Attachment_2_POT-TS1148_-_Alignment_for_ATP.PDF

PDF 66 KB Posted

Attached to
Malaysian SITS Federal contract opportunity
Solicitation number
N00024-13-R-4406
Issued by
Department of the Navy Naval Sea Systems Command

About this file

Attachment 2- Alignment for ATP

View the file

Other files for this federal contract opportunity

Other files attached to Malaysian SITS, newest first.
File Type Posted
Malaysian_SITS_Bidder's_QA_9-30-13.pdf PDF
13R4406_Amend_0002.pdf PDF
NAVSEA_ltr_Ser_391r-0164_29OCT12.pdf PDF
NAVSEA_ltr_Ser_394-0815_01DEC11.pdf PDF
NAVSEA_Ltr_Ser_394-0010_08JAN10.pdf PDF
13R4406_Amend_0001.docx DOCX document
Attachment_6_-_Table_L.xlsx XLSX spreadsheet
Attachment_2__POT-TS1146_-_Weight_and_Center_of_Gravity.pdf PDF
Attachment_2_POT-TS1147_-_Alignment_for_LARS.PDF PDF
N00024-13-R-4406_SITS_RFP_Final.docx DOCX document
SITS_CDRLs.pdf PDF
Attachment_2_POT-TS1149_-_Load_Test.pdf PDF
Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Test Procedure POT-TS1148 Air Transport Pallet Integration Test of the

LARS Base Load Spreading Engineering Change (LSEC)

OII Document TM305124, Rev B for the

SUBMARINE RESCUE DIVING AND

RECOMPRESSION SYSTEM (SRDRS) PROGRAM

Prepared for:

NAVAL SEA SYSTEMS COMMAND

ADVANCED UNDERSEA SYSTEMS, PMS-394RR

SUBMARINE RESCUE DIVING AND RECOMPRESSION SYSTEM

Contract Number N00024-05-C-4208

Prepared by:

Oceaneering International, Inc.

7001 Dorsey Road

Hanover, MD 21076

SRDRS Document

DISTRIBUTION STATEMENT A;

Approved for public release; distribution is unlimited.

LARS Base LSEC Air Transport Pallet Integration Test, Test Procedure POT-TS1148

TM305124 Revision B

Change Record ECO # Revision OQE Date 04145 - 2/24/10 05315 A Retracted 7/19/11 05444 B 9/15/11

1.0 Purpose

1.1 The purpose of this test is to verify that the LARS Base LSEC can be stacked onto the Air Transport Pallets (ATP), to obtain an accurate weight of both pallets, and to determine the center of gravity (cg) of both pallets.

2.0 References and Prerequisites

2.1 References

NOTE

The most current revision of the referenced document shall be used to ensure up-to-date information is used for the performance of this test procedure. Indicate document revision in space provided.

2.1.1 NAVSEA Drawing 7412876 (-), Rev: _____; LARS Base LSEC General Arrangement

2.1.2 NAVSEA Drawing 7413241 (-), Rev:____; Rev. 1 LARS Base Pallet 1 & 2 Sling

Arrangement

2.1.3 NAVSEA Drawing 7413239 (-), Rev:____; Rev. 1 LARS Base Pallet 1 Lashing

Configuration

2.1.4 NAVSEA Drawing 7413240 (-), Rev:____; Rev. 1 LARS Base Pallet 2 Lashing

Configuration

2.2 Prerequisites

The following prerequisites, or the applicable portions of, shall be satisfactorily completed prior to starting the performance of this test procedure.

2.2.1 For the integration test, there are no prerequisites.

2.2.2 For the weight and CG test, verify all equipment has been installed in accordance with reference 2.1.3 and 2.1.4 and is ready to test.

Signature Date

3.0 General Notes

3.1 All data observed during the performance of this test must be regarded as significant. If sufficient space is not provided for the recording of required test data, it should be made on an attachment to the test procedure.

3.2 Completed test procedures shall be completely filled in, dated, signed and/or initialed at each entry as indicated. If certain data called for is not recorded, an entry shall be made in Section 6.0 explaining the missing information.

3.3 Any substitution of components or equipment during the course of the test must carry complete documentation, i.e. cleanliness, calibration information, etc. This information shall be recorded in the applicable sections of the test procedure.

3.4 Discrepancies and/or omissions encountered during the performance of this test shall be reported to the engineer responsible for the component/system. The discrepancy or omission shall be recorded in Section 6.0.

3.5 Deviations from this test procedure or changes in the installation from approved drawings shall not be made without prior approval from the engineer responsible for the system. Deviations must be recorded in Section 6.0 and ultimately must be approved by all reviewers of the test procedure.

