MSW_Unit_4_Cell_5_Addendum_01_-_Drawings_IFP.pdf
PDF 5 MB Posted
- Solicitation number
- RFP #27008
- Issued by
- Greenville County, South Carolina
About this file
This addendum document contains engineering drawings and technical specifications for Unit 4 Cell 5 Liner Construction at Twin Chimneys Landfill in Greenville County, South Carolina. The project encompasses construction of an 8.2-acre municipal solid waste cell liner system within an active landfill facility. The scope of work includes subgrade preparation, installation of 24 inches of on-site compacted clay liner (1x10-5 cm/sec permeability), geosynthetic clay liner, 60-mil textured HDPE geomembrane, geocomposite drainage media, leachate collection piping in various diameters (8-inch through 22-inch), and 24 inches of operational cover soil with site seeding. The drawings detail cell configuration relative to existing active cells (Cells 2, 3, and 4), grading and drainage requirements, control points for quality assurance, and construction details for liner anchor trenches, leachate pipe connections, and tie-ins with adjacent cells. Proposed quantities include approximately 28,000 cubic yards of compacted soil liner, 1,910 cubic yards of leachate column stone, and 28,000 cubic yards of operational cover material. The contractor must obtain on-site clay from available stockpiles and source off-site protective cover soil and riprap from approved borrow areas. Substantial Completion is required within 180 calendar days from Notice to Proceed, with Final Completion within 210 calendar days, subject to liquidated damages of $1,000 per day and $500 per day respectively.
The contractor is responsible for all construction quality control, surveying, and production of as-built documentation, while Greenville County will provide Construction Quality Assurance through a separate consultant. Key technical requirements include proof rolls of the subgrade to demonstrate stability, permeability testing of clay liner, thickness verification, HDPE panel layout approval, and GPS-controlled fine grading for precision installation. All leachate collection hardware must be stainless steel, perforated pipes require specific perforation patterns based on diameter, and temporary stormwater management infrastructure must be maintained throughout construction. The contractor must verify existing ground conditions prior to construction initiation and immediately notify the engineer of any groundwater encountered during excavation. A fuel price adjustment clause applies to soil work and materials, with triggers at 1.10 and 0.90 ratios using SCDOT monthly fuel price indices. The County will retain 10 percent from monthly invoices pending satisfactory completion, and the contractor must provide a 5 percent bid bond and performance/payment bonds equal to 100 percent of the contract value within fifteen working days of award. Insurance coverage must include $1,000,000 per occurrence general liability and automobile liability with statutory workers' compensation coverage.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
720720
710710
0 75
0750 76
76076
ACTIVE CELL 4
ACTIVE CELL 3
8.5 ACRES
10.3 ACRES
8.5 ACRES
ACTIVE CELL 2
MW-24
PZ-6d
PZ-54
PZ-56
PZ-6s
PZ-77
MW-23
MW-22
MW-25
8.2 ACRES
PROPOSED CELL 5
3:1
3:1
3:
3:
3:1
3:1
4.0%
5.0%
10.0%
4.0%
UNIT 4 CELL 5 SUBGRADE
15C-02A.dwg
1"=60' 15C-02A
0 07/2026 ISSUED FOR PROPOSAL
1 08/2026 ADDENDUM 01
PL
LEGEND
EXISTING 2025 MAJOR CONTOURS
GENERAL NOTES:
1. CONTRACTOR SHALL PROVIDE AN AS-BUILT SURVEY OF THE SUBGRADE SIGNED
AND SEALED BY A LAND SURVEYOR, FOR ENGINEERS ACCEPTANCE PRIOR TO
INITIATING CLAY LINER INSTALLATION.
2. CONTRACTOR MAY UTILIZE THE SKIMMER DURING CLAY INSTALLATION. THE
CONTRACTOR MAY ABANDON THE SKIMMER PER THE DETAIL AND USE A PUMP
AND SILT BAG.
3. EXISTING CONDITIONS WITHIN THE CELL ARE BASED ON A DRONE SURVEY ON
AUGUST 06, 2026.CONTRACTOR TO VERIFY CONDITIONS PRIOR TO INITIATING
CONSTRUCTION.
4. PROPOSED CONTOURS WITHIN CONSTRUCTION BASELINE REPRESENT
SUBGRADE OF CELL 5.
5. AN ACCEPTABLE PROOF ROLL (AS DEFINED BY THE CQA CONSULTANT) MUST BE
OBSERVED TO DEMONSTRATE A STABLE SUBGRADE PRIOR TO CONSTRUCTION
OF THE LINER SYSTEM. THE SUBGRADE MAY BE ACCEPTED IN STAGES TO
FACILITATE CONSTRUCTION. REFER TO TECHNICAL SPEC SECTION 31 38 10.
6. REFER TO SPECIFICATIONS AND CQA PLAN FOR SURVEYING REQUIREMENTS TO
PRODUCE AS-BUILT DRAWINGS AND TO PROVIDE BASIS FOR VERIFYING
EXCAVATION QUANTITIES.
