 243-10-001 |
| Main Propulsion Shafting Forward Boss Fairing; repair |
| 243-11-001 |
| Starboard Stern Tube Shaft Seal; overhaul |
| 243-11-002 |
| Propulsion Shafting; inspect and repair |
| 243-12-001 |
| Port Stern Tube Shaft Seal; overhaul |
| 243-12-002 |
| Propulsion Shafting; inspect and repair |
| 243-80-001 |
| ShipAlt LPD17-84077D, Modify Port and Starboard Shaft Bossing Sections; accomplish |
| 244-11-001 |
| Main Propulsion Line Shaft Bearing Alignment; accomplish |
| 244-11-002 |
| Outboard Propulsion Shafting, Bearing Clearance Measurement; accomplish |
| 244-11-003 |
| Propulsion Shaft and Bearing Alignment; Assess |
| 244-12-001 |
| Outboard Propulsion Shafting, Bearing Clearance Measurement; accomplish |
| 244-12-002 |
| Propulsion Shaft and Bearing Alignment; assess |
| 245-11-001 |
| Controllable Pitch Propeller (CPP) Hub; replace |
| 245-11-002 |
| Controllable Pitch Propeller (CPP) Oil Distribution (OD) Box; replace |
| 245-11-003 |
| Controllable Pitch Propeller (CPP) Valve Rod Assembly; repair |
| 245-11-004 |
| Controllable Pitch Propeller (CPP) Blade; inspect and repair |
| 245-11-005 |
| Number One Main Reduction Gear (MRG) Controllable Pitch Propeller (CPP) Attached Pump Foundation; repair |
| 245-12-001 |
| Controllable Pitch Propeller (CPP) Hub; replace |
| 245-12-002 |
| Controllable Pitch Propeller (CPP) Oil Distribution (OD) Box; replace |
| 245-12-003 |
| Controllable Pitch Propeller (CPP) Valve Rod Assembly; repair |
| 245-12-004 |
| Controllable Pitch Propeller (CPP) Blade; inspect and repair |
| 245-12-005 |
| Number 2 Main Reduction Gear (MRG) Controllable Pitch Propeller (CPP) Attached Pump Foundation; repair |
| 256-61-001 |
| Number 1A Main Propulsion Diesel Engine (MPDE) Central Freshwater (CFW) Heat Exchanger; clean and inspect |
| 256-61-002 |
| Number 1B Main Propulsion Diesel Engine (MPDE) Central Freshwater (CFW) Heat Exchanger; clean and inspect |
| 259-11-001 |
| Main Propulsion Diesel Engine (MPDE), Exhaust Fastener and Exhaust Bellow; replace |
| 259-12-001 |
| Main Propulsion Diesel Engine (MPDE), Exhaust Expansion Joint and Exhaust Fastener; replace |
| 259-13-001 |
| Main Propulsion Diesel Engine (MPDE), Exhaust Expansion Joint and Exhaust Fastener; replace |
| 259-14-001 |
| Main Propulsion Diesel Engine (MPDE), Exhaust Expansion Joint and Exhaust Fastener; replace |
| 259-80-001 |
| ShipAlt LPD17-88788D, Main Propulsion Diesel Engine (MPDE) Expansion Joint Replacement; accomplish |
| 262-11-001 |
| Lube Oil Piping; repair |
| 262-11-002 |
| Lube Oil Piping; repair |
| 262-12-001 |
| 2B Main Propulsion Diesel Engine Lube Oil Filter Differential Pressure Gauge Tubing; repair |
| 262-12-002 |
| 2A Main Propulsion Diesel Engine (MPDE) Lube Oil Cooler Inlet Pressure Gauge Tubing; repair |
| 262-90-001 |
| ShipAlt LPD17-79652K, Main Propulsion Diesel Engine Filter Modification; accomplish |
| 262-90-002 |
| ShipAlt LPD17-78278K, Main Propulsion Diesel Engine Lube Oil Pump Crossover Piping Modification; accomplish |
| 264-11-002 |
| Number 2A MPDE Rocker Lube Oil Gage Piping; replace |
