MSW_Unit_4_Cell_5_Addendum_01_-_00_42_13_-_PROPOSAL_FORM_IFP.pdf
PDF 95 KB Posted
- Solicitation number
- RFP #27008
- Issued by
- Greenville County, South Carolina
About this file
This is an Addendum 01 to the Proposal Form for Unit 4 Cell 5 Liner Construction at Twin Chimneys Landfill, submitted to Greenville County, South Carolina. The project encompasses construction of an 8.6-acre municipal solid waste cell liner system requiring excavation (11,000 cubic yards), structural fill (2,000 cubic yards), compacted soil liner (26,500 cubic yards), geosynthetic clay liner (GCL), 60-mil HDPE geomembrane, geocomposite drainage layer, leachate collection piping in multiple sizes (5-inch through 22-inch diameters totaling 2,775 linear feet), leachate column stone (1,840 cubic yards), separator geotextile (5,800 square yards), operational cover (26,500 cubic yards), seeding (10 acres), termination berm, temporary stormwater drainage, sediment basin decommissioning, rain cover (4.6 acres), and access road (6,000 cubic yards). Proposals are due August 21, 2026, with a non-mandatory pre-proposal meeting scheduled for August 5, 2026. The County anticipates award on September 4, 2026, with contract negotiations occurring September 4-18 and Notice to Proceed expected September 18, 2026. Substantial Completion is required within 180 calendar days from Notice to Proceed, with Final Completion within 210 calendar days, subject to liquidated damages of $1,000 per day for Substantial Completion delays and $500 per day for Final Completion delays.
Pricing is structured as a combination of lump sum and unit price line items, with contractors responsible for independent quantity verification and prohibited from claiming compensation for deviations between estimated and actual quantities on lump sum items. Unit prices must be consistent with typical industry norms and may be challenged as non-responsive if they appear unreasonable. Greenville County will procure the GCL, 60-mil HDPE geomembrane, and geocomposite drainage material separately; contractors must furnish all remaining materials and are responsible for construction quality control testing and surveying services. Contractors must obtain on-site clay material from the existing Clay Stockpile and source off-site protective cover soil and stone from accessible borrow pits maintained throughout the construction schedule. A 5 percent bid bond and performance and payment bond equal to the total bid price (due within fifteen working days of award) are required. Insurance requirements include $1,000,000 per occurrence general liability and automobile liability coverage and statutory workers' compensation. The County retains 10 percent from all monthly invoices until satisfactory completion. A fuel price adjustment clause applies to selected line items, with adjustments triggered at 1.10 (upward) and 0.90 (downward) ratios using SCDOT monthly fuel price indices.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
HDR Project No. 10404585 Greenville County July 2026 Twin Chimneys MSW Unit 4 Cell 5 Landfill Liner Issued for Proposals
PROPOSAL FORM
00 42 13 - 1 Addendum 01
SECTION 00 42 13
PROPOSAL FORM
PROJECT IDENTIFICATION: Twin Chimneys Landfill MSW Unit 4 Cell 5 Liner Construction
THIS PROPOSAL IS SUBMITTED TO: Mr. Robert Brewer, Director, Procurement Services Division, Greenville County, hereinafter referred to as OWNER.
1. PROPOSAL PRICE
A. The Base Proposal Schedule in the following section outlines all major components of the Work required to complete the project as specified. The Base Proposal Total indicated in numbers and in words at the end of the Base Proposal Schedule, shall be used for determination of the successful Proposer.
B. The Proposer is directed to Base Proposal Schedule and Measurement and Basis for Payment for a narrative description of each item in the Base Proposal Schedule.
C. The quantities outlined below represent an approximation as estimated by the Engineer. All quantities depicted in the Base Proposal Schedule, represent in-place, constructed quantities (as constructed in the proposed Work). The Proposer is responsible for verifying quantities for bidding. Engineer’s estimated quantities are provided for informational purposes only and are not to be relied upon as the sole basis for the Proposal.
D. Lump sum line items will constitute the total payment for the Work.
E. Unit price items will be measured and payment will be for the actual quantity.
In the event the Owner desires to modify the quantity (reduce or increase) of work for one or more lump sum Proposal Schedule line items during construction, the general basis for establishing the corresponding change in contract price will be to divide the lump sum bid price by the Engineer’s estimated quantity, thereby yielding a unit price by which to modify the line item total price. Other methods for price adjustment may be considered at the Owner’s and Engineer’s discretion.
