About this file

This Request for Quotation (RFQ #25/26-091) is issued by the Clay County Board of County Commissioners for the replacement of shade structures at a public park facility in Florida. The solicitation requests quotes from qualified contractors for two thirty-foot tri-sail shade net replacements, including new cable, hardware, and installation at Moody Avenue Park located at 3510 Moody Avenue, Orange Park, Florida 32065. The RFQ was released on July 13, 2026, with a bid deadline of July 28, 2026, at 4:00 p.m. Responses must be submitted electronically through the specified procurement portal. No site visit or bidder's conference is mentioned in the document. The contract term requires the awarded contractor to have the replacement shade sails fully installed no later than fourteen calendar days after material delivery. The successful contractor must maintain a two-year warranty on all workmanship and materials from the completion date.

The project is funded in whole or in part through FEMA Public Assistance Agreement No. 2024/2025-76 related to Hurricane Helene disaster recovery efforts, administered by the Florida Division of Emergency Management. Contractors must comply with all applicable federal laws, regulations, and the Uniform Guidance (2 CFR Part 200). Pricing proposals must include line items for the tri-sail shade net replacements, new cabling and hardware, freight, installation, and permits. The contractor must be licensed, carry comprehensive insurance coverage including commercial general liability of at least $1,000,000 per occurrence, and provide proof of workers' compensation insurance. Contractors must demonstrate a minimum of five years of experience performing similar work and are responsible for obtaining all required permits, paying associated fees, site cleanup, and compliance with OSHA standards and local regulations.

View the file

Other files

File Type Posted
Moody_Park_Shade_Sail_Replacement_(Addendum_#1_Revision).pdf PDF
Existing_Poles_(Spacing).jpeg JPEG file
Existing_Poles_(Lower_Mounting_Point).jpeg JPEG file
Existing_Poles_(Higher_Mounting_Point).jpeg JPEG file
DR4828-825369_FEMA_SOW.pdf PDF
2024-2025-76_FDEM_Hurricane_Helene_.pdf PDF
W-9_(2024).pdf PDF
EFT_FORM.pdf PDF
Certificate_of_final_payment.pdf PDF
Performance_&_Payment_Bond.doc DOC document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REQUEST FOR QUOTATION

25/26-091

MOODY PARK SHADE SAIL REPLACEMENT

Clay County

477 Houston Street

Green Cove Springs, FL 32043

RELEASE DATE: July 13, 2026

LAST DATE FOR INQUIRIES: undefined, undefined

BID DUE: July 28, 2026, 4:00 pm

RESPONSES MUST BE SUBMITTED ELECTRONICALLY TO:

https://secure.procurenow.com/portal/claycounty https://secure.procurenow.com/portal/%7bproject.government.code%7d

Clay County

REQUEST FOR QUOTATION

Moody Park Shade Sail Replacement

I. Introduction II. Scope of Work

III. Pricing Proposal IV. Supplier Questionnaire

Attachments:

A - 2024-2025-76 FDEM Hurricane Helene

B - Certificate of final payment

C - W-9 (2024)

D - EFT FORM

Request For Quotation #25/26-091 Title: Moody Park Shade Sail Replacement

1. Introduction

1.1. Summary

Clay County Board of County Commissioners is requesting quotes from qualified Contractors for two (2) thirty foot (30') Tri-Sail Shade Net Replacements, including new cable, hardware, and installation for

Moody Avenue Park located at 3510 Moody Avenue, Orange Park, FL 32065.

1.2. Contact Information

If you need immediate assistance, at any point during the solicitation process, please email the

Purchasing Department at: Purchasing@Claycountygov.com in addition to the Purchasing Department

Staff Member listed below.

Danielle Connaughton

Procurement Analyst

477 Houston Street

Green Cove Springs, FL 32043

Email: danielle.connaughton@claycountygov.com

Phone: (904) 793-5187

Department:

Parks and Recreation

Department Head:

Justin Pierce

Parks and Recreation Director

1.3. Timeline

Request Date July 13, 2026

Quotation Deadline July 28, 2026, 4:00pm mailto:Purchasing@Claycountygov.com mailto:danielle.connaughton@claycountygov.com tel:(904)793-5187

2. Scope of Work

2.1. Scope of Work

Clay County Board of County Commissioners is requesting quotes from qualified Contractors for two (2) thirty foot (30') Tri-Sail Shade Net Replacements, including new cable, hardware, and installation for

Moody Avenue Park located at 3510 Moody Avenue, Orange Park, FL 32065.

2.2. Grant Funded

This Project is being supported, in whole or in part, by Agreement No. 2024/2025-76 between Clay

County and the Federal Emergency Management Agency (FEMA)

Hurricane Helene caused significant damage throughout Clay County, impacting public infrastructure and essential community facilities. Through this FEMA Public Assistance grant agreement, administered by the Florida Division of Emergency Management, the Clay County Board of County Commissioners will receive federal funding to support disaster response, recovery, and eligible mitigation efforts. This funding will assist the County in restoring damaged public facilities and infrastructure to their pre-disaster condition in accordance with applicable federal and state requirements.

The awarded Contractor must comply with all Federal laws, rules, regulations, and executive orders applicable to the receipt of funding from the Grant and will be subject to the provisions of the Uniform

Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards (2 CFR part

200) (the Uniform Guidance), including the cost principles and restrictions on general provisions for selected items of cost.

2.3. Contractor and Subcontractor Requirements

1. The Contractor shall be licensed to perform all work listed in the Scope of Work provided.

2. Contractor shall obtain all permits to complete the project in accordance with the contract documents.

3. All work will be performed in accordance with the most applicable state and local regulations.

4. The Contractor shall own or have full access to the appropriate personnel and equipment to complete the project requested.

