EASR Program WBS
L1 L2 L3 L4 L5
1.0 Enterprise Air Surveillance Radar (EASR)
1.1 Prime Mission Product (PMP)
1.1.1 Radome / RF Radiator
1.1.2 Non-LRU RF Hardware
1.1.3 T/R Line Replaceable Units (LRUs)
1.1.3.1 T/R Modules
1.1.3.1.1 GaN MMICs
1.1.3.1.2 GaAs MMICs
1.1.3.1.3 Misc. TR Module HW
1.1.3.1.4 T/R Module Assembly and Test
1.1.3.2 DC-to-DC Converters
1.1.3.3 Other LRU Assembly
1.1.3.3.1 LRU Other Misc. HW
1.1.3.3.2 LRU Integration, Assembly, Test and Checkout
1.1.4 Receiver/Exciters
1.1.5 Digital Beamformer
1.1.6 Beam Steering Controller
1.1.7 Data/Signal Processing Equipment
1.1.7.1 Radar Control Processor
1.1.7.2 Radar Signal Processor
1.1.8 Mechanical Structure
1.1.8.1 Variant 1 Mechanical Structure
1.1.8.1.1 Antenna
1.1.8.1.2 Pedestal
1.1.8.1.3 Rotary Joint
1.1.8.1.4 Drive Motor(s)
1.1.8.1.5 Enclosure
1.1.8.1.6 Other
1.1.8.2 Variant 2 Mechanical Structure
1.1.8.2.1 Antenna
1.1.8.2.2 Deckhouse Mounting
1.1.8.2.3 Other
1.1.9 Array Power System
1.1.10 Array Cooling System
1.1.11 Inertial Navigation Unit
1.1.12 Other Equipment
1.1.13 PMP Applications Software
1.1.13.1 Control Processor - Software
1.1.13.2 Signal Processor- Software
1.1.13.3 Digital Beamformer- Software
1.1.13.4 Other
1.1.14 PMP System Software
1.1.14.1 Operating Systems
1.1.14.2 Licenses for Software
1.1.14.3 Maintenance Agreements
1.1.14.4 Other
1.1.15 Integration, Assembly, Test and Checkout
1.2 Platform Integration
1.3 Systems Engineering/Program Management
1.3.1 Program Management
1.3.2 System Engineering
1.4 System Test and Evaluation
1.4.1 Development Test and Evaluation
1.4.1.1 T&E Software
1.4.1.1.1 Simulations
1.4.1.1.2 Test Control Software
1.4.1.2 Data Analysis Tools
1.4.1.3 Testing at Contractor Facility
1.4.1.3.1 Test Plan Development
1.4.1.3.2 Analysis Planning
1.4.1.3.3 Test Conduct and Analysis
1.4.1.4 Land Based Testing
1.4.2 Operational Test and Evaluation
1.4.3 Mock-ups / System Integration Laboratories (SIL)
1.4.4 Test and Evaluation Support
1.4.5 Test Facilities
1.5 Training
1.6 Data
1.6.1 Technical Publications
1.6.2 Engineering Data
1.6.3 Management Data
WBS NUMBERS
WBS Description Definition
1.0 Enterprise Air Surveillance
Radar (EASR)
This WBS element includes developing the system; complete full system integration; developing an affordable and executable manufacturing process; ensuring operational supportability with particular attention to minimizing the logistics footprint; implementing human systems integration
(HSI); designing for producibility; ensuring affordability; protecting Critical Program Information
(CPI); and demonstrating system integration, interoperability, safety, and utility.
1.1 Prime Mission Product (PMP)
EASR hardware and software used to accomplish the primary mission of the defense materiel item. Includes, for example:
a. All integration, assembly, test and checkout, as well as all technical and management activities associated with individual hardware/software elements
b. Integration, assembly, test and checkout associated with the PMP.
c. All whole and partial prime contractor, subcontractor, and vendor breadboards, brass boards, and qualification test units
d. The design, development and production of complete units (i.e., the prototype or operationally configured units which satisfy the requirements of their applicable specification(s), regardless of end use)
e. Factory special test equipment, special tooling, and production planning required to fabricate the PMP
Excludes, for example:
a. Only those "less than whole" units (e.g., test, spares, etc.) consumed or planned to be consumed in support of system level tests
b. Duplicate or modified factory special test equipment delivered to the Government for depot repair (should be included in the peculiar support equipment element).
