MST Attachment F - Form of Final Contract.pdf
PDF 153 KB Posted
- Attached to
- PennDOT Mainframe Services
- Solicitation number
- 3525R03
- Issued by
- Pennsylvania
About this file
This is a Form of Final Contract template issued by the Pennsylvania Department of Transportation (PennDOT) for mainframe services, as outlined in RFP 3525R03. The contract establishes the agreement between the Commonwealth of Pennsylvania, acting through PennDOT, and the selected contractor for the provision of IBM-compatible mainframe services. These services encompass hosting, management, infrastructure support, disaster recovery, and security compliance for approximately 100 applications, including critical operational systems. The document serves as the standard form template and does not specify explicit response dates, due dates, site visits, bidder conferences, award dates, or contract term details, as these elements would be populated in the final executed contract based on the RFP requirements and negotiated terms between the parties.
The contract establishes a hierarchical order of precedence for governing documents, with the executed contract form at the top level, followed by contract terms and conditions, final negotiated technical proposal documents, cost submittals, and the original RFP with all appendices and addenda. The contractor is required to meet and maintain commitments to Small Diverse Businesses (SDB), Veteran Business Enterprises (VBE), and Diverse Businesses (DB) as specified in their respective submittals, with quarterly utilization reporting requirements through the Department of General Services' PRiSM system within ten business days after each calendar quarter ends. The contractor must also submit monthly Diverse Business Status Reports (Form EO-402) within the first five business days of each month documenting all DB payments. Pricing terms, funding sources, and specific contract duration are not detailed in this template document and would be established through the final negotiated cost submittal and RFP requirements.
View the file
Other files
Show all 35
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Pennsylvania Department of Transportation (PennDOT)
Mainframe Services
MST Attachment F
Form of Final Contract
RFP 3525R03
OGC Standard Form – Revised 2/2/2024 Contract # ________________
CONTRACT FOR ________________ SERVICES
This contract for ______ services is between the Commonwealth of Pennsylvania (“Commonwealth”), acting through the ____________________ (“Agency”), with its principal offices located at ___________________________________, and __________________ (“Contractor”), with its principal offices located at __________________________.
The Agency issued a Request for Proposals for the provision of ________________, RFP No. _______________ (“RFP”), and the Contractor submitted a proposal in response to the RFP.
The Agency determined that the Contractor’s proposal was the most advantageous to the Commonwealth after taking into consideration all of the evaluation factors set forth in the RFP and selected Contractor for contract negotiations.
The parties, intending to be legally bound, agree as follows:
1. Order of Precedence. This contract is comprised of the following documents, which are listed in the order of precedence:
a. this contract;
b. the Contract Terms and Conditions, set forth in Exhibit A;
c. the Final Negotiated Technical Proposal Documents and Clarifications set forth in
Exhibit B;
d. the Contractor’s Cost Submittal1 set forth in Exhibit C;
e. the Contractor’s Small Diverse Business (SDB) Submittal2 set forth in Exhibit D;
f. the Contractor’s Veteran Business Enterprise (VBE) Submittal3, set forth in Exhibit
E;
g. the Contractor’s Diverse Business (DB) Submittal, set forth in Exhibit F;
h. the RFP, including all of the referenced Appendices and all Addenda to the RFP, set forth in Exhibit G; and
i. the Contractor’s Technical Submittal, set forth in Exhibit H.
1 Replace with BAFO Cost Submittal or Final Negotiated Cost Submittal, if applicable.
2 Replace with BAFO Small Diverse Business or Final Negotiated Small Diverse Business Submittal, if applicable.
3 Replace with BAFO Veteran Business Enterprise Submittal or Final Negotiated Veteran Business Enterprise Submittal, if applicable.
2. Services. The Contractor shall provide the services set forth in the RFP, the Final Negotiated Technical Proposal and Clarifications, if any, and the Contractor’s Technical Submittal (“Services”).
3. Cost. The Contractor shall provide the Services for the price set forth in the Cost Submittal.
4. Small Diverse Business (SDB) Requirements.
a. Contractor Commitments. The Contractor shall meet and maintain the commitments to the small diverse businesses set forth in its Small Diverse Business Submittal4.
b. Proposed Changes. The Contractor shall submit any proposed change to its small diverse business commitment to the Department of General Services’ Bureau of Diversity Inclusion and Small Business Opportunities (“BDISBO”). BDISBO shall review the proposal and make a recommendation to the Agency’s Contracting Officer.
c. Reporting Requirements. The Contractor shall complete and submit quarterly utilization reports through BDISBO’s PRiSM system within ten business days after the end of each calendar quarter.
5. Veteran Business Enterprise (VBE) Requirements.
commitments to the veteran business enterprises set forth in its Veteran Business Enterprise Submittal5.
b. Proposed Changes. The Contractor shall submit any proposed change to its veteran business enterprise commitment to BDISBO. BDISBO shall review the proposal and make a recommendation to the Agency’s Contracting Officer.
c. Reporting Requirements. The Contractor shall complete and submit quarterly utilization report through BDISBO’s PRiSM system within ten business days after the end of each calendar quarter.
6. Diverse Business (DB) Requirements:
commitments to Diverse Businesses made in its Diverse Business (DB) Participation Submittal.
4 Replace with BAFO Small Diverse Business Submittal or Final Negotiated Small Diverse Business and Submittal, if applicable.
5 Replace with BAFO Veteran Business Enterprise Submittal or Final Negotiated Veteran Business Enterprise Submittal, if applicable.
b. Proposed Changes. The Contractor shall submit any proposed change to a Diverse
Business commitment to the Department of Transportation, Bureau of Workforce and Business Opportunity (BWBO), which will make a recommendation as to a course of action to the Contracting Officer.
c. Reporting Requirements. The Contractor shall document all Diverse Business payments via the Monthly DB Status Report, EO-402. The form is to be submitted to pd-non-ecms-db@pa.gov within the first five (5) business days of each calendar month, for the proceeding month’s activity, the Contract is in effect.
[SIGNATURE PAGE FOLLOWS.]6
6 Remove if the blank space at the end of the statement of agreement is not significant. Remove if all signature lines can fit on this page. Remove if this sentence is the only thing on the page.
The parties, through their authorized representatives, have signed this contract on the dates indicated below.
[INSERT CONTRACTOR NAME]
Signature Date
Printed Name
Title
Federal I.D. Number
COMMONWEALTH OF PENNSYLVANIA
[INSERT AGENCY NAME]
<<To be signed electronically.>> [Agency Head/Designee] Date [Title]
APPROVED AS TO FORM AND LEGALITY:
<<To be obtained electronically.>> <<To be obtained electronically.>>
Office of Chief Counsel Date Office of General Counsel Date
<<To be obtained electronically.>> Office of Attorney General Date
APPROVED:
<<To be obtained electronically.>> Comptroller Operations Date
CONTRACT FOR ________________ SERVICES
File details come from the government source that posted it. Updated .