7. REMOVE ALL WET AND SOFT SOILS PRIOR TO BEGINNING STRUCTURAL FILL
PLACEMENT. COMPACT PER SPECIFICATIONS. "BRIDGE LIFTS" REQUIRE
APPROVAL OF ENGINEER AND CQA CONSULTANT.
8. PROTECT EXISTING WELLS, DROP INLETS AND OTHER STRUCTURES DURING THE
WORK.
9. IF CONTRACTOR ENCOUNTERS GROUNDWATER DURING EXCAVATION,
IMMEDIATELY STOP WORKING IN THAT AREA AND NOTIFY ENGINEER. EXISTENCE
OF WATER MAY REQUIRE REVISION TO GRADING. THE CONTRACTOR SHALL
IMPLEMENT ALL CHANGES BASED ON EXISTENCE OF GROUNDWATER IN THE
EXCAVATION.
EXISTING 2025 MINOR CONTOURS
WETLANDS
UNIT AND CELL BASELINES
PROPERTY LINE
GRADING LIMITS
PROPOSED MAJOR CONTOURS
PROPOSED MINOR CONTOURS
EXISTING TREELINE
METHANE MONITORING (MM)
PIEZOMETER (PZ)
MONITORING AND OBSERVATION
WELL (MW,OW)
PROPOSED EXISTING ABANDONED
MW-P
MM-P
MW-A
MM-#
PZ-#PZ-#
PROPOSED
CONSTRUCTION
BASELINE
TEMPORARY
SEDIMENT BASIN A
SF
SILT FENCE
GEOSYNTHETIC CLAY LINER
(WITHIN CBL)
LOCATION THIS SHEET
2' OPERATIONAL COVER
SUBGRADE
2' SOIL LINER
60 MIL HDPE GEOMEMBRANE
GEOCOMPOSITE DRAINAGE MEDIA
KEY MAP
RAINCOVER
NTS
A
B
C
2 3 4 5 6 7 8
D
ISSUE DESCRIPTION
PROJECT MANAGER
PROJECT NUMBER
0 1" 2" FILENAME
SCALE
SHEET
DATE
UNIT 4 CELL 5 LINER
Greenville County South Carolina10174879
P. WESTMORELAND, P.E.
HDR Engineering Inc.
440 S. Church St. Suite 1200 Charlotte, NC 28202-2075 704.338.6700 of the Carolinas
PROJECT ENGINEER
DRAWN BY
PROPOSED
CONSTRUCTION
BASELINE
15C-09
8/25/26
POINT TABLE
POINT NO.
NORTHING
983645.29
983663.83
983659.04
983657.57
983503.02
983496.46
983468.88
983492.70
983540.40
983364.12
983289.52
983205.49
983095.06
983305.92
983332.60
983344.21
983379.36
983651.30
983666.68
983632.10
983620.77
983631.84
983309.83
983380.04
983286.96
983283.49
983236.07
983209.88
983361.19
983428.75
983586.77
EASTING
1605184.98
1605185.30
1605284.56
1605314.79
1605568.82
1605614.40
1605806.30
1605865.29
1605983.38
1606121.88
1606067.06
1606021.22
1605842.28
1605002.72
1604919.21
1604893.50
1604887.94
1605088.65
1605115.86
1605113.12
1605371.75
1605208.37
1605114.98
1604892.28
1605432.09
1605447.96
1605664.73
1605771.18
1606016.72
1606071.10
1605431.14
ELEVATION
730.00
0.00
728.00
754.00
754.00
710.00
701.59
700.00
754.00
718.11
720.30
723.03
729.97
754.63
758.00
759.12
751.00
754.00
750.00
743.66
724.00
740.00
740.00
750.00
710.73
710.00
700.00
696.00
693.47
691.89
720.00
DESCRIPTION
SG
SG
SG
SG
SG
SG
SG
SG
SG
SG
SG
SG
SG
SG
SG
SG
SG
SG
SG
SG
SG
SG
SG
SG
SG
SG
SG
SG
SG
SG
SG
111 112 113
3:1
3:1
3:
3:
3:
3:1
4.0%
4.0%
5.0%10.0%
14110.0%
UNIT 4 CELL 5 SUBGRADE CONTROL
15C-02A.dwg
1"=60' 15C-03
0 07/2026 ISSUED FOR PROPOSAL
1 08/2026 ADDENDUM 01
LEGEND
CONTROL LINE
PROPOSED MAJOR CONTOURS
PROPOSED MINOR CONTOURS
PROPOSED CELL 5
8.2 ACRES
NOTES
1. CONSTRUCT THE CELL FLOOR AND DITCHES TO THE GRADES SHOWN ON
THIS DRAWING. UTILIZE GPS EQUIPMENT FOR FINE GRADING SUBGRADE AND
THE CLAY LINER.
2. CONTOURS INSIDE THE CONSTRUCTION BASELINE REPRESENT PROPOSED
SUBGRADE AS SHOWN ON SHEET 15C-02.
3. EACH PANEL (PLANE) DEPICTS AN AREA OF CONSTANT GRADE. REFER TO
THE DETAILS FOR BASEGRADE GEOMETRY AROUND THE PIPING.