5. The County reserves the right to approve all subcontractors for this contract. If subcontractors are to be utilized, the subcontractors must possess an active and valid license issued by the Florida

Department of Business and Professional Regulation in the appropriate category. Subcontractors may be added during the contract period only with PRIOR WRITTEN PERMISSION from the County, and only for reasonable cause, as judged by the County. Responsibility for the performance of the contract remains with the main Contractor exclusively.

6. The Contractor and subcontractors may be requested to provide a list of equipment with identification (i.e. serial #, VIN, etc.), personnel with their position (e.g. foreman, laborer, etc.), and percentage of work performed.

7. Contractors must have been in business for a minimum of 5 years doing similar work.

2.4. Site Inspections

It is incumbent upon all Contractors to examine the site and insure that they are aware of all conditions that may affect the contract work. The County will not be responsible for conclusions made by the

Contractor. No claims for additional compensation will be considered on behalf of any Contractor, subcontractor, materials suppliers or others on account of that person’s failure to be fully informed of all requirements of all parts of this Request For Quotes.

2.5. Work Hours

Workdays and hours – Normal work hours of Monday through Friday, 7:30 a.m. to 5:00 p.m. unless approved by the County Project Manager or designee.

Any work performed outside of the normal County business hours will require prior County approval and payment to the County for all expenses incurred by the County may be required.

2.6. Permit & Fees

The Contractor shall comply with all applicable State and local laws, ordinances, codes, and regulations.

The Contractor is required to familiarize themselves with all permits required that pertain to the Scope of Work specified in this Request For Quotes. If a County permit is required, this project is not exempt from permit fees and permit fees must be paid to the County Building Department by the Contractor.

For questions about Clay County permitting please contact:

Clay County Building Department

Phone: (904) 269-6307

Email: permits@claycountygov.com

Website: https://www.claycountygov.com/government/building

All applicable permits, fees, licenses, and final County and municipality inspections are the responsibility of and will be paid for by the Contractor as specified in the plans.

All other permits, assessments, fees, bonds, and other charges as necessary to perform and complete the work of the awarded Contract are the responsibility of and will be paid for by the Contractor, including any related inspection fees. Utility service connection fees and required utility service fees, if any, will be paid for and coordinated by the Contractor. Utility service connection, if any shall be coordinated by the Contractor. Utility service connection fees shall be paid for by the County.

2.7. Clean up & Restoration of Site

Contractor shall remove all debris from site and dispose of the debris appropriately and the Contractors expense.

Contractor shall maintain work site in a safe manner, and daily clear construction debris.

mailto:permits@claycountygov.com https://www.claycountygov.com/government/building

2.8. Workmanship

Where not more specifically described in this document, workmanship shall conform to all of the methods and operations of best standards and accepted practices of the trade or trades involved, and shall include all items of fabrication, construction or installation regularly furnished or required for completion of the services.

2.9. Damage to Public or Private Property

The Contractor is responsible for anything damaged due to the direct result of installation or construction. Remove all debris from site and dispose of appropriately at Contractor expense. If property (public or private) is damaged while Contractor is performing work specified or is removed for the convenience of the work, it shall be repaired or replaced at the expense of the Contractor in a manner acceptable to the County prior to the final acceptance of the work. Contractor will be responsible for applying and securing any permits that may be required to complete such repairs.

Contractor must provide protection necessary to prevent damage to property being repaired or replaced.

If the work site has any pre-existing damage, the Contractor shall notify the County Project Manager in writing. Failure to do so shall obligate the Contractor to make repairs per the above section. Any damage to property (public or private) caused by the action of the Contractor shall be repaired or replaced at the expense of the Contractor to the satisfaction of the County. Failure to restore said property within five (5) working days following notification will result in a deduction from the final payment invoice. All damages which occur as a result of the Contractor's application of materials shall be remedied by the Contractor at no additional cost to the County. Repairs made as a result of damage must be guaranteed for a period of thirty (30) days. Should the replacement be damaged within the thirty (30) day period, the Contractor shall replace the materials continually until the area is re-established.

Should the County have any expenses incurred due to the Contractor not restoring the property/damage within said time, any appropriate labor, material, and/or equipment use or rental to restore damaged property to its original condition will be deducted from the final Invoice prior to a payment being made.

2.10. Compliance with Occupation Safety and Health Act

The Contractor warrants that the product(s) and/or service(s) supplied to Clay County shall conform in all respects to the standards set forth in the Occupational Safety and Health Act (OSHA) of 1970 as amended and the failure to comply will be considered a breach of contract. Clay County shall be held harmless against any unsafe conditions and contractor employee incidents.

Contractor certifies that all material, equipment, services, etc., furnished in this Request For Quotes meets all OSHA requirements for the applicable Sectors. Contractor further certifies that, if the successful Contractor, and the material, equipment, service, etc., delivered or provided is subsequently found to be deficient in any OSHA requirement in effect on date of delivery or service fulfillment date, all costs necessary to bring the material, equipment, service, etc., into compliance with the aforementioned requirements shall be borne by the Contractor. All Personal Protective Equipment used by the Contractor and their employees shall be ANSI certified and meet OSHA standards.

2.11. Unsatisfactory Equipment and/or Services

The County will discuss all instances of unacceptable equipment and/or services with the awarded

Contractor. This shall be immediately rectified by the Contractor at no charge to the County, to include any labor and materials as it may apply.

During this time, the County may suspend service with the Contractor until the problem(s) are corrected or may elect to use another company on an emergency basis. A record of failure to perform or of an unsatisfactory performance may result in supplier debarment.