1.1.1 Radome / RF Radiator
Structure that provides environmental protection to the EASR system. It can be spherical in shape or have other physical dimensions. The radome is transparent to the radar transmit and receive frequencies.
Radiators are the physical RF elements that transfers the RF energy from coaxial conduction to atmospheric propagation.
1.1.2 Non-LRU RF Hardware
EASR Non-LRU RF hardware includes on-array RF elements other than those in the T/R LRUs, such as circulators, filters, anti-ice control.
1.1.3 T/R Line Replaceable Units
(LRUs)
EASR Transmit Receive Line Replaceable Units are integrated assemblies containing RF switches, power amplifiers, low-noise amplifiers, DC-to-DC Converters, phase shifters, step attenuators, T/R modules and other T/R module assembly. These components amplify and control low-level signals from the Receiver/Exciter for transmission to and from free-space.
1.1.3.1 T/R Modules
This WBS element includes both recurring and non-recurring costs. This WBS element includes
T/R Module Transition to Production, including Monolithic Microwave Integrated Circuit (MMIC) fabrication process and test updates, and MMIC fab and screening; T/R Module assembly process and test updates, and T/R Module fab and Design Verification (DVT) test; and generation of a TDP. This WBS also includes technical and product engineering support and
MMIC Fab and T/R Module Assembly and test. This WBS also includes special test equipment costs and ODC costs (including TEMR and other costs related to T/R Module design and production) are included.
1.1.3.1.1 GaN MMICs
This WBS element includes the recurring costs for MMIC fabrication process and test updates, and GaN MMIC fabrication and screening.
1.1.3.1.2 GaAs MMICs
This WBS element includes the recurring costs for MMIC fabrication process and test updates, and GaAs MMIC fabrication and screening.
1.1.3.1.3 Misc. TR Module HW
This WBS includes the recurring costs for all of the T/R Module HW excluding MMICs. T/R
Module includes Housing, Circulators, Thick Film Substrates and other required COTs integrated circuits to build up the module assemblies. The module housing is a metallic hermetic enclosure, thick film networks (TFNs) are alumina substrates that route signals between components.
Multiple COTS silicon integrated circuits switch and condition bias voltages within the module.
The circulator is a micro strip device that provides output match protection to the power amplifies and routes incoming RF signals to the receive chain in the module.
Enterprise Air Surveillance Radar (EASR)
Program Work Breakdown Structure (WBS)
1.1.3.1.4 T/R Module Assembly and
Test
This WBS element includes integration of components in the module assembly, inspection, burn in and, tooling, ODC, management, and test of T/R modules. Manufacturing tooling includes common carriers to transport modules between assembly operations, shipping trays for modules, RF test fixture and sealing fixtures (nests). Other Direct Costs (ODC) include consumable materials such as epoxy, gold wire and ribbon and chemicals for cleaning.
1.1.3.2 DC-to-DC Converters
This WBS element includes both recurring and non-recurring costs. This WBS element includes the design and production costs of the DC to DC converter and control circuitry, including supporting firmware updates. This WBS also includes the CCA special test equipment material costs and ODC costs (including TEMR and other costs related to CCA design and production) are included.
1.1.3.3 Other LRU Assembly
This WBS element includes both recurring and non-recurring costs. This WBS element includes the design and production costs for LRU Fabrication, Assembly, Integration and Test (FAIT).
This WBS includes a design update including engineering level drawings, design review preparation and delivery for the LRU Assembly. This WBS also includes the build and test of the functional and burn-in test equipment for the LRU assembly. This WBS also includes engineering build support to production and design verification testing. Includes costs to assemble the T/R Modules and CCAs into the LRU Level assembly and complete LRU level integration and test. Related ODC costs (including TEMR and other costs related to CCA design and production) are included.
1.1.3.3.1 LRU Other Misc. HW
This WBS element includes both recurring and non-recurring costs. This WBS element includes the LRU fabrication, assembly, Integration and test. Includes costs to assemble the T/R Modules and CCAs into the LRU Level assembly and complete LRU level integration and test. Related
ODC costs (including TEMR and other costs related to CCA design and production) are included.