4. THE CONTROL POINTS DEFINE THE LOCATION OF THE CONSTRUCTION
BASELINE AND THE PANELS THAT MAKEUP THE CELL.
5. IF THERE ARE ANY CONFLICTS BETWEEN INFORMATION ON THIS SHEET AND
OTHER REPRESENTATIONS OF THE WORK, NOTIFY THE ENGINEER. THE
ENGINEER WILL DETERMINE PRECEDENCE OF CONFLICTS.
A
B
C
2 3 4 5 6 7 8
D
ISSUE DESCRIPTION
PROJECT MANAGER
PROJECT NUMBER
0 1" 2" FILENAME
SCALE
SHEET
DATE
UNIT 4 CELL 5 LINER
Greenville County South Carolina10174879
P. WESTMORELAND, P.E.
HDR Engineering Inc.
440 S. Church St. Suite 1200 Charlotte, NC 28202-2075 704.338.6700 of the Carolinas
PROJECT ENGINEER
DRAWN BY
ACTIVE CELL 4
10.3 ACRES
ACTIVE CELL3
8.5 ACRES
ACTIVE CELL 2
LF@1.1%
211 LF@2.5%
431 LF@2.5%
234 LF@2.0%
111 LF@2.5%
50 LF@2.0%
740740740
730730
ACTIVE
CELL 2
8.6 ACRES
ACTIVE
CELL 4
10.3 ACRES
MW-62
MW-24
MW-63
PZ-54
PZ-56
PZ-77
PZ-25
PZ-25d
MW-21
MW-23
MW-22
CELL 3
8.5 ACRES
PROPOSED
CELL 5
8.2 ACRES
10.0%
10.0% 4.0%
5.0%
5.0% 4.0%
4.0%
3:1
3:1
3:1
3:1
.3%
UNIT 4 CELL 5 TOP OF LINER
15C-04.dwg
1"=60' 15C-04
0 07/2026 ISSUED FOR PROPOSAL
1 08/2026 ADDENDUM 01
2' OPERATIONAL COVER
SUBGRADE
2' SOIL LINER
KEY MAP
NTS
GEOSYNTHETIC CLAY LINER
60 MIL HDPE GEOMEMBRANE
GEOCOMPOSITE DRAINAGE MEDIA
RAINCOVER
LEGEND
UNIT AND CELL BASELINES
PROPOSED MAJOR CONTOURS
PROPOSED MINOR CONTOURS
1. CLAY FOR THE SOIL LINER SHALL BE OBTAINED
FROM THE CLAY STOCKPILE .
2. BACKFILL THE ANCHOR TRENCH WITH THE SAME
MATERIAL AS USED FOR SOIL LINER
COMPONENT.
3. THE CONSTRUCTION BASELINE GENERALLY
REPRESENTS THE HORIZONTAL EXTENT OF THE
LINER SYSTEM. SEE LINER DETAILS.
4. THESE CONTOURS REPRESENT THE TOP OF
SOIL LINER GRADES.
5. REFER TO SPECIFICATIONS AND CQA PLAN FOR
SURVEYING REQUIREMENTS TO PRODUCE
AS-BUILT DRAWINGS AND TO PROVIDE BASIS
FOR VERIFYING EXCAVATION QUANTITIES AND
REQUIRED LINER THICKNESS.
6. RECORD ALL PERMEABILITY TEST LOCATIONS BY
GPS, OR CONVENTIONAL SURVEY. DOCUMENT
LOCATION OF ALL OTHER TESTS BY METHOD
APPROVED BY CQA CONSULTANT.
7. CERTIFY IN WRITING TO THE CQA ENGINEER
THAT THE CLAY LINER MEETS SPECIFICATIONS
INCLUDING THICKNESS VERIFICATION PRIOR TO
INSTALLING HDPE LINER.
8. SUBMIT A HDPE LINER PANEL LAYOUT TO THE
ENGINEER FOR APPROVAL PRIOR TO
INSTALLATION. THE PANELS SHALL BE SEAMED
PARALLEL TO LINE OF MAXIMUM SLOPE. FLOOR
PANELS SHALL GENERALLY BE LAPPED ON THE
DOWNHILL SIDE. REFER TO SPECIFICATIONS AND
CQA PLAN.
9. USE TEXTURED 60 MIL HDPE GEOMEMBRANE
FOR ALL AREAS.
10. ALL LEACHATE PIPES TO BE PERFORATED. ALL
CONNECTIONS TO BE FUSED.
11. JOIN INTERSECTING PIPES WITH
APPROPRIATELY SIZED FITTINGS AND BUTT
FUSION WELDS.
12. PIPES SHOULD BE LAID STRAIGHT BETWEEN
CONTROL POINTS. ALL CLEANOUTS SHALL RUN
PERPENDICULAR TO SLOPE.
13. TEMPORARY STORM WATER PIPE MUST BE
SOLID AND SMOOTH WALLED. CONNECT
PROPOSED PIPE TO EXISTING CELL 2 PIPE USING
FUSION WELD.