2.12. Payment

The Contractor may request payment no more than once monthly, based on the amount of work completed. All partial estimates and payments found to be in error shall be subject to correction in the estimates and payments subsequent thereto, and in the final estimate and payment. Payments will be made in accordance with the Florida Local Government Prompt Payment Act.

The amount of such payments shall be the total value of the project work completed to the date of the estimate, based on the quantities and the Contract unit and/or lump sum prices, less an amount retained and less payments previously made. The amount retained shall be determined in accordance with Section 255.078, Florida Statutes.

2.13. Warranty

The Contractor shall provide a warranty for all workmanship and materials for a period of two (2) years unless a longer manufacture warranty/guarantee time is given. Warranty shall begin from the date of

Completion.

2.14. Term

Contractor shall have the replacement shade sail fully installed no later than (14) calendar days after the delivery of the materials.

2.15. Insurance Requirements:

a. Commercial General Liability

Coverage must be afforded under a Commercial General Liability policy with limits not less than:

• $1,000,000 each occurrence and $2,000,000 aggregate for Bodily Injury, Property

Damage, and Personal and Advertising Injury (project specific aggregate may be required for construction projects)

• $1,000,000 each occurrence and $2,000,000 aggregate for Products and Completed

Operations

• $50,000 each occurrence for Damage to Rented Premises

• $5,000 Medical Expenses (any one person)

Commercial and General Liability policy must include coverage for contractual liability and independent contractors.

b. Business Automobile Liability

Coverage must be afforded for all Owned, Hired, Scheduled, and Non-Owned vehicles for Bodily

Injury and Property Damage in an amount not less than $1,000,000 combined single limit each accident. If the Bidder does not own vehicles, the Bidder shall maintain coverage for Hired and

Non-Owned Auto Liability, which may be satisfied by way of endorsement to the Commercial

General Liability policy or separate Business Auto Liability policy.

c. Workers’ Compensation and Employer’s Liability

Any person or entity performing work for or on behalf of the County must provide Workers’

Compensation and Employer’s Liability insurance in limits not less than:

● Workers Compensation Statutory limits

● Employers Liability $100,000 Each Accident

$500,000 Disease Policy

$100,000 Disease-Each Employee

Exceptions and exemptions may be allowed by the County Manager, if they are in accordance with Florida Statutes.

The Contractor waives, and the Contractor shall ensure that its insurance carrier waives, all subrogation rights against the County, its employees, agents, boards, and commissions, for all losses or damages. The County requires the policy to be endorsed with WC 00 03 13 Waiver of our Right to Recover from Others or equivalent.

The Contractor must be in compliance with all applicable State and federal workers’ compensation laws, including the U.S. Longshore Harbor Workers’ Act and the Jones Act, if applicable.

For any Contractor who has exempt status as an individual, the County requires proof of

Workers’ Compensation insurance coverage for that Contractor’s employees, leased employees, volunteers, and any workers performing work.

d. Property Coverage (Builder’s Risk) – Applies to Construction related Projects

Coverage must be afforded in an amount not less than 100% of the total Project value, including soft costs, with a deductible of no more than $25,000 each claim. Named Windstorm

Deductibles, if any, must be disclosed to the County.

Coverage form shall include, but not be limited to:

• All Risk Coverage including Flood and Windstorm with no coinsurance clause

• Waiver of Occupancy Clause Endorsement, which will enable the County to occupy the property/structure under construction/renovation during the activity

• Storage and transport of materials, equipment, supplies of any kind whatsoever to be used on or incidental to the project

• Equipment Breakdown for cold testing of all mechanized, pressurized, or electrical equipment

• LEG2 Coverage or equivalent

For installation of property and/or equipment, Builder’s Risk Installation insurance must be provided to include coverage for materials or equipment stored at the Project site, while in transit, or while stored at a temporary location. Coverage limit must be no less than replacement cost.

The Property Coverage (Builder’s Risk) policy shall insure the interests of the owner, contractor, and subcontractors in the property against all risk of physical loss and damage, and name the

County as a loss payee. Additionally, the County shall be named as an Additional Insured for its interest in the property/structure and for any materials purchased directly by the County. This insurance shall remain in effect until the work is completed and the property has been accepted by the County.

e. Professional Liability and/or Errors and Omissions – Applies to Projects involving

Professional Services

Coverage must be afforded for Wrongful Acts in an amount not less than $1,000,000 each claim and $1,000,000 aggregate.

Insurance must be kept in force until the third anniversary of the expiration or termination of any Contract that may be entered into between the parties.

f. Umbrella/Excess Insurance

If the Contractor’s primary insurance policy/policies do not meet the minimum requirements, the Contractor may provide an Umbrella/Excess insurance policy to comply with the insurance requirements.

Providing and maintaining adequate insurance coverage is a material obligation of the

Contractor. Upon being awarded the Bid and prior to commencement of the Services, the successful Contractor must deliver valid certificates of insurance for the required insurance coverage to the County’s Purchasing Department.

The certificates of insurance for the required coverages, with the exception of Workers’

Compensation, Employer’s Liability, and Professional Liability, shall name “Clay County, a political subdivision of the State of Florida, and The Board of County Commissioners, Clay

County, Florida, its employees, agents, boards and commissions, as their interests may appear” as “Additional Insureds”. The coverage shall contain no special limitation on the scope of protection afforded to the County, its employees, agents, officials, boards, and commissions.

The certificates of insurance shall indicate if coverage is provided under a claims-made or occurrence form. If any coverage is provided on a claimsmade form, the certificates of insurance will show a retroactive date, which should be the same date of the initial Contract or prior. The Contract number, Bid number, event dates, or other identifying reference must be listed on the certificates of insurance.

