RFP-RFQ_Q_AND_A_-__127-128.pdf
PDF 17 KB Posted
- Attached to
- USS MITSCHER (DDG 57) FY15 ESRA(d) Execution
- Solicitation number
- N00024-15-R-4406
View the file
Other files
| File | Type | Posted |
|---|---|---|
| RFP-RFQ_Q_AND_A_-__130-131.pdf | ||
| Amendment_8_-_MOD.pdf | ||
| Amendment_8_-_Conformed.pdf | ||
| RFP-RFQ_Q_AND_A_-__129.pdf | ||
| MITSCHER_RFP_Conformed_Amendment_7.pdf | ||
| Amendment_7.pdf | ||
| RFP-RFQ_Q_AND_A_-__122-126.pdf | ||
| J-4_Work_Item_Index_-_3_MAR_2015.xlsx | XLSX spreadsheet | |
| Amendment_6_-_Modification_Copy.pdf | ||
| Amendment_6_-_Conformed_Copy.pdf | ||
| Attachment_J-8_Award_Fee_Intra-Availability_Milestones.docx | DOCX document | |
| 0005_-_Conformed.pdf | ||
| J-4_Work_Item_Index_-_2_MAR_2015.xlsx | XLSX spreadsheet | |
| 0005.pdf | ||
| RFP-RFQ_Q_AND_A_-__97-121.pdf | ||
| 0004-_Conformed.pdf | ||
| 0004-_MOD.pdf | ||
| N00024-15-R-4406-0003.pdf | ||
| RFP-RFQ_Q_AND_A_-__91-96.pdf | ||
| N00024-15-R-4406-0002.pdf | ||
| RFP-RFQ_Q_AND_A_-__46-90.pdf | ||
| RFP-RFQ_Q_AND_A_-__46-90.pdf | ||
| RFP-RFQ_Q_AND_A_-__1-45.pdf | ||
| N00024-15-R-4406-0001.pdf | ||
| MITSCHER_RFP.zip | ZIP file |
Show all 25
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
NAVAL SEA SYSTEMS COMMAND
N00024-15-R-4406
QUESTIONS AND ANSWERS
The following are answers to questions received from potential offerors. The answers provide clarification only and DO NOT constitute an amendment to the solicitation.
127. Regarding Solicitation– Questions and Answers – GFI
Recent issuance of GFI requires that the cut-off date for Requests for Information/Clarification be waived.
1) There are Milestones date discrepancies between the original J-6 Attachment, and the dates listed in “DDG MOD Critical Path Equipment” file contained in the Addendum CD.
Specifically the dates for the 25% Conf, 50% Conf, VCHT, Turnover 1, Fiber testing, and 75% Conf. There is also a discrepancy between the A+ dates in the “DDG MOD Critical Path Equipment” on the “GEDMS” tab and “SY Execution Milestone Rev7d” tab. In addition, the MS Project file “SRA DDG57 Mitscher” Milestone dates for Undock, ALO and Fast Cruise are different than the J-6 attachment and “DDG MOD Critical Path Equipment” file
Please confirm all Milestone and A+ dates.
2) The Addendum CD contains a single MS Project file “SRA DDG57 MITSCHER” which is inclusive of the KTR and all AIT Alterations, and 73 separate MS Project files containing each AIT Alteration separately. Required Integration data that is included in the 73 individual MS Project files as per TS 9090 AIT Scheduling Guide has been omitted or modified in the single all inclusive “SRA DDG57 MITSCHER” MS Project file. (dates for same tasks are different in the single vs combined Project File, Locations are in the required designated column in the 73 Single Project files but not in the combined Project file, Required Task Successor information is contained in the 73 single Project files but not in the combined Project file)
Please confirm which MS Project has the correct dates and information to Integrate into the KTR’s Master Integrated Schedule.
3) MS Project file “DDG-57 EC 78909 POA&M.mpp” and corresponding PDF “DDG-57 EC
78909 POA&M.pdf” contained in Addendum CD could not be opened.
Please provide operable files.
ANSWER:
1. Key Event/Milestones contained in 3.1 (J-6) of the RFP shall be utilized for creating the integrated production schedule.
2. The single MS Project file “SRA DDG57 MITSCHER” contains the correct dates in accordance with Attachment J-6 of the RFP. The 73 single Project files are provided as GFI to assist all offerors’ critical path analysis and creation of an integrated production schedule in accordance with 1.3 and Attachments J-6 and J-8 of the RFP.
3. The government will provide the referenced information upon request.
128. Regarding Addendum 3 – 415-90-001.
This new item received today says The SHIPALT number for the USG-2B is:
1.1 SHIPALT DDG51-79526K, AN/USG-2B Installation; accomplish
1) Please confirm the correct SHIPALT number for item 415-90-001 is 79256K as drawings indicate.
2) Please confirm that an AIT will in fact be accomplishing work for this ShipAlt per Section 4
NOTES.
ANSWER:
1. Work Item 415-90-001 is for Industrial Activity (SY) to accomplish S/A 79256K.
2. A government activity will perform tasks as per reference 2.24 of Errata 5.