NOTES
SEDIMENT BASIN #12
PROPOSED
CONSTRUCTION
BASELINE
A15C-09
C
C -0
CELL 2, 3 & 4 TIE-IN
WITH CELL 5 W/O PIPE
15C-08
LEACHATE PIPE3
15C-08
LEACHATE COLLECTION PIPE
(SIZE VARIES)
EXISTING MAJOR CONTOURS780
EXISTING MINOR CONTOURS
PIPE PERFORATION
(TYP)
15C-08
A
B
C
2 3 4 5 6 7 8
D
ISSUE DESCRIPTION
PROJECT MANAGER
PROJECT NUMBER
0 1" 2" FILENAME
SCALE
SHEET
DATE
UNIT 4 CELL 5 LINER
Greenville County South Carolina10174879
P. WESTMORELAND, P.E.
HDR Engineering Inc.
440 S. Church St. Suite 1200 Charlotte, NC 28202-2075 704.338.6700 of the Carolinas
PROJECT ENGINEER
DRAWN BY
B 15C-09
CELL 2, 3 & 4 TIE-IN
WITH CELL 5 W/ PIPE
15C-08
LEACHATE
CLEANOUT
(TYP.)
15C-08
CONNECT TO EXISTING 15"
HDPE STORMWATER PIPE
(NOTE 13)
TEMPORARY
STORMWATER PIPE
15C-08
PIPE CROSS
CONNECTIONS
(TYP.)
15C-08
CELL 5 FUTURE
TIE-IN W/O PIPE
15C-08
CELL 5 FUTURE
TIE-IN W/PIPE
15C-08
METHANE MONITORING (MM)
PIEZOMETER (PZ)
MONITORING AND OBSERVATION
WELL (MW,OW)
PROPOSED EXISTING ABANDONED
MW-P
MM-P
PZ-# PZ-#
MM-#
MW-A
(WITHIN CBL)
LOCATION THIS SHEET
STORMWATER
DIVERSION CHANNEL
42 43
45 46
LF@1.1%
211 LF@2.5%
431 LF@2.5%
234 LF@2.0%
111 LF@2.5%
50 LF@2.0%
726728
SITE LAYOUT COORDINATE POINTS TABLE
POINT NO.