The Certificate Holder on the certificates of insurance should read as follows: “Clay County

Board of County Commissioners, P.O. Box 1366, Green Cove Springs, FL 32043” or as otherwise designated by the County’s Purchasing Department.

The certificates of insurance shall be provided to the County with a thirty (30) day notice of cancellation; ten (10) days’ notice if cancellation is for nonpayment of premium. In the event that the insurer is unable to accommodate the cancellation notice requirement, it shall be the responsibility of the Contractor to provide the proper notice. Such notification will be in writing by registered mail, return receipt requested, and addressed to the Certificate Holder. In the event the Contract term goes beyond the expiration date of any insurance policy, the

Contractor shall provide the County’s Purchasing Department with an updated certificate of insurance no later than ten (10) days prior to the expiration of the insurance currently in effect.

The County reserves the right to suspend the Contract until this requirement is met. If any required insurance coverage is canceled, terminated, or revoked, the Contractor agrees to immediately suspend its operations until replacement insurance is obtained and verified.

Any exclusions or provisions in the insurance maintained by the Contractor that excludes coverage for work or services contemplated under the Bid shall be deemed unacceptable, a material violation of the County’s Bidding requirements, and shall be considered a breach of any Contract entered into after a Bid Award.

It is the successful Contractor’s responsibility to ensure that all independent and subcontractors comply with the insurance requirements. All coverages for independent and subcontractors shall be subject to all of the requirements stated herein. Any and all deficiencies are the responsibility of the Contractor.

The County Manager may modify the insurance requirements for particular projects and/or

Services.

2.16. Additional Services

If the County and/or awarded Contractor identifies any additional services to be provided by Contractor that are not covered under the Agreement but are beneficial to the County, such additional services shall be mutually negotiated between the County and the Contractor.

3. Pricing Proposal

Line Item Description Quantity Unit of

Measure Unit Cost Total

1 Thirty foot (30') Tri-Sail Shade Net

Replacement (Blue) 2 Lump Sum

2 New Cabling and Hardware 2 Lump Sum

3 Freight 1 Lump Sum

4 Installation 1 Lump Sum

5 Permit 1 Lump Sum

TOTAL

4. Supplier Questionnaire

4.1. Response Acknowledgement *

I acknowledge the following:

I will respond to this solicitation in the manner that is being requested of me.

I am not to embed any documents within the questionnaire, as they may not be accessed / reviewed / evaluated.

When a document is required to be uploaded, it must be in PDF format and unlocked.

☐ Please confirm

*Response required

4.2. Litigation, Investigations, and Disputes Disclosure (A)* Has Contractor (including any parent company, subsidiaries, affiliates, officers, directors, or key personnel) been involved in any litigation, arbitration, or administrative proceedings (past or pending) related to its business operations within the past ten (10) years?

If Yes, please provide a detailed explanation, including:

• Case caption and number

• Jurisdiction (court or administrative body)

• Brief description of the nature of the dispute

• Status or outcome (e.g., pending, settled, dismissed, judgment entered)

• Copies of legal documentation substantiating the information provided above

Important: Failure to fully disclose any relevant information, or any misrepresentation or omission of facts, may result in any remedy deemed to be in the best interest of the County.

☐ Yes

☐ No

*Response required

4.3. Litigation, Investigations, and Disputes Disclosure (B)

If Contractor answered 'Yes' to Litigation, Investigations, and Disputes Disclosure (A), please provide a detailed explanation, including:

• Case caption and number

• Jurisdiction (court or administrative body)

• Brief description of the nature of the dispute

• Status or outcome (e.g., pending, settled, dismissed, judgment entered)

• Copies of legal documentation substantiating the information provided above

Important: Failure to fully disclose any relevant information, or any misrepresentation or omission of facts, may result in any remedy deemed to be in the best interest of the County.

4.4. Legal Name *

Please enter your Company's Legal Name.

*Response required

4.5. Approved Designated Signee*

Please provide the full name, title, and email address of the authorized signee for your company.

*Response required

4.6. Approved Designated Signee*

Please provide the full name, title, and email address of the authorized signee for your company.

*Response required

4.7. Company Primary Contact*

Please provide the following details for your Company's primary contact person:

A. Organization Primary Contact Name:

(First and Last Name)

B. Organization Primary Contact Role:

(Position or Title within the Organization)

C. Organization Primary Contact Phone Number:

(Include Area Code)

D. Organization Primary Contact Email Address:

(Please provide a valid and frequently monitored email address)

*Response required

4.8. Company Remittance Address*

Please provide your Company's remittance address.

The Address should include:

Street Address: This should include the building number, street name, and, if applicable, suite number.

City, State, and ZIP Code: The city and state should be fully spelled out (unless state abbreviations are standard), followed by the ZIP Code.

Example of a Complete Address:

John Doe

1234 Elm Street, Apt 5B

Springfield, IL 62704

*Response required

4.9. W-9*

Please download the W-9 below, complete, and upload.

• W-9_(2024).pdf

*Response required

4.10. EFT Authorization Form

Please download the below documents, complete, and upload.

• EFT_FORM.pdf

4.11. SunBiz Verification*

Please enter your EIN number below.

*Response required

4.12. E-Verify *

Please enter your Company's legal name.

*Response required

4.13. E-Verify *

Please download the below documents, complete, and upload.

• E-Verify_(1).pdf

*Response required

4.14. Conflict of Interest Disclosure: *

County Employee: Please mark yes or no if you work for Clay County as an employee.

☐ Yes

☐ No

*Response required

4.15. Conflict of Interest Disclosure: *

An outside personal economic relationship which affords present or future financial benefits to an employee, his family or to individuals with whom he has business or financial ties may be considered a conflict of interest requiring evaluation by the County Manager.