2. BASE PROPOSAL SCHEDULE
A. PROPOSER will complete the Work in accordance with the Contract Documents for the following prices:
Item
Description
Estimated
Quantity
Units
Payment
Total Cost
1. Bonds, Insurance, and Mobilization 1 LS LS $____________
2. Construction Quality Control 1 LS LS $____________
3. Survey and Control 1 LS LS $____________
4. Excavation 11,000 CY $_________/CY $____________
5. Structural Fill 2,000 CY $_________/CY $____________
6. Subgrade Preparation 8.2 AC LS $____________
7. Compacted Soil Liner 26,500 CY LS $____________
PROPOSAL FORM
00 42 13 - 2 Addendum 01
Item
Description
Estimated
Quantity
Units
Payment
Total Cost
8. Geosynthetic Clay Liner (GCL) 8.2 AC LS $____________
9. 60 mil HDPE Geomembrane Liner 8.2 AC LS $____________
10. Geocomposite Drainage Layer 8.2 AC LS $____________
11. HDPE Leachate Collection Piping
Cleanouts
22” Perforated HDPE Pipe
20” Perforated HDPE Pipe
18” Perforated HDPE Pipe
10” Perforated HDPE Pipe
8” perforated HDPE pipe
EA
LF
LF
LF
LS
LS
LS
12. Leachate Column Stone 1,840 CY LS $____________
13. Separator Geotextile 5,800 SY LS $____________
14. Operational Cover 26,500 CY LS $____________
15. Seeding 10 AC $_________/AC $____________
16. Termination Berm 305 LF LS $____________
17. Temporary Stormwater Drain
17a. Geoxtextile 210 SY $_________/SY $____________
17b. Rip Rap (off site) 140 TON $________/TON $____________
17c. Stone (on site) 90 CY $_________/CY $____________
17d. Storm Drain Pipe 1,125 LF $_________/LF $____________
18.
Temporary Sediment Basin A Decommissioning 1 EA LS $___________
19. Rain Cover 4.6 AC $_________/AC $____________
20. Access Road 6,000 CY $_________/CY $____________
TOTAL BASE PROPOSAL PRICE IN NUMBERS $
PROPOSAL FORM
00 42 13 - 3 Addendum 01
IN WORDS
3. MEASUREMENT AND BASIS FOR PAYMENT
The line items below provide further description of the Work listed in the Proposal Schedule. Some of the line items include approximate quantities as estimated by the ENGINEER. The CONTRACTOR shall not rely on the quantities given, but shall instead estimate all quantities independently as required to complete the Proposal. The price associated with each Lump Sum item shall be the full compensation paid for the Work described, regardless of the ENGINEER’s or CONTRACTOR’s estimated quantity. For Lump Sum items, no claim shall be made by the CONTRACTOR for deviations between the CONTRACTOR's estimated quantity and the actual quantity required to complete the Work described.
A. Base Proposal Schedule:
1. BONDS, INSURANCE, AND MOBILIZATION: This Work shall consist of securing the appropriate bonds and insurance policies for the Project, and performance of preparatory construction operations, including the movement of personnel and equipment to the Project site, safety equipment and other facilities to begin work on a substantial phase of the Contract. Payment for this item will be made on a Lump Sum basis, wherein no measurement will be made. The Lump Sum price proposed shall be full compensation for performing the Work specified and the furnishing of all materials, labor, tools, equipment, and incidentals necessary to mobilize and subsequently demobilize.
2. CONSTRUCTION QUALITY CONTROL: This Work shall consist of all soils and material testing work required by the Contract Documents. This includes the testing of structural fill, installed soil liner, leachate collection stone, operational cover material, geomembranes, geocomposites, concrete (leachate collection pipe anchor blocks) and other materials as defined in the Specifications. The lump sum proposed shall be full compensation for performing the testing work required. Payment for this item shall be made on a lump sum basis.
3. SURVEY AND CONTROL: This Work shall consist of all survey and control work required by the Contract Documents. This includes establishment of appropriate local site benchmarks, baseline surveys, location of utilities, stakeout of elevation and positional information required to complete the construction, and obtaining all survey information required to compile Record (As-Built) Drawings as required by the Contract Documents.
The lump sum proposed shall be full compensation for performing the surveying work required. Payment for this item shall be made on a lump sum basis.
4. EXCAVATION: This Work shall consist of furnishing all labor, materials, equipment, and appurtenances necessary to excavate material within Cell 5 to achieve subgrade, haul and stockpile in the Miscellaneous Soil Stockpile indicated on Drawing 15C-10. Payment shall be made on a unit price basis with quantities measured by comparison of surveys.
5. STRUCTURAL FILL: This Work shall consist of furnishing all necessary materials, equipment, labor, and appurtenances necessary to place structural fill in Cell 5 from either the on-site Clay Stockpile or the Miscellaneous Soil Stockpile. Testing will be paid under the Construction Quality Control item. Payment shall be made on a unit price basis with quantities measured by comparison of surveys.