NORTHING
983591.53
983341.92
983312.42
983337.97
983305.92
983094.93
983224.67
983364.12
983663.17
983663.83
983380.33
983308.54
983431.34
983429.27
983330.14
983636.85
983657.76
983643.91
983620.77
983334.34
983347.86
983503.03
983468.88
983492.74
983540.40
983631.84
983318.12
983379.41
983312.55
983312.07
983288.11
983666.68
983648.69
983236.40
983210.87
983245.70
983348.27
983102.68
983209.88
983271.93
983612.63
983657.57
983547.29
983473.32
983303.71
983209.03
983312.15
983312.30
983317.62
EASTING
1605384.10
1604968.10
1604828.12
1604882.30
1605002.72
1605841.31
1606031.70
1606121.88
1605199.01
1605185.30
1604877.36
1605001.10
1606069.06
1606070.68
1604838.14
1605115.42
1605310.97
1605315.99
1605371.75
1605017.97
1605396.74
1605568.76
1605806.30
1605865.38
1605983.38
1605208.37
1605108.70
1604888.29
1605104.04
1605118.11
1605431.42
1605115.86
1605170.31
1605665.05
1605768.54
1605950.40
1606008.16
1605744.31
1605351.33
1605126.18
1605158.05
1605314.79
1605496.02
1605775.38
1605383.92
1605773.08
1605115.65
1605111.08
1605100.08
ELEVATION
724.00
748.00
749.00
757.99
754.63
730.00
723.33
718.11
732.00
732.22
749.98
754.01
694.07
694.00
750.00
744.00
728.98
732.00
726.00
746.00
716.00
714.00
703.59
702.00
699.45
742.00
740.35
751.48
742.56
741.76
713.06
750.00
737.92
702.00
698.11
698.39
695.80
734.14
745.00
751.00
743.72
728.95
718.23
704.95
716.00
698.16
742.00
742.18
742.66
DESCRIPTION
MAINT-AREA
MAINT-AREA
MAINT-AREA
MAINT-AREA
MAINT-AREA
MAINT-AREA
MAINT AREA
MAINT AREA
MAINT-AREA
MAINT-AREA
MAINT-AREA
MAINT-AREA
22" LLEACH
MAINT-AREA
MAINT-AREA
MAINT-AREA
8" LEACH
MAINT-AREA
MAINT. AREA
10" LEACH
10" LEACH
MAINT-AREA
MAINT=-AREA
MAINT=-AREA
MAINT=-AREA
MAINT-AREA
MAINT-AREA
MAINT-AREA
MAINT-AREA
CLEANOUT
CLEANOUT
MAINT-AREA
MAINT-AREA
MAINT-AREA
MAINT-AREA
MAINT AREA
CLEANOUT
CLEANOUT
CLEANOUT
CLEANOUT
8" LEACH
MAINT-AREA
10" LEACH
10" LEACH
CLEANOUT
CLEANOUT
16" LEACH
MAINT-AREA
MAINT-AREA
UNIT 4 CELL 5 TOP OF LINER CONTROL
15C-05.dwg
1"= 60' 15C-05
0 07/2026 ISSUED FOR PROPOSAL
1 08/2026 ADDENDUM 01
LEGEND
CONTROL LINE
PROPOSED MAJOR CONTOURS
PROPOSED MINOR CONTOURS
A
B
C
2 3 4 5 6 7 8
D
ISSUE DESCRIPTION
PROJECT MANAGER
PROJECT NUMBER
0 1" 2" FILENAME
SCALE
SHEET
DATE
UNIT 4 CELL 5 LINER
Greenville County South Carolina10174879
P. WESTMORELAND, P.E.
HDR Engineering Inc.
440 S. Church St. Suite 1200 Charlotte, NC 28202-2075 704.338.6700 of the Carolinas
PROJECT ENGINEER
DRAWN BY
PROPOSED CELL 5
8.2 ACRES
ACTIVE CELL 4
10.3 ACRES
ACTIVE CELL3
8.5 ACRES
ACTIVE CELL 2
TEMPORARY
STORMWATER PIPE
740740740
730730
MW-24
PZ-6d
PZ-54
PZ-56
PZ-6s
PZ-77
MW-23
MW-22
ACTIVE
CELL 2
ACTIVE
CELL 4
10.3 ACRES
ACTIVE
CELL 3
8.5 ACRES
LF@1.1%
211 LF@2.5%
431 LF@2.5%
234 LF@2.0%
111 LF@2.5%
50 LF@2.0%
10.0%
5.0%
4.0%
3.
7%
PROPOSED
CELL 5
8.2 ACRES
UNIT 4 CELL 5 OPERATIONAL COVER
15C-06.dwg
1"=60 15C-06
0 07/2026 ISSUED FOR PROPOSAL
1 08/2026 ADDENDUM 01
KEY MAP
2' SOIL LINER
SUBGRADE
2' OPERATIONAL COVER
GEOSYNTHETIC CLAY LINER
(WITHIN CBL)
LOCATION THIS SHEET
60 MIL HDPE GEOMEMBRANE
GEOCOMPOSITE DRAINAGE MEDIA
RAINCOVER
PL
LEGEND
UNIT AND CELL BASELINES
PROPERTY LINE
PROPOSED MAJOR CONTOURS
PROPOSED MINOR CONTOURS
1. THE GRADES WITHIN CELL 5 GENERALLY REPRESENT THE
TOP OF OPERATIONAL COVER.
2. CERTIFY IN WRITING TO THE CQA ENGINEER THAT THE
OPERATIONAL COVER MEETS SPECIFICATIONS INCLUDING
THICKNESS VERIFICATION.
3. TEMPORARY STORM WATER PIPE MUST BE SOLID AND
SMOOTH WALLED. CONNECT PROPOSED PIPE TO EXISTING
CELL 2 PIPE USING FUSION WELD.
NOTES
PROPOSED
CONSTRUCTION
BASELINE
CELL 2,3 & 4 TIE-IN
WITH CELL 5 W/O PIPE
15C-08
METHANE MONITORING (MM)
PIEZOMETER (PZ)
MONITORING AND OBSERVATION
WELL (MW,OW)
PROPOSED EXISTING ABANDONED
MW-P
MM-P
MW-A
MM-#
PZ-#PZ-#
LEACHATE
COLUMN
15C-08
EXISTING MAJOR CONTOURS780
EXISTING MINOR CONTOURS
A
B
C
2 3 4 5 6 7 8
D
ISSUE DESCRIPTION
PROJECT MANAGER
PROJECT NUMBER
0 1" 2" FILENAME
SCALE
SHEET
DATE
UNIT 4 CELL 5 LINER
Greenville County South Carolina10174879
P. WESTMORELAND, P.E.
HDR Engineering Inc.
440 S. Church St. Suite 1200 Charlotte, NC 28202-2075 704.338.6700 of the Carolinas
PROJECT ENGINEER
DRAWN BY
CELL 2,3 & 4 TIE-IN
WITH CELL 5 W PIPE
15C-08
TEMPORARY
STORMWATER PIPE
LEACHATE CLEANOUT
TOE OF SLOPE8
15C-08
A15C-09
C
C -0
B 15C-09
12" THICK CLASS "A" RIP
RAP WITH UNDERLYING
NON-WOVEN GEOTEXTILE
STORMWATER PIPE
CROSSING THROUGH
THE BERM
10.0%
10.0%
5.0%
4.0%
3.
7%
3:1
3:1
3:1
3:1
740740
232233
OPERATIONAL COVER CONTROL TABLE
POINT NO.
NORTHING
983631.84
983591.40
983476.93
983347.78
EASTING
1605208.37
1605384.06
1605321.69
1605396.74
ELEVATION
744.00
726.00
724.93
718.00
DESCRIPTION
OPERATIONAL COVER
OPERATIONAL COVER
OPERATIONAL COVER
OPERATIONAL COVER
OPERATIONAL COVER CONTROL TABLE
POINT NO.