This certifies that neither my family nor myself are employees of the County and will benefit financially by doing business with Clay County.

https://government-project.s3.us-west-2.amazonaws.com/26612/3c9ba02e-cf5c-4b5b-bab9-8e681a7ee333_W-9_%282024%29.pdf?X-Amz-Algorithm=AWS4-HMAC-SHA256&X-Amz-Content-Sha256=UNSIGNED-PAYLOAD&X-Amz-Credential=ASIA47RIURE4BXJVR3FP%2F20260713%2Fus-west-2%2Fs3%2Faws4_request&X-Amz-Date=20260713T190043Z&X-Amz-Expires=72000&X-Amz-Security-Token=IQoJb3JpZ2luX2VjEDsaCXVzLXdlc3QtMiJHMEUCIQDhyMKGnQausIeOeDNE8OmhFw6bFI7qgriZ%2BAJcm92BogIgf052Iug8Gai4UksDh3Kykdww4ouKRtXHpIypGUPuP5cqjAUIBBACGgw4OTIzNjQ2ODc2NzIiDB64QeBOK7RuF4OF7SrpBN51%2ByfCic3KUGG4HUbDwf%2BUwzKRrfZzHYNk6M0kjOGsMYhvx9b48j11xLAj1y0Is9mJkOe%2FZMVw37ADn7RFOmQz2kZZ%2BmzjOI%2Bqc1i8ERDSXIwfsV27GZp7EqY7gghH2zYu2fBXx1xpFIjTwCdX6qfkCTZR5Xj0mfUqRTGVqYWFJZLinRofkp%2FaaY7849sVxTWBvUqxvcglGQ%2BftxBFlC66V3uhQiCg07rGougmJzUa2RMV6lJTMxKiP%2BRkqNm1hFpI1UGYN75AyEyQ35HpJY9MngGWTBDOqdO0AbViQGHTeAH1EFXq7jlDuOolAajtUQFCtwXHy2GZK%2BJKmByLaTalLAeYDSNCG3kCodKWCO3fOJqFzPF73vapF%2BMTE5gyaTggs0KdPh4eHxCO8GFm0WXfMlTApsdZxxCiSDik6huGyhV0OsrYwN%2BVlECT5ZlXxBApSo8I0DKEisdnhrYQmtdHiJZxPYugIuYRbjyHL0rhHqkXTzuazRKrLjihdUD%2BHWQxslHmQBz2DvbSiQSVZdZ0rgtW8CPD%2BtigG4PWAcBfi8xIuSe6tBcPNJHOR0Hg4zHxCj7xSc4XN5ognuTg%2F5AMFKD2uUe1yoQ1mGX%2Fiymt1rWRNlzDdeM6Ojx%2FQBpzaO3454zjZWlNe%2BObKgJTuGXoMybxPtcdW5OVqd9AOWrACHV6hz9PKVO61dZQ1mRqC5i6BPvO1kVtJ4pE8Ib8DUo%2Fn2%2FKdIYh3DtlP5TlCkt4oOvKE%2BqngRTCpCmaZCfsHrpgKMHI4kFXGjaYaSfryaCnLf307qgk%2BYLleGdKfkAXKAxxANLSuqceMIPq1NIGOpkBKbRO23gt7dGtS%2BkU4qS2g%2F0%2BmCvgXYOJcdcgWRH%2BLu0x0PBAv7rp8Ojik0LHY0rnnx9aY%2BvtQ0T8egT1XkiiA4uXKy9MX0zG8BWhhHm224wTgG%2FBGWuPVssm1V7%2B0AdKdDX9QNKfXpcIN7BQW1u%2BpCjZc6ME%2BVclvl%2BrGEEG2WzS6%2FRrZxar0CDPvNL4Smmsx%2F%2F%2BaAAalTvR&X-Amz-Signature=83c4e626c65b4cfff70e7a676db24731efd7aff737a7057a1b5c7f3958f87c30&X-Amz-SignedHeaders=host&response-content-disposition=attachment%3B%20filename%3D%22W-9_%282024%29.pdf%22&x-id=GetObject https://government-project.s3.us-west-2.amazonaws.com/26612/067f458f-ec41-461d-a7f5-ab49431f3f07_EFT_FORM.pdf?X-Amz-Algorithm=AWS4-HMAC-SHA256&X-Amz-Content-Sha256=UNSIGNED-PAYLOAD&X-Amz-Credential=ASIA47RIURE4BXJVR3FP%2F20260713%2Fus-west-2%2Fs3%2Faws4_request&X-Amz-Date=20260713T190043Z&X-Amz-Expires=72000&X-Amz-Security-Token=IQoJb3JpZ2luX2VjEDsaCXVzLXdlc3QtMiJHMEUCIQDhyMKGnQausIeOeDNE8OmhFw6bFI7qgriZ%2BAJcm92BogIgf052Iug8Gai4UksDh3Kykdww4ouKRtXHpIypGUPuP5cqjAUIBBACGgw4OTIzNjQ2ODc2NzIiDB64QeBOK7RuF4OF7SrpBN51%2ByfCic3KUGG4HUbDwf%2BUwzKRrfZzHYNk6M0kjOGsMYhvx9b48j11xLAj1y0Is9mJkOe%2FZMVw37ADn7RFOmQz2kZZ%2BmzjOI%2Bqc1i8ERDSXIwfsV27GZp7EqY7gghH2zYu2fBXx1xpFIjTwCdX6qfkCTZR5Xj0mfUqRTGVqYWFJZLinRofkp%2FaaY7849sVxTWBvUqxvcglGQ%2BftxBFlC66V3uhQiCg07rGougmJzUa2RMV6lJTMxKiP%2BRkqNm1hFpI1UGYN75AyEyQ35HpJY9MngGWTBDOqdO0AbViQGHTeAH1EFXq7jlDuOolAajtUQFCtwXHy2GZK%2BJKmByLaTalLAeYDSNCG3kCodKWCO3fOJqFzPF73vapF%2BMTE5gyaTggs0KdPh4eHxCO8GFm0WXfMlTApsdZxxCiSDik6huGyhV0OsrYwN%2BVlECT5ZlXxBApSo8I0DKEisdnhrYQmtdHiJZxPYugIuYRbjyHL0rhHqkXTzuazRKrLjihdUD%2BHWQxslHmQBz2DvbSiQSVZdZ0rgtW8CPD%2BtigG4PWAcBfi8xIuSe6tBcPNJHOR0Hg4zHxCj7xSc4XN5ognuTg%2F5AMFKD2uUe1yoQ1mGX%2Fiymt1rWRNlzDdeM6Ojx%2FQBpzaO3454zjZWlNe%2BObKgJTuGXoMybxPtcdW5OVqd9AOWrACHV6hz9PKVO61dZQ1mRqC5i6BPvO1kVtJ4pE8Ib8DUo%2Fn2%2FKdIYh3DtlP5TlCkt4oOvKE%2BqngRTCpCmaZCfsHrpgKMHI4kFXGjaYaSfryaCnLf307qgk%2BYLleGdKfkAXKAxxANLSuqceMIPq1NIGOpkBKbRO23gt7dGtS%2BkU4qS2g%2F0%2BmCvgXYOJcdcgWRH%2BLu0x0PBAv7rp8Ojik0LHY0rnnx9aY%2BvtQ0T8egT1XkiiA4uXKy9MX0zG8BWhhHm224wTgG%2FBGWuPVssm1V7%2B0AdKdDX9QNKfXpcIN7BQW1u%2BpCjZc6ME%2BVclvl%2BrGEEG2WzS6%2FRrZxar0CDPvNL4Smmsx%2F%2F%2BaAAalTvR&X-Amz-Signature=7c2002a215ecc1d4adc33caec9560751db5cc850e407a09e91ed7ceb98aeaf0c&X-Amz-SignedHeaders=host&response-content-disposition=attachment%3B%20filename%3D%22EFT_FORM.pdf%22&x-id=GetObject https://government-project.s3.us-west-2.amazonaws.com/26612/6d7a0d7c-821d-49c6-bd01-3168d19ec223_E-Verify_%281%29.pdf?X-Amz-Algorithm=AWS4-HMAC-SHA256&X-Amz-Content-Sha256=UNSIGNED-PAYLOAD&X-Amz-Credential=ASIA47RIURE4BXJVR3FP%2F20260713%2Fus-west-2%2Fs3%2Faws4_request&X-Amz-Date=20260713T190043Z&X-Amz-Expires=72000&X-Amz-Security-Token=IQoJb3JpZ2luX2VjEDsaCXVzLXdlc3QtMiJHMEUCIQDhyMKGnQausIeOeDNE8OmhFw6bFI7qgriZ%2BAJcm92BogIgf052Iug8Gai4UksDh3Kykdww4ouKRtXHpIypGUPuP5cqjAUIBBACGgw4OTIzNjQ2ODc2NzIiDB64QeBOK7RuF4OF7SrpBN51%2ByfCic3KUGG4HUbDwf%2BUwzKRrfZzHYNk6M0kjOGsMYhvx9b48j11xLAj1y0Is9mJkOe%2FZMVw37ADn7RFOmQz2kZZ%2BmzjOI%2Bqc1i8ERDSXIwfsV27GZp7EqY7gghH2zYu2fBXx1xpFIjTwCdX6qfkCTZR5Xj0mfUqRTGVqYWFJZLinRofkp%2FaaY7849sVxTWBvUqxvcglGQ%2BftxBFlC66V3uhQiCg07rGougmJzUa2RMV6lJTMxKiP%2BRkqNm1hFpI1UGYN75AyEyQ35HpJY9MngGWTBDOqdO0AbViQGHTeAH1EFXq7jlDuOolAajtUQFCtwXHy2GZK%2BJKmByLaTalLAeYDSNCG3kCodKWCO3fOJqFzPF73vapF%2BMTE5gyaTggs0KdPh4eHxCO8GFm0WXfMlTApsdZxxCiSDik6huGyhV0OsrYwN%2BVlECT5ZlXxBApSo8I0DKEisdnhrYQmtdHiJZxPYugIuYRbjyHL0rhHqkXTzuazRKrLjihdUD%2BHWQxslHmQBz2DvbSiQSVZdZ0rgtW8CPD%2BtigG4PWAcBfi8xIuSe6tBcPNJHOR0Hg4zHxCj7xSc4XN5ognuTg%2F5AMFKD2uUe1yoQ1mGX%2Fiymt1rWRNlzDdeM6Ojx%2FQBpzaO3454zjZWlNe%2BObKgJTuGXoMybxPtcdW5OVqd9AOWrACHV6hz9PKVO61dZQ1mRqC5i6BPvO1kVtJ4pE8Ib8DUo%2Fn2%2FKdIYh3DtlP5TlCkt4oOvKE%2BqngRTCpCmaZCfsHrpgKMHI4kFXGjaYaSfryaCnLf307qgk%2BYLleGdKfkAXKAxxANLSuqceMIPq1NIGOpkBKbRO23gt7dGtS%2BkU4qS2g%2F0%2BmCvgXYOJcdcgWRH%2BLu0x0PBAv7rp8Ojik0LHY0rnnx9aY%2BvtQ0T8egT1XkiiA4uXKy9MX0zG8BWhhHm224wTgG%2FBGWuPVssm1V7%2B0AdKdDX9QNKfXpcIN7BQW1u%2BpCjZc6ME%2BVclvl%2BrGEEG2WzS6%2FRrZxar0CDPvNL4Smmsx%2F%2F%2BaAAalTvR&X-Amz-Signature=c5bacc8e93c9f9b3b85ad57381c9d9924f39a8d1f7cb48e4ef2872d05371beae&X-Amz-SignedHeaders=host&response-content-disposition=attachment%3B%20filename%3D%22E-Verify_%281%29.pdf%22&x-id=GetObject

☐ I certify that neither my family nor myself are employees of the County and will benefit financially by doing business with Clay County.