1.1.3.3.2 LRU Integration, Assembly, Test and Checkout
This WBS element includes both recurring and non-recurring costs. This WBS includes a design update including engineering level drawings, design review preparation and delivery for the LRU
Assembly. This WBS also includes the build and test of the functional and burn-in test equipment for the LRU assembly. This WBS also includes engineering build support to production and design verification testing.
1.1.4 Receiver/Exciters
1. EASR Receiver Group – The receiver typically amplifies and attenuates the returned RF signal collected by the antenna and processed by the T/R modules and mixes (i.e. downconverts) it with other RF signals to yield an intermediate frequency (IF) signal. The IF signal is then processed (amplified, attenuated and filtered) and then downconverted to video where the signal is detected and then digitized. This RF processing is done in a channel, which is a physical path comprised of electronic circuits that change the magnitude and waveform of the input signal.
The principle cost drivers are the number of RF channels, the frequency of operation and the number of downconversions.
2. EASR Exciter Group – The exciter generates the RF frequencies needed by the radar. It consists of oscillators, frequency multipliers, phase lock loops and filters integrated with waveguide and micro strip into RF modules. Exciters produce the coherent waveforms needed for timing, downconversion and for RF transmission. The synthesizer generates the RF frequencies needed by the RF assemblies to operate. The principle cost drivers are the number of exciters and the frequency of operation.
1.1.5 Digital Beamformer
EASR Beamforming is the combination of radio signals from a set of small non-directional antennas to simulate a large directional antenna. In radar applications, beamforming can be used to steer an antenna to determine the direction of the signal source.
1.1.6 Beam Steering Controller
EASR Beam Steering is the function of controlling the direction of the radar’s output beam. A processor or computer typically performs this function. The beam steering processor consists of electronic CCAs with CPUs, memory (RAM, ROM, EEPROM, etc.) chips, input/output functions and bus interface hardware. These processors usually consist of many digital ICs along with resistors, capacitors and some other discrete components. The principle cost drivers are the number of elements controlled and the number of phase shifter bits.
1.1.7 Data/Signal Processing
Equipment
1. Signal Processor – The signal processor processes the radar echo signal. This function in today’s radars starts after A/D conversion of the electrical signals and includes real time image processing. Finite impulse response filtering, FFT processing, Doppler clutter rejection, moving target indication and thresholding and detection are functions usually performed in the signal processor. The signal processing function in radars is implemented with many digital ICs along with resistors, capacitors and other discrete components.
2. Data Processor – Data processors typically perform the data analysis and control function of the system or box. In radar systems data processors typically perform position refinement, track association, tracking, trajectory generation and sensor control functions. Data processors for radar systems implement microprocessors with their support circuitry to perform the processing and system control function. Data processors consist of CPUs, memory, input/output functions and bus interface hardware. Data processors usually consist of many digital ICs along with resistors, capacitors and some other discrete components. The principle cost driver for data processors is the throughput and memory capacity of the processor.
3. Controls & Displays– Controls and displays provide the human-to-radar system interface.
Controls and displays typically perform or assist in the data analysis and control function of the system. In radar systems, the control function is typically performed by a data processing workstation.
1.1.7.1 Radar Control Processor
This WBS element includes both recurring and non-recurring costs. This WBS includes the definition, design, analysis, assembly and test of the COTS computing hardware racks for the
Radar Control Processor (RCP), Embedded Simulation and Network Subsystems for the EDM system. This element also includes all material cost, assembly, integration and test costs. All directly associated support costs, including ODC, are included within this WBS. This WBS also includes System / Sub-system component-level testing.
1.1.7.2 Radar Signal Processor
This WBS element includes both recurring and non-recurring costs. This WBS includes the
COTS definition, design, analysis, assembly and test of the computing hardware and racks for the Radar Signal Processor (RSP). This WBS includes the Digital Signal Processor subsystem which contains the Adaptive Beamforming (ABF) and Signal Processor (SP) subsystems. This element also includes all material cost, assembly, integration and test costs. All directly associated support costs, including ODC, are included within this WBS. This WBS also includes System / Sub-system component-level testing.
1.1.8 Mechanical Structure
The EASR antenna structure is the framework for mounting the antenna electrical and electronic equipment. It can consist of steel beams, metal networks, concrete structures, tubular structures, panels, or other items that are used to mount the radiators, T/R modules, feed systems, and other electronic assemblies into an operational antenna array.