NORTHING
983547.29
983473.32
983645.63
983287.72
983663.83
983657.57
983503.02
983468.88
983540.40
983423.02
983431.91
983357.66
983335.60
983296.10
983266.30
983206.39
983159.90
983123.16
983101.74
983100.66
983092.96
983085.85
983100.46
983211.13
983659.03
983632.41
983400.42
983236.82
983492.74
983293.87
983215.27
983295.75
983310.93
EASTING
1605496.02
1605775.38
1605295.67
1605431.65
1605185.30
1605314.79
1605568.82
1605806.30
1605983.38
1606075.59
1606068.61
1606128.10
1606097.19
1606081.19
1606054.84
1606021.37
1605995.02
1605930.07
1605904.96
1605871.98
1605810.17
1605777.94
1605748.34
1605768.90
1605284.62
1605171.78
1605132.84
1605665.61
1605865.38
1605981.61
1605913.20
1605381.61
1605115.30
ELEVATION
720.23
706.95
736.00
714.46
732.22
730.77
716.00
705.59
701.45
698.19
696.10
718.11
722.00
720.00
724.00
726.00
724.66
730.00
728.00
732.00
734.00
732.00
736.00
700.10
732.00
746.00
742.97
703.99
704.00
699.54
701.02
718.00
744.00
DESCRIPTION
OPERATIONAL COVER
OPERATIONAL COVER
OPERATIONAL COVER
OPERATIONAL COVER
OPERATIONAL COVER
OPERATIONAL COVER
OPERATIONAL COVER
OPERATIONAL COVER
OPERATIONAL COVER
OPERATIONAL COVER
OPERATIONAL COVER
OPERATIONAL COVER
OPERATIONAL COVER
OPERATIONAL COVER
OPERATIONAL COVER
OPERATIONAL COVER
OPERATIONAL COVER
OPERATIONAL COVER
OPERATIONAL COVER
OPERATIONAL COVER
OPERATIONAL COVER
OPERATIONAL COVER
OPERATIONAL COVER
OPERATIONAL COVER
OPERATIONAL COVER
OPERATIONAL COVER
OPERATIONAL COVER
OPERATIONAL COVER
OPERATIONAL COVER
OPERATIONAL COVER
OPERATIONAL COVER
OPERATIONAL COVER
OPERATIONAL COVER
UNIT 4 CELL 5 OPERATIONAL COVER CONTROL
15C-07.dwg
1"=60' 15C-07
0 07/2026 ISSUED FOR PROPSAL
1 08/2026 ADDENDUM 01
LEGEND
CONTROL LINE
PROPOSED MAJOR CONTOURS
PROPOSED MINOR CONTOURS
A
B
C
2 3 4 5 6 7 8
D
ISSUE DESCRIPTION
PROJECT MANAGER
PROJECT NUMBER
0 1" 2" FILENAME
SCALE
SHEET
DATE
UNIT 4 CELL 5 LINER
Greenville County South Carolina10174879
P. WESTMORELAND, P.E.
HDR Engineering Inc.
440 S. Church St. Suite 1200 Charlotte, NC 28202-2075 704.338.6700 of the Carolinas
PROJECT ENGINEER
DRAWN BY
PROPOSED CELL 5
8.2 ACRES
ACTIVE CELL 4
10.3 ACRES
ACTIVE CELL3
8.5 ACRES
GEOCOMPOSITE DRAINAGE MEDIA
HDPE GEOMEMBRANE
GEOSYNTHETIC CLAY LINER
2'
1'
1" = 1'
ANCHOR TRENCH2
24" INITIAL SOIL BARRIER
GEOSYNTHETIC CLAY LINER (GCL)
HDPE GEOMEMBRANE
GEOCOMPOSITE DRAINAGE MEDIA
24" OPERATIONAL LAYER
SUBGRADE
NOTES:
1. GCL AND GEOCOMPOSITE DRAINAGE NET ARE PRESENT
IN ALL LOCATIONS WHERE HDPE IS DETAILED.
2. THE REQUIRED THICKNESS OF LAYERS IS MEASURED
PERPENDICULAR TO THE SURFACE. THE HORIZONTAL
LOCATION OF THE SLOPE TOES WILL VARY BASED ON
INTERSECTING SLOPES.
3. GEOSYNTHETIC MATERIAL THICKNESS ARE
EXAGGERATED FOR ILLUSTRATION PURPOSES WHERE
SHOWN AND OMITTED FOR DETAIL CLARITY WHERE NOT
SHOWN.
SLOPESLOPE
B
SEPARATOR
GEOTEXTILE
2' M
IN
PERFORATED PIPE
RAINCOVER (TO BE REMOVED)
CONSTRUCTION
BASELINE
WELDED CAP TO BE
REMOVED AND NEW PIPE
WELDED TO EXISTING PIPE
6'
LINER AND RAINCOVER
ANCHOR TRENCH
LEACHATE
PIPE
2.00'
LEACHATE
PIPE
EXISTING
CELL 2/3/4
RAINCOVER
(TO BE REMOVED)
CONSTRUCTION
BASELINE
6.0'
LINER AND RAINCOVER
ANCHOR TRENCH
2.0'
2.0'
2.