☐ I have a conflict of interest with the County and require a evaluation by the County Manager.

*Response required

4.16. Conflict of Interest Disclosure:*

Please identify yourself, family member or other conflict of interest.

Please enter N/A if this does not apply.

*Response required

4.17. Certificate of Insurance*

Provide certificate(s) of insurance.

Failure to provide proof of insurance may result in a Contractor being deemed non-responsive and therefore removed from consideration.

Please upload Insurance document(s) here.

*Response required

4.18. Certificate of Insurance *

Provide certificate(s) of insurance.

Failure to provide proof of insurance may result in a Bidder being deemed non-responsive and therefore removed from consideration.

Please upload Insurance document(s) here.

*Response required

4.19. Workers' Compensation Exemption (A)*

Is Contractor currently exempt from carrying Workers’ Compensation insurance?

If Yes, Contractor must provide a valid Certificate of Election to be Exempt issued by the Florida

Division of Workers’ Compensation.

☐ Yes

☐ No

*Response required

4.20. Workers' Compensation Exemption (B)

If Contractor Answered 'Yes' to Workers' Compensation Exemption (A), please upload a valid

Certificate of Election to be Exempt issued by the Florida Division of Workers’ Compensation here.

4.21. Section 287.05701, Florida Statutes - Prohibition against considering social, political, or ideological interests in government contracting*

Contractors are hereby notified of the provision of section 287.05701, Florida Statutes, as amended, that the Clay County Board of County Commissioners will not request documentation of or consider a

Contractor's social, political, or ideological interests when determining if the Contractor is a responsible

Contractor.

The Contractor acknowledges they were notified of the provisions in section 287.05701, Florida

Statutes.

☐ Please confirm

*Response required

4.22. Term Acknowledgement *

The Contractor acknowledges that they have thoroughly reviewed the term outlined in the Scope of

Work.

☐ Please confirm

*Response required

4.23. Site Acknowledgement *

I acknowledge that I, the Contractor, have been provided an opportunity by the County to visit the site or have been informed that the site is open to the public, to insure that I am aware of all conditions that may affect the Contract work thereon and therein.

I acknowledge that the County will not be responsible for conclusions made by the Contractor.

I acknowledge no claims for additional compensation will be considered on behalf of any Contractor, Sub-Contractor, materials suppliers or others on account of that person’s failure to be fully informed of all requirements of all parts of this bid.

☐ Please confirm

*Response required

4.24. Material Lead Time*

Are there any long lead times associated with obtaining the materials required to perform the work outlined in this informal quote?

☐ Yes

☐ No

*Response required

4.25. Material Lead Time *

http://www.leg.state.fl.us/statutes/index.cfm?App_mode=Display_Statute&URL=0200-0299/0287/0287.html

If yes, please provide a detail summary of the the lead times for the materials required to fulfill the work outlined in this Informal Quote.

If no, please state that there are no lead times for the materials required to fulfill the work outlined in this Informal Quote.

*Response required

4.26. License / Certification List *

Please list all current licenses and certifications held in the format listed below:

License Name:

License #:

Issuing Agency:

Expiration Date:

*Response required

4.27. License / Certification List *

Please upload a copy of each current license or certification provided in the response above.

*Response required

4.28. Warranty Form *

Please upload a sample or draft of your Warranty.

The Warranty must cover both labor and parts for a minimum of 2 years.

*Response required

4.29. Scrutinized Companies Certification*

Please download the below documents, complete, and upload.

• Scrutinized_Companies_Certi...

*Response required

4.30. FEMA Compliance Required Contract Clauses*

Please download the below documents, complete, and upload.

• f89a25b0-4b3f-4172-b48a-99c...

*Response required

4.31. Clay County Federal Purchasing Policy*

Please download the below documents, complete, and upload.

• 34a585fa-a707-476b-9cfe-99f...