PROPOSAL FORM
00 42 13 - 4 Addendum 01
6. SUBGRADE PREPARATION: The County has a separate construction contract to remove the overburden. The remaining excavation is part of the Excavation line item. This Line item shall consist of furnishing all necessary materials, equipment, labor, and appurtenances necessary to fine grade to the subgrade shown in the drawings and prepare the subgrade for the compacted soil liner. Overburden resulting from fine grading is hauled to be stockpiled in the Miscellaneous Soil Stockpile indicated on Drawing 15C-10. This item also includes protection and maintenance of the subgrade. Payment will be made on a lump sum basis wherein no measurement will be made. After subgrade preparation is complete, an as-built survey of the subgrade will be required prior to installing the compacted soil liner. The cost for the survey shall be in the Survey and Control line item.
7. COMPACTED SOIL LINER: This Work shall consist of furnishing all equipment, materials, labor, and appurtenances necessary to complete the soil liner installation including (Borrow Source Characterization Study of the on-site Clay Stockpile per Specification 31 38 10, prior to installation), completion of all aspects of the test strip, furnishing and installing the soil liner component, in lifts as detailed in the Contract Documents. Material shall be obtained from the on-site Clay Stockpile and shall be placed in the Work. Payment will be on a lump sum basis, wherein no measurement will be made. After Soil Liner is complete, an as-built survey will be required to confirm the minimum thickness and grade prior to installing the Geosynthetic Clay Liner (GCL). The cost for the survey shall be the Survey and Control line item.
8. GEOSYNTHETIC CLAY LINER (GCL): The Owner has obtained the material for this project. This Work shall consist of furnishing all equipment, materials, labor, and appurtenances necessary to install the GCL. This Work shall include protection, deployment placement, connections, and testing involving installation of the GCL. Payment will be on a lump sum basis, wherein no measurement will be made.
9. 60-mil HDPE GEOMEMBRANE LINER: The Owner has obtained the material for this project. This Work shall consist of furnishing all equipment, materials, labor, and appurtenances necessary to install the HDPE geomembrane above the GCL. This Work shall include protection, deployment, placement, Construction Quality Control (CQC) testing, cleaning, patching, and seaming of geomembrane components. Payment will be on a lump sum basis, wherein no measurement will be made.
10. GEOCOMPOSITE DRAINAGE LAYER: The Owner has obtained the material for this project. This Work shall consist of furnishing all equipment, materials, labor, and appurtenances necessary to install the geocomposite drainage layer above the 60 mil HDPE geomembrane component of the liner system. This Work shall include protection, deployment, cleaning, securing, seaming, repairing, and testing of the geocomposite layer.
Payment will be on a lump sum basis, wherein no measurement will be made.
11. HDPE LEACHATE COLLECTION PIPING: This Work shall consist of furnishing all equipment, materials, labor, and appurtenances necessary to install the leachate collection piping and cleanouts, including providing the perforated pipe, reducers, field welding (butt-fusion) the pipe segments, installation of caps on unconnected ends, placement of collection pipes, preparation of fabrication drawings, shop fabricated fittings, placement of bedding, backfilling, cleanout anchor blocks, cleaning, video and dewatering. This Work includes cleaning HDPE leachate piping as necessary and supplying video documentation to demonstrate it was properly installed and clean. See Section 40 05 33. Payment will be on a lump sum basis, wherein no measurement will be made.
12. LEACHATE COLUMN STONE: This Work shall consist of furnishing all equipment, materials, labor, and appurtenances necessary, including documentation of compliance with the Specifications, production, delivery, stockpiling, testing and placing the stone material.
This item includes all stone placed in the leachate columns. Payment will be on a lump sum basis, wherein no measurement will be made.
13. SEPARATOR GEOTEXTILE: This Work shall consist of furnishing all equipment, materials, labor, and appurtenances necessary to install the nonwoven geotextile material around the leachate collection stone. This Work shall include delivery, stockpiling, inventory, protecting, PROPOSAL FORM
00 42 13 - 5 Addendum 01 placing, and testing of the geotextile layer in accordance with the Specifications and Drawings. Payment will be on a lump sum basis, wherein no measurement will be made.
14. OPERATIONAL COVER: This Work shall consist of furnishing all equipment, materials, labor, and appurtenances necessary to complete operational cover installation including identification and testing, furnishing and installing the operational cover layer. Material shall be obtained from an off-site source. Payment will be on a lump sum basis, wherein no measurement will be made. Contractor must provide borrow source name and location with proposal. Borrow sources must be accessible to contractor at all times to avoid delays in contract schedule. If borrow source is not accessible at all times, contractor to make provisions to stockpile material on the project site to avoid periods when the borrow site is inaccessible. After the Operational Cover is complete, an as-built survey will be required. The cost for the survey shall be the Survey and Control line item.