0'
EXISTING
CELL 2/3/4
CELL 5
SEPARATOR GEOTEXTILE
(EXPOSED GEOTEXTILE TO BE
REMOVED BY THE OWNER
PRIOR TO WASTE PLACEMENT)
1" = 5'
LINER SECTION1
1" = 5'
LEACHATE COLUMN3
15C-05
1" = 5'
CELL 6 FUTURE TIE-IN W/O PIPE4
15C-04 1" = 5'
CELL 2, 3 & 4 TIE-IN
WITH CELL 5 W/O PIPE5
15C-02
1" = 5'
CELL 6 FUTURE TIE IN W/PIPE6
15C-04
1" = 5'
CELL 2,3 & 4 TIE-IN
WITH CELL 5 W/PIPE7
15C-04
LINER
SECTION
1" = 5'
TEMPORARY STOMWATER PIPE10
15C-04
3.
6'
1.
3'
3.0'
0.
7' 3.5'
10'
A B C QTY
8 12 10 5
1" = 5'
LEACHATE COLLECTION CLEANOUT9
15C-04
NOTE: ALL LEACHATE COLLECTION
HARDWARE TO BE STAINLESS STEEL
CAST IN PLACE
CONCRETE
FRONT VIEW
SOLID HDPE PIPE "A"Ø
FUTURE
WASTE
SOLID HDPE CLEANOUT
PIPE "A"Ø
HDPE PROTECTIVE CASING "C"ØANCHOR BLOCK
"B"Ø PIPE
CONSTRUCTION BASELINE
PERFORATED HDPE PIPE "A"Ø
BLIND FLANGE
15" SMOOTH WALL
HDPE STORM DRAIN
PIPE @ 0.5% SLOPE
LINER SECTION
36.0'
18"
GEOTEXTILE
OVERLAP
7.5'
NOTE:
1. OVERLAP GEOTEXTILES 18" AT ALL SEAMS.
LINER SECTION
2.0'
2.
0'
M
IN
3.0'
EXPOSED GEOTEXTILE REMOVED
BY OWNER PRIOR TO WASTE
PLACEMENT
PERFORATED HDPE LEACHATE
COLLECTION HEADER PIPE
1" = 5'
TOE OF SLOPE8
15C-06
NOTE:
1. CONTRACTOR MUST PROVIDE FABRICATION DRAWING FOR
ALL PIPE CROSS CONNECTIONS FOR ENGINEER APPROVAL.
NOT TO SCALE
PIPE CROSS CONNECTION12
15C-04
PIPE DIA. (INCHES) B (FT)
8 TO 12 2
16 TO 22 3
CELL 5
CONSTRUCTION
BASELINE
1.0'
LINER ANCHOR
TRENCH
2.0'
2.0'
2.
0'
12'
RAIN COVER
ANCHOR TRENCH
RAIN COVER
RAIN COVER
BALLAST
17'
CONSTRUCTION
BASELINE
WELDED CAP
1.00'
LINER ANCHOR TRENCH
LEACHATE
PIPE
2.00'
12'
RAIN COVER
RAIN COVER
ANCHOR TRENCH
RAIN COVER
BALLAST
17'
NOTES:
1. CONCRETE TO BE READY MIXED CONCRETE CONFORMING TO ASTM C94/C94M.
2. CONCRETE MUST HAVE MIN. 28-DAY COMPRESSIVE STRENGTH OF 4000 PSI.
RAIN COVER (IN AREA SHOWN)
SPACING
4" CENTER
HOLE/PATTERN: 6/STAGGERED
3/8"Ø STAGGERED
PERFORATIONS
6" TO 14"
6" CENTER SPACING
1/2"Ø STAGGERED
PERFORATIONS
HOLE/PATTERN: 16/STAGGERED
16"- 36"
NOT TO SCALE
PIPE PERFORATION11
LINER DETAILS
15C-08.dwg
AS SHOWN 15C-08
0 07/2026 ISSUED FOR PROPOSAL
1 08/2026 ADDENDUM 01
A
B
C
2 3 4 5 6 7 8
D
ISSUE DESCRIPTION
PROJECT MANAGER
PROJECT NUMBER
0 1" 2" FILENAME
SCALE
SHEET
DATE
UNIT 4 CELL 5 LINER
Greenville County South Carolina10174879
P. WESTMORELAND, P.E.
HDR Engineering Inc.
440 S. Church St. Suite 1200 Charlotte, NC 28202-2075 704.338.6700 of the Carolinas
PROJECT ENGINEER
DRAWN BY
-0+50 0+00 0+50 1+00 1+50 2+00 2+50 3+00
-0+50 0+00 0+50 1+00 1+50 2+00
-0+50 0+00 0+50 1+00 1+50 2+00
TRASH GUARD
RISER
SKIMMER
NOTES:
1. CONTRACTOR TO CAREFULLY REMOVE THE SKIMMER, RISER, AND TRASH GUARD
AND PROVIDE TO THE OWNER.