| 264-31-001 |
| Main Reduction Gear Lube Oil Purifier Heater; replace |
| 264-31-002 |
| Main Reduction Gear Lube Oil Purifier Heater; replace |
| 299-21-001 |
| Main Propulsion Diesel Engine Hydraulic Hand Pump; repair |
| 311-21-002 |
| Ship's Service Diesel Generator (SSDG) Exhaust Fastener; replace |
| 311-21-004 |
| Ships Service Diesel Generator (SSDG) Aftercooler; repair |
| 311-21-005 |
| Number One Ship's Service Diesel Generator (SSDG) Fuel Oil Heat Exchanger; clean and inspect |
| 311-21-006 |
| Ship's Service Diesel Generator (SSDG) Top End Overhaul; accomplish |
| 311-22-002 |
| Ship's Service Diesel Generator (SSDG) Exhaust Expansion Joint and Exhaust Fastener; replace |
| 311-22-003 |
| Ships Service Diesel Generator (SSDG) Aftercooler; repair |
| 311-22-004 |
| Number 2 Ship's Service Diesel Generator (SSDG) Air Inlet Shutoff Valve; replace |
| 311-22-005 |
| Number 2 Ship's Service Diesel Generator (SSDG) Fuel Oil Heat Exchanger; clean and inspect |
| 311-23-003 |
| Ships Service Diesel Generator (SSDG) Aftercooler; repair |
| 311-23-004 |
| Ship's Service Diesel Generator (SSDG) Exhaust Fastener; replace |
| 311-23-005 |
| Number 3 Ship's Service Diesel Generator (SSDG) Fuel Oil Heat Exchanger; clean and inspect |
| 311-23-006 |
| Ship's Service Diesel Generator (SSDG) Top End Overhaul; accomplish |
| 311-24-002 |
| Number 4 Ship's Service Diesel Generator (SSDG) Air Inlet Shutoff Valve; replace |
| 311-24-003 |
| Ships Service Diesel Generator (SSDG) Aftercooler; repair |
| 311-24-004 |
| Ship's Service Diesel Generator (SSDG) Exhaust Expansion Joint and Exhaust Fastener; replace |
| 311-24-005 |
| Number 4 Ship's Service Diesel Generator (SSDG) Fuel Oil Heat Exchanger; clean and inspect |
| 311-25-003 |
| Ships Service Diesel Generator (SSDG) Aftercooler; repair |
| 311-25-004 |
| Ship's Service Diesel Generator (SSDG) Exhaust Expansion Joint and Exhaust Fastener; replace |
| 311-25-005 |
| Number 5 Ship's Service Diesel Generator (SSDG) Fuel Oil Heat Exchanger; clean and inspect |
| 311-25-006 |
| Ship's Service Diesel Generator (SSDG) Top End Overhaul; accomplish |
| 320-90-001 |
| ShipAlt LPD17-82335K, Sliding Padeye Kingpost Cabling Modification; accomplish |
| 324-80-001 |
| ShipAlt LPD17-83481D, Relocate Automatic Bus Transfer (ABT) and Transformer; accomplish |
| 324-90-001 |
| ShipAlt LPD17-82611K Switchgear and Panels 60 Hertz Power Distribution; accomplish |
| 324-90-002 |
| ShipAlt LPD17-82512K, Vacuum Collection Holding Tank Power Source Modification; accomplish |
| 422-11-001 |
| Masthead and Task Light; replace |
| 433-90-001 |
| ShipAlt LPD17-82449K, Radar Cross Section Reducing (RCSR) Speaker Cover Modification; accompish |
| 453-48-001 |
| SPS-48E Antenna; replace |
| 506-11-001 |
| Vent Tank Sounds and Overflow Piping; repair |
| 508-11-002 |
| Cableway Insulation; install |
| 508-11-003 |
| Cableway Insulation; install |
| 508-12-001 |
| Lagging and Insulation, Outside Machinery Space; replace |
| 512-11-001 |
| Galley and Laundry Exhaust Ventilation; clean |
