Pototential Source Question and Answer.pdf
PDF 36 KB Posted
- Attached to
- MJU-76B One on One Meetings Federal contract opportunity
- Solicitation number
- MJU-76B_SSS
About this file
This document contains a question and answer exchange between an interested vendor and the government regarding the MJU-76/B Infrared Countermeasure Flare procurement opportunity.
The vendor's question concerns the Authority Data Acquisition Document DI-QCIC-81960 referenced in MSE CDRL A012 & A013, specifically regarding requirements for equipment purchase and testing under the AAIE section. The government clarifies that the MSE CLIN scope is administrative only and does not require equipment purchases, though it does include testing and compiling test results in CDRL format. The government also indicates they will accept draft MSE submissions and may issue First Article delivery orders prior to final MSE receipt, contingent on FOPR issuance, proposal receipt, and evaluation. An approved MSE CDRL must be in place before First Article work can begin.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Potential Source Question and Answer.pdf | ||
| Potential Source One on One Meeting.pdf | ||
| Potential Source One on One meetingv2.pdf | ||
| JQR MJU-76.pdf | ||
| SSS On SAM.gov.pdf | ||
| FD2020-24-52553 MJU-76B DD1423Pkg_2024Oct09-Signed.pdf | ||
| MJU-76B SSS-2.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Interested Vendor Question and Answer
Question:
The Authority Data Acquisition Document DI-QCIC-81960 referenced on the MSE CDRL A012 & A013 requires items under the AAIE section (specifically the “final design” section) that imply equipment must be purchased and tested. Same with non-destructive test equipment. If items like test results and calibrations are required for the MSE CDRL, then qualified vendors must price in the cost of equipment, testing, and compiling test results at risk of USG approval in order to satisfy that DID, which I don’t think is your intent. We also could not purchase, install and test that equipment within the 120 day requirement.
Answer:
MSE CLIN scope of work is administrative work only and does not include the purchase of equipment. The MSE CLIN scope does include testing and compiling test results into appropriate CDRL format.
In addition, the Government will allow the awardees to submit a draft MSE. the Government may elect to issue the First Article delivery order prior to receipt of the final MSE based on completeness and quality of the draft MSE. Issuing the First Article delivery order would also be contingent on the Government previously issuing a FOPR (Fair Opportunity Proposal Request) for the first article, receiving a proposal, and evaluating the proposal. An approved MSE CDRL is required prior to beginning work on First Article.