1.1.8.1 Variant 1 Mechanical Structure
EASR antenna structure is the framework for mounting the antenna electrical and electronic equipment for the Variant 1 system
1.1.8.1.1 Antenna EASR antenna element includes the mechanical structure related to Variant 1 antenna
1.1.8.1.2 Pedestal
The EASR pedestal element includes the mechanical structure and hardware that mounts the antenna to the ship structure.
1.1.8.1.3 Rotary Joint
The EASR rotary joint element is a electromechanical device that allows power, control, and RF signals to pass from the stationary structure (pedestal) to the rotating antenna.
1.1.8.1.4 Drive Motor(s) The EASR drive motor element includes any drive motor and drive motor electronics.
1.1.8.1.5 Enclosure
The EASR enclosure element inlcudes housing that protects the antenna from natural and man made elements.
1.1.8.1.6 Other Other electromechanical equipment not included in above elements
1.1.8.2 Variant 2 Mechanical Structure
EASR antenna structure is the framework for mounting the antenna electrical and electronic equipment for the Variant 2 system
1.1.8.2.1 Antenna EASR antenna element includes the mechanical structure related to Variant 2 antenna
1.1.8.2.2 Deckhouse Mounting
The EASR deck house element includes the mounting nessesary to interface the antenna and the ship structure.
1.1.8.2.3 Other Other electromechanical equipment not included in above elements
1.1.9 Array Power System
EASR Array Power System includes AC/DC Converter, DC/DC Converter, Power Conditioner and all power conversion equipment from the ship's prime power to the RF transmitting elements. EDM includes cables.
1.1.10 Array Cooling System
EASR Array Cooling System includes: Liquid to liquid or liquid to air heat exchanger unit, all pumping equipment, all distribution equipment, and the antenna cold plates. EDM includes piping.
1.1.11 Inertial Navigation Unit
The Inertial Navigation System (INS) is mounted within the antenna shelter. It measures pitch, roll, and yaw angles as well as X, Y, and Z-axis translations. The INS also measures absolute position (latitude, longitude, altitude) and orientation (relative to true north) by a combination of inertial sensing and GPS aiding. Measurements from the INS, along with data from any IMUs mounted to the antenna, are used to determine the pointing position of the antenna in absolute coordinates.
1.1.12 Other Equipment Other equipment not covered in above elements.
1.1.13 PMP Applications Software
The software that is specifically produced for the functional use of a computer system (ref.
ANSI/IEEE Std 610.12).
Includes, for example:
1. Battle management, weapons control, and data base management INCLUDING but are not limited to:
a. System Control
b. Search functions
c. Tracking functions
d. Radar scheduling e.Contact Characterization
f. Weapons support (Missile tracking and communications)
g. Fault monitoring support
h. Fault detection and fault isolation support
i. Real Time Radar Control
j. Signal processing
k. Support for other functions (weather, etc.)
l. Operator Control and Display
m. Interface With the CS
n. Maintain a Common Time Base with CS
o. Environmental and clutter mapping
p. Training, Diagnostics and calibration
q. Data recording
r. Data extraction and reduction
s. Digital Beamforming functionality
2. All effort required to design, develop, integrate, and checkout the PMP applications computer software configuration items (CSCIs), not including the non-software portion of PMP firmware development and production.
Excludes, for example: All software that is an integral part of any specific hardware subsystem specification.
1.1.13.1 Control Processor - Software
The Radar Control Processor (RCP) performs radar control functions. This WBS element includes the following non-recurring effort: Design, Code, Unit Test and Integration (DCTI), Software Item Qualification Testing (SIQT), Performance Optimization (PO). This WBS element also includes on-site vendor labor costs associated with the development of this software.
1.1.13.2 Signal Processor- Software
The Radar Signal Processing (RSP) processes data signals from the hardware to create target returns. This WBS element includes the following non-recurring effort: Design, Code, Unit Test and Integration (DCTI), Software Item Qualification Testing (SIQT), Performance Optimization
(PO), Toolsmith & Build Support, Software Management, Defects Correction and Post SIQT
Integration and Test.