2. EXCAVATE INTO THE BERM TO THE REMOVE A PORTION OF THE BARREL AS SHOWN.
3. GROUT THE REMAINING BARREL.
4. PLACE COMPACTED FILL OVER THE EXCAVATED AREA.
36" CPP 150 - FT LONG4'
BARREL
REMOVE THIS
PORTION OF THE
BARREL
CROSS SECTIONS
15C-09.dwg
AS SHOWN 15C-09
0 07/2026 ISSUED FOR PROPOSAL
1 08/2026 ADDENDUM 01
A
B
C
2 3 4 5 6 7 8
D
ISSUE DESCRIPTION
PROJECT MANAGER
PROJECT NUMBER
0 1" 2" FILENAME
SCALE
SHEET
DATE
UNIT 4 CELL 5 LINER
Greenville County South Carolina10174879
P. WESTMORELAND, P.E.
HDR Engineering Inc.
440 S. Church St. Suite 1200 Charlotte, NC 28202-2075 704.338.6700 of the Carolinas
PROJECT ENGINEER
DRAWN BY
H: 1" = 30' V: 1" = 30'
CROSS SECTIONSA
15C-04
H: 1" = 30' V: 1" = 30'
CROSS SECTIONSB
15C-04
H: 1" = 30' V: 1" = 30'
CROSS SECTIONSC
15C-04
EXISTING 2026 SURVEY
CELL 5 OPERATIONAL COVER
CELL 5 TOP OF LINER
EXISTING 2026 SURVEY CELL 5 OPERATIONAL COVER
CELL 5 TOP OF LINER
EXISTING 2025 SURVEY
CELL 5 OPERATIONAL COVER
CELL 5 TOP OF LINER
TEMPORARY SEDIMENT BASIN A
NTS
15C-02
720720
720 720
710710
0 75 0750 76
76076
DENSE BRUSH
DENSE BRUSH
RIP RAP
RIP RAP
RIP RAP
RIP RAP
RIP RAP
RIP RAP
RIP RAP
RIP RAP
RIP RAP
RIP RAP
RIP RAP
RIP RAP
RIP RAP
RIP RAP
RIP RAP
RIP RAP
RIP RAP
C/L DITCH
C/L DITCH
C/L DITCH
C/L DITCH
C/L DITCH
C/L DITCH
RIP RAP
RIP RAP
RIP RAP
RIP RAP
LIMITS OF SURVEY
LIMITS OF SURVEY
LIMITS OF SURVEY
MW-24
OW-103
PZ-76
PZ-6d
PZ-54
PZ-56
PZ-6s
PZ-77
MW-23
MW-25
ACCESS ROAD AND
RAIN COVER
15C-10.dwg
1" = 100' 15C-100 08/2026 ISSUED FOR PROPOSAL
GENERAL NOTES:
1. EXISTING TOPOGRAPHY FROM TWO SEPARATE SURVEYS,FREELAND
& ASSOCIATES AERIAL SURVEY DATED JULY 15, 2021 AND DRONE
SURVEY IN UNIT 1,2 & 4 AREA BY RP &ASSOCIATES DATED JULY 09,
2025.
2. STOCKPILE ALL EXCAVATED SOIL MATERIALS IN MISCELLANEOUS
SOIL STOCKPILE.
BORINGS (SB & B)
METHANE MONITORING (MM)
PIEZOMETER (PZ)
MONITORING AND OBSERVATION
WELL (MW,OW)
PROPOSED EXISTING ABANDONED
MW-P
MM-P
PL
LEGEND
EXISTING 2021 & 2025 MAJOR CONTOURS
EXISTING 2021 & 2025 MINOR CONTOURS
WETLANDS
UNIT AND CELL BASELINES
PROPERTY LINE
EXISTING TREELINE
CONSTRUCTION AREA
MW-A
MM-#
B-# B-#
PZ-#PZ-#
A
B
C
2 3 4 5 6 7 8
D
ISSUE DESCRIPTION
PROJECT MANAGER
PROJECT NUMBER
0 1" 2" FILENAME
SCALE
SHEET
DATE
UNIT 4 CELL 5 LINER
Greenville County South Carolina10174879
P. WESTMORELAND, P.E.
HDR Engineering Inc.
440 S. Church St. Suite 1200 Charlotte, NC 28202-2075 704.338.6700 of the Carolinas
PROJECT ENGINEER
DRAWN BY
CELL 1
17.0 ACRES
CELL 2
8.6 ACRES
CELL 3
8.5 ACRES
CELL 4
10.3 ACRES
PROPOSED CELL 5
8.2 ACRES
ACTIVE UNIT 4 MSW
MISC. SOIL STOCKPILE
1" = 5'
ACCESS ROAD1
CONSTRUCTION
BASELINE
2.0'
2.
0'
EXISTING RAIN COVER
EXISTING
RAIN COVER
BALLAST
17'
20'
EXISTING
20' WIDE
ACCESS ROAD
RAIN COVER
RAIN COVER
File details come from the government source that posted it. Updated .