3.6 Where tolerances are specified for the test data, every effort shall be made to meet such tolerances. Where not possible, the engineer responsible for the system shall be notified immediately. Any changes to the specified tolerances will require concurrence from the engineer responsible for the system.

3.7 All minor changes made during the performance of the test must be recorded in Section

6.0. Actual changes shall be initialed and dated by the engineer responsible for the system.

4.0 Test Equipment, Consumables and Miscellaneous Topics

4.1 Calibrated Test Equipment

The following test equipment shall be in calibration prior to the performance of this test procedure.

Instrument Description Serial No. Cal Date Cal Due Date Floor load cell* (R1)

12,000 lb capacity

Floor load cell* (R2)

Floor load cell* (R3)

Floor load cell* (R4)

* The floor load cells are Intercomp PT300.

4.2 General Test Equipment

4.2.1 Straps, slings and hoisting equipment capable of lifting LARS Base assemblies (5,000 lb or greater per lift point), installation fixtures (1,000 lb or greater per lift point), Bearing block adapter plates (800 lb per lift point), HPU Support beams (<200 lb) and the two ATP’s in the loaded configuration (40,000 lbs; refer to Ref. 2.1.3 and 2.1.4).

4.2.2 Suitable equipment to read load cell output if required.

4.2.3 Forklift capable of lifting 4,000 lbs.

4.2.4 Crane capable of lifting LARS Base assemblies (<40,000 lbs estimated per loaded ATP)

4.2.5 Miscellaneous shackles, pins, etc. necessary to attach straps, slings, load cells and other hoisting equipment to crane from items being hoisted.

4.3 Test Consumables

4.3.1 None.

4.4 Safety Precautions

4.4.1 Only personnel directly involved in the execution of this test shall be in the test area.

Personnel performing tests must not stand on or underneath items being hoisted. All applicable company safety regulations and requirements shall be followed during the performance of this test.

4.5 Hazardous Material/Waste Notes

4.5.1 None.

5.0 Test Procedure

Use reference 2.1.1 to identify equipment.

Recommend at least one tag line be affixed to the corner of any item hoisted to allow control of orientation and sway.

Record raw data using units native to the measuring device. Include units of measurement in data record.

5.1 Integration test.

5.1.1 Assemble pallet #1 per reference 2.1.3. Verify external dimensions are within 389” X 108” X 96”.

5.1.2 Assemble pallet #2 per reference 2.1.4. Verify external dimensions are within 384” X 108” X 96”.

5.2 Weight and CG test of LARS Base LSEC in shipping configuration

This test is to be completed for both shipping pallets as loaded in reference 2.1.3 and 2.1.4 and with slings arranged in accordance with reference 2.1.2.

5.2.1 Arrange the four floor load cells on shop floor in a 294” X 102” box as shown in Figure 1. Note that dimensions are from the centers of the load cell. Mark each load cell with a number as noted in Figure 1.

5.2.2 Set all four floor load cells to read zero. Initial column in Table 3 when scales are zeroed.

5.2.3 Hoist shipping pallet and center onto floor load cells (the forward end of the pallets per Ref.

2.1.3 and 2.1.4 are positioned near load cells 1 and 3 as shown in Figure 1). Disconnect all lifting equipment and move away from pallet.

5.2.4 Measure and record the distance from reference edge to Datum C (REFC) in Table 1. This is the distance from the edge nearest load cells 1 or 3.

Table 1

Shipping pallet REFC

Pallet #1

Pallet #2

5.2.5 Measure and record the distance from reference edge to Datum D (REFD) in Table 2. This is the distance from the edge nearest load cells 3 or 4.

Table 2 Shipping pallet REFD

5.2.6 Read and record the output from all four floor load cells in Table 3.

Table 3 Shipping pallet All scales zeroed (Initial)

Load cell #1 R1

Load cell #2 R2

Load cell #3 R3

Load cell #4 R4

5.2.7 Calculate the weight (Ws) and center of gravity in the lateral and longitudinal directions (CGxs and CGys) using the following formulas, and record in Table 4:

Ws = R1+R2+R3+R4

CGxs (inches) = (294” * (R2+R4) / Ws) + REFC

CGys (inches) = (102” * (R1+R2) / Ws) + REFD

Table 4

Shipping pallet Weight Ws

Long. CG CGxs [inches]

Lat. CG CGys [inches]

5.2.8 Repeat Section 5.2 for shipping pallet #2.

6.0 Notes and Test Review

6.1 Notes. List any changes or deviations from this test procedure, along with justification.

6.2 Reviewer Notes. Test reviewer shall verify the test performed has met the objectives of the test procedure.

Reviewing Engineer’s Signature Date

Figure 1 - Load cell layout for LARS Base assemblies in the shipping configuration

294”

Test Procedure POT-TS1148
SRDRS Document
NOTE

File details come from the government source that posted it. Updated .