1.1.13.3 Digital Beamformer- Software
Include Antenna Interface (AI) and Digital Beamforming Interface. The AI adapts the digital control and status messages received from the RCP into the internal format required by the hardware and firmware based Receiver Exciter (REX) subsystem. The AI SI generates beam steering commands for the array. The AI SI also provides internal status monitoring of the antenna hardware and provides summary status back to the RCP.This WBS element includes the non-recurring effort for: Design, Code, Unit Test and Integration (DCTI), Software Item
Qualification Testing (SIQT), Performance Optimization (PO), Defects Correction and Post SIQT
Integration and Test.
1.1.13.4 Other Other application software not covered in above elements.
1.1.14 PMP System Software
The software designed for a specific computer system or family of computer systems to facilitate the operation and maintenance of the computer system and associated programs. (ref.
ANSI/IEEE Std 610.12)
Includes, for example:
a. Operating systems, compilers, licenses, maintenance agreements and utilities
b. All effort required to design, develop, integrate, and checkout the PMP system software including all software developed to support PMP-applications-software development
c. PMP system software which is required to facilitate development, integration, and maintenance of any PMP software build and CSCI
Excludes, for example:
d. Software that is an integral part of any specific hardware subsystem specification or is specifically designed and developed for system test and evaluation
1.1.14.1 Operating Systems
This WBS element contain any scope / cost related to the operating systems development.
1.1.14.2 Licenses for Software
This WBS element contains the non-recurring cost of software licenses associated with the computing environment and recurring cost of the software licenses during development.
1.1.14.3 Maintenance Agreements This WBS element contains cost associated with maintenance agreements
1.1.14.4 Other Other system software not covered in above elements.
1.1.15 Integration, Assembly, Test
and Checkout
Integration, Assembly, Test and Checkout. This element includes all technical and functional activities associated with the design, development, and production of mating surfaces, structures, equipment, parts, materials, and software required to assemble the Level 2 equipment (hardware/software) elements into a Level 1 mission equipment (hardware/ software) as a whole and not directly part of any other individual Level 2 element.
Includes, for example:
a. The development of engineering layouts, determination of overall design characteristics, and determination of requirements of design review
b. The set up, conduct, and review of testing assembled components or subsystems prior to installation
c. The detailed production design, producibility engineering planning (PEP), and manufacturing process capability, including the process design development and demonstration effort to achieve compatibility with engineering requirements and the ability to produce economically and consistent quality
d. Inspection activities related to receiving, factory and vendor liaison
e. Design maintenance effort
f. Quality planning and control
g. Tooling (initial production facilities, factory support equipment) including planning, design, and fabrication
h. The joining or mating and final assembly of Level 3 equipment elements to form a complete prime mission equipment when the effort is performed at the manufacturing facility
i. Integration of software (including loading and verification of firmware) with the hardware elements.
j. Conduct of production acceptance testing
Excludes, for example:
a. All systems engineering/program management and system test and evaluation which are associated with the overall system
1.2 Platform Integration All aspects of integrating the antenna and associated equipment into the ship.
1.3 Systems Engineering/Program
Management
Systems Engineering and Program Management. These elements are defined as the systems engineering and technical control as well as the business management of particular systems and programs. Systems engineering and program management elements should be reported separately and their levels will be specified by the requiring activity.
Includes, for example:
a. The overall planning, directing, and controlling of the definition, development, and production of a system or program including functions of logistics engineering and integrated logistics support e.g., maintenance support, facilities, personnel, training, testing, and activation of a system
Excludes, for example:
a. Systems engineering and program management efforts that can be associated specifically with the equipment (hardware/software) element
b. Suite System Engineering - The technical and management efforts of directing and controlling a totally integrated engineering effort of a radar system.
c. Suite Program Management - The business and administrative planning, organizing, directing, coordinating, controlling, and approval actions designated to accomplish overall program objectives which are not associated with specific hardware elements and are not included in systems engineering.
d. ILS This includes Supportability Engineering tasks, System Safety; Software Safety;
Reliability, Maintainability and Availability; and Human Systems Integration (HSI).
1.3.1 Program Management
This WBS element includes both recurring and non-recurring costs. This WBS includes the
Radar Integrated Product Team (IPT) technical management, hardware quality management, configuration management and data management efforts, including subcontractor costs. This
WBS element also includes the radar systems engineering technical management and the development/update of the EASR A specifications, B2 specifications, B5 specifications, Interface requirements specifications, requirements maintenance, performance analysis, and modeling and simulation development and maintenance. This WBS also includes the development and submittal of the Data Accession List (DAL) and the Data Library. This WBS includes subcontractor support for program management.