*Response required https://government-project.s3.us-west-2.amazonaws.com/26612/665af7c5-4cfc-4990-aaa9-368d0aadd18b_Scrutinized_Companies_Certification_%283%29.pdf?X-Amz-Algorithm=AWS4-HMAC-SHA256&X-Amz-Content-Sha256=UNSIGNED-PAYLOAD&X-Amz-Credential=ASIA47RIURE4BXJVR3FP%2F20260713%2Fus-west-2%2Fs3%2Faws4_request&X-Amz-Date=20260713T190043Z&X-Amz-Expires=72000&X-Amz-Security-Token=IQoJb3JpZ2luX2VjEDsaCXVzLXdlc3QtMiJHMEUCIQDhyMKGnQausIeOeDNE8OmhFw6bFI7qgriZ%2BAJcm92BogIgf052Iug8Gai4UksDh3Kykdww4ouKRtXHpIypGUPuP5cqjAUIBBACGgw4OTIzNjQ2ODc2NzIiDB64QeBOK7RuF4OF7SrpBN51%2ByfCic3KUGG4HUbDwf%2BUwzKRrfZzHYNk6M0kjOGsMYhvx9b48j11xLAj1y0Is9mJkOe%2FZMVw37ADn7RFOmQz2kZZ%2BmzjOI%2Bqc1i8ERDSXIwfsV27GZp7EqY7gghH2zYu2fBXx1xpFIjTwCdX6qfkCTZR5Xj0mfUqRTGVqYWFJZLinRofkp%2FaaY7849sVxTWBvUqxvcglGQ%2BftxBFlC66V3uhQiCg07rGougmJzUa2RMV6lJTMxKiP%2BRkqNm1hFpI1UGYN75AyEyQ35HpJY9MngGWTBDOqdO0AbViQGHTeAH1EFXq7jlDuOolAajtUQFCtwXHy2GZK%2BJKmByLaTalLAeYDSNCG3kCodKWCO3fOJqFzPF73vapF%2BMTE5gyaTggs0KdPh4eHxCO8GFm0WXfMlTApsdZxxCiSDik6huGyhV0OsrYwN%2BVlECT5ZlXxBApSo8I0DKEisdnhrYQmtdHiJZxPYugIuYRbjyHL0rhHqkXTzuazRKrLjihdUD%2BHWQxslHmQBz2DvbSiQSVZdZ0rgtW8CPD%2BtigG4PWAcBfi8xIuSe6tBcPNJHOR0Hg4zHxCj7xSc4XN5ognuTg%2F5AMFKD2uUe1yoQ1mGX%2Fiymt1rWRNlzDdeM6Ojx%2FQBpzaO3454zjZWlNe%2BObKgJTuGXoMybxPtcdW5OVqd9AOWrACHV6hz9PKVO61dZQ1mRqC5i6BPvO1kVtJ4pE8Ib8DUo%2Fn2%2FKdIYh3DtlP5TlCkt4oOvKE%2BqngRTCpCmaZCfsHrpgKMHI4kFXGjaYaSfryaCnLf307qgk%2BYLleGdKfkAXKAxxANLSuqceMIPq1NIGOpkBKbRO23gt7dGtS%2BkU4qS2g%2F0%2BmCvgXYOJcdcgWRH%2BLu0x0PBAv7rp8Ojik0LHY0rnnx9aY%2BvtQ0T8egT1XkiiA4uXKy9MX0zG8BWhhHm224wTgG%2FBGWuPVssm1V7%2B0AdKdDX9QNKfXpcIN7BQW1u%2BpCjZc6ME%2BVclvl%2BrGEEG2WzS6%2FRrZxar0CDPvNL4Smmsx%2F%2F%2BaAAalTvR&X-Amz-Signature=bcd0b664625597c194c380007d352bcadb6b6ad923dd063cceee23a56ea86282&X-Amz-SignedHeaders=host&response-content-disposition=attachment%3B%20filename%3D%22Scrutinized_Companies_Certification_%283%29.pdf%22&x-id=GetObject https://government-project.s3.us-west-2.amazonaws.com/258505/b541db0d-2e3a-4fa2-b780-6c332ec1a817_f89a25b0-4b3f-4172-b48a-99cf19fce6fb_FEMA_CONTRACT_CLAUSES.pdf https://government-project.s3.us-west-2.amazonaws.com/258505/b77a99c2-8206-470b-b1b3-f61dc48b4c1c_34a585fa-a707-476b-9cfe-99f8d30f2132_Agreement_2023-2024-44_Resolution_and_Federal_policy.pdf

4.32. I have read and acknowledge the document(s) (Clay County Resolution and Federal Policy)*

☐ Please confirm

*Response required

1. Introduction
1.1. Summary
1.2. Contact Information
1.3. Timeline
2. Scope of Work
2.1. Scope of Work
2.2. Grant Funded
2.3. Contractor and Subcontractor Requirements
2.4. Site Inspections
2.5. Work Hours
2.6. Permit & Fees
2.7. Clean up & Restoration of Site
2.8. Workmanship
2.9. Damage to Public or Private Property
2.10. Compliance with Occupation Safety and Health Act
2.11. Unsatisfactory Equipment and/or Services
2.12. Payment
2.13. Warranty
2.14. Term
2.15. Insurance Requirements:
2.16. Additional Services
3. Pricing Proposal
4. Supplier Questionnaire
4.1. Response Acknowledgement *
4.2. Litigation, Investigations, and Disputes Disclosure (A)*
4.3. Litigation, Investigations, and Disputes Disclosure (B)
4.4. Legal Name *
4.5. Approved Designated Signee*
4.6. Approved Designated Signee*
4.7. Company Primary Contact*
4.8. Company Remittance Address*
4.9. W-9*
4.10. EFT Authorization Form
4.11. SunBiz Verification*
4.12. E-Verify *
4.13. E-Verify *
4.14. Conflict of Interest Disclosure: *
4.15. Conflict of Interest Disclosure: *
4.16. Conflict of Interest Disclosure:*
4.17. Certificate of Insurance*
4.18. Certificate of Insurance *
4.19. Workers' Compensation Exemption (A)*
4.20. Workers' Compensation Exemption (B)
4.21. Section 287.05701, Florida Statutes - Prohibition against considering social, political, or ideological interests in government contracting*
4.22. Term Acknowledgement *
4.23. Site Acknowledgement *
4.24. Material Lead Time*
4.25. Material Lead Time *
4.26. License / Certification List *
4.27. License / Certification List *
4.28. Warranty Form *
4.29. Scrutinized Companies Certification*
4.30. FEMA Compliance Required Contract Clauses*
4.31. Clay County Federal Purchasing Policy*
4.32. I have read and acknowledge the document(s) (Clay County Resolution and Federal Policy)*