| 512-80-001 |
| ShipAlt LPD17-83498D, Ventilation Motor Controller Relocation; accomplish |
| 512-90-001 |
| ShipAlt LPD17-82533K, Heating, Ventilation and Air Conditioning (HVAC) System Modification; accomplish |
| 512-90-002 |
| ShipAlt LPD17-82399K, MK46 Toxic Gas Vent Modification; accomplish |
| 512-90-003 |
| ShipAlt LPD17-82469K, Ship Service Diesel Generator (SSDG) Ventilation Modification; accomplish |
| 514-11-001 |
| Chilled Water Expansion Tank; replace |
| 514-11-002 |
| Chilled Water System Ball Valves; replace and flush |
| 514-11-003 |
| Chilled Water System Ball Valves; repair |
| 514-80-001 |
| Shipalt LPD17-83291D, Chilled Water System Modification; accomplish |
| 514-90-002 |
| ShipAlt LPD17-82536K Chill Water Pump Transducer Modification; accomplish |
| 514-90-003 |
| Shipalt LPD-17-82534K Chilled Water System Modification; accomplish |
| 520-11-001 |
| Sea Valve; repair and replace |
| 521-11-001 |
| Firemain Piping System; repair |
| 521-90-001 |
| ShipAlt LPD17-81157.01K Auxiliary Sea Water System Valve Replace; accomplish |
| 521-90-002 |
| ShipAlt LPD17-81157.02K Auxiliary Sea Water System Valve Replace; accomplish |
| 521-90-003 |
| ShipAlt LPD17-85606.05K, 85606.06K, 85606.09K, 85606.11K, Firemain Branch Piping Modifications; accomplish |
| 524-11-001 |
| Auxiliary Sea Water System (ASW) Piping; chemical clean (Optional) |
| 524-90-001 |
| ShipAlt LPD17-81157.04K Auxiliary Seawater System Valve Replace; accomplish |
| 524-90-002 |
| ShipAlt LPD17-81157.03K Auxiliary Seawater System Valve Replace; accomplish |
| 524-90-003 |
| ShipAlt LPD17-81415K Ship's Service Diesel Generator (SSDG) Auxiliary Seawater System Piping Upgrade; accomplish |
| 532-90-001 |
| ShipAlt LPD17-82460K SPS-48E Expansion Tank Relocation; accomplish |
| 533-11-001 |
| Water Heater; repair |
| 533-80-001 |
| ShipAlt LPD17-80861D, Potable Water Electrolytic Chlorine Recirculating Capable; accomplish |
| 536-11-001 |
| Number 1A Main Propulsion Diesel Engine (MPDE) Jacket Water (JW) Keep Warm Pump and Motor; repair |
| 536-11-002 |
| Number 1B Main Propulsion Diesel Engine (MPDE) Jacket Water (JW) Keep Warm Pump and Motor; repair |
| 536-11-003 |
| Number 2A Main Propulsion Diesel Engine (MPDE) Jacket Water (JW) Keep Warm Pump and Motor; repair |
| 536-11-004 |
| Number 2B Main Propulsion Diesel Engine (MPDE) Jacket Water (JW) Keep Warm Pump and Motor; repair |
| 536-12-002 |
| Number 1B Main Propulsion Diesel Engine Jacket Water Heater; replace |
| 541-11-001 |
| Fuel Oil Fill and Transfer Piping System; repair |
| 555-51-001 |
| Water Mist Firefighting (WMFF) Valve and Actuator; repair |
| 555-51-002 |
| Water Mist Firefighting (WMFF) Pump; repair |
| 555-80-001 |
| ShipAlt LPD17-80860D, Watermist Fire Extinguishing System Pump Modification; accomplish |
| 561-80-002 |
| ShipAlt LPD17-83657D, Steering Gear Tiller Modification; accomplish |
| 562-11-001 |
| Rudder Bearing Seal and Rudderstock Seal; repair |
| 584-21-001 |
| Lower Stern Gate Gasket; replace |
This is the start of the file's text. The full file is on GovTribe.