1.3.2 System Engineering
This WBS element Includes the following non-recurring effort:
1) Generate the EASR A Specification, EASR Emulator, and Maintenance Manual A-
Specifications.
2) Generate the EASR B2 specifications. Development of the EASR Emulator B2.
3) Completion of the EASR B5 (SRS). Development of EASR Emulator B5 and Maintenance
Manual B5.
4) Development of the EASR Interface Requirements Specification (IRS), the EASR Hardware
Interface Description Document (IDD) and the EASR Software IDD. Development of the
Maintenance Manual IRS. Complete development of EASR HM&E IRS and EASR HM&E ICD.
5) Development of the EASR External IRS.
6) System Performance Analysis including EASR performance analysis and TPM assessment against SRD requirements and identified Test Cases.
7) Model and Simulation Development and Maintenance (M&S) of the EASR functionality including M&S plan, development and delivery of Models and Simulations.
8) Model and Simulation Verification, Validation and Accreditation including Validation &
Verification (V&V) Plan, Accreditation Plan, V&V Report and Accreditation Report.
9) Model and Simulation User Manuals and Training.
10) Systems Engineering lead support for the EASR Radar activities including the Systems
Engineering Integrated Product Team (IPT) lead and Control Account Manager.
1.4 System Test and Evaluation
The use of prototype, production, or specifically fabricated hardware/ software to obtain or validate engineering data on the performance of the EASR system during the development phase of the program. It also includes all effort associated with the design and production of models, specimens, fixtures, and instrumentation in support of the system level test program.
Includes, for example:
a. Detailed planning, conduct, support, data reduction and reports (excluding the contract data requirements list data) from such testing, and all hardware/software items which are consumed or planned to be consumed in the conduct of such testing
1.4.1 Development Test and
Evaluation
EASR Development Test and Evaluation. This WBS element includes non-recurring costs. This
WBS element includes the software development for the EASR simulation/emulation tools, tasks, and testing. This effort is planned, conducted and monitored by the developing agency of the DoD component. It includes test and evaluation conducted to:
a. Demonstrate that the engineering design and development process is complete.
b. Demonstrate that the design risks have been minimized
c. Demonstrate that the system will meet specifications
d. Estimate the system's military utility when introduced
e. Determine whether the engineering design is supportable (practical, maintainable, safe, etc.)
for operational use
f. Provide test data with which to examine and evaluate trade-offs against specification requirements, life cycle cost, and schedule
g. Perform the logistics testing efforts to evaluate the achievement of supportability goals, the adequacy of the support package for the system, (e.g., deliverable maintenance tools, test equipment, technical publications, maintenance instructions, and personnel skills and training requirements, etc.).
Includes, for example:
a. All contractor in-house effort
b. All programs, where applicable; models, tests and associated simulations such as wind tunnel, static, drop, and fatigue; integration ground tests; test bed aircraft and associated support; qualification test and evaluation, development flight test, test instrumentation, environmental tests, ballistics, radiological, range and accuracy demonstrations, test facility operations, test equipment (including its support equipment), chase and calibrated pacer aircraft and support thereto, and logistics testing.
1.4.1.1 T&E Software
This WBS element includes non-recurring costs. This WBS element includes the software development for the EASR simulation/emulation tools, tasks, and testing.
1.4.1.1.1 Simulations
This WBS element includes non-recurring costs. This WBS element includes the software development for the EASR simulation/emulation tools, tasks, and testing.
1.4.1.1.2 Test Control Software
This WBS element includes non-recurring costs. This WBS element includes the software development for the EASR simulation/emulation tools, tasks, and testing.
1.4.1.2 Data Analysis Tools
This WBS element includes non-recurring costs. This WBS element includes the software development for the EASR simulation/emulation tools, tasks, and testing.
1.4.1.3 Testing at Contractor Facility
This WBS element includes the non-recurring effort required to support component-level testing, LRU environmental qualification test plan and the counterfeit part analysis, COTS component
Confidence testing including test procedure generation, test fixture design and test conduct, SRR/TRR preparation and conduct, incorporation of SW drops, EMI testing, De-installation of the test assets after testing, and all directly related OPS material, vendor support and operations test equipment maintenance and repair.
