This is a Q&A document from a one-on-one vendor meeting regarding an RFP for MJU-76/B Infrared Countermeasure Flares. The Department of Air Force plans to release the RFP between February-March with a 30-day response period and expects contract award in May-June. The acquisition involves a 5-year IDIQ contract for 500,000-750,000 total units including FMS requirements, with a split award strategy.
Key timeline details include 120 days for MSE completion, 6 months for First Article after MSE approval, and 365 days for production. The document addresses numerous CDRL requirements, including GFP consumption reports, test inspection reports, failure analysis reports, and production status reports. Government will provide MJU-11 Magazines and CCU 145F, with steel pallets under consideration. Production output at Crane facility is approximately 100,000 flares annually. Response times for RFVs are specified as 45 days for minors and 60 days for majors. While government pricing estimates exist, they were not shared during the meeting.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Pototential Source Question and Answer.pdf | ||
| Potential Source Question and Answer.pdf | ||
| Potential Source One on One meetingv2.pdf | ||
| JQR MJU-76.pdf | ||
| FD2020-24-52553 MJU-76B DD1423Pkg_2024Oct09-Signed.pdf | ||
| SSS On SAM.gov.pdf | ||
| MJU-76B SSS-2.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Interested Vendor One on One Meeting
Timeline for Release of RFP in Feb. - Mar. time frame.
30 day response period.
Intend to issue a draft RFP prior.
MSE separately priced CLIN.
The goal is 120 days pop for the MSE.
6 months pop (on or before) for the First Article after receipt of approval of MSE.
365 day POP for production.
May - June contact award.
Additional time may be required for extension of RFP. The intent of the draft RFP is to minimize that.
Current acquisition strategy is to do a split award.
Requirement includes 5 year IDIQ for between 500K and 750K total units.
This will include FMS which are harder to forecast.
Questions
Question: CDRL A001 GFP consumption report does not require a specific template.
Answer: Intent is to avoid issues with cartridges left over at the end of the contract.
Note: Dispensers are linked to the contract.
Question: A008 Test inspection report has 30 day response time and can that be reduced?
Answer: No, but government will attempt to do that as soon as possible.
Question: CDRL A009 the failure summary and analysis report – Is it ok to not submit report?
Answer: No - submit per CDRL with letter of transmittal.
Question: Does email notification suffice for notification for CDRL A009
Answer: Yes it has to be submitted to CO.
Question: can we extend the preliminary report 7 days to 15 days and push revision or final report from 15 days to 30 days.
Answer: Yes
Question: Can A010 acceptance and description sheets be waived?
Answer: No.
Question: Can you tell me what the difference is between A012 and A013?
Answer: One is AIE (A012) - Is what you have done before.
One is MSA (A013) – Doing analysis which ties into automated systems. Deals with acceptance parameter.
Question: What is goal of CDRL A016 Diminishing Manufacturing Sources and material.
Answer: Goal is to call out risks in the report and ensure communication between Gov. and contractor occurs to minimize risk.
Question: CDRL A015 shows DID 81949/t. A019 shows 80442/t. Does /t mean anything?
Answer: Government will investigate and provide reason or an
Question: CDRL A017 Report of Record of meeting minutes. When is it required and what content is required?
Answer: Provide weekly and power point presentation.
Question: What is intent of A018 Production status report?
Answer: The intent is a monthly recap of production status and how we are looking on the overall schedule.
Question: Is there preferred template for A019?
Consumption report will suffice per format provided in CDRL to notify the government what it has and for managing inventory.
Question: Will A021 SPC Plan be included in MSE package?
Answer: Yes.
Question: Is it possible to go see production at Crane.
Answer: Yes with a 14 day notice.
Question: Will USG provide MJU-11 Magazines?
Answer: Yes
Question: Will USG provide steel pallets?
Answer: Government will look into that.
Question: Is Government providing the CCU 145F
Answer: Yes
Question: Is there a timeline for Government tests.
Answer: Yes, but not for flight test.
Question: Is it possible to make DTL a recommended document?
Answer: No
Question: What is the Response time to RFVs?
Answer: Minors are 45 days and Majors are 60 days
Question: Is there contractual language to distinguish between minor and major RFVs.
Answer: Mil Handbook for configuration management. Will look up.
Question: Is there a unit price the Government has in mind?
Answer: Government has its estimates but can’t share.
Question: What is the output for Crane?
Answer: Output is roughly a 100,000 flares a year.
Question: Can AF commit to evaluating lots in consecutive order?
Answer: No
Question: Will Gov. provide comprehensive FMEA (Failure Analysis)?
Answer: We currently do not have to one to provide, but we will look into that.
File details come from the government source that posted it. Updated .