15. SEEDING: This Work consists of furnishing all equipment, materials, labor, and appurtenances to provide seeding to those areas which have been disturbed by the CONTRACTOR (outside of Cell 5) and/or require repair. All areas to be seeded are subject to approval by Owner and Engineer. The Owner may elect to approve any portion of the area or none. Payment will be on a unit price basis, wherein measurement will be made by plan quantity.
16. TERMINATION BERM: This Work consists of furnishing all equipment, materials, labor, and appurtenances to provide material and installation of the berm along the west side of Cell 5 as shown on Sheet 15C-08 Details 4 and 6. This item includes the soil (same as the operational cover soil) and the rain cover. Payment will be on a lump sum basis, wherein no measurement will be made.
17. TEMPORARY STORMWATER DRAIN: This Work consists of furnishing all equipment, materials, labor, and appurtenances to provide material and installation of the temporary stormwater drain on the interior slope of Cell 5 as shown on Sheet 15C-08 Detail 10.
a. This item is for the geotextile under the rip rap. Payment will be on a unit price basis, wherein measurement will be made.
b. This item is for Class A rip rap from an off-site source to be installed at the inlet of the pipe. Payment will be on a unit price basis, wherein measurement will be made.
c. This item may be used in lieu of the Class A rip rap. This item is for stone from the on-site Rock Stockpile shown on Drawing 15G-01 to be installed at the inlet of the pipe.
The stone used from the Rock Stockpile will need to be similar size as Class A rip rap.
Payment will be on a unit price basis, wherein measurement will be made.
d. This item is for the pipe and includes connection to the existing pipe and installation of the pipe. Payment will be on a unit price basis, wherein measurement will be made.
18. TEMPORARY SEDIMENT BASIN A DECOMISSIONING: This Work shall consist of furnishing all necessary materials, equipment, labor, and appurtenances necessary to remove and salvage the skimmer and riser followed by removing a portion of the barrel then grouting the barrel with flowable fill. Payment for this item shall be made on a lump sum basis.
19. GEOSYNTHETIC RAIN COVER: This Work shall consist of furnishing all equipment, materials, labor, and appurtenances necessary to complete the installation of the rain cover on the Cell 5 footprint indicated on Sheet 15C-06, including furnishing specified materials, documentation, deployment, protection, seaming, patching and ballasting. Payment will be on a unit price basis, wherein measurement will be made.
20. ACCESS ROAD: This Work shall consist of furnishing all necessary materials, equipment, labor, and appurtenances necessary to install the soil access road shown on Drawing 15C-
10. Soil for the access road can be obtained from the on-site Miscellaneous Soil Stockpile.
Payment will be on a unit price basis, wherein measurement will be made.
PROPOSAL FORM
00 42 13 - 6 Addendum 01
4. UNIT PRICE DEVIATIONS
The PROPOSER is responsible for providing Unit Prices consistent with typical industry norms for the Work described. Unit Prices which appear inconsistent with typical prices for similar Work shall be justified by the PROPOSER at the request of the ENGINEER. Providing Unit Prices which do not reasonable reflect the Work described, either high or low, which are not justified satisfactorily to the ENGINEER, may deem the PROPOSER non-responsive and invalidate their Proposal.
5. COMPLETION
PROPOSER agrees that the Work will be substantially completed and ready for final payment in accordance with the General Conditions.
PROPOSER accepts the provisions of the Agreement as to liquidated damages in the event of failure to complete the Work within the times specified in the Agreement.
6. ATTACHED DOCUMENTS
Required Proposal Security in the form of _______________________.
7. ADDRESS FOR COMMUNICATIONS
Communications concerning this Proposal shall be addressed to
Contact Name: ____________________________________________
Contact Address: _____________________________________________
Contact Email address: _________________________________________
Contact Telephone Number: _____________________________________
SUBMITTED on ________________________________________, 20___.
If PROPOSER is:
An Individual
By_____________________________________________________ (SEAL) (Individual's name)
Doing business as: _____________________________________________________
Business address:
PROPOSAL FORM
00 42 13 - 7 Addendum 01
A Partnership
By_____________________________________________________(SEAL) (Firm name)
(General partner)
Business address:
A Corporation
By_____________________________________________________ (SEAL) (Corporation name)
(State of incorporation)
By_____________________________________________________ (SEAL) (Name of person authorized to sign)
(Title) (Corporate Seal)
Attest _________________________________________________________
(Secretary)
Business address: ________________________________
Date of Qualification to do business is _____________________.
A Joint Venture
By_____________________________________________________ (SEAL) (Name)
(Address)
By_____________________________________________________ (SEAL) (Name)
(Address)
PROPOSAL FORM
00 42 13 - 8 Addendum 01
NOTE: Each joint venture must sign. The manner of signing for each individual, partnership and corporation that is a party to the joint venture should be in the manner indicated above.
END OF SECTION