1.4.1.3.1 Test Plan Development
This WBS element includes non-recurring costs. This WBS element includes the development of
EASR verification test plans for specification verification. This WBS also includes the LRU environmental qualification test plan and the counterfeit part analysis.
1.4.1.3.2 Analysis Planning
This WBS element includes non-recurring costs. This WBS element includes the development of
EASR analysis plans for specification verification.
1.4.1.3.3 Test Conduct and Analysis
This WBS element includes non-recurring costs. This WBS includes COTS component
Confidence testing including test procedure generation, test fixture design and test conduct. This
WBS element includes the TRR/TER preparation and conduct, incorporation of SW drops, EMI testing, de-installation of the test assets at the end of testing, and OPS material, vendor support and operations test equipment maintenance and repair.
1.4.1.4 Land Based Testing
This WBS element includes the non-recurring effort required to support testing at a land-based site, as required, including component-level testing, LRU environmental qualification test plan and the counterfeit part analysis, COTS component Confidence testing including test procedure generation, test fixture design and test conduct, TRR/TER preparation and conduct, incorporation of SW drops, EMI testing, De-installation of the test assets after testing, and all directly related OPS material, vendor support and operations test equipment maintenance and repair.
1.4.2 Operational Test and
Evaluation
Formal testing conducted prior to deployment to evaluate the operational effectiveness and suitability of the EASR system with respect to its mission. This includes Early Operational
Assessments (EOA), Operational Assessment (OA), and Initial Operational Test and Evaluation
(IOT&E).
1.4.3 Mock-ups / System Integration
Laboratories (SIL)
The design engineering and production of EASR mock-ups which have special contractual or engineering significance, or which are not required solely for the conduct of one of the above elements of testing.
SILs are often used in lieu of (or in addition to) mock-ups. SILs are risk reduction facilities where software and hardware can be developed, integrated, tested and evaluated for both stand alone functionality and/or interoperability prior to being fielded.
1.4.4 Test and Evaluation Support
EASR Test and Evaluation Support. The support elements necessary to operate and maintain, during test and evaluation, systems and subsystems which are not consumed during the testing phase and are not allocated to a specific phase of testing.
Includes, for example:
a. Repairable spares, repair of repairables, repair parts, warehousing and distribution of spares and repair parts, test and support equipment, test bed vehicles, drones, surveillance aircraft, tracking vessels, contractor technical support
Excludes, for example:
a. Operational and maintenance personnel, consumables, special fixtures, special instrumentation, etc., which are utilized and/or consumed in a single element of testing and which should be included under that element of testing
1.4.5 Test Facilities
The special test facilities required for performance of the various developmental tests necessary to prove the design and reliability of the EASR system or subsystem.
Includes, for example:
a. Test tank test fixtures, propulsion test fixtures, white rooms, test chambers
Excludes, for example:
a. Brick and mortar-type facilities identified as industrial facilities
1.5 Training
EASR Operator and Maintenance Training equipment and software. Deliverable training services, devices, accessories, aids, equipment, and parts used to facilitate instruction through which personnel will learn to operate and maintain the system with maximum efficiency.
Includes:
a. All effort associated with the design, development, and production of deliverable training equipment and its associated software as well as the execution of training services
Excludes:
a. Overall planning, management, and task analysis function inherent in the WBS element systems engineering/program management
1.6 Data
The deliverable data required to be listed on a contract data requirements list, DD Form 1423.
Includes:
a. Only such effort that can be reduced or avoided if the data item is eliminated
b. Engineering, management, and support data and Technical publications
c. Government-peculiar data; acquiring, writing, assembling, reproducing, packaging, storing and shipping the data
d. Transforming into Government format, reproducing and shipping data identical to that used by the contractor but in a different format.
1.6.1 Technical Publications
The deliverable data required to be listed on a contract data requirements list, DD Form 1423.
1.6.2 Engineering Data This WBS element includes the recurring engineering data inputs.
1.6.3 Management Data This WBS element includes the recurring data management support.
1.6.4 Support Data This WBS element includes the recurring support data effort/cost.
1.6.5 Data Depository This WBS element includes the recurring Data Depository effort/cost.
File details come from the government source